N3B_Industry_Day_Agenda_4_8_19.pdf
PDF 435 KB Posted
- Attached to
- Industry Day
- Solicitation number
- RFP-0000297
About this file
Updated Industry Day Agenda 4_8_19
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry_Day_2019_attendees.pdf | ||
| N3B_2019_Industry_Presentation.pptx | PPTX presentation | |
| Industry_Day_Schedule_Draft_FedBizOps.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3B Industry Day Agenda
Wednesday, April 10th, 2019 (Day 1, Morning)
Time Schedule Overview Title
8:00 Open N3B Program Manager /ER Program Manager
Ethics Manager, Project Field Execution
Safety ER Program Manager
Ground Rules ER Manager Procurement and Subcontracts
Schedule Overview Manager, Project Field Execution
8:45 Water Programs Director, Water Programs
9:15 Aggregate Areas Manager, Aggregate Area Soils Remediation Program
9:45 TA-21 Manager, TA-21 D&D and Cleanup Program
10:15 BREAK
10:30 Material Disposal Areas Manager, MDA Remediation & Closure Program
11:00 Small Business Programs Subcontract Administrator/Small Business Liaison
11:30 Lunch - On Your Own
Wednesday, April 10th, 2019 (Day 1, Afternoon)
1:00 ES&H ER ES&H Specialist/ ER Environmental Specialist
QA Director, Quality Assurance Program
Security Badging Security Specialist
Proposal Compliance and N3B
Feedback
ER Manager Procurements and Subcontracts/Manager, Project
Field Execution
2:15
Chaquehui/South Ancho/ Lower
Water Pre-Proposal
Technical Overview
Field Execution Technical Lead/Manager, Aggregate Area Soils
Remediation Program
3:00 BREAK
3:15 Procurement Process and Guidelines ER Manager Procurement and Subcontracts
3:45 Questions and Answers
Manager, Project Field Execution/ER Manager Procurements and
Subcontracts
4:15 - 5:00 Networking
Thursday, April 11th, 2019 (Day 2, Morning)
Time Schedule Overview Title
8:00 Open
Safety Manager, Project Field Execution
Ethics Director, RCRA Remediation Program
Schedule Overview Manager, Project Field Execution
8:45 DP West Slabs and Basements Pre- Proposal
Technical Overview TA-21 Project Manager
10:15 BREAK
10:30 Procurement Process and Guidelines ER Manager Procurement and Subcontracts
11:00 Questions and Answers Manager, Project Field Execution/ER RCRA Procurements and Subcontracts
11:30-12:55 LUNCH
Thursday, April 11th, 2019 (Day 2, Afternoon)
1:00 - 4:00 Breakout Sessions/Vendor Interactions
Tables with N3B Representatives from Procurement, Small Business Program, ER Program, TA- 21 Program, Project Field Execution Team
1:00 Leave for TA-21 and Chaquehui Site Visits
5:00 Return from TA-21 Chaquehui Site Visits