This Request for Proposal is issued by the Colorado Department of Health Care Policy and Financing (HCPF) for Enterprise Solutions Integration (ESI) Platform and Centralized Data and Reporting Hub Support services. The Department is soliciting competitive proposals from experienced organizations to assume responsibility for operating, maintaining, and supporting the existing ESI Platform and implementing a new Centralized Data and Reporting Hub solution. Offerors may bid on one or both standalone modules. The anticipated contract term begins upon the Contract Effective Date with a transition period ending June 30, 2027, followed by an initial operational period of one year, with a total anticipated duration of five years including any options exercised by the State. The State reserves the right to extend the contract beyond the anticipated term or choose not to exercise any option or extension term in its sole discretion. The Department will evaluate proposals based on the offeror's organizational experience, personnel qualifications, technical approach, project management methodology, security and governance capabilities, and ability to manage concurrent CMES module integrations within a multi-contractor environment.

The RFP requires offerors to demonstrate specific experience within the last five years, including streamlining complex IT ecosystems, integrating COTS-based systems, working with Medicaid and healthcare data, and implementing service-oriented architecture and API design patterns. Key personnel requirements include an Account Manager, Project Management/PMO Director, Master Project Scheduler, Business Lead, Enterprise/Integration Architect, Technical Lead, Configuration Manager/Administrator, Testing and Quality Manager, Security and Privacy Manager, Data & Cloud Architect, and Data Conversion Specialist, each with defined minimum qualifications and experience requirements. Contractor shall assume full responsibility for the existing ESI Platform, including all transition activities, documentation, and assets from the incumbent provider or the State. The contract encompasses design, development, implementation, operations, maintenance, and ongoing continuous development initiatives. Pricing is not specified in the SOW section, though the RFP references a Pricing Worksheet in Appendix E and invoicing tied to accepted deliverables. The Department currently utilizes MuleSoft for the ESI integration platform and Centralized Data and Reporting Hub and provides licenses for this software. All work must comply with HIPAA, federal Medicaid regulations, CMS Standards and Conditions, state security policies, and applicable governance frameworks.

View the file

Other files

File Type Posted
Appendix C - W-9 Cover Page.pdf PDF
Appendix A Administrative Information.pdf PDF
Appendix G - ESI Interfaces and Tasks.xlsx XLSX spreadsheet
Appendix D - Terminology.pdf PDF
Appendix B Draft Contract.pdf PDF
Appendix E - Pricing Worksheet.xlsx XLSX spreadsheet
Appendix C - W-9 FORM.pdf PDF
Appendix F - VPAT.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HCPF Solicitation #:

RFP UHAA 2026000274

Enterprise Solutions Integration Platform and

Centralized Data and Reporting Hub Support

TABLE OF CONTENTS

SECTION 1.0 INTRODUCTION AND BACKGROUND

1.1. GENERAL INFORMATION

1.2. ANTICIPATED CONTRACT TERM

1.3. DRAFT CONTRACT

1.4. TERMINOLOGY

1.5. BACKGROUND

1.6. SUBRECIPIENT STATUS

SECTION 2.0 OFFEROR’S EXPERIENCE AND PERSONNEL

2.1. ORGANIZATIONAL EXPERIENCE

2.2. PERSONNEL REQUIREMENTS

SECTION 3.0 ESI MODULES

3.1. MODULAR APPROACH

3.2. STANDALONE MODULES

3.3. MODULAR EXPECTATIONS

3.4. MODULAR REQUIREMENTS

SECTION 4.0 GENERAL SERVICES REQUIREMENTS ALL MODULES

4.1. STATEMENT OF WORK

4.2. CONTRACTOR REQUIREMENTS

4.3. PROJECT TIMELINE

4.4. APPROACH FOR HOW TO MANAGE CONCURRENT CMES MODULE DATA

EXCHANGES AND INTEGRATIONSCONTRACT MANAGEMENT

4.5. PROJECT MANAGEMENT

4.6. GOVERNANCE

4.7. SECURITY

4.8. TRANSITION AND TAKEOVER SERVICES

4.9. GENERAL REQUIREMENTS, ALL MODULES

4.10. OPTIONAL SERVICES

SECTION 5.0 MODULE 1: INTEGRATION PLATFORM AND INFRASTRUCTURE SERVICES

(ESI PLATFORM)

5.1. STATEMENT OF WORK

5.2. INTEGRATION PLATFORM AND INFRASTRUCTURE (ESI PLATFORM) REQUIREMENTS

SECTION 6.0 MODULE 2: OPERATIONAL DATA STORE SERVICES (CENTRALIZED DATA

AND REPORTING HUB PLATFORM)

6.1. STATEMENT OF WORK

6.2. CENTRALIZED DATA AND REPORTING HUB REQUIREMENTS

SECTION 7.0 PERFORMANCE STANDARDS ALL MODULES

SECTION 8.0 DELIVERABLE REQUIREMENTS ALL MODULES

8.2. ACCESSIBILITY REQUIREMENTS

SECTION 9.0 COMPENSATION AND INVOICING

9.1. COMPENSATION

9.2. INVOICING AND PAYMENT PROCEDURES

9.3. BUDGET

SECTION 10.0 EVALUATION METHODOLOGY

10.1. EVALUATION PROCESS

10.2. EVALUATION COMMITTEE

10.3. COMPLIANCE

10.4. PROPOSAL EVALUATION CRITERIA

10.5. SCOPE OF NEGOTIATIONS

APPENDIX A – ADMINISTRATIVE INFORMATION DOCUMENT

APPENDIX B – DRAFT CONTRACT

APPENDIX C – W-9

APPENDIX D – TERMINOLOGY

APPENDIX E – PRICING WORKSHEET

APPENDIX F - VPAT

Solicitation #: RFP UHAA 2026000274 Page 1 of 180

SECTION 1.0 INTRODUCTION AND BACKGROUND

1.1. GENERAL INFORMATION

1.1.1. The Colorado Department of Health Care Policy and Financing (Department), Enterprise Solutions Integration (ESI) Division is soliciting competitive, responsive proposals from experienced and financially sound organizations to perform all core

ESI Platform and Centralized Data and Reporting Hub tasks and services. Offerors may bid on one or both of the ESI and Centralized Data and Reporting Hub

Platforms.

1.1.2. General solicitation information, timelines and proposal submission requirements are available in Appendix A, Administrative Information Document. To be considered responsive, an Offeror shall comply with all of the requirements and timelines contained in Appendix A.

1.2. ANTICIPATED CONTRACT TERM

1.2.1. Contractor’s transition period is anticipated to begin upon on the Contract

Effective Date and end on June 30, 2027.

1.2.2. The initial operational period of the Contract is anticipated to begin at the end of the start-up period and will last for one year.

1.2.3. The total duration of the Contract, including the Department’s exercise of any options, is anticipated to be five years.

1.2.4. The State may take steps to extend the Contract beyond the anticipated term in accordance with the Colorado Procurement Code, and in the event that the State determines an extension is necessary.

1.2.5. The State may, within its sole discretion, choose not to exercise any option or extension term in the Contract for any reason. If the State chooses not to exercise any option or extension term, it may re-procure the goods and/or services in its sole discretion.

1.3. DRAFT CONTRACT

Solicitation #: RFP UHAA 2026000274 Page 2 of 180

1.3.1. A draft Contract is included as Appendix B, Draft Contract. The terms of the Draft

Contract shall become contractual obligations following award of the Statement of

Work. The Offeror affirms its willingness to enter into a Contract containing terms substantially similar to those in Appendix B, Draft Contract, including its exhibits, by submitting a proposal. The successful Offeror may have an opportunity to request modification to the terms of the Draft Contract, as described in Appendix

A, but the Department may choose to not accept any requested modifications. The

Department will not accept any proposals that are conditional on acceptance of modified terms and conditions.

1.4. TERMINOLOGY

1.4.1. Acronyms and abbreviations are defined at their first occurrence in this Request for Proposals (RFP). Appendix D, Terminology is provided to assist the reader in understanding acronyms, abbreviations, and terminology used throughout this solicitation.

1.5. BACKGROUND

1.5.1. Department of Health Care Policy and Financing Background

1.5.1.1. The Department serves as the Medicaid Single State Agency as defined by 45

C.F.R. §205.100. The Department develops and implements policy and financing for Medicaid and the Children’s Health Insurance Program, called Child Health

Plan Plus (CHP+) in Colorado, as well as a variety of other publicly funded health care programs for Coloradans who qualify. For more information about the

Department, visit www.Colorado.gov/HCPF.

1.5.1.2. The Department is a Covered Entity under the Health Insurance Portability and

Accountability Act of 1996 (HIPAA) (42 U.S.C. §§1320d – 1320d-8) and its implementing regulations.

1.5.1.3. The Department operates the Colorado Medicaid Program, known as Health

First Colorado, in accordance with the Colorado Medical Assistance Act (§§25.5-

4-104, et seq., C.R.S.) and Title XIX of the Social Security Act. Colorado

Medicaid is annually funded from appropriations authorized by the Colorado

General Assembly and matched by federal funds.

http://www.colorado.gov/HCPF

Solicitation #: RFP UHAA 2026000274 Page 3 of 180

1.5.2. Project Background

1.5.2.1. Enterprise Solutions Integration

1.5.2.1.1. The Enterprise Solutions Integration Platform and Centralized Data and

Reporting Hub serve as the central data & integration hub for managing, storing, orchestrating, transforming and transmitting data exchanges between the CMES modules, providing governance oversight, integration industry best practices and standards, while ensuring the CMES Module

Vendors adhere to MITA standards and conditions. The ESI solution provides a standardized technical approach coupling and decoupling system processes for integrating data, enabling the secure, consistent flow of data through APIs, batch processes, data services, and interface files, while improving transparency and organizational change management for ease of use.

1.5.2.1.2. This module component/service approach allows the Department to focus on superior functionality, leverage private-sector business practices, and align with the principles outlined in the Centers for Medicare and Medicaid

Services (CMS) Standards and Conditions for Enhanced Funding. The ESI

Platform and Centralized Data and Reporting Hub are a core foundational need in an environment of multiple modules provided by multiple contractors which work together. The awarded vendor(s) shall ensure that all modules work together seamlessly, ensure overall security and privacy remain intact, and manage risks that may arise between multiple modules and contractors.

1.5.2.2. The Department currently utilizes MuleSoft for ESI integration Platform and the

Centralized Data and Reporting Hub.

1.5.2.2.1. The Department currently provides licenses for MuleSoft.

1.6. SUBRECIPIENT STATUS

Solicitation #: RFP UHAA 2026000274 Page 4 of 180

1.6.1. Contractor will not be considered a subrecipient subject to the requirements of the Office of Management and Budget Uniform Guidance, 2 CFR Part 200.

SECTION 2.0 OFFEROR’S EXPERIENCE AND PERSONNEL

2.1. ORGANIZATIONAL EXPERIENCE

2.1.1. The Department has determined that it desires specific experience and skills for an Offeror to possess in order for the Offeror to be able to complete the Work efficiently while meeting the demands and deadlines of the Department.

2.1.2. The Department will evaluate the Offeror’s experience pertaining to the following:

2.1.2.1. Experience within the last five years.

2.1.2.2. Experience streamlining and integrating complex IT ecosystems with multiple data sources.

2.1.2.3. Experience working with Medicaid, CHP+, health care, or public/commercial health data and systems.

2.1.2.4. Experience integrating Commercial Off the Shelf (COTS) based systems.

2.1.2.5. Experience integrating complex system components within a “system-of-systems” environment with interoperability and interdependencies to process

Medicaid and CHP+ data accurately and completely based on State and Federal program rules and regulations.

2.1.2.6. Experience with CMS and state regulatory guidance required for certifying systems and modules that receive federal financial participation (FFP).

2.1.2.7. Experience implementing services-oriented architecture (SOA) and Application

Programming Interfaces (API) design patterns, including (but not limited to)

Fast Healthcare Interoperability Resources (FHIR) (http://www.hl7.org/fhir), Health Level 7 (HL7), Consolidated Clinical Document Architecture (CCDA), HIPAA Compliant Accredited Standards Committee (ASC X12), National Council for Prescription Drug Program (NCPDP).

2.1.2.8. Experience facilitating vendor relationships and communication to build a cohesive, collaborative program that is mutually beneficial and productive.

Solicitation #: RFP UHAA 2026000274 Page 5 of 180

Provide a detailed description of Offeror’s organizational experience related to the Work, including all of the following:

a. Address years of experience with state agencies, including processing and managing Medicaid as a Systems Integrator or any other capacity processing

Medicaid Data, Healthcare, Health Insurance, and other healthcare-related integrations and data experience.

b. Address project experience with state agencies, including successful and failed projects in Medicaid operating as a Systems Integrator or any other capacity processing Medicaid Data, Healthcare, Health Insurance, and other healthcare-related implementations.

c. Address the Offeror’s organizational priorities on quality in work and deliverables.

d. Disclose any sanctions taken against the Offeror’s organization.

2.2. PERSONNEL REQUIREMENTS

2.2.1. All personnel requirements are shown below and. the following personnel shall be required of Offerors who are awarded either or both modules.

2.2.2. The Key Personnel for the Contract are as follows:

2.2.2.1. Account Manager

2.2.2.1.1. The Account Manager shall have the following qualifications:

2.2.2.1.1.1. Ten years or more of experience leading Systems Integrations projects.

2.2.2.1.1.2. Five years of Health and Human Services or Medicaid experience.

2.2.2.1.2. The Account Manager shall be responsible for all of the following:

2.2.2.1.2.1. Serving as Contractor’s primary point of contact for the Department.

2.2.2.1.2.2. Directing the completion of work in accordance with the Contract’s requirements.

2.2.2.1.2.3. Overseeing Contractor’s personnel.

2.2.2.2. Project Management/PMO Director

Solicitation #: RFP UHAA 2026000274 Page 6 of 180

2.2.2.2.1. The Project Manager/PMO Director shall have the following qualifications:

2.2.2.2.1.1. Ten years or more of experience leading Systems Integrations projects.

2.2.2.2.1.2. Five years or more of Health and Human Services or Medicaid experience.

2.2.2.2.1.3. A Project Management certification.

2.2.2.2.2. The Project Manager/PMO Director shall be responsible for the following:

2.2.2.2.2.1. Leading Project Management Officer (PMO) for Contractor.

2.2.2.2.2.2. Directing the Project team’s day-by-day activities and Deliverables.

2.2.2.3. Master Project Scheduler

2.2.2.3.1. The Master Project Scheduler shall have the following qualifications:

2.2.2.3.1.1. Eight years of professional experience in integrated master scheduling for large-scale technology programs.

2.2.2.3.1.2. Three years of experience on a program with total contract value, organizational complexity, or implementation scope comparable to this

Contract.

2.2.2.3.1.3. Demonstrated experience managing integrated schedules that include transition activities, operational work, enhancement work, and third-party dependencies.

2.2.2.3.1.4. Demonstrated experience with schedule logic development, baseline establishment, critical path analysis, float analysis, dependency management, variance analysis, and corrective action planning.

2.2.2.3.1.5. Demonstrated experience supporting formal governance, change control, deliverable tracking, performance reporting, and executive stakeholder communications.

2.2.2.3.1.6. Demonstrated experience coordinating schedule information across multiple vendors, State staff, and business and technical workstreams.

2.2.2.3.2. The Master Project Scheduler shall be responsible for the following:

2.2.2.3.2.1. Leading schedule management and project controls for a large-scale platform transition, operations, and module onboarding environment.

Solicitation #: RFP UHAA 2026000274 Page 7 of 180

2.2.2.4. Business Lead

2.2.2.4.1. The Business Lead shall have the following qualifications:

2.2.2.4.1.1. Five years or more of business analysis experience.

2.2.2.4.1.2. Five years or more of Health and Human Services or Medicaid experience.

2.2.2.4.2. The Business Lead shall be responsible for the following:

2.2.2.4.2.1. Leading business and requirements analysis.

2.2.2.4.2.2. Leading development of requirements-related Deliverables.

2.2.2.5. Enterprise/Integration Architect

2.2.2.5.1. The Enterprise/Integration Architect shall have the following qualifications:

2.2.2.5.1.1. Five years or more of experience in leading enterprise architectures.

2.2.2.5.1.2. Two years or more of Health and Human Services or Medicaid experience.

2.2.2.5.2. The Enterprise/Integration Architect shall be responsible for the following:

2.2.2.5.2.1. Leading development of architecture-related Deliverables.

2.2.2.6. Technical Lead

2.2.2.6.1. The Technical Lead shall have the following qualifications:

2.2.2.6.1.1. Five years or more of experience leading technical teams on systems integration projects.

2.2.2.6.1.2. Three years or more of Health and Human Services or Medicaid experience.

2.2.2.6.2. The Technical Lead shall be responsible for the following:

2.2.2.6.2.1. Leading project development activities.

2.2.2.7. Configuration Manager/Administrator

2.2.2.7.1. The Configuration Manager/Administrator shall have the following qualifications:

2.2.2.7.1.1. Three years or more of experience in administering and managing complex systems integration project configurations.

Solicitation #: RFP UHAA 2026000274 Page 8 of 180

2.2.2.7.2. The Configuration Manager/Administrator shall be responsible for the following:

2.2.2.7.2.1. Managing and overseeing project configurations.

2.2.2.7.2.2. Leading development of configuration management-related

Deliverables.

2.2.2.8. Testing and Quality Manager

2.2.2.8.1. The Testing and Quality Manager shall have the following qualifications:

2.2.2.8.1.1. Two years or more of Health and Human Services or Medicaid experience.

2.2.2.8.1.2. Five years or more leading systems testing activities.

2.2.2.8.2. The Testing and Quality Manager shall be responsible for the following:

2.2.2.8.2.1. Leading development of testing-related Deliverables.

2.2.2.8.2.2. Leading project testing activities.

2.2.2.9. Security and Privacy Manager

2.2.2.9.1. The Security and Privacy Manager shall have the following qualifications:

2.2.2.9.1.1. Five years of security leadership experience.

2.2.2.9.1.2. One year or more of Healthcare, Human Services, or MMIS-related security experience.

2.2.2.9.2. The Security and Privacy Manager shall be responsible for the following:

2.2.2.9.2.1. Leading development of security-related Deliverables.

2.2.2.9.2.2. Leading security and privacy policy and procedure systems implementation work.

2.2.2.10. Data & Cloud Architect

2.2.2.10.1. The Data Architect shall have the following qualifications:

2.2.2.10.1.1. Five years or more of experience in data modeling, data analytics, and

Amazon Web Services (AWS).

2.2.2.10.2. The Data Architect shall be responsible for the following:

Solicitation #: RFP UHAA 2026000274 Page 9 of 180

2.2.2.10.2.1. Leading the development of data-related Deliverables.

2.2.2.10.2.2. Leading the data development project work.

2.2.2.11. Data Conversion Specialist

2.2.2.11.1. The Data Conversion Specialist shall have the following qualifications:

2.2.2.11.1.1. Five years or more of data conversion experience.

2.2.2.11.1.2. Two years or more of Healthcare, Health and Human Services, or MMIS-related experience.

2.2.2.11.2. The Data Conversion Specialist shall be responsible for the following:

2.2.2.11.2.1. Leading project data conversion activities.

2.2.2.11.2.2. Leading conversion-related Deliverables.

2.2.3. Additional Key Personnel

2.2.3.1. Contractor shall use its discretion to determine the number of additional, non-

Key Personnel necessary to perform the Work in accordance with the requirements of this Contract.

2.2.3.1.1. The Department shall not be responsible for Contractor’s non-performance due to inadequate staffing, and Contractor shall provide adequate staffing at no additional cost to the Department.

2.2.3.2. Contractor shall ensure that all Other Personnel have sufficient training and experience to complete all portions of the Work assigned to them. Contractor shall provide all necessary training to its Other Personnel, except for State-provided training specifically described in this Contract.

2.2.3.3. Contractor may subcontract to complete a portion of the Work required by the

Contract. The conditions for using a Subcontractor or Subcontractors are as follows:

2.2.3.3.1. Contractor shall provide the following information to the Department as part of Contractor’s Resource Management Plan for each Subcontractor

(“Subcontractor Information”), which information shall be updated as

Contractor contracts with each Subcontractor:

Solicitation #: RFP UHAA 2026000274 Page 10 of 180

2.2.3.3.1.1. Organizational name of each Subcontractor;

2.2.3.3.1.2. The address of each Subcontractor;

2.2.3.3.1.3. All items to be worked on by each Subcontractor;

2.2.3.3.1.4. Statement regarding the subcontractor's use of offshore resources and whether the subcontractor will perform any contract related activities outside the United States;

2.2.3.3.1.5. Verification that the Subcontractor has represented to Contractor that the Subcontractor is willing to perform the identified work;

2.2.3.3.1.6. Verification that Contractor has taken steps to validate that the

Subcontractor has established non-discrimination policies in its employment practices;

2.2.3.3.1.7. Certification from the Subcontractor that the Subcontractor’s employment practices comply with and satisfy Federal and State employment-related statutes and regulations; and

2.2.3.3.1.8. If requested by the Department, a copy of the Subcontractor’s statement of work between the Subcontractor and Contractor.

2.2.3.3.2. Contractor shall provide the Subcontractor Information to the Department the later of five Business Days prior to the Subcontractor beginning work or three days after the Effective Date of this Contract, as applicable, with quarterly updates thereafter (Reference: Master Project Plan).

2.2.3.3.3. Contractor shall obtain prior consent and written approval for any use of

Subcontractor(s).

2.2.3.3.4. Contractor shall, if it enters into any subcontract as permitted by this

Contract, serve as the Prime Contractor with respect to all such subcontracts and shall remain solely responsible for the integration and performance of all Work under this Contract, whether performed by

Contractor or any Subcontractor.

2.2.3.3.4.1. Contractor shall ensure that all Subcontractors comply with the same protocols, rules, regulations, and contractual requirements applicable to

Solicitation #: RFP UHAA 2026000274 Page 11 of 180

Contractor, including the terms and conditions of this Contract and all applicable SLAs, and shall ensure that Subcontractors are trained on such requirements and provide written attestation of compliance to the

Department.

2.2.3.3.4.2. Contractor shall work solely with the Department to perform all Contract administration activities of this Contract, including tasks for which the

Subcontractor may be responsible.

Provide a detailed explanation of how the Offeror will provide sufficient personnel to perform the Work, including all of the following:

a. How the Offeror will provide Key Personnel that meets or exceeds the requirements contained in this RFP in Appendix B.

b. How the Offeror will provide and train all Other Personnel so that the Work is completed accurately and within the Department’s specified timeline.

Additionally, include a listing of the position titles for each position related to the Contract, the general responsibilities of that position, the number of individuals filling that position and the numbers of hours each week the position will be dedicated to the Work.

c. A plan for how the Offeror will replace all Key Personnel and Other Personnel so that the transition between personnel does not impact the ability of

Contractor to complete the Work.

d. If the Offeror intends to use a Subcontractor, the Offeror shall provide a description of how the Offeror will use Subcontractors and the percentages of the Work that will be completed by each Subcontractor. This description shall also include the anticipated positions provided by the Subcontractor and the roles of those positions, as well as a plan for how the Offeror will manage the

Subcontractor and all Subcontractor personnel to ensure that the portions of the Work assigned to the Subcontractor will be completed accurately and within the Department’s specified timeline.

SECTION 3.0 ESI MODULES

Solicitation #: RFP UHAA 2026000274 Page 12 of 180

3.1. MODULAR APPROACH

3.1.1. The Department has separated its current ESI needs into Integration Platform and

Infrastructure Services (ESI Platform) and Centralized Data and Reporting Hub modules. Offerors may respond to either standalone module or both. The

Department may award separate Contracts for each module or award multiple modules to a single Offeror based on evaluation results and best value in the interest of the State.

3.2. STANDALONE MODULES

3.2.1. Standalone modules are ESI Platform Takeover and Implementation of new

Centralized Data and Reporting Hub solution.

3.2.2. The individual modules for this procurement are:

3.2.2.1. Module 1: Integration Platform and Infrastructure Services (ESI Platform)

3.2.2.2. Module 2: Centralized Data and Reporting Hub Platform

3.3. MODULAR EXPECTATIONS

3.3.1. The Department’s Enterprise Solutions Integration Platform and Centralized Data and Reporting Hub Platform oversee the integration and data exchanges implementation of all CMES modules and to ensure the accuracy of all Medicaid

Data and Medicaid integration are implemented and aligned across the CMES

Ecosystem.

3.3.2. The Department desires Contractor(s) with experience facilitating relationships and communication to build a cohesive, collaborative program that is mutually beneficial and productive. Contractors are expected to work cooperatively with all other Contractors and Stakeholders and support to integration solutions within the

State’s CMES ecosystem.

3.3.2.1. The Department’s ESI Contractor(s) will be responsible for Identity and Access

Management tools, such as Single Sign On (SSO), across the CMES ecosystem.

Contractors will be required to provide solutions that can easily integrate with the Department’s Identity and Access Management tools and comply with OIT security standards.

Solicitation #: RFP UHAA 2026000274 Page 13 of 180

3.3.2.2. The Department expects that module Contractor(s) will participate in cloud platform data exchange within and between modules using industry proven cloud hosting technologies (such as Amazon Web Services) to accelerate implementations and improve stability and performance of data exchanges.

3.3.2.3. The Department expects that module Contractor(s) will participate in end-to-end testing of data exchanges between modules in an end-to-end testing environment prior to moving data exchanges to production.

3.3.2.4. A data supplier interfaces and APIs exchanges are modified and/or upgraded, Contractor shall facilitate change management efforts to minimize disruption to business and technical operations.

Provide a detailed description of Offeror’s experience facilitating vendor relationships and communication to build a cohesive, collaborative program that is mutually beneficial and productive.

3.4. MODULAR REQUIREMENTS

3.4.1. Offerors responding to either or both modules shall provide services that meet the needs of all components listed in the following Statements of Work (and associated requirements set forth in Appendix E). Responses that fail to address all relevant components in will be considered unresponsive during the Evaluation phase.

SECTION 4.0 GENERAL SERVICES REQUIREMENTS ALL MODULES

4.1. STATEMENT OF WORK

4.1.1. Upon award of the ESI Platform module, Contractor shall provide technical and consultative services to assume responsibility for, operate, maintain, and support the existing ESI Platform with shared enterprise capability. Contractor shall manage the ESI Platform to ensure continuity of Medicaid operations while performing ongoing development activities necessary to support system evolution, regulatory changes, and business needs. Contractor shall also provide the capacity to design, develop, and implement enhancements and new functionality throughout the Contract term as directed by the State to advance the ESI Platform and its capabilities.

Solicitation #: RFP UHAA 2026000274 Page 14 of 180

4.1.2. Upon award of the Centralized Data and Reporting Hub solution module, Contractor shall provide a Centralized Data and Reporting Hub solution that serves as the

Department's centralized enterprise operational data hub and persistent storage layer for operational data. The Centralized Data and Reporting Hub shall provide a secure, scalable, and governed repository for operational data received from multiple internal and external source systems, supporting data consistency, operational reporting, interoperability, and enterprise data sharing. The solution shall leverage and be fully compatible with the Department's existing enterprise integration platform, which shall remain responsible for data integration, routing, orchestration, and transformation. The Centralized Data and Reporting Hub shall maintain the authoritative operational copy of integrated data while allowing designated source applications to continue performing their operational business functions. Contractor shall provide the Department with a self-service data access and extraction tool, together with all required software licenses, that enables authorized Department personnel to query, extract, and export data from the

Centralized Data and Reporting Hub for reporting, business intelligence, analytics, audit, and other authorized business purposes without requiring Contractor assistance.

4.1.3. Contractor shall perform all Work in accordance with the Contract, approved

Deliverables, approved plans, applicable service levels, performance standards, and applicable State and federal laws and regulations.

4.1.4. Upon award, Contractor shall assume full responsibility of the ESI Platform, including platform services, operations, configurations, governance services, documentation, and related assets from the incumbent provider or the State, including the completion of all transition activities necessary to ensure continuity of operations without disruption of service levels. Following completion of the transition, Contractor shall operate, support, monitor, maintain, govern, and upgrade the systems and services. Contractor shall also complete any remaining system buildout activities identified by the State. Contractor's responsibilities shall include: (a) correcting defects and errors; (b) applying patches, updates, and security fixes; (c) performing system, infrastructure, and application upgrades; (d) implementing changes required by federal or state law, regulation, policy, or

Solicitation #: RFP UHAA 2026000274 Page 15 of 180 program requirements; and (e) developing, testing, and implementing State-approved new or modified functionality. Contractor shall perform these activities in a manner that ensures the systems and services remain operational, secure, compliant with applicable requirements, and in conformance with all Contract requirements, Service Levels, and Performance Standards. Such activities shall include ongoing improvements and modifications required to sustain and evolve the systems and services in the ordinary course of operations.

4.2. CONTRACTOR REQUIREMENTS

4.2.1. Contractor shall provide technical, operational, and Medicaid program expertise necessary to operate, maintain, and complete the buildout of the awarded ESI

Platform, Centralized Data and Reporting Hub Platform, or both, as follows:

4.2.1.1. Strategic recommendations to reduce impact to state resources, members, and providers.

4.2.1.2. Consultative services for technology and interoperability that will increase

Colorado's maturity along the MITA Framework and compliance with CMS

Standards and Conditions.

4.2.1.3. Lead, plan, coordinate, and oversee all activities required for the standardized and successful integration of all remaining CMES modules into the ESI platform, including but not limited to technical integration, data exchange enablement, testing, and transition to production.

4.2.1.4. Compliance with the current data governance framework to enforce industry best practices and standards across CMES systems and modules.

4.2.1.5. Administration of a complete and accurate data model that includes APIs, interfaces, and transparent and traceable data shared across multiple

Contractors.

4.2.1.6. Risk, issue awareness, and management.

4.2.1.7. Modifications and enhancements as required by regulatory changes, policy updates, system modernization, and operational improvement initiatives.

4.2.2. Contractor shall perform the following general services:

Solicitation #: RFP UHAA 2026000274 Page 16 of 180

4.2.2.1. Contract Administration: Administrative contract management activities, including the development, submission, modification, and maintenance of required deliverables; preparation of accurate and complete invoices; provision of status reporting; tracking and reporting of performance measures; retention of contract documentation; and full cooperation with audits and reviews.

4.2.2.2. Project Management: Project management services in accordance with

Department Enterprise Project Management Office (EPMO) standards, tools, templates, and processes.

4.2.2.3. Integration Services (ESI Only): Buildout completion, updates related to new integrations, and operation and maintenance of the ESI Platform and support, including CMES Module re-procurement technical consultative services, for enterprise integration activities for CMES modules and data exchanges.

4.2.2.4. Centralized Data and Reporting Hub Services (Centralized Data and Reporting

Hub Only): New solution, including the plan for integrating with the ESI Platform and CMES Modules, the plan and execute operation and maintenance of the

Centralized Data and Reporting Hub Platform, including, but not limited to, ingestion, exposing APIs, consuming APIs, validate, accept, secure, store and processing batch files, data modeling, validation, and access support for data storage and data exchanges.

4.2.2.5. Governance Support: Execution support, analysis, and reporting required to support Department governance processes.

4.2.2.6. Security and Privacy: Compliance with Contract security and privacy requirements, including incident notification and response support.

4.2.2.7. Staffing and Continuity: Staffing, onboarding, and knowledge transfer sufficient to maintain continuity of operations.

4.2.3. Contractor shall collect and analyze operational performance data and provide monitoring and reporting documents as required by the incorporated SLA, KPI, and

Quality Management Deliverables.

4.3. PROJECT TIMELINE

4.3.1. The Contract shall include the following activities:

Solicitation #: RFP UHAA 2026000274 Page 17 of 180

4.3.1.1. Transition.

4.3.1.2. Takeover of ESI Platform.

4.3.1.3. New Centralized Data and Reporting Hub solution.

4.3.1.4. Operations, maintenance, continuous DDI activities, and updates.

4.3.1.5. Contractor shall provide the Department with a schedule within 30 Calendar

Days following the Contract Effective Date and the Department will approve the final duration and start and end dates for each activity.

4.3.2. Contractor shall perform Work in accordance with the Department-approved project schedule.

4.3.3. Contractor shall not begin a new activity until the Department confirms that the entrance criteria for that activity have been met.

4.3.4. Contractor shall complete all required activities and Deliverables for an activity before the Department confirms that the exit criteria for that activity have been met.

Describe Offeror’s recommended sequence, timeline, and approach for the ESI Platform transition, takeover, and operations, maintenance, remaining DDI activities, and updates activities, including proposed entrance criteria and exit criteria for each activity. At minimum, include the following information:

a. High-level timeline of key milestones

b. Approach for how to manage concurrent CMES Module re-procurement timelines with ESI governance

c. Contract Deliverables associated with each activity

Describe Offeror’s recommended sequence, timeline, and approach for the implementation of the Centralized Data and

Reporting Hub, the operations, maintenance, including proposed entrance criteria and exit criteria for each activity.

At minimum, include the following information:

Solicitation #: RFP UHAA 2026000274 Page 18 of 180

a. High-level timeline of key milestones

4.4. APPROACH FOR HOW TO MANAGE CONCURRENT CMES MODULE DATA EXCHANGES

AND INTEGRATIONSCONTRACT MANAGEMENT

4.4.1. Contractor shall meet all performance metrics, service levels, and quality management requirements stated in the Contract and incorporated exhibits.

4.4.2. Contractor shall work within a multi‑contractor environment and shall immediately disclose any actual, potential, or perceived conflicts of interest with another

Contractor and in accordance with the Contract.

4.4.3. Contractor shall perform administrative contract management activities including, but not limited to, the following:

4.4.3.1. Preparation of invoices tied to accepted Deliverables.

4.4.3.2. Maintenance of supporting documentation for invoicing and acceptance.

4.4.3.3. Response to Department inquiries within one business day.

4.4.3.4. Support for audit, monitoring, and review activities.

4.4.4. Contractor shall track all Deliverables in accordance with the Contract, Deliverables exhibit, and Department-approved tracking mechanisms.

Describe Offeror’s approach to Contract Management and quality assurance procedures for all Contract activities.

4.5. PROJECT MANAGEMENT

4.5.1. Contractor shall manage the Work in accordance with the Project Management

Institute’s (PMI) Project Management Body of Knowledge (PMBOK), Sixth Edition or later versions as they are published.

4.5.2. Contractor shall comply with Department EPMO standards, tools, templates, and processes.

4.5.3. Contractor shall maintain complete and accurate project records of all meetings, system development life cycle (SDLC) documents, presentations, project artifacts, and any other interactions or Deliverables described in the Contract.

Solicitation #: RFP UHAA 2026000274 Page 19 of 180

4.5.3.1. Contractor shall make such records available to the Department through a shared repository and upon request.

4.5.4. Contractor shall assume responsibility for, maintain, and update the existing

Master Project Management Plan (Master PMP) provided by the Department.

Updates to the Master PMP shall incorporate Contractor recommendations and

Department-directed revisions and shall include, at a minimum:

4.5.4.1. Deliverable Management Tracking Document.

4.5.4.2. Schedule Development and Maintenance Procedures Document.

4.5.4.3. Communication Management Plan.

4.5.4.4. Documentation Management Plan.

4.5.4.5. Resource Management Plan and Organizational Structure.

4.5.4.6. ESI Project Risk and Issue Management Plan.

4.5.4.7. Scope Management Plan.

4.5.4.8. ESI Change Management and Governance Control Board Plans.

4.5.4.9. Organizational Change Management.

4.5.4.10. Quality Management Plan.

4.5.4.11. Background Check Attestation.

4.5.4.12. Staff Resource Plan.

4.5.4.13. Personnel Transition Document.

4.5.4.14. Subcontractor Information.

4.5.4.15. Meeting Plan.

4.5.4.16. Kickoff Meeting Agenda & Materials.

4.5.4.17. Meeting Agendas.

4.5.4.18. Meeting Minutes and Meeting Records.

4.5.4.19. SDLC Management Plan.

4.5.4.20. Progress Report.

Solicitation #: RFP UHAA 2026000274 Page 20 of 180

4.5.4.21. Daily Status Update.

4.5.4.22. Weekly Progress Report.

Describe Offeror’s Project Management approach and proposed governance as it relates to their understanding of the ESI SOW. Please include the following information:

a. Project management methodology and SDLC approach

b. Proposed approach to development and maintenance of an integrated project schedule

c. Recommended project management tools, including the use of Department project management tools

4.6. GOVERNANCE

4.6.1. Contractor shall support execution of the Department’s SDLC and governance framework applicable to the awarded scope.

4.6.2. Contractor shall implement SDLC and governance management practices to enforce compliance across CMES module contractors within the scope.

4.6.3. Contractor shall enforce Department data and integration governance by operationalizing governance decisions, establishing and implementing effective policies and procedures for governance across the CMES Ecosystem.

4.6.4. Contractor shall provide the Department with analysis of integration behavior, impacts, and issues necessary to support governance decisions.

4.6.5. Contractor shall maintain a maintain a Vendor Accountability Matrix that identifies the Responsible, Accountable, Consulted and Informed Parties for CMES integrations.

Describe Offeror’s approach to governance enforcement of the SDLC framework across all CMES Module Contractors and translating insights of integration behavior to the Department.

4.7. SECURITY

Solicitation #: RFP UHAA 2026000274 Page 21 of 180

4.7.1. Contractor shall perform all Work in compliance with applicable State and federal privacy and security requirements relevant to Medicaid data, including HIPAA, 42

CFR Part 2, IRS Publication 1075, PCI-DSS, the FBI CJIS Security Addendum, CMS

Minimum Acceptable Risk Standards, SSA Electronic Information Exchange Security

Requirements, and applicable State security policies.

4.7.2. Contractor shall identify and notify the Department immediately of any Privacy and/or Security Incident or Privacy and/or Security Incident or Breach.

4.7.2.1. Contractor shall cooperate with the Department and law enforcement, if there is any Privacy and/or Security Incident or Breach, and perform all required activities to stabilize, recover, and remediate any loss to the Department.

4.7.2.2. Unless Contractor establishes that Contractor and Contractor’s agents, personnel, or Subcontractors were not the cause or source of the Privacy and/or

Security Incident or Privacy and/or Security Breach, Contractor shall bear all notice and response costs required under the Contract.

4.7.2.3. After a Privacy and/or Security Incident or Privacy and/or Security Breach, Contractor shall manage and track the issue and take any steps necessary to reduce the risk of incurring a similar type of Privacy and/or Security Incident or Privacy and/or Security Breach in the future, which may include, but is not limited to, developing and implementing a remediation plan that is approved by the Department at no additional cost to the Department.

4.7.2.4. Privacy and/or Security Incidents and Privacy and/or Security Breaches include but are not limited to:

4.7.2.4.1. Virus or malicious software code.

4.7.2.4.2. Unauthorized access.

4.7.2.4.3. Disclosure of protected information.

4.7.2.4.4. Lost or stolen devices, badges or data.

4.7.2.4.5. Unapproved transmission of protected information.

4.7.2.4.6. Sharing of authentication passwords.

4.7.2.4.7. Bypass or failure to comply with security controls.

Solicitation #: RFP UHAA 2026000274 Page 22 of 180

4.7.3. Contractor shall maintain and test disaster recovery capabilities supporting all ESI and Centralized Data and Reporting Hub environments.

4.7.4. Contractor shall comply with HIPAA privacy and security requirements and shall support secure connections for all entities interacting with the awarded integration services.

4.7.5. Contractor shall identify and comply with all Department, State, and Federal standards, protocols, and methodologies to:

4.7.5.1. Facilitate the security function across the ESI integrated solution.

4.7.5.2. Facilitate secure integration activities.

4.7.5.3. Develop, maintain, and execute privacy and security audit processes.

4.7.5.4. Execute security procedures.

4.7.5.5. Store and maintain audit trail information.

4.7.5.6. Restrict access when anomalies are detected.

4.7.5.7. Immediately report anomalies to the Department.

4.7.6. Contractor shall maintain written security policies, procedures, and controls applicable to the Work and shall update them as necessary to remain compliant with applicable State and federal requirements. Material changes impacting security and privacy shall be submitted for Department review and approval.

4.8. TRANSITION AND TAKEOVER SERVICES

4.8.1. Contractor shall propose and complete a transition and takeover process that aligns with the incumbent vendor’s transition plan which will be provided by the

Department, minimizes disruption to Department, project stakeholders, CMES module contractors, and authorized Centralized Data and Reporting Hub users.

4.8.2. Contractor shall develop and implement a transitional plan in alignment with the incumbent vendor’s transitional plan to support continuity of operations while the transition from the incumbent vendor is in progress.

4.8.3. Contractor shall participate in weekly and monthly transition status meetings as directed by Department.

Solicitation #: RFP UHAA 2026000274 Page 23 of 180

4.8.4. Contractor shall create and execute a Transition Plan that includes, at a minimum:

4.8.4.1. Communication management.

4.8.4.2. Risk and issue tracking.

4.8.4.3. Change control.

4.8.4.4. Training and knowledge transfer.

4.8.4.5. Milestone management.

4.8.4.6. Deliverables tracking.

4.8.5. Contractor shall complete takeover activities that include, at a minimum:

4.8.5.1. Identification of resource requirements, including key personnel, other personnel, facilities, and other resources.

4.8.5.2. Coordination of Department‑provided hardware, software, licenses, and environments required for the awarded scope, including continuity planning for

Department‑provisioned software and licenses.

4.8.5.3. Overview Sessions.

4.8.5.4. Training sessions for transferred systems, services, and tools.

4.8.5.5. Turnover of software and configuration information necessary for operations.

4.8.5.6. Turnover of test data and test assets, to the extent available and permitted.

4.8.6. Contractor shall complete training and knowledge transfer activities that address, at a minimum:

4.8.6.1. Canonical Data Model.

4.8.6.2. CMES inbound and outbound interfaces.

4.8.6.3. System tools.

4.8.6.4. Leading practices.

4.8.6.5. Data dictionary data marts, or both, as applicable.

4.8.6.6. Existing incumbent-developed training materials relevant to the awarded scope.

Solicitation #: RFP UHAA 2026000274 Page 24 of 180

4.8.7. In addition to the knowledge transfer activities, Contractor shall demonstrate operational readiness through structured transition activities, including, at a minimum:

4.8.7.1. Parallel Operations: Contractor shall execute parallel operations with the incumbent vendor for a Department-defined period, during which Contractor independently performs all operational functions. Contractor outputs shall be validated against incumbent outputs in accordance with Department-defined acceptance criteria for accuracy, completeness, and timeliness.

4.8.7.2. Reverse Shadowing: Contractor shall assume primary responsibility for operations under incumbent observation and support for a Department-defined period, demonstrating the ability to perform all required functions without material intervention and in accordance with Department-defined acceptance criteria.

4.8.7.3. Testing and Validation: Contractor shall successfully complete all Department-required testing prior to Go-Live, including but not limited to system integration testing (SIT), user acceptance testing (UAT), data validation, and interface reconciliation. All testing results shall meet Department-defined acceptance criteria.

4.8.7.4. Operational Readiness Assessment: Contractor shall participate in a formal

Operational Readiness Assessment (ORA), conducted by the Department, to evaluate Contractor’s ability to meet all contractual, technical, and operational requirements based on Department-defined acceptance criteria.

4.8.8. Contractor shall complete transition and takeover to formal completion. Formal completion shall require Department confirmation that:

4.8.8.1. Required activities, Deliverables, and milestones have been completed.

4.8.8.2. Operational responsibility has been successfully transferred.

4.8.8.3. Continuity of operations has been maintained.

4.8.9. Contractor shall not proceed to Go-Live until the Department has provided explicit written approval, confirming that all training, knowledge transfer, testing, deliverables, and operational readiness requirements have been completed.

Solicitation #: RFP UHAA 2026000274 Page 25 of 180

Describe Offeror’s recommended sequence, timeline, and approach to transition and takeover, including entrance and exit criteria for each activity. At a minimum, include the following information:

a. A proposed transition plan summary.

b. A proposed knowledge transfer approach.

c. A proposed staffing and resource mobilization approach.

d. A proposed readiness review approach.

e. A proposed formal completion approach that includes risk assessment, risk mitigation, and contingency planning.

4.9. GENERAL REQUIREMENTS, ALL MODULES

4.9.1. INTRODUCTION

4.9.2. This Contract necessitates the new ESI Contractor's assumption of full responsibility for all existing systems, services, operations, configurations, governance services, project management, collaborating with the Enterprise Testing Vendor (ETV), conducting integration and end-to-end testing with CMES modules and data partners, DEVOPS testing, ongoing security controls, document management, and related assets from the incumbent provider or the State, including the completion of all transition activities necessary to ensure continuity of operations without disruption of service levels. Following such transition, Contractor shall operate, support, monitor, maintain, upgrade, and provide governance services for the systems and services, including the correction of defects, application of updates, performance of upgrades, and development and implementation of new or modified functionality as necessary to ensure that such systems and services remain functional, secure, compliant, and in accordance with all applicable requirements, service levels, and performance standards. Such activities shall include ongoing improvements and modifications required to sustain and evolve the systems and services in the ordinary course of operations.

4.9.3. This SOW is focused on (1) takeover and transition of the ESI Platform; (2) the

Centralized Data and Reporting Hub; (3) MuleSoft Integration Platform and licensing, and AWS Transfer Family and its configurations, DEVOPS tools with

Solicitation #: RFP UHAA 2026000274 Page 26 of 180

Continuing Integrations/Continuing Deployment (CI/CD), security tools and configurations, and Infrastructure; (4) takeover and transition of operations, maintenance, and updates of the ESI Platform and Integrated Modules; (5)

Takeover and transition ongoing DDI activities including, but not limited to, the

Integration Platform Roadmap, the CMES Module Roadmap and the associated module integration Work, Data Sharing Roadmap, continue constructing and curating all Medicaid and CHP+ data within the ESI Platform and Centralized Data and Reporting Hub; (6) Data consumption interfaces and APIs published and discoverable through the Developer Portal and Data Catalog.

4.9.4. The Work in this Contract encompasses DDI and O&M services across the ESI

Platform, CMES Modules, the Centralized Data and Reporting Hub, and

Governance. The Project Schedules drive the Work Contractor performs for each category, and activities scheduled for a specific category may be reorganized based on the availability of Department resources, budget, and the Department’s review and approval of all Deliverables and Work Products.

4.9.5. GENERAL REQUIREMENTS

4.9.5.1. Contractor shall provide an ESI Strategic Roadmap identifying the sequence of integrating all CMES Modules and a defined timeline of meeting the implementations within 45 Calendar Days following contract execution.

4.9.5.1.1. DELIVERABLE: ESI Platform and Centralized Data and Reporting Hub

Strategic Roadmap

4.9.5.1.2. DUE: As identified in Section Section 8.0 (Deliverables Table)

4.9.5.2. Contractor shall assume responsibility for the ongoing development, buildout completion, and maintenance of the ESI Platform and Centralized Data and

Reporting Hub Strategic Roadmap with no disruption to Medicaid API and file processing.

4.9.5.3. Contractor shall takeover and maintain coordination with the CMES Vendors for integration and governance services activities when performing the following, but not limited to:

Solicitation #: RFP UHAA 2026000274 Page 27 of 180

4.9.5.3.1. Identifying integration API or batch file processing issues and concerns affecting the CMES ecosystem.

4.9.5.3.2. Integrated Project Schedule.

4.9.