Summary of Matrix of RFP Changes for NLS II RFP 10-99-021, Revision T
This document is a matrix of RFP changes for the NLS II (National Leadership Survey II) 2026 On-Ramp Effort under RFP 10-99-021, Revision T. The matrix catalogs modifications across two amendments. Amendment 1 includes six FAR clauses added to Section C, Clause 36.0 (FAR 52.203-6, 52.222-50, 52.226-8, 52.232-40, 52.233-3, and 52.233-4), an update to NPD 2810.1A changed to 2810.1F in Attachment D1 Section 6.0, removal of TDRSS Compatible Telemetry System from Attachment D1 Section 25.0, a change from NASA/TBP Center to TBD Center in Attachment D1 Exhibit 4, and removal of PDF format and email format specifications from Attachment E2 Section 10.3.
Amendment 2 adds a single FAR clause (FAR 52.222-90) to Section C, Clause 36.0. These changes appear to address federal compliance requirements, documentation standards, center designations, and technical system requirements. The document serves as a reference guide for proposers to identify all modifications made to the original RFP through its current revision.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3. RFP10-99-0021 Rev T_Amendment 2.docx | DOCX document | |
| FAR 52.222-90.pdf | ||
| LSP-PD-120.05_Rev_D-2025-02-03.pdf | ||
| 3. RFP10-99-0021 Rev T_Amendment 1.docx | DOCX document | |
| 2026 On-Ramp Questions and Answers.pdf | ||
| 2. Matrix of Changes_Amendment 1.pdf | ||
| 3. RFP10-99-0021 Rev T.pdf | ||
| 2. Matrix of Changes.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Changes to the NLS II RFP for the 2026 On-Ramp Effort
Matrix of RFP Changes
RFP 10-99-021
Revision T
RFP Section Summary of Change Page #
RFP Section Summary of Change Page # Section C, Clause 36.0 Added FAR 52.203-6
Added FAR 52.222-50 Added FAR 52.226-8 Added FAR 52.232-40 Added FAR 52.233-3 Added FAR 52.233-4
C-92: C-93
Attchment D1, Section 6.0 Updated NPD 2810.1A to 2810.1F D1-28 Attachment D1, Section 25.0 Removed TDRSS Campatible Telemtry System D1-48 Attachment D1, Exhibit 4 Changed NASA/TBP Center to TBD Center D1-49 Attachment E2, Section 10.3 Removed 'PDF Format' and 'Documents should be emailed in
MS Word or PDF Format' E2-9
RFP Section Summary of Change Page # Section C, Clause 36.0 Added FAR 52.222-90 C-95
Amendment 1 Changes
Amendment 2 Changes