ANSWERS TO QUESTIONS RAISED AND HOW TO PRESENT YOUR OFFER
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7900916__COVER_LETTER.pdf | ||
| 7900916_REVISED_SOW_FOR_NEC_PM_ON_PARALLEL_SWITCH_GEAR_SYSTEMS_2019.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP # 7900916
Preventive maintenance (PM) contract for parallel switch gear systems.
· Is the most convenient airport for personal to utilize Nnamdi Azikiwe International Airport? Yes, but your travel agent will advise you better on travel matters
· What type of Visa is required? Normal regular visa
· Is there any lodging available on the embassy property? None
· Are there any meals available on the embassy property? There is a cafeteria, but not free
· Will any of this scope be performed in a CAA or PCC area? No
· If so can a secret clearance be issued for this purpose? Is there such a thing a job specific or temporary clearance? Clearance not required per scope
· Can one of our people with a top-secret clearance escort our other personnel? N/A
· How and where are tools and equipment received in the embassy? To be Coordinated with COR
· Is there any standard means of this for construction projects? No
· Can contractor tools and equipment be stored on the embassy property? Yes
· Will Federal Express packages be received by the embassy? Yes
· Does the embassy offer a truck dock and fork truck for contractor use? If required, the need will be addressed as appropriate.
· Is a one-line diagram of each of the electrical distribution systems in this scope available? Yes to be provided during project performance
· Is there a count and type of equipment / breakers available including trip unit model numbers? Yes to be provided during project performance
· Is the embassy served by a public electric utility? Yes
· If so will an electrical outage for this scope be required? Most likely Yes but also depends on the Checklist submitted and pre-approved by and for contractor
· Who is responsible for facilitating any required electrical outage with public utility? USG
· Will it be possible to work 4 continuous days at a minimum of 8 hours each day? Depending on which time of the day the 8 hours occurs
· Is any site-specific training or orientation required? To be coordinated with the COR
· If so, how much time should be allowed?
· We will require the following power for our test equipment: 200 amps single phase at 415 volts. Single phase 200A @ 415V is not available only on 3phase. Single phase voltage in Nigeria is 220V while 3-phase is 415V.
· Where will that power source be located while the switch gear is shut down? How far away will it be? Readily Available and accessible.
NOTE: PROPOSALS SHOULD BE SUBMITTED IN TWO ATTACHMENTS:
1. PRICE PROPOSAL USING THE FORMAT IN THE RFP
2. TECHNICAL PROPOSAL WITHOUT PRICING INFORMATION USING THE SOLICITATION PACKAGE INCLUDING INFORMATION SHOWING CAPACITY TO PERFORM THE CONRACT