This document is a detailed project schedule for the DAS Wallace Demolition project for the State of Iowa, covering the complete demolition process of the Wallace Building within the Capitol Complex. The project timeline spans from June 2025 to May 2026 and includes multiple critical phases: preconstruction, consultant selection, hazardous materials assessment, design development, bid letting for abatement and demolition, construction administrative tasks, and project closeout. Key milestones include design consultant procurement (June-July 2025), hazardous materials assessment and report (June-August 2025), design development stages with multiple design review meetings, bid lettings for abatement (September-October 2025) and demolition (October-November 2025), and construction activities from October 2025 to April 2026.
The project involves comprehensive demolition activities, including hazardous materials abatement, utility disconnections, building and foundation removal, and site improvements. Administrative requirements include notifications to the DNR (Department of Natural Resources) and Iowa Division of Labor for asbestos abatement. The demolition scope encompasses complete removal of the building, foundations, and tunnels, followed by site backfill, temporary stabilization, and final site improvements with sodding. The project concludes with owner punch list reviews, training, and occupancy in May 2026, demonstrating a methodical and structured approach to a complex demolition project within a state government complex.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# Remaining Duration
Start Finish Activity Name
1 9478.00 DAS Wallace Demolition9478.00 DAS Wallace Demolition9478.00 DAS Wallace Demolition9478.00 DAS Wallace Demolition 2 PreconstructionPreconstructionPreconstructionPreconstruction 3 Consultant SelectionConsultant SelectionConsultant SelectionConsultant Selection 4 Design ConsultantDesign ConsultantDesign ConsultantDesign Consultant
5 13 11-Jun-25 27-Jun-25 RFP Procurement
6 0 17-Jun-25 Pre-Proposal Meeting #01
7 0 20-Jun-25 Pre-proposal Meeting #02
8 0 23-Jun-25 Questions Due - RFP
9 0 25-Jun-25 Final Addendum - RFP
10 0 27-Jun-25 RFPs Due
11 2 30-Jun-25 01-Jul-25 RFP Evaluation
12 0 02-Jul-25 Designer NOI
13 5 02-Jul-25 09-Jul-25 Designer 5 Day Appeal Period
14 8 02-Jul-25 14-Jul-25 Design Contract Execution
15 Hazardous Materials ConsultantHazardous Materials ConsultantHazardous Materials ConsultantHazardous Materials Consultant
16 10 12-Jun-25 25-Jun-25 Hazardous Materials Consultant Procurement (MA)
17 0 13-Jun-25 NOI
18 5 13-Jun-25 19-Jun-25 Contract Execution
19 Wallace BuildingWallace BuildingWallace BuildingWallace Building 20 Wallace PreconstructionWallace PreconstructionWallace PreconstructionWallace Preconstruction 21 DesignDesignDesignDesign
22 40 20-Jun-25 15-Aug-25 Hazardous Materials Assessment & Report
23 0 15-Jul-25 Design Kick-Off Meeting
24 2 15-Jul-25 16-Jul-25 Onsite Investigation
25 30 17-Jul-25 27-Aug-25 50% CD Development
26 20 18-Aug-25 15-Sep-25 Hazardous Materials Abatement Design
27 0 27-Aug-25 50% CD Submittal
28 10 28-Aug-25 11-Sep-25 50% CD Constructability Review & Bid Packaging
29 20 28-Aug-25 25-Sep-25 95% CD Development
30 10 28-Aug-25 11-Sep-25 50% CD Budget Development
31 0 11-Sep-25 50% CD Review Meeting
32 0 25-Sep-25 95% CD Submittal
33 10 26-Sep-25 09-Oct-25 100% Bid Doc Coordination
34 5 26-Sep-25 02-Oct-25 95% CD Constructability Review & Bid Packaging
35 5 26-Sep-25 02-Oct-25 95% CD Budget Development
36 0 02-Oct-25 95% CD Review Meeting
37 0 09-Oct-25 100% Bid Doc Submittal
38 Bid Letting AbatementBid Letting AbatementBid Letting AbatementBid Letting Abatement
39 1 16-Sep-25 16-Sep-25 Issue RFB to Procurement (State)
40 2 17-Sep-25 18-Sep-25 Post RFB to TSB (State), MBI, Planrooms
41 13 19-Sep-25 07-Oct-25 RFB Procurement
42 0 29-Sep-25 RFB Pre-bid Meeting
43 0 01-Oct-25 RFB Questions Due
44 0 03-Oct-25 RFB Final Addendum
45 0 07-Oct-25 Bids Due
46 0 08-Oct-25 Contractor NOIs
11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 May 2025 June 2025 July 2025 August 2025 S October 2025 N D January 2026 F March 2026 April 2026 May 2026 June 2026 July 2026
RFP Procurement
Pre-Proposal Meeting #01
Pre-proposal Meeting #02
Questions Due - RFP
Final Addendum - RFP
RFPs Due
RFP Evaluation
Designer NOI
Designer 5 Day Appeal Period
Design Contract Execution
Hazardous Materials Consultant Procurement (MA)
NOI
Contract Execution
Hazardous Materials Assessment & Report
Design Kick-Off Meeting
Onsite Investigation
50% CD Development
Hazardous Materials Abatement Design
50% CD Submittal
50% CD Constructability Review & Bid Packaging
95% CD Development
50% CD Budget Development
50% CD Review Meeting
95% CD Submittal
100% Bid Doc Coordination
95% CD Constructability Review & Bid Packaging
95% CD Budget Development
95% CD Review Meeting
100% Bid Doc Submittal
Issue RFB to Procurement (State)
Post RFB to TSB (State), MBI, Planrooms
RFB Procurement
RFB Pre-bid Meeting
RFB Questions Due
RFB Final Addendum
Bids Due
Contractor NOIs
9478.00 DAS Wallace Demolition DCI - Print 09-Jun-25 14:55
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 2 TASK filter: Hide Done Activities.
© Oracle Corporation
# Remaining Duration
Start Finish Activity Name
47 5 08-Oct-25 14-Oct-25 Contractor 5 Day Appeal Period
48 10 08-Oct-25 21-Oct-25 Contractor Contract Execution
49 Bid Letting DemolitionBid Letting DemolitionBid Letting DemolitionBid Letting Demolition
50 1 10-Oct-25 10-Oct-25 Issue RFB to Procurement (State)
51 2 13-Oct-25 14-Oct-25 Post RFB to TSB (State), MBI, Planrooms
52 13 15-Oct-25 31-Oct-25 RFB Procurement
53 0 23-Oct-25 RFB Pre-bid Meeting
54 0 27-Oct-25 RFB Questions Due
55 0 29-Oct-25 RFB Final Addendum
56 0 31-Oct-25 Bids Due
57 0 03-Nov-25 Contractor NOIs
58 5 03-Nov-25 07-Nov-25 Contractor 5 Day Appeal Period
59 10 03-Nov-25 14-Nov-25 Contractor Contract Execution
60 ConstructionConstructionConstructionConstruction 61 AdministrativeAdministrativeAdministrativeAdministrative
62 10 08-Oct-25 22-Oct-25 DNR Notification of Demolition & Renovation
63 10 08-Oct-25 22-Oct-25 Iowa Division of Labor Asbestos Abatement Notification
64 5 22-Oct-25 28-Oct-25 Contractor Site Specific Safety Plans Submitted
65 DemolitionDemolitionDemolitionDemolition
66 5 22-Oct-25 28-Oct-25 Mobilization
67 20 29-Oct-25 25-Nov-25 Hazardous Materials Abatement
68 1 17-Nov-25 17-Nov-25 Construction Kick-Off Meeting
69 5 18-Nov-25 24-Nov-25 Disconnects
70 10 18-Nov-25 03-Dec-25 Utility Removals and Relocations
71 45 25-Nov-25 30-Jan-26 Building, Foundations, & Tunnel Demolition
72 5 02-Feb-26 06-Feb-26 Backfill
73 3 09-Feb-26 11-Feb-26 Temporary Site Stabilization
74 20 01-Apr-26 28-Apr-26 Site Improvements & Sod
75 0 01-Apr-26* Spring Start
76 CloseoutCloseoutCloseoutCloseout 77 Wallace BuildingWallace BuildingWallace BuildingWallace Building 78 1 29-Apr-26 29-Apr-26 Owner & Design Team Punch List
79 1 30-Apr-26 30-Apr-26 Owner Training (Irrigation)
80 3 30-Apr-26 04-May-26 Owner & Design Team Punch List Corrections
81 0 30-Apr-26 Owner Closeout Conference
82 0 04-May-26 Owner Occupancy
11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 05 12 19 26 May 2025 June 2025 July 2025 August 2025 S October 2025 N D January 2026 F March 2026 April 2026 May 2026 June 2026 July 2026
Contractor 5 Day Appeal Period
Contractor Contract Execution
Issue RFB to Procurement (State)
Post RFB to TSB (State), MBI, Planrooms
RFB Procurement
RFB Pre-bid Meeting
RFB Questions Due
RFB Final Addendum
Bids Due
Contractor NOIs
Contractor 5 Day Appeal Period
Contractor Contract Execution
DNR Notification of Demolition & Renovation
Iowa Division of Labor Asbestos Abatement Notification
Contractor Site Specific Safety Plans Submitted
Mobilization
Hazardous Materials Abatement
Construction Kick-Off Meeting
Disconnects
Utility Removals and Relocations
Building, Foundations, & Tunnel Demolition
Backfill
Temporary Site Stabilization
Site Improvements & Sod
Spring Start
Owner & Design Team Punch List
Owner Training (Irrigation)
Owner & Design Team Punch List Corrections
Owner Closeout Conference
Owner Occupancy
9478.00 DAS Wallace Demolition DCI - Print 09-Jun-25 14:55
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 2 of 2 TASK filter: Hide Done Activities.
© Oracle Corporation