RFP SC-27-724 Metals Development Steam Replacement with all Appendices.pdf
PDF 10 MB Posted
- Solicitation number
- RFP-SC-27-724
- Issued by
-
Department of Energy Ames Laboratory
About this file
This document is a PDF portfolio cover page. The image shows an Adobe Acrobat binder with the red Adobe logo on a white background with red accent corners. The page contains instructions directing users to open the PDF portfolio in Acrobat X or Adobe Reader X, or later versions, with a button to download Adobe Reader. No contract opportunity information, solicitation details, products, services, timelines, pricing terms, or federal agency information is present on this cover page.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
I HEREBY CERTIFY THAT THIS ENGINEERING DOCUMENT WAS
PREPARED BY ME OR UNDER MY DIRECT PERSONAL SUPERVISION
AND THAT I AM A DULY LICENSED PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF IOWA.
COREY BENTON METZGER, PE
REG. NO. DATE:
MY LICENSE RENEWAL DATE IS DECEMBER 31, 2027
PAGES OR SHEETS COVERED BY THIS SEAL:
P21049
ALL MECHANICAL SHEETS
L
IC
E N S E
D
PR
OFE
SSIONAL
N G I N E
R
O WI A
COREY
BENTON
METZGER
P21049
MEP ENGINEER:
RESOURCE CONSULTING
ENGINEERS, LLC
PROJECT NO:
ISSUED:
©2026
DATEMARK
REVISION INFORMATION
DESCRIPTION
301 ALEXANDER AVENUE
SUITE C
AMES, IA 50010
515-292-2500 www.resourcece.com
2026.013.00
A M
T
IO
B
O
Y
V
P
IR
ID
I
U
G000
TITLE SHEET
IA
11/24/2026
THESE DOCUMENTS HAVE BEEN PREPARED BY RESOURCE
CONSULTING ENGINEERS, LLC FOR THE METALS DEVELOPMENT
STEAM REPAIRS PROJECT. THE DOCUMENTS SHALL REMAIN THE
PROPERTY OF RESOURCE CONSULTING ENGINEERS, LLC, AND SHALL
NOT BE USED ON OTHER PROJECTS, OR IN OTHER LOCATIONS
WITHOUT THE EXPRESS WRITTEN APPROVAL AND PARTICIPATION OF
RESOURCE CONSULTING ENGINEERS, LLC. RESOURCE CONSULTING
ENGINEERS, LLC SHALL RETAIN ALL COMMON LAW, STATUTORY, AND
OTHER RESERVED RIGHTS, INCLUDING THE COPYRIGHT THERETO.
AMES NATIONAL LABORATORY METALS DEVELOPMENT
STEAM REPAIRS
DRAWING INDEX:
PROJECT
LOCATION
RCE PROJECT NUMBER: 2026.013.00
PROJECT LOCATION:
METALS DEVELOPMENT
2415 PAMMEL DR.
AMES, IA 50011
G000 TITLE SHEET
M000 MECHANICAL SYMBOLS AND ABBREVIATIONS
MD100 BASEMENT FLOOR MECHANICAL DEMO PLAN
MD101 FIRST FLOOR MECHANICAL DEMO PLAN
MD102 SECOND FLOOR MECHANICAL DEMO PLAN
M100 BASEMENT FLOOR MECHANICAL PLAN
M101 FIRST FLOOR MECHANICAL PLAN
M102 SECOND FLOOR MECHANICAL PLAN
M400 ENLARGED MECHANICAL PLANS
M600 MECHANICAL DETAILS AND SCHEDULES
M700 STEAM RISER DIAGRAMS
OWNER INFORMATION:
AMES LAB
2408 PAMMEL DR.
AMES, IA 50011
PROJECT DESCRIPTION
THIS PROJECT CONSISTS OF REMOVING AND/OR REPLACING SEVERAL PIECES OF STEAM PIPING EQUIPMENT SERVING THE AMES LAB
METALS DEVELOPMENT BUILDING LOCATED ON IOWA STATE UNIVERSITY'S CAMPUS.
THE SCOPE OF WORK SHALL CONSIST OF THE FOLLOWING:
• DEMOLITION AND REPLACEMENT OF THE EXISTING STEAM EXPANSION FITTING LOCATED IN THE BUILDING SERVICE TUNNEL.
• PROVIDE NEW BUILDING ISOLATION VALVE LOCATED IN THE UTILITY SERVICE TUNNEL ON THE "BUILDING SIDE" OF THE NEW
EXPANSION DEVICE.
• DEMOLITION OF THE EXISTING MAIN PRV STATION. PRV STATION CONSISTS OF A 1/3-2/3, 90 PSI TO 25 PSI SETUP AND A SINGLE
PRV THAT TAKES REDUCES 90 PSI STEAM TO 12 PSI.
• INSTALLATION OF A NEW PRV STATION REDUCING 90 PSI STEAM DOWN TO 15 PSI STEAM AND RECONNECTING TO EXISTING 25
PSI AND 12 PSI STEAM PIPING.
• DEMOLITION OF 2 EXISTING SAFETY RELIEF VALVES AND THE INSTALLATION OF A SINGLE RELIEF VALVE.
• DEMOLITION OF SEVERAL POINT OF USE PRV'S THAT REDUCE 25 PSI STEAM TO 10-12 PSI AT INDIVIDUAL PIECES OF EQUIPMENT
THROUGHOUT THE BUILDING. NEW PIPING SHALL BE INSTALLED TO REPLACE THE REMOVED VALVES.
PROPOSED PHASING
1. ISOLATE STEAM MAIN SERVING METALS DEVELOPMENT LOCATED IN UTILITY SERVICE TUNNEL AND DRAIN SYSTEM.
2. PERFORM DEMOLITION AND NEW WORK RELATED TO EXPANSION FITTING AND MAIN PRV STATION.
3. PERFORM DEMOLITION AND NEW WORK RELATED TO POINT-OF-USE PRV'S LOCATED THROUGHOUT BUILDING.
4. SCOPE OF WORK IN THE UTILITY TUNNEL, BASEMENT MECHANICAL ROOM, AND ELSEWHERE IN THE BUILDING MAY BE
PERFORMED CONCURRENTLY TO MINIMIZE SHUTDOWN.
5. REOPEN TUNNEL ISOLATION VALVE, FILL AND WARM UP SYSTEM.
GENERAL SYMBOLS
REVISION NUMBER - SHOWN
ON PLANS
CONNECT TO EXISTING
NUMBER OF DETAIL ON SHEET
NUMBER OF SHEET WHERE
DETAIL APPEARS
CONTINUATION SYMBOL
Room
6 ROOM NAME AND NUMBER
SECTION/ELEVATION VIEW
ITEM TO BE DEMOLISHED
2" PIPE SIZE TAG DIAMETER
INVERT: -105' - 1"
PIPE INVERT ELEVATION TAG
(E) EXISTING PIPE TAG
(D) DEMOLISHED PIPE AND TAG
MECHANICAL PIPING SYMBOLS
CHR CHILLED WATER RETURN
CHILLED WATER SUPPLY
CONDENSATE DRAINAGE
CONDENSER WATER RETURN
CONDENSER WATER SUPPLY
DUAL TEMPERATURE WATER RETURN
DUAL TEMPERATURE WATER SUPPLY
FUEL OIL RETURN
FUEL OIL SUPPLY
FUEL OIL VENT
GEOTHERMAL WATER RETURN
GEOTHERMAL WATER SUPPLY
PIPE RISE
PIPE DROP
PIPE TEE
CAP
REDUCING 45
DEGREE TEE
45 DEGREE TEE
4"
2"
4"
PLUG
PIPE SYMBOLS
PIPE ACCESSORY TAGS
GLOBE VALVE
BALANCING VALVE
SHUTOFF BALL VALVE
CHECK VALVE
3-WAY MIXING VALVE
MOTORIZED CONTROL VALVE
3-WAY MOTORIZED CONTROL VALVE
PRESSURE REDUCING VALVE
STRAINER WITH BLOWDOWN CONNECTION
BUTTERFLY VALVE
HEATING WATER RETURN
HEATING WATER SUPPLY
NATURAL GAS
NON-POTABLE COLD WATER
REFRIGERANT - HOT GAS
REFRIGERANT - LIQUID
REFRIGERANT - SUCTION
STEAM - CONDENSATE RETURN
STEAM - HIGH PRESSURE, 90 PSIG
STEAM - MEDIUM PRESSURE, 25 PSIG
STEAM - LOW PRESSURE, 15 PSIG
CHS
CD
CWR
CWS
DTWR
DTWS
FOR
FOS
FOV
GWR
GWS
HWR
HWS
NG
NPCW
RHG
RL
RS
STC
STM-90 PSIG
STM-25 PSIG
STM-15 PSIG
STEAM - LOW PRESSURE, 12 PSIGSTM-12 PSIG
APPLICABLE CODES
A. 2015 INTERNATIONAL BUILDING CODE AS ADOPTED BY IOWA ADMINISTRATIVE RULES
661-201 AND 661-301
B. 2015 INTERNATIONAL FIRE CODE AS ADOPTED BY IOWA ADMINISTRATIVE RULE 661-201
C. 2012 INTERNATIONAL ENERGY CONSERVATION CODE AS ADOPTED BY IOWA
ADMINISTRATIVE RULE 661-303
D. 2015 INTERNATIONAL EXISTING BUILDING CODE AS ADOPTED BY IOWA ADMINISTRATIVE
RULE 661-301 AND 661-350, AS APPLICABLE.
E. 2012 NFPA 101 LIFE SAFETY CODE AS ADOPTED BY IOWA ADMINISTRATIVE RULE
661-205
F. 2010 AMERICANS WITH DISABILITIES ACT AS ADOPTED BY IOWA ADMINISTRATIVE RULE
661-302
G. 2024 INTERNATIONAL MECHANICAL CODE AS ADOPTED BY THE IOWA DEPARTMENT OF
PUBLIC HEALTH, IOWA ADMINISTRATIVE RULE 641-61
H. 2024 UNIFORM PLUMBING CODE AS ADOPTED BY THE IOWA DEPARTMENT OF PUBLIC
HEALTH, IOWA ADMINISTRATIVE RULE 641-25
I. 2023 NATIONAL ELECTRICAL CODE AS ADOPTED BY THE IOWA ELECTRICAL LICENSING
BOARD, IOWA ADMINISTRATIVE RULE 661-504.
M000
MECHANICAL SYMBOLS
AND ABBREVIATIONS
, I
INV INVERT
INFO INFORMATION
IN INCH / INCHES
IMC INTERNATIONAL MECHANICAL CODE
IFGC INTERNATIONAL FUEL GAS CODE
IECC INTERNATIONAL ENERGY CONSERVATION CODE
ID INSIDE DIAMETER
IBC INTERNATIONAL BUILDING CODE
HZ HERTZ WG WATER GAUGE
HVAC HEATING, VENTILATION, AND AIR CONDITIONING WC WATER COLUMN
HP HORSEPOWER WB WET BULB
H ENTHALPY W/ WITH
GYP GYPSUM BOARD W WATT
GS GALVANIZED STEEL VTR VENT THROUGH ROOF
GPM GALLONS PER MINUTE VP VELOCITY PRESSURE
GPH GALLONS PER HOUR VENT VENTILATION
GC GENERAL CONTRACTOR VAV VARIABLE AIR VOLUME
GAL GALLON V VOLTS
GA GAUGE UL UNDERWRITERS LABORATORIES
FTG FOOTING UG UNDERGROUND
FT FOOT / FEET TYP TYPICAL
FSP FIRE SUPPRESSION TSP TOTAL STATIC PRESSURE
FPS FEET PER SECOND TOP TOP OF PIPE
FPM FEET PER MINUTE TOD TOP OF DUCT
FLA FULL LOAD AMPS THRU THROUGH
FL FLOOR TEMP TEMPERATURE
EXH EXHAUST TCC TEMPERATURE CONTROL CONTRACTOR
EWT ENTERING WATER TEMPERATURE STD STANDARD
EWB ENTERING WET BULB SS STAINLESS STEEL
ETR EXISTING TO REMAIN SPEC SPECIFY / SPECIFIED / SPECIFICATION
ETC ET CETERA SP STATIC PRESSURE
ESP EXTERNAL STATIC PRESSURE SM SURFACE MOUNT
EQUIP EQUIPMENT SF SQUARE FOOT/FEET
ELEV ELEVATOR SCH SCHEDULE
ELEC ELECTRICAL RPM REVOLUTIONS PER MINUTE
EDB ENTERING DRY BULB RM ROOM
EC ELECTRICAL CONTRACTOR RH RELATIVE HUMIDITY
EAT ENTERING AIR TEMPERATURE REV REVISION
E.G. FOR EXAMPLE RED REDUCER
DP DIFFERENTIAL PRESSURE REC RECESSED
DN DOWN RCP REFLECTED CEILING PLAN
DIA (ALSO Ø) DIAMETER RCE RESOURCE CONSULTING ENGINEERS, LLC
DEMO DEMOLISH / DEMOLITION QTY QUANTITY
DDC DIRECT DIGITAL CONTROL PWR POWER
DBA A-WEIGHTED DECIBELS PSIG POUNDS PER SQUARE INCH GAUGE
DB DRY BULB PSIA POUNDS PER SQUARE INCH ABSOLUTE
CxA COMMISSIONING AGENT PSI POUNDS PER SQUARE INCH Cx COMMISSIONING PSF POUNDS PER SQUARE FOOT
CV CONSTANT VOLUME PRESS PRESSURE
CU COPPER PLBG PLUMBING
CS CARBON STEEL PG PROPYLENE GLYCOL
COP CENTER OF PIPE PD PRESSURE DROP
CONT CONTINUED PCF POUNDS PER CUBIC FOOR
COD CENTER OF DUCT PC PLUMBING CONTRACTOR
CLG CEILING OFOI OWNER FURNISHED, OWNER INSTALLED
CL CENTERLINE OFCI OWNER FURNISHED, CONTRACTOR INSTALLED
CFM CUBIC FEET PER MINUTE OD OUTSIDE DIAMETER
CFH CUBIC FEET PER HOUR OC ON CENTER
CAP CAPACITY NTS NOT TO SCALE
BTUH BRITISH THERMAL UNITS PER HOUR NPS NOMINAL PIPE SIZE
BTU BRITISH THERMAL UNITS NO NORMALLY OPEN
BOP BOTTOM OF PIPE NIC NOT IN CONTRACT
BOD BOTTOM OF DUCT NFPA NATIONAL FIRE PROTECTION ASSOCIATION
BMS BUILDING MANAGEMENT SYSTEM NC NORMALLY CLOSED
BLW BELOW N/A (ALSO NA) NOT APPLICABLE
BFF BELOW FINISHED FLOOR MTR MOTOR
BAS BUILDING AUTOMATION SYSTEM MOCP (ALSO MCP) MAXIMUM OVERCURRENT PROTECTION
AUTO AUTOMATIC MISC MISCELLANEOUS
ASTM AMERICAN SOCIETY FOR TESTING AND MATERIALS MIN MINIMUM
ARCH ARCHITECT/ARCHITECTURAL MFR MANUFACTURER
AP ACCESS PANEL MEP MECHANICAL, ELECTRICAL, AND PLUMBING
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE MECH MECHANICAL
ALT ALTERNATE MCF ONE THOUSAND CUBIC FEET
AL ALUMINUM MCA MAXIMUM CURRENT AMPACITY
AHJ AUTHORITY HAVING JURISDICTION MC MECHANICAL CONTRACTOR
AFUE ANNUAL FUEL UTILIZATION EFFICIENCY MBH ONE THOUSAND BTU PER HOUR
AFF ABOVE FINISHED FLOOR MAX MAXIMUM
ADJ ADJUSTABLE LWT LEAVING WATER TEMPERATURE
ADD ADDENDUM LWB LEAVING WET BULB
ACT ACOUSTICAL CEILING TILES LRA LOCKER ROTOR AMPS
ABV ABOVE LF LINEAL / LINEAR FOOT
A AMPS / AMPERE LDB LEAVING DRY BULB
°F DEGREES FAHRENHEIT LB/HR POUNDS PER HOUR
(R) RELOCATED LB POUND
(E) EXISTING LAT LEAVING AIR TEMPERATURE
(D) DEMOLISHED KW KILOWATT
ABBREVIATIONS ABBREVIATIONS CONT.
xP PUMP (CHP, HWP, GSP, ETC.)
xF FAN (SF, EF, RF, KEF, ETC.)
xCV CONTROL VALVE (CCV, HCV, ETC.)
xC COIL (CC, HC, PHC, EDC, RHC, ETC.)
xAS AIR SILENCER (SAS, RAS, OAS, EAS, ETC.)
xABD AUTOMATIC BALANCING DEVICE (SABD, OABD, EABD,...
WWHP WATER TO WATER HEAT PUMP
VT VOLUME TANK
VRF VARIABLE REFIRGERANT FLOW
VFD VARIABLE FREQUENCY DRIVE
UH UNIT HEATER
T THERMOSTAT
ST STEAM TRAP
SFPB SERIES FAN POWERED BOX
RTU ROOFTOP UNIT
R REGISTER
PRV POWER ROOF VENTILATOR
PR PRESSURE REGULATOR
PR PANEL RADIATOR
PHC PRE-HEAT COIL
PFPB PARALLEL FAN POWERED BOX
NO2 NITROGEN DIOXIDE / NITROGEN DIOXIDE SENSOR
MAU MAKEUP AIR UNIT
L LOUVER
KEH KITCHEN EXHAUST HOOD
HX HEAT EXCHANGER
HU HUMIDIFICATION UNIT
HRU HEAT RECOVERY UNIT
HP HEAT PUMP
HF HYDRONIC FILTER
H HUMIDITY SENSOR
GRV GRAVITY ROOF VENTILATOR
GIH GRAVITY INTAKE HOOD
GFP GLYCOL FEED PUMP
G GRILLE
FTR FIN TUBE RADIATOR
FCU FAN COIL UNIT
F FURNACE
ET EXPANSION TANK
ERW ENERGY RECOVERY WHEEL
ERV ENERGY RECOVERY VENTILATOR
DOAS DEDICATED OUTDOOR AIR SYSTEM
DHU DEHUMIDIFICATION UNIT
DF DUCT FILTER
DC DRY COOLER
D DIFFUSER
CUH CABINET UNIT HEATER
CU (ALSO COND) CONDENSING UNIT
CT COOLING TOWER
CRU CONDENSATE RETURN UNIT
CO2 CARBON DIOXIDE / CARBON DIOXIDE SENSOR
CO CARBON MONOXIDE / CARBON MONOXIDE SENSOR
CH CHILLER
CD CONTROL DAMPER
CCT CLOSED CIRCUIT COOLING TOWER
CBF CHEMICAL BYPASS FEEDER
CB CHILLED BEAM
BT BUFFER TANK
B BOILER
AWHP AIR TO WATER HEAT PUMP
AS AIR SEPARATOR
AHU AIR HANDLING UNIT
AFMS AIRFLOW MEASURING STATION
AC AIR-COOLED CHILLER
EQUIPMENT ABBREVIATIONS
K
J
H
F
C
1 2 3 4 5
6 7 8
9 10 11 1312 14
M400
NOT EXCAVATED
MECH ROOM
BB16
CORRIDOR
BB18
MECH
BD17
LOBBY
BE17
EL. EQUIP
BE19
PIPE TUNNEL
IP
EL
6" STM-90 PSIG
3/4" STC
CONDENSATE
RECEIVER TANK (E)
DUPLEX CONDENSATE
PUMP (E)
PRV STATION #1 (D)
6" STM-25 PSIG
3" STC 2 1/2" STC
5" STM-25 PSIG
EXISTING
UVU
2 1/2" STC UP
3" STM-25 PSIG UP
6" STM-25 PSIG UP
3" STC UP
5" STM-90 PSIG UP
5" STM-25 PSIG UP
5" STM-90 PSIG
2" STM-VENT
4" STM-VENT
MD100
BASEMENT FLOOR
MECHANICAL DEMO PLAN
MECHANICAL GENERAL NOTES
A CONTRACTOR SHALL SECURE AND PAY ALL FEES AND PERMITS PERTAINING TO
WORK.
B CONTRACTOR IS RESPONSIBLE FOR ALL RIGGING, HANDLING, AND PROTECTION OF
MATERIALS.
C ALL EQUIPMENT SHALL BE INSTALLED IN STRICT COMPLIANCE WITH
MANUFACTURER’S WRITTEN INSTRUCTIONS. THE CONTRACTOR SHALL PROVIDE
ALL HANGERS AND SUPPORTS REQUIRED FOR A COMPLETE INSTALLATION.
D FOR CLARITY OF INFORMATION ON DRAWING, ALL EXISTING CONDUIT, PIPING,
DUCTWORK, EQUIPMENT, DEVICES, ETC. ARE NOT SHOWN. CONTRACTOR SHALL BE
RESPONSIBLE FOR REVIEWING ACTUAL SITE CONDITIONS AND COORDINATING
WORK WITH EXISTING SYSTEMS, UTILITIES, AND GENERAL CONSTRUCTION
COMPONENTS IN SPACE.
E WORK SHALL BE SCHEDULED TO MINIMIZE DURATION OF INTERRUPTIONS TO
MECHANICAL SYSTEMS IN BUILDING. SHUTDOWNS AFFECTING AREAS OUTSIDE OF
WORK AREA SHALL BE SCHEDULED WITH OWNER, WITH MINIMUM OF 48 HOURS
NOTICE PRIOR TO SHUTDOWN. SHUTDOWNS IMPACTING HEATING OR COOLING OF
OTHER BUILDING AREAS SHALL BE LIMITED IN DURATION, AND SHALL BE
APPROVED BY OWNER PRIOR TO WORK PROGRESSING.
F CONTROLS SYSTEM SHALL BE MODIFIED AS INDICATED ON DRAWINGS, WITH
EXISTING SENSORS/CONTROL DEVICES RELOCATED TO NEW LOCATIONS AS
INDICATED. WIRING WILL BE RE-ROUTED FROM NEW LOCATION BACK TO
CONTROLLER OR EQUIPMENT SERVED.
G NEW CONTROL COMPONENTS SHALL MATCH EXISTING CONTROL COMPONENTS.
ALL CONTROLLED DEVICES SHALL BE INTEGRATED INTO BUILDING AUTOMATION
SYSTEM.
H REQUIRED ACCESS AREA FOR MECHANICAL EQUIPMENT IS TYPICALLY INDICATED
ON DRAWINGS. CONTRACTOR SHALL COORDINATE FINAL EQUIPMENT LOCATIONS
WITH WORK OF OTHER TRADES TO ENSURE EQUIPMENT IS ACCESSIBLE FOR
MAINTENANCE, FILTER REPLACEMENTS, ETC.
KEYNOTE LEGEND
KEY VALUE KEYNOTE TEXT
1 DEMOLISH EXISTING SAFETY RELIEF VALVE AND PIPING TO EXTENTS
SHOWN.
2 CONNECTION OF 2" AND 4" STEAM RELIEF VENT PIPING.
3 DEMOLISH PRV STATION IN ITS ENTIRETY. REFER TO VIEW 3 ON SHEET
M400 FOR MORE DETAILS.
4 METALS DEVELOPMENT STEAM ISOLATION VALVE. NOTIFY OWNER AND
ENGINEER IF VALVE DOES NOT FULLY CLOSE.
5 DEMOLISH EXISTING PACKED TYPE EXPANSION FITTING AND PIPING AS
INDICATED TO ALLOW INSTALLATION OF NEW EXPANSION FITTING AND
ACCESSORIES. EXISTING ANCHOR POINT TO REMAIN.
8' 16'4'0
1/8" = 1'-0"
BASEMENT FLOOR MECHANICAL PLAN - DEMOLITION
1 2 3 4 5 6 7 8 9 10 11 1312 14
Space
BB26
BB27
ROOM
158B
158C
158D
158E
158F
158G
158H
158I
158J
150B
BB30
BB29
Room-1
150C
160D
160C
160A
160B
162A
158L ROOM
158K
167D ROOM
167C
167B
167A
MEN
107Space
111B
111A
120Space
123Space
WOMEN
STAIR STAIR
STAIR
HALL
2 1/2" STC DN
3" STM-25 PSIG DN
AHU-150
6" STM-25 PSIG DN
3" STC DN
3" STM-12 PSIG UP
PRV STATION #3
VU
25 PSI STEAM
SERVING AHU-150
/4
-2
IG
5" STM-90 PSIG UP & DN
3 1/2" STM-25 PSIG UP
3" 25 PSI STEAM
CONTINUES TO
SERVE EXISTING VU'S
2 1/2" STC UP & DN
5" STM-12 PSIG UP & DN
5" STM-25 PSIG DN
MD101
FIRST FLOOR MECHANICAL
DEMO PLAN
RESPONSIBLE FOR REVIEWING ACTUAL SITE CONDITIONS AND COORDINATING
WORK AREA SHALL BE SCHEDULED WITH OWNER, WITH MINIMUM OF 48 HOURS
NOTICE PRIOR TO SHUTDOWN. SHUTDOWNS IMPACTING HEATING OR COOLING OF
1 DEMOLISH EXISTING PRESSURE REDUCING VALVE AND ASSOCIATED
ACCESSORIES. PREPARE PIPING FOR NEW CONNECTION.
FIRST FLOOR MECHANICAL PLAN - DEMOLITION
BB57
BB59
BB60
BB58
BB56
BB55
224B
228A
211A
PRV STATION #2 (D)
3" STM-12 PSIG DN
5" STM-12 PSIG DN
3 1/2" STM-25 PSIG
-9
3 1/2" STM-25 PSIG DN
5" STM-90 PSIG DN
2" STM-90 PSIG
12 PSI STEAM TO
AHUS IN 295A
2" STM-25 PSIG
AHU-240
AHU-282
PRV
STATION #4 (D)
STEAM GENERATOR
2" STM-12 PSIG 1
PRV STATION #5 (D)
AHU-257A
12 PSIG SERVICE TO
HEAT EXCHANGER
MD102
SECOND FLOOR
MECHANICAL DEMO PLAN
RESPONSIBLE FOR REVIEWING ACTUAL SITE CONDITIONS AND COORDINATING
WORK AREA SHALL BE SCHEDULED WITH OWNER, WITH MINIMUM OF 48 HOURS
NOTICE PRIOR TO SHUTDOWN. SHUTDOWNS IMPACTING HEATING OR COOLING OF
1 DEMOLISH EXISTING PRESSURE REDUCING VALVE AND ASSOCIATED
ACCESSORIES. PREPARE PIPING FOR NEW CONNECTION.
SECOND FLOOR MECHANICAL PLAN - DEMOLITION
1 2 3 4 5
9 10 11 1312 14
CORRIDOR
BB18
LOBBY
BE17
EL. EQUIP
BE19
IP
EL
CONDENSATE
RECEIVER TANK (E)
DUPLEX CONDENSATE
PUMP (E)
PRV STATION #1
EXPANSION
FITTING
6" STM-25 PSIG
3" STC 2 1/2" STC
5" STM-25 PSIG
2 1/2" STC UP
3" STM-25 PSIG UP
6" STM-25 PSIG UP
3" STC UP
5" STM-90 PSIG UP
5" STM-25 PSIG UP15
STEAM ISOLATION VALVE
M100
MECHANICAL PLAN
RESPONSIBLE FOR REVIEWING ACTUAL SITE CONDITIONS AND COORDINATING
WORK AREA SHALL BE SCHEDULED WITH OWNER, WITH MINIMUM OF 48 HOURS
NOTICE PRIOR TO SHUTDOWN. SHUTDOWNS IMPACTING HEATING OR COOLING OF
BASEMENT FLOOR MECHANICAL PLAN
BB26
BB27
158B
158C
158D
158E
158F
158G
158H
158I
158J
150B
BB30
BB29
Room-1
150C
160D
160C
160A
160B
162A
158L ROOM
158K
167D ROOM
167C
167B
167A
MEN
107Space
111B
111A
120Space
123Space
WOMEN
3" STM-25 PSIG DN
6" STM-25 PSIG DN
3" STC DN
3" STM-12 PSIG UP
25 PSI STEAM
SERVING AHU-150
/4
5" STM-90 PSIG UP & DN
3 1/2" STM-25 PSIG UP
3" 15 PSI STEAM
CONTINUES TO
SERVE EXISTING VU'S
2 1/2" STC UP & DN
5" STM-12 PSIG UP & DN
5" STM-25 PSIG DN
M101
FIRST FLOOR MECHANICAL
PLAN
RESPONSIBLE FOR REVIEWING ACTUAL SITE CONDITIONS AND COORDINATING
WORK AREA SHALL BE SCHEDULED WITH OWNER, WITH MINIMUM OF 48 HOURS
NOTICE PRIOR TO SHUTDOWN. SHUTDOWNS IMPACTING HEATING OR COOLING OF
1 PROVIDE CONNECTING PIPE IN PLACE OF DEMOLISHED PRV, MATCH
EXISTING PIPE SIZE.
FIRST FLOOR MECHANICAL PLAN
BB57
BB59
BB60
BB58
BB56
BB55
224B
228A
211A
3" STM-12 PSIG DN
5" STM-12 PSIG DN
3 1/2" STM-25 PSIG
-9
3 1/2" STM-25 PSIG DN
5" STM-90 PSIG DN
2" STM-90 PSIG
15 PSI STEAM
TO AHUS IN
295A
2" STM-25 PSIG15
AHU-240
STEAM GENERATOR
STM-12 PSIG15
1 1/2" STM-25 PSIG15
STEAM PIPING TO
HEAT EXCHANGER
M102
MECHANICAL PLAN
RESPONSIBLE FOR REVIEWING ACTUAL SITE CONDITIONS AND COORDINATING
WORK AREA SHALL BE SCHEDULED WITH OWNER, WITH MINIMUM OF 48 HOURS
NOTICE PRIOR TO SHUTDOWN. SHUTDOWNS IMPACTING HEATING OR COOLING OF
1 PROVIDE CONNECTING PIPE IN PLACE OF DEMOLISHED PRV, MATCH
EXISTING PIPE SIZE.
SECOND FLOOR MECHANICAL PLAN
8" STM-25 PSIG
-1
8" STM-25 PSIG15
ISU CAMPUS UTILITY
DISTRIBUTION TUNNEL
EXISTING CORRUGATED
WALL PANEL SYSTEM
EXP-1
EXISTING ANCHOR,
TO REMAIN
EXP-1
FIRST GUIDE SECOND GUIDE
2'-0" MAX 2'-0" MAX 7'-0" MAX
ADDITIONAL
GUIDES (TYP.)
48'-0" MAX 6" STM-90 PSIG
NOTES:
1. GUIDE SPACING SHOWN IS RECOMMENDED BY MANUFACTURER.
2. CONTRACTOR TO VERIFY LOCATION AND SPACING OF ANY EXISTING GUIDES AND REPORT TO
ENGINEER.
3. ESTIMATED LENGTH BETWEEN ANCHORS IS 125'. QUANTITY OF REQUIRED GUIDES IS 5. FROM THE
SECOND GUIDE TO THE ANCHOR LOCATED NEAREST METALS DEVELOPMENT, SPACE ALL ADDITIONAL
GUIDES EVENLY.
-12' - 9"
B.O. ELEV. SHAFT
-5' - 0"
FIRST FLOOR
0' - 0"
BYPASS
PRV-1
PRV-2
NCNC
NO NO
5" 6"
6"
ST-1
ST-2
M600
(TYP.)
8" STM-15 PSIG
6" STM-15 PSIG
-12' - 9"
B.O. ELEV. SHAFT
-5' - 0"
0' - 0"
5" STM-12 PSIG
5" STM-90 PSIG
6" STM-90 PSIG3"
EXISTING ANCHOR
TO REMAIN
ENLARGED MECHANICAL
PLANS
1/4" = 1'-0"
ENLARGED MECHANICAL ROOM PLAN
0 4' 8'2'
ENLARGED BASEMENT FLOOR MECHANICAL PLAN - TUNNEL
0 4' 8'2'
STEAM EXPANSION DEVICE - TUNNEL SECTION - NEW WORK
PRV STATION - NEW WORK
PRV STATION - DEMOLITION
STEAM EXPANSION DEVICE - TUNNEL SECTION - DEMOLITION
1 DEMOLISH EXISTING EXPANSION FITTING AND DOWNSTREAM PIPING AS
NEEDED FOR NEW EXPANSION DEVICE
2 PROVIDE LINE SIZE VALVE AND CAP FOR FUTURE CONNECTION TO STEAM
TURBINE
3 DRIP LEGS AND BLOWDOWNS ARE NOT ALL SHOWN. CONTRACTOR TO
PROVIDE ADDITIONAL DRIP LEG TRAP AS NEEDED TO PREVENT WATER
HAMMER.
4 PROVIDE NEW PIPE GUIDES FOR STEAM PIPING. REFER TO DETAIL 6 ON THIS
SHEET FOR MORE REQUIREMENTS.
5 NEW SAFETY RELIEF VALVE. CONNECT OUTLET PIPING TO EXISTING 4"
RELIEF VENT PIPING.
6 EXISTING 90-25 PSIG 2/3 PRV.
7 EXISTING 90-25 PSIG 1/3 PRV.
8 EXISTING 90-12 PSIG PRV.
9 VALVE AND CAP EXISTING 5" 90-PSIG PIPING.
10 APPROXIMATE LOCATION OF EXISTING PIPE ANCHOR. CONTRACTOR TO
CONFIRM AFTER REMOVAL OF WALL PANEL.
11 NEW "BUILDING SIDE" STEAM ISOLATION VALVE.
12 EXISTING PIPE ANCHOR, TO REMAIN. ESTIMATED DISTANCE BETWEEN
ANCHORS IS 125'.
RESPONSIBLE FOR REVIEWING ACTUAL SITE CONDITIONS AND COORDINATING
WORK AREA SHALL BE SCHEDULED WITH OWNER, WITH MINIMUM OF 48 HOURS
NOTICE PRIOR TO SHUTDOWN. SHUTDOWNS IMPACTING HEATING OR COOLING OF
TEST VALVE
SHUT-OFF VALVE
CHECK VALVE
UNION
STRAINER WITH
BLOWDOWN VALVE
STEAM
TRAP (IB)
NOTE:
STRAINER TO BE INSTALLED WITH DRAIN LEG LEVEL WITH COND PIPE.NOTE:
FIGURE NUMBERS ARE TYPICAL TO GRINNELL SUPPORT NUMBERS.
HANGER ROD ATTACHED TO
STRUCTURE ABOVE
PROVIDE RIB-LOCK INSULATION
PROTECTION SHIELD (FIGURE 168) FOR
INSULATED PIPING
(FIGURE CT-65 FOR COPPER TUBING)
PIPE INSULATION
NON-INSULATED
PIPE
INSULATED
CLEVIS HANGER
(PROVIDE OVERSIZED HANGER FOR
INSULATED PIPING)
TYPE 1
ADJUSTABLE CLEVIS
HANGER
(FIGURE 260)
TYPE 1
ADJUSTABLE CLEVIS
HANGER
(FIGURE 260)
INTERIOR
PIPE WITH OR
WITHOUT
INSULATION
CAULK AND SEAL
ANNULAR SPACE
BETWEEN PIPE AND
SLEEVE
1. TYPICAL FOR NON-INSULATED PIPE AND CONDUIT.
2. ALL CAULKING AND SEALANT SHALL BE FIRE RATED (SEE
SPECIFICATIONS).
3. WHERE PIPING IS EXPOSED AT FINISHED WALL, FLUSH MOUNT
SLEEVE AND PROVIDE AN ESCUTCHEON PLATE.
SCH 40 GALV STEEL
SLEEVE SECURED TO
PARTITION
TYPE 39A, 39B, 40A & 40B PIPE
INSULATION PROTECTION SADDLE.
(FIGURE 160-165)
TYPE 34
SIDE BEAM BRACKET
(FIGURE 202)
TYPE 31 - LIGHT
TYPE 32 - MEDIUM
TYPE 33 - HEAVY
WELD STEEL BRACKET
(FIGURE 193, 194, 195, 99)
NOTE:
FIGURE NUMBERS ARE TYPICAL TO
GRINNELL SUPPORT NUMBERS.
TYPE 41
SINGLE PIPE
ROLLER
(FIGURE 171)
TYPE 43
SINGLE PIPE
ROLLER
(FIGURE 181)
INSULATION THICKNESS
1. SUPPORT PIPE WITH HANGERS OR ROLLERS SO THAT GUIDE DOES
NOT SUPPORT PIPE LOAD.
PIPE OUTSIDE
RADIUS +2"
STAINLESS STEEL ANCHOR BOLT
BOLTS OT BE 4-6" LONG, USE
LARGEST BOLT THAT IS SMALLER
THAN BOLT HOLE
304 STAINLESS STEEL FEET
AS REQ'D
FIELD CUT TO LENGTH
FACTORY FABRICATE
HYSPAN SERIES 9500
OR APPROVED EQUAL
CARBON STEEL GUIDE
1. AIR TUBING: 1/4" 0. D. COPPER, ASTM B75 FULLY ANNEALED WITH 0.028" MIN. WALL. BRASS FITTINGS AND VALVES WITH FLARELESS CONNECTIONS.
2. STEAM TUBING: 3/8" O. D. COPPER, ASTM B75 FULLY ANNEALED WITH 0.035” MIN. WALL. BRASS FITTINGS AND VALVES WITH FLARELESS CONNECTIONS.
3. PRESSURE SENSING LOCATIONS SHALL BE LOCATED A MINIMUM OF 48" DOWNSTREAM OF BYPASS RECONNECTION. LOCATIONS SHALL BE APPROVED BY OWNER.
4. BUTTERFLY VALVE.
5. PROVIDE PIGTAIL SIPHON LOOP FOR ALL PRESSURE SENSING LINES.
6. PRESSURE GAUGE SHALL BE ASHCROFT #45-1279-A-04L-0/30
7. PRESSURE SENSOR FURNISHED BY JOHNSON CONTROLS INC.
8. STEAM RELIEF DRIP PAN ELBOW. PIPE TO NEAREST FLOOR DRAIN.
9. CONTROL PRV FURNISHED BY OWNER, INSTALLED BY CONTRACTOR.
10. BYPASS LINE WITH GLOBE VALVE. BYPASS LINE PRV (PRV-2) TO BE OWNER FURNISHED, CONTRACTOR INSTALLED.
11. PROVIDE DRIP LEG WITH TRAP ASSEMBLY AT LOW POINTS.
12. STRAINER WITH BLOWDOWN SHALL BE INSTALLED WITH DRAIN LEG LEVEL WITH PIPING.
90 PSIG
UNION (TYP)
NC
NO NO
PRV-1
PRV-2
15 PSIG
REDUCER (TYP)
(TYP.)
NC
30" MIN.
48" MIN.
SAFETY RELIEF VALVE
MECHANICAL DETAILS AND
SCHEDULES
EXP-1 TUNNEL 4 6 METRAFLEX METRAGATOR
MANUFACTURER MODEL
DESIGNATION LOCATION
COMPRESSION
CAPACITY (IN)
PIPE SIZE (IN)
BASIS OF DESIGN
NOTES
STEAM EXPANION FITTING SCHEDULE
3. PRV IS OWNER FURNISHED, CONTRACTOR INSTALLED.
2. PROVIDE WITH THE FOLLOWING ACCESSORIES: INLET AND OUTLET PRESSURE GAUGES, REMOVABLE INSULATION JACKETS, AND INLETS STRAINERS.
1. CAPACIITES BASED ON CONDITIONS INDICATED IN SCHEDULE.
PRV-2 MECH-BB16 - - 2 6 90 6 15 FISHER 92B-81 2, 3
PRV-1 MECH-BB16 1000 4200 2 6 90 6 15 FISHER ES WHISPER III-667 SIZE 40i-C1 1, 2,3
PIPE DIAMETER (IN) PRESSURE (PSIG) PIPE DIAMETER (IN) PRESSURE (PSIG) MANUFACTURER MODEL
MIN CAPACITY
(LBS/HR)
MAX CAPACITY (LBS/HR) VALVE SIZE (IN)
INLET OUTLET BASIS OF DESIGN
STEAM PRESSURE REDUCING VALVE SCHEDULE
ST-2 MECH-BB16 ARMSTRONG 800 IB 400 3/4 7/64
ST-1 MECH-BB16 ARMSTRONG 800 IB 400 3/4 7/64
TYPE
MIN.
CAPACITY...
INLET/OUTLET
DIAMETER (IN.)
ORIFICE SIZE (IN) NOTES
STEAM TRAP SCHEDULE
NOT TO SCALE
STEAM TRAP PIPING DETAIL
SINGLE PIPE CLEVIS HANGER
PIPE PENETRATION THRU INTERIOR WALLS
SINGLE PIPE CLEVIS HANGER
2-1/2" AND LARGER SCHEDULE 80, TYPE E, BLACK STEEL, ASTM A106, GRADE B WELDED OR FLANGED CLASS 150, WROUGHT-STEEL FIBERGLASS 4" AND LARGER 3 ASJ-SSL (FACTORY APPLIED)
STC STEAM CONDENSATE ALL
2" AND SMALLER
INTERIOR - ABOVE GRADE
SCHEDULE 80, TYPE S, BLACK STEEL, ASTM A106, GRADE B THREADED CLASS 125, MALLEABLE IRON FIBERGLASS 3" AND SMALLER 2 1/2 ASJ-SSL (FACTORY APPLIED)
2-1/2" AND LARGER SCHEDULE 40 TYPE E BLACK STEEL, ASTM A106, GRADE B WELDED OR FLANGED CLASS 150, WROUGHT STEEL FIBERGLASS 2" AND LARGER 4 1/2 ASJ-SSL (FACTORY APPLIED)
STM STEAM ALL
2" AND SMALLER
INTERIOR - ABOVE GRADE
SCHEDULE 40 TYPE S BLACK STEEL, ASTM A106, GRADE B THREADED CLASS 125, MALLEABLE IRON FIBERGLASS 1 1/2" AND SMALLER 4 ASJ-SSL (FACTORY APPLIED)
SYSTEM
DESIGNATION
SYSTEM DESCRIPTION SYSTEM PRESSURE PIPE SIZE RANGE (IN.) LOCATION PIPING MATERIAL CONNECTION TYPE(S) FITTINGS INSULATION TYPE PIPE SIZE RANGE (IN.)
THICKNESS (IN)
JACKETING NOTES
MECHANICAL PIPING MATERIAL AND INSULATION SCHEDULE
SPIDER TYPE PIPE ALIGNMENT GUIDE
NO SCALE
STEAM PRV STATION DETAIL
2. MODULATING PILOT TYPE, CS MAIN VALVE BODY, SS PILOT VALVE & TRIM, PTFE MAIN VALVE SEAT & SEALS, PEEK PILOT SEAT, PTFE PILOT SEALS & DIAPHRAGM, PLAIN LIFT LEVER, ASME SECTION VIII/XIII...
1. CAPACIITES BASED ON CONDITIONS INDICATED IN SCHEDULE.
SRV-1 MECH-BB16 6400 3 4 25 ANDERSON GREENWOOD 54605L34/S1 1, 2
RATED CAPACITY
(LBS/HR)
INLET DIAMETER
(IN)
OUTLET DIAMETER
(IN)
PRESSURE SETTING
(PSIG)
STEAM RELIEF VALVE SCHEDULE
12 PSI
25 PSI
90 PSI
12 PSI STEAM TO HEATING
HOT WATER HEAT EXCHANGER
IN ROOM 240
ROOF
AHU HUMIDIFIER
PRV STATION #3
AHU IN
12 PSI
90 PSI FROM TUNNEL
PRV STATION #1
90 PSI
12 PSI STEAM
TO AHU-240
PRV STATION #4
DWH
PRV STATION #2
5 PSI STEAM TO
PRV STATION #5
AHU-282 25 PSI
15 PSI
15 PSI STEAM TO HEATING
HOT WATER HEAT EXCHANGER
ROOF
15 PSI STEAM TO
AHU HEATING
COIL IN ROOM 240
90 PSI FROM TUNNEL
NEW PRV STATION #1
PREHEAT
AND HUM.
15 PSI STEAM
TO AHU-240
DWH
PROVIDE LINE SIZE VALVE AND
CAP FOR FUTURE CONNECTION
TO STEAM TURBINE
NEW PRV
RELOCATED PRV
ON BYPASS LINE
M700
STEAM RISER DIAGRAMS
STEAM RISER DIAGRAM - DEMOLITION
STEAM RISER DIAGRAM - NEW WORK
Sheets
G000 - TITLE SHEET
M000 - MECHANICAL SYMBOLS AND ABBREVIATIONS
M100 - BASEMENT FLOOR MECHANICAL PLAN
M101 - FIRST FLOOR MECHANICAL PLAN
M102 - SECOND FLOOR MECHANICAL PLAN
M400 - ENLARGED MECHANICAL PLANS
M600 - MECHANICAL DETAILS AND SCHEDULES
M700 - STEAM RISER DIAGRAMS
MD100 - BASEMENT FLOOR MECHANICAL DEMO PLAN
MD101 - FIRST FLOOR MECHANICAL DEMO PLAN
MD102 - SECOND FLOOR MECHANICAL DEMO PLAN
PROJECT MANUAL FOR
RFP# SC-27-724
STEAM REPLACEMENT
Ames National Laboratory
2408 Pammel Dr
Ames, IA 50011
(515) 294-3483
Resource Consulting Engineers
301 Alexander Avenue, Suite C
Ames, Iowa 50010
Issued: November 24, 2026
BID ISSUE
This page intentionally left blank
SC-27-724 Ames National Laboratory Metals Development Steam Replacement 00 0101 - 1
PROJECT TITLE PAGE
11-24-2026
SECTION 00 0101
PROJECT TITLE PAGE
PROJECT MANUAL
FOR
METALS DEVELOPMENT BUILDING STEAM REPLACEMENT
ENGINEER'S PROJECT NUMBER: 2026.013.00.
OWNER'S PROJECT NUMBER: SC-27-724.
OWNER: AMES NATIONAL LABORATORIES
2408 PAMMEL DR.
AMES, IOWA 50011
DATE: 11-24-2026
PREPARED BY:
RESOURCE CONSULTING ENGINEERS. LLC
END OF SECTION
Metals Development Steam Replacement 00 0102 - 1
INFORMATION
SECTION 00 0102
PROJECT INFORMATION
PART 1 GENERAL
1.01 PROJECT IDENTIFICATION
A. Project Name:Metals Development Building Steam Replacement, located at:
1. 2408 Pammel Dr.
2. Ames, Iowa, 50011.
B. Engineer's Project Number: 2026.013.00.
C. Owner's Project Number: SC-27-724.
D. The Owner, hereinafter referred to as Owner:
E. Owner's Project Manager: Kelsey Lindemann.
1. Title: Manager of Construction Projects.
2. 2408 Pammel Dr.
3. Ames, Iowa, 50011.
4. E-mail: kelseym@ameslab.gov.
1.02 NOTICE TO PROSPECTIVE BIDDERS
A. These documents constitute an Invitation to Bid to a Single-Prime Contractor or General
Contractor for the construction of the project described below.
1.03 PROJECT DESCRIPTION
A. Summary Project Description: The project consists of providing construction services required for the repair, replacement, and upgrade of the steam piping and associated equipment serving the Metals Development Building.
B. Contract Scope: Construction and demolition.
C. Contract Terms: Lump sum (fixed price, stipulated sum).
1.04 PROJECT CONSULTANTS
A. The Engineer, hereinafter referred to as Engineer: Resource Consulting Engineers, LLC .
1. Address: 301 Alexander Ave., Suite C.
2. City, State, Zip: Ames, IA 50010.
3. Phone/Fax: (515) 292-2500.
4. E-mail: chuck.heldenbrand@resourcece.com.
1.05 PROCUREMENT TIMETABLE
A. Pre-Proposal Briefing: December 7th, 2026 at 1:30 PM.
B. Pre-Proposal Site Tour: December 7th, 2026, immediately following briefing.
C. Last Request for Substitution Due: December 14th, 2026.
D. Last Request for Information Due: December 14th, 2026.
E. Proposal Due Date: January 8, 2027, 4 PM local time.
F. Notice of Intent to Award: Within 14 days of award execution.
G. Proposals May Not Be Withdrawn Until: 30 days after due date.
H. Contract Time: To be stated in bid documents.
I. Desired Construction Start date: Late-Spring 2027 J. Desired Final Completion Date: Not later than 120 calendar days from Notice of Award.
Metals Development Steam Replacement 00 0102 - 2
INFORMATION
K. The Owner reserves the right to change the schedule or terminate the entire procurement process at any time.
1.06 PROCUREMENT DOCUMENTS
A. Availability of Documents: Complete sets of procurement documents may be obtained:
1. From Owner at the Project Manager's address listed above.
B. Documents are on display at the offices of the following construction plan rooms:
1. Greater Fort Dodge Growth Alliance, 24 North 9th Street, Suite A, Fort Dodge, IA 50501
2. Dodge Data & Analytics Planroom, 4300 Beltway Place, Suite150, Arlington,TX 76018, 413-507-0211
3. Des Moines Construction Update Plan Room Network (Master Builders of Iowa), 4100
Westown Pkwy, West Des Moines, IA 50266
4. Bid+Builders Exchange, 4814 E. Broadway, Madison, WI 53716
5. Minnesota Builders Exchange, 1123 Glenwood Avenue, Minneapolis, MN 55405
6. Omaha Builders Exchange, 4255 South 94th Street, Omaha, NE 68127
1.07 BID SECURITY
A. Bids shall be accompanied by a bid bond as follows:
1. Security made payable to Owner in an amount of five percent of proposer's maximum proposal price.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
Metals Development Steam Replacement 00 0103 - 1
PROJECT DIRECTORY
SECTION 00 0103
PROJECT DIRECTORY
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Identification of project team members and their contact information.
1.02 OWNER:
A. Name: Ames National Laboratories
1. Address Line 1: 2408 Pammel Dr..
2. City: Ames .
3. State: Iowa .
4. Zip Code: 50011 .
B. Primary Contact: All correspondence from the Contractor to the Owner will be through this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.
1. Owner's Contact: Kelsey Lindemann
2. Title: Manager of Construction Projects.
3. Email: kelseym@ameslab.gov
1.03 CONSULTANTS:
A. Engineer: Design Professional of Record. All correspondence from the Contractor regarding construction documents authored by Engineer's consultants will be through this party, unless alternate arrangements are mutually agreed upon at preconstruction meeting.
1. Company Name: Resource Consulting Engineers. LLC.
a. Address: 301 Alexander Ave., Suite C
b. City: Ames.
c. State: Iowa.
d. Zip Code: 50010.
e. Telephone: (515) 292-2500.
2. Primary Contact:
a. Title: Sr. Engineer.
b. Name: Chuck Heldenbrand, PE.
c. Email: chuck.heldenbrand@resourcece.com.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
Metals Development Steam Replacement 00 0107 - 1
SEALS PAGE
SECTION 00 0107
SEALS PAGE
kortney.morgan
Image kortney.morgan
Text Box
Metals Development Steam Replacement 00 0110 - 1
TABLE OF CONTENTS
SECTION 00 0110
PROCUREMENT AND CONTRACTING REQUIREMENTS
1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
A. 00 0101 - Project Title Page B. 00 0102 - Project Information C. 00 0103 - Project Directory D. 00 0107 - Seals Page E. 00 0110 - Table of Contents F. 00 0115 - List of Drawing Sheets G. 00 1000 - Procurement and Contract Requirements H. 00 2000 - Supplementary Conditions I. 00 3000 - Special Conditions
J. 00 4100 - APPENDIX L - PROPOSAL FORM
SPECIFICATIONS
2.01 DIVISION 01 -- GENERAL REQUIREMENTS
A. 01 1000 - Summary B. 01 2000 - Price and Payment Procedures C. 01 2500 - Substitution Procedures D. 01 3000 - Administrative Requirements E. 01 3216 - Construction Progress Schedule F. 01 4000 - Quality Requirements G. 01 4200 - References H. 01 5500 - Vehicular Access and Parking I. 01 6000 - Product Requirements J. 01 7000 - Execution and Closeout Requirements K. 01 7419 - Construction Waste Management and Disposal L. 01 7800 - Closeout Submittals M. 01 7900 - Demonstration and Training
2.02 DIVISION 02 -- EXISTING CONDITIONS
A. 02 4100 - Demolition
2.03 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
A. 23 0516 - Expansion Fittings and Loops for HVAC Piping B. 23 0517 - Sleeves and Sleeve Seals for HVAC Piping C. 23 0519 - Meters and Gauges for HVAC Piping D. 23 0523 - General-Duty Valves for HVAC Piping E. 23 0529 - Hangers and Supports for HVAC Piping and Equipment F. 23 0553 - Identification for HVAC Piping and Equipment G. 23 0719 - HVAC Piping Insulation
Metals Development Steam Replacement 00 0110 - 2
H. 23 0913 - Instrumentation and Control Devices for HVAC I. 23 2213 - Steam and Condensate Heating Piping J. 23 2214 - Steam and Condensate Heating Specialties
Metals Development Steam Replacement 00 0115 - 1
LIST OF DRAWING
SHEETS
SECTION 00 0115
LIST OF DRAWING SHEETS
1.01 LIST OF DRAWINGS
A. Drawings: Drawings consist of the Contract Drawings and other drawings listed in the Table of
Contents on the Title Sheet of the separately bound drawing set titled Ames National Laboratories - Metals Development Building Steam Replacement, dated 11-24-2026, as modified by subsequent Addenda and Contract modifications.
B. List of Drawings: Drawings consist of the following Contract Drawings and other drawings of type indicated:
1. G000 COVER SHEET
2. M000 MECHANICAL SYMBOLS AND ABBREVIATIONS
3. MD100 BASEMENT FLOOR MECHANICAL DEMO PLAN
4. MD101 FIRST FLOOR MECHANICAL DEMO PLAN
5. MD102 SECOND FLOOR MECHANICAL DEMO PLAN
6. M100 BASEMENT FLOOR MECHANICAL PLAN
7. M101 FIRST FLOOR MECHANICAL PLAN
8. M102 SECOND FLOOR MECHANICAL PLAN
9. M400 ENLARGED MECHANICAL PLANS
10. M600 MECHANICAL DETAILS AND SCHEDULES
11. M700 STEAM RISER DIAGRAMS
Metals Development Steam Replacement
PROCUREMENT AND
CONTRACTING REQUIREMENTS
00 1000 - 1
SECTION 00 1000
PROCUREMENT AND CONTRACTING REQUIREMENTS
TABLE OF ARTICLES
A. GENERAL PROVISIONS
B. OWNER
C. CONTRACTOR
D. ADMINISTRATION OF THE CONTRACT
E. SUBCONTRACTORS
F. CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
G. CHANGES IN THE WORK
H. TIME
I. PAYMENTS AND COMPLETION
J. UNCOVERING AND CORRECTION OF WORK
K. MISCELLANEOUS PROVISIONS
ARTICLE 1 - GENERAL PROVISIONS
1.01 BASIC DEFINITIONS
A. THE CONTRACT DOCUMENTS
1. The Contract Documents consist of the Agreement between Owner and Contractor (hereinafter the Agreement), conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, addenda issued prior to execution of the Contract, and any other documents listed in the Agreement and Modifications issued after execution of the Contract. A Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive or (4) a written order for a minor change in the Work.
B. THE CONTRACT
1. The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Design Professional and Contractor, (2) between the Owner and a Subcontractor or Sub-subcontractor or (3) between any persons or entities other than the Owner and Contractor.
C. THE WORK
1. The term "Work" means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor's obligations. The Work may constitute the whole or a part of the Project.
D. THE PROJECT
00 1000 - 2
1. The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner or by separate contractors.
E. THE DRAWINGS
1. The Drawings are the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules and diagrams. Drawings are intended to show general arrangements, design, and dimensions of work and are partly diagrammatic. Dimensions shall not be determined by scale or rule. If figured dimensions are lacking, they shall be supplied by the Design Professional on the Contractor’s written request to the Owner’s Representative.
F. THE SPECIFICATIONS
1. The Specifications are that portion of the Contract Documents consisting of the written requirements for materials, equipment, construction systems, standards and workmanship for the Work, and performance of related services.
G. THE PROJECT MANUAL
1. The Project Manual is the volume usually assembled for the Work which may include the bidding requirements, sample forms, Conditions of the Contract and Specifications.
H. THE DESIGN PROFESSIONAL
1. The Design Professional is an entity engaged by the Owner to provide professional design services for the Project.
I. THE OWNER
1. The Owner is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The term "Owner" means the Ames Laboratory at Iowa State University or the Laboratory’s authorized representative.
J. THE CONTRACTOR
1. The Contractor is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The term "Contractor" means the Contractor or the Contractor's authorized representative.
K. THE SUBCONTRACTOR
1. A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of the Work at the site. The term "Subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor. The term "Subcontractor" does not include a separate contractor or subcontractors of a separate contractor.
L. THE SUB-SUBCONTRACTOR
1. A Sub-subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to perform a portion of the Work at the site. The term "Sub-subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Sub-subcontractor or an authorized representative of the Sub-subcontractor.
M. PUNCH LIST
1. The term “punch list” shall mean the list of items prepared in connection with the inspection of the Project by the Owner’s Representative and/or Design Professional in connection with Substantial Completion of the Work or a portion of the Work which the Owner’s Representative and/or Design Professional has designated as remaining to be performed, completed or corrected before the Work will be accepted by the Owner.
1.02 EXECUTION, CORRELATION AND INTENT
A. Execution of the Contract by the Contractor is a representation that the Contractor has visited the site, become familiar with local conditions under which the Work is to be performed and
00 1000 - 3 correlated personal observations with requirements of the Contract Documents. The Contractor represents that it has performed its own investigation and examination of the Work site and its surroundings and satisfied itself before entering into this Contract as to:
1. conditions bearing upon transportation, disposal, handling, and storage of materials;
2. the availability of labor, materials, equipment, water, electrical power, utilities and roads;
3. conditions bearing upon security and protection of material, equipment, and Work in progress;
4. the extent of the Work site, including the surface and sub-surface conditions;
5. the extent and nature of Work and materials necessary for the execution of the Work; and,
6. the means of access to the site and the accommodations it may require.
The Owner assumes no responsibility or liability for the physical condition or safety of the Work site or any improvements located on the Work site. The Contractor shall be solely responsible for providing a safe place for the performance of the Work. The Owner shall not be required to make any adjustment in either the Contract Sum or Contract Time concerning any failure by the Contractor or any Subcontractor to comply with the requirements of this Paragraph.
B. The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all; performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the intended results.
C. Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade.
D. Unless otherwise stated in the Contract Documents, words which have well-known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings.
E. Data in the Contract Documents concerning lot size, ground elevations, present obstructions on or near the site, locations and depths of sewers, conduits, pipes, wires, etc., position of sidewalks, curbs, pavements, etc., and nature of ground and subsurface conditions have been obtained from sources the Design Professional believes reliable. The Contractor shall verify such data to the extent possible through normal construction procedures, including but not limited to, contacting utility owners and by prospecting after receiving Notice of Award.
1.03 OWNERSHIP AND USE OF DRAWINGS, SPECIFICATIONS AND OTHER DOCUMENTS
A. All Drawings, Specifications and other documents, and copies thereof, are and shall remain the Owner's property. They are not to be reproduced or used on any other project.
ARTICLE 2 - OWNER
2.01 INFORMATION AND SERVICES REQUIRED OF THE OWNER
A. The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the Project.
B. Except for permits and fees which are the responsibility of the Contractor under the Contract Documents, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities.
C. Information or services under the Owner's control shall be furnished by the Owner with reasonable promptness to avoid delay in orderly progress of the Work.
D. Unless otherwise provided in the Contract Documents, the Contractor will be furnished, free of charge, such copies of Drawings and Project Manuals as are reasonably necessary for execution of the Work.
00 1000 - 4
E. The foregoing are in addition to other duties and responsibilities of the Owner enumerated herein and especially those in respect to Article 6 (Construction by Owner or by Separate Contractors), Article 9 (Payments and Completion).
2.02 OWNER'S RIGHT TO CARRY OUT THE WORK
A. If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a seven-day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from payments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation for additional services and expenses made necessary by such default, neglect or failure. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner.
ARTICLE 3 - CONTRACTOR
3.01 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
A. The Contractor shall carefully study and compare the Contract Documents with each other and with information furnished by the Owner and shall at once report to the Owner errors, inconsistencies or omissions discovered. The Contractor shall not be liable to the Owner for damage resulting from errors, inconsistencies or omissions in the Contract Documents unless the Contractor recognized such error, inconsistency or omission and knowingly failed to report it to the Owner. If the Contractor performs any construction activity knowing it involves a recognized error, inconsistency or omission in the Contract Documents without such notice to the Owner, the Contractor shall assume appropriate responsibility for such performance and shall bear an appropriate amount of the attributable costs for correction.
B. The Contractor shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions and other information known to the Contractor with the Contract Documents before commencing activities. Errors, inconsistencies or omissions discovered shall be reported to the Owner at once.
C. Figured dimensions on the Plans shall be used in preference to scaling the Drawings. If Contractor scales Drawings, dimensions so obtained shall be the sole responsibility of the Contractor.
D. Where the Work of the Contractor is affected by finish dimensions of manufacturer's equipment, the finish dimensions shall be determined by the Contractor, who shall assume the responsibility for proper coordination.
E. During the progress of work, the Contractor shall verify all field measurements prior to fabrication of building components or equipment, and proceed with the fabrication to meet field conditions. The Contractor shall consult all Contract Documents to determine the exact location of all work and verify spatial relationships of all work. Any question concerning said location or spatial relationships, shall be submitted to the Owner’s Representative and Design Professional. Specific locations for equipment, pipelines, ductwork and other such items of work, where not dimensioned on plans, shall be determined in consultation with Owner’s Representative and Design Professional. The Contractor shall be responsible for the proper fitting of Work in place.
3.02 SUPERVISION AND CONSTRUCTION PROCEDURES
A. The Contractor shall supervise and direct the Work, using the Contractor's best skill and attention. The Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless Contract Documents give other specific instruction concerning these matters.
00 1000 - 5
B. The Contractor shall be responsible to the Owner for acts, defaults and omissions of the Contractor's employees, Subcontractors and their agents and employees, and other persons performing portions of the Work under a contract with the Contractor.
C. The Contractor shall not be relieved of obligations to perform the Work in accordance with the Contract Documents either by activities or duties performed in the administration of the Contract, or by tests, inspections or approvals required or performed by persons other than the
D. The Contractor shall be responsible for inspection of portions of the Work already performed under this Contract to determine that such portions are in proper condition to receive subsequent work.
E. The Contractor shall perform the Work so as to cause a minimum of inconvenience to and interruption of the Owner's operations. Any and all interruptions of the operations of the Owner necessary for the performance of the Work shall be noted in the progress schedule and the Contractor shall additionally give the Owner sufficient advance notice of such interruptions as to allow the Owner time to adjust its operations accordingly. Contractor's failure to give the Owner timely notice of such intentions shall place the responsibility for any resulting delays, additional costs, or other liabilities solely with the Contractor.
F. The Contractor shall forward all communications to the Owner through the Owner's Representative.
G. Prior to commencing the Work under the Contract, the Contractor shall contact all affected entities supplying utilities and arrange for the moving of such utility installations as is necessary for the performance of the Work. It shall be the responsibility of the Contractor to coordinate the Work with that of the affected entities in such a manner as to cause the least possible interference.
3.03 TAXES
A. Except when sales tax exemption certificates are provided by the Owner in accordance with Paragraph 3.03 B, the Contractor shall pay sales, consumer, use and similar taxes for the Work or portions thereof provided by the Contractor which are legally enacted when bids are received or negotiations concluded, whether or not yet effective or merely scheduled to go into effect.
B. Iowa Construction Sales Tax Exemption Certificates and authorization letters will be provided by the Owner to the Contractor and Subcontractors for use on this project in accordance with the regulations of the Iowa Department of Revenue and Finance. This exemption certificate will authorize suppliers to sell construction materials that will be incorporated into and made part of the Work exempt from Iowa sales tax and any applicable local option sales tax and school infrastructure local option sales tax. Complete information on qualifying materials can be found on the Iowa Department of Revenue and Finance web site at www.state.ia.us/tax. It is the responsibility of the Contractor and Subcontractors to maintain records identifying the materials purchased and verifying they were used on this project. Any materials purchased tax-free and not used on the project are subject to sales and local option taxes and these taxes must be paid directly to the Iowa Department of Revenue and Finance.
3.04 PERMITS, FEES AND NOTICES
A. Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for permits and governmental fees, licenses and inspections necessary for proper execution and completion of the Work which are customarily secured after execution of the Contract and which are legally required when proposals are received or negotiations concluded.
B. All construction under this contract shall conform to the requirements of the Iowa State Building Code. The provisions of the Iowa State Building Code will be strictly adhered to and will take precedence over local governmental bodies’ regulations. Work not regulated by the Iowa State Building Code shall be performed in accordance with other applicable local regulations. The
00 1000 - 6
Contractor shall…