This is a Request for Proposal (RFP) issued by the Carroll County School System in Georgia for Construction Management at Risk (CM at Risk) services for additions and modifications to the Carroll County Transportation and Maintenance Facility located in Carrollton, Georgia. The project scope includes construction of a new access drive, modifications to existing buildings for a bus maintenance shop, and transportation offices. A mandatory pre-proposal meeting is required on April 27, 2023, at 10:00 a.m. at the project site (1625 Bankhead Highway, Carrollton, GA 30117); proposals not submitted by attendees will be rejected. Written proposals must be received by May 11, 2023, at 12:00 noon at 164 Independence Drive, Carrollton, GA 30116, with six copies required in sealed packages. The project selection timeline includes a public advertisement period beginning April 13, 2023, a written questions deadline of May 2, 2023, and final selection and board approval scheduled for May 18, 2023, at 6:00 p.m. The anticipated total budget shall not exceed $5,000,000.
The CM proposal fee will be submitted as a percentage for both "Overhead and Profit" and "General Conditions," with detailed cost breakdowns required in separate sealed envelopes. The evaluation committee will select the most qualified CM based on four criteria: Firm History and Information (25%), Relevant Experience and References (25%), Project Approach (10%), and Fee Structure (40%). The selected CM will be the prime contractor responsible for all services, including pre-construction planning, value engineering, bidding and award of trade contracts, construction management with an on-site superintendent, and post-occupancy warranty implementation over one year. The CM must secure a 100 percent Performance and Payment Bond, maintain specified insurance coverage including general liability with $2,000,000 general aggregate limits, worker's compensation, automobile liability, and umbrella excess liability, and comply with Georgia immigration and work authorization requirements. A modified AIA A133 contract will be executed upon selection, with a Guaranteed Maximum Price (GMP) to be negotiated and approved by the Board of Education before subcontract procurement begins.
Text of this file
CARROLL COUNTY SCHOOL SYSTEM
REQUEST FOR PROPOSAL FOR
ADDITIONS AND MODIFICATIONS TO:
CARROLL COUNTY TRANSPORTATION AND
MAINTENANCE FACILITY
INTRODUCTION
The Carroll County School System is requesting a proposal from interested and qualified Construction
Management Firms for the construction of Additions and Modifications to: Carroll County
Transportation and Maintenance Facility in Carrollton Georgia. The approximate total anticipated budget for all phases shall not exceed but could possibly be up to $5,000,000.00.
The Carroll County School System (hereinafter referred to as School System) plans to select the most qualified Construction Management Firm (hereinafter referred to as CM) to enter into a CM at Risk contract for the construction for the above referenced project. The proposed fee to be submitted as a part of the CM Proposal will include “Overhead and Profit” to be awarded as a percentage and “General
Conditions” also awarded on a percentage.
The services to be performed by the CM will have as their objective the efficient, economical, and timely delivery of the project by managing the construction of the project within the time and cost limitations and within established quality requirements. The services will be performed during the pre-construction phase, construction phase and post construction phase including working with the owner in estimating, value engineering, arrangements of bid packages, bidding and award of the trade contracts, and management of construction until occupancy is achieved, and implementing the one (1) year warranty and one (1) year warranty inspection.
A mandatory pre-proposal meeting will be held at 10:00 am on April 27, 2023 at the site; 1625
Bankhead Hwy. Carrollton, GA. 30117. Any person or entity that fails to attend the mandatory pre-proposal meeting will not be permitted to submit a Proposal for the Project and any Proposal submitted by a person or entity that did not attend the mandatory pre-proposal meeting will be returned unopened.
Responses must be received by the School System at 164 Independence Drive, Carrollton, GA. 30116 on or before 12:00 noon on May 11, 2023. After which time and date they will no longer be accepted.
Late responses will be returned unopened and will not be considered. To be accepted, all responses must be submitted in a sealed package marked “Proposal for Additions and Modifications to: Carroll
County Transportation and Maintenance Facility - CM at Risk Services”. Six (6) copies of each proposal must be forwarded or delivered to:
Mr. Terry Jones, Assistant Superintendent
CARROLL COUNTY SCHOOL SYSTEM
164 Independence Drive
Carrollton, GA 30116
Oral or telegraphic (including FAX) responses are not acceptable.
Project selection timeline:
Public Advertisement/RFP Available: Thursday, April 13, 2023
Mandatory Pre-Bid Meeting: Thursday, April 27, 2023; 10:00 am
Deadline for Written Questions Tuesday, May 2, 2023; 12:00 noon
Proposals Due: Tuesday, May 11, 2023; 12:00 noon
Final Selection and Board Approval: Thursday, May 18, 2023; 6:00 pm
GENERAL INFORMATION
Please direct all questions regarding this Proposal Request and the program it represents to:
Mr. Terry Jones, Mr. Gregory J. Schillinger, AIA
CARROLL COUNTY SCHOOL SYSTEM Southern A&E, LLC
164 Independence Drive 7951 Troon Circle
Carrollton, Georgia 30116 Austell, GA 30168
Ph: 770-832-3568 Ph: 770-819-7777
Email: terry.jones@carrollcountyschools.com Email: gschillinger@southernae.com
No questions other than written will be accepted, and no response other than written will be binding upon the school system.
Site visits to inspect the site and/or facilities can be arranged by appointment with Mr. Mike Beers, Coordinator of Maintenance. It is the responsibility of the respondent to arrange and conduct any site visits necessary to familiarize themselves with existing conditions.
A copy of this RFP will be posted at the school systems website (www.carrollcountyschools.com) as well as on Southern A & E’s online plan service. If you don’t have a log-in to the plan service, you may receive access by calling 770-819-7777 to request a password and a link to Southern A & E’s online plan service to view the documents. Upon further request documents may be downloaded for printing. The school system reserves the right to amend this RFP prior to the proposal due date. All amendments and mailto:terry.jones@carrollcountyschools.com mailto:gschillinger@southernae.com http://www.carrollcountyschools.com/ additional information will be e-mailed to proposers of record and posted to Southern A & E’s online plan service.
Submission of a proposal authorizes the school system to make inquiries concerning the proposer and its officers, agents, and representatives to any persons or firms deemed appropriate by the school system.
Proposals are subject to the Georgia Open Records Act. The School System cannot protect proprietary data submitted in proposals.
Submission of proposals indicates Respondent’s acceptance of the evaluation technique and
Respondent’s recognition that some subjective judgments must be made by the school system during the determination of ranking order and award.
The school system reserves the right to select or reject any and all responses as a result of this Request for Proposal. The school system is not liable for any costs incurred by any person or firm responding to this Request for Proposal.
The Scope of Work is being discussed and finalized at this time and may include the construction of a new access drive into the property, modifications to existing buildings for a bus maintenance shop and transportation offices. The scope is subject to change but shall not exceed the anticipated budget.
GENERAL REQUIREMENTS
CM Responsibility
The selected CM will be required to assume total responsibility for all services offered in his/her proposal. The selected CM will be considered the prime contractor and the sole point of contact with regard to all contractual matters. The CM shall also be expected to obtain at least three bids for each bid package (work category), exclusive of the CM’s guaranteed maximum price for the individual bid packages (work categories). If a work category does not receive at least 3 bids, the bids for that work category will not be opened and the work category shall be re-bid. The CM will not perform any portion of the project with its own forces except as may be mutually agreed to by the owner and the
CM and as allowed by the Georgia Department of Education. The CM shall be required to submit a
GMP for each bid package (work category) to Carroll County School System prior to the opening of subcontractor bids. All subcontractor bids shall be opened in a location designated by the
Carroll County School System and all subcontractor bids shall be opened in the presence of a representative of the Carroll County School System. Individual trade contracts will be between the
CM and the Trade Contractors, subject to school system approval.
The CM agrees to perform all work in compliance with O.C.G.A.13-10-91, Georgia Security and
Immigration Compliance Act. The CM shall state affirmatively that the individual, firm, or corporation which is contracting with the Carroll County School System, has registered with and is participating in a federal work authorization program using any of the electronic verification of work authorization programs operated by the United States Department of Homeland Security or any equivalent federal work authorization program operated by the United States Department of Homeland
Security to verify information of newly hired employees, pursuant to the Immigration Reform and
Control Act of 1986 (IRCA), P.L. 99-603], in accordance with the applicability provisions and deadlines established in O.C.G.A. 13-10-91.
The CM further agrees that, should it employ or contract with any subcontractor(s) in connection with the physical performance of services pursuant to this contract with CCSS, contractor will secure from such subcontractor(s) similar verification of compliance with O.C.G.A. 13-10-91 on the Subcontractor
Affidavit provided in Rule 300-10-01-08 or a substantially similar form. The contractor further agrees to maintain records of such compliance and provide a copy of each such verification to the Carroll
County School System at the time the subcontractor(s) is retained to perform such service.
The CM also agrees to perform all work in compliance with O.C.G.A. 50-36-1 Systematic Alien
Verification for Entitlements (SAVE) program. The CM agrees that, should it employ or contract with any subcontractor(s) pursuant to this contract with CCSS, the CM will secure from such subcontractor(s) similar verification of compliance with O.C.G.A. 50-36-1. The CM further agrees to provide verification of compliance with executed affidavits available on the Department of Audits and
Accounts website at, http://www.audits.ga.gov/NALGAD/Files/OCGA_50-36-1xex2x/pdf. The CM further agrees to maintain records of such compliance and provide a copy of each such verification to the Carroll County School System at the time the subcontractor(s) is retained to perform such service.”
Required Bonds and Insurance
Prior to the award of a GMP contract, the CM shall provide the school system with a 100 percent
Performance and Payment Bond from a bonding institution listed in the current edition of the Federal
Register as a surety for its faithful performance of this contract. Bonds must be kept in force for the duration of the contract; and, executed by a resident agent of the State of Georgia; and, be in compliance with Georgia Revised Statutes.
All insurance must be occurrence based coverage. The Carroll County School System shall be named as additional insured. All insurance will be primary to any insurance maintained by the Carroll County
School System.
To adequately protect the interests of the school system, the successful respondent shall procure, and maintain in effect during the life of the agreement, the following insurance coverage:
1. Worker’s Compensation:
a. State: Statutory
b. Employer’s Liability:
1. Each Accident: $500,000
2. Disease Policy Limit: $500,000
3. Disease Each Employee: $500,000
2. Comprehensive General Liability, including Premises-Operations; Independent Contractor’s
Protective; Products and completed Operations; Broad Form Property Damage; X-C/U Explosion, Collapse and Underground Coverage.
a. General Aggregate: $2,000,000
b. Products and Completed Operations Aggregate: $2,000,000
c. Products and Completed Operations – Each Occurrence: $1,000,000
d. Personal and Advertising Injury: $1,000,000
e. Fire Damage – Any One Event: $100,000
3. Comprehensive Automobile Liability
a. Combined Single Limit: $1,000,000
4. Umbrella Excess Liability
a. General Aggregate: $1,000,000
b. Products and Completed Operations Aggregate: $1,000,000
c. Products and Completed Operations – Each Occurrence: $1,000,000
d. Personal and Advertising Injury: $1,000,000
5. Completed Value/Builders Risk including interests of the Owner, Contractor, Subcontractors and
Sub-subcontractors and covering the entire project including materials stored off site and materials in transit.
Evidence of required bonds and insurance shall be presented prior to the execution of a GMP contract.
The required bond shall be indicated as a single line item on the CMs GMP breakdown, and the bonding amount shall be adjusted by change order when all contract cost are established by procurement of subcontract bids. Insurance policies to be carried under the agreement shall not be changed, canceled, or allowed to expire without thirty (30) days prior written notification to the school system.
Should the CM elect to require certain subcontractors to provide Performance Bonds and Labor and
Material Payment Bonds, the cost of these subcontractor provided bonds shall be the responsibility of the CM and shall not be included in the GMP. The cost of these subcontractor provided bonds shall be itemized as a separate line item on the subcontractor’s bid form.
Taxes, Fees, Code Compliance and Licensing
The CM shall be responsible for the payment of any required taxes or fees associated with the execution of a GMP contract. The CM shall also be responsible for compliance with all applicable codes and statutes. All installation and construction work shall be done by sub- contractors licensed in the State of Georgia.
Payment
CM shall submit monthly payment applications using AIA G702 and AIA G703 Continuation Sheets in addition to Georgia State Department of Education DE Form 0263, July 1982 Edition.
The CM shall hold harmless and indemnify the Owner, the Architect, and other design consultants against all claims, suits, actions, costs, council fees, expenses, damages and/or judgments in decrees by reason of persons or property being damaged or injured by the CM or any of the CM employees/subcontractors in any capacity during the progress of the work, whether by negligence or otherwise.
REPRESENTATIVE SERVICES TO BE PROVIDED BY THE CM
Project Planning
1. Evaluate preliminary documents for constructability, value opportunities and scheduling at each phase of design.
2. Participate and assist in planning meetings.
3. Provide estimates at the Construction Document phase and an estimated monthly construction payment schedule to assist the owner with financial budgets.
4. Conduct a Value Engineering review, including Life Cycle Cost, and evaluations for alternate materials and systems.
5. Prepare and submit cash flow analysis to Owner.
Bidding and Awarding Phase
1. Separate construction work into appropriate work categories (See attachment 1; page 11).
2. Develop requirements to ensure time, cost, and quality control during construction.
3. Provide an estimated construction schedule for issuance with the bid package.
4. Identify bidders and generate bidder interest. Maintain a list of firms contacted and dates of contact for review by the Owner.
5. Schedule and conduct pre-bid conferences in conjunction with the architect and representatives from the School System.
6. Advertise and distribute bidding documents.
7. Assist in the development of necessary addenda and distributing of these addenda to known bidders.
8. Monitor bidder activity.
9. Review and analyze bids and recommend awards.
10. Collect executed contracts, purchase orders, affidavits of assurance, insurance certificates, and performance and payment bonds and distribute copies to Owner, Architect, and contractors.
11. Update schedule.
12. Assist in Pre-Construction meetings.
Construction Phase
1. Maintain staff for construction management to include an on-site superintendent.
Superintendent shall have supervised past projects of equal size and scope and have excellent performance references from the owners for a minimum of three (3) projects within a period of five (5) years maximum. CM shall submit his proposed superintendent/superintendents and references for review by the Owner and Architect with this proposal.
2. Mobilization of job site – Provide and maintain a fully equipped project office facility on-site to perform all required CM duties and meetings and coordination of on-site temporary facilities.
3. Assure timely procurement of all required permits.
4. Establish and maintain coordination procedures.
5. Develop and maintain a detailed schedule including delivery, approvals, inspection, testing, construction, and occupancy.
6. Conduct and record weekly job progress meetings following a CM generated agenda with the Architect, Owner and all active trades, and follow-up with distribution of minutes to all parties.
7. Coordinate and log all requests for information (RFI’s).
8. Maintain a daily log of jobsite activities.
9. Prepare and submit change order documentation for review and approval by the architect and
School System. Review change order proposals to verify validity, purpose, and cost.
10. Maintain a system for review and approval of shop drawings.
11. Maintain written and photographic records and submit routine reports to the architect and School
System.
12. Maintain quality control and ensure conformity to contract documents.
13. Establish and maintain a jobsite safety program.
14. Provide cost control through progress payment review and verification according to the approved schedule and contract amounts.
15. Provide coordination of post completion activities, including the assembly of guarantees, manuals and the owner’s final acceptance.
16. Coordinate and ensure timely completion of final punch list.
17. Compile as-built drawings throughout construction.
18. Assemble close-out documents and forward them to Architect for approval.
19. Coordinate any training specified for Owner’s personnel.
20. Provide all services listed under “General Conditions” in Attachment 2.
Post Occupancy Phase
1. Implement and coordinate the one (1) year warranty and one (1) year warranty inspection.
2. Respond to request for corrections for work items found not to be installed correctly.
3. Respond to warranty related request.
4. Assist in post-construction review of the facility.
SELECTION PROCESS
The services being sought under the RFP are considered professional in nature. Consequently, the evaluation of the proposals will be based upon consideration of the demonstrated qualifications and capabilities of the responding firms and will result in an award that is in the best interest of the
School System. Evaluations will be performed by a committee. Final selection will be made in accordance with the policies and administrative directives of the School System and any other statutory provisions. The following is a summary of the selection process:
Proposal Evaluation
Interested CM’s responding to this proposal request must provide the information required to meet the criteria contained in “Response Format and Contents”. The evaluation committee will evaluate submittals and choose the most highly qualified CM. The following criteria will be considered in choosing the most highly qualified CM:
1. Firm History and Information
2. Relevant Experience & References
3. Project Approach
4. Fee Structure
Negotiation and Signing of Contract
Upon completion of proposal evaluations and the determination that the project is feasible and acceptable to the Carroll County Board of Education, a modified AIA A133 contract without Mandatory
Amendment #1 will be executed between the selected CM and the School System. A GMP will be prepared by the CM and shall incorporate all costs incurred by the CM for each phase or phases associated with the projects. The GMP shall be submitted to the school system and shall include a preliminary schedule of values, a preliminary schedule of work category bid packages and a preliminary monthly cash flow chart. Upon agreement by all parties on the GMP, and acceptance of the GMP by the
Board of Education, the Mandatory Amendment #1 will be completed, signed and attached to the contract and shall constitute the full contract for the projects. Upon completion of Mandatory
Amendment #1, procurement of subcontract bids will commence. In the event a GMP cannot be agreed upon by all parties, the CM will receive no compensation for pre-construction services.
RESPONSE FORMAT AND CONTENTS
General Information
Responses must be submitted in the format outlined in this section. Each response will be reviewed to determine if it is complete prior to actual evaluation. Failure to provide accurate, up-to-date responses to any and all portions of the RFP may result in disqualification without prejudice. The school system reserves the right to eliminate from further consideration any responses that are deemed to be substantially or materially unresponsive to the requests for information contained in this section. The intent of the school system is that all responses follow the same format in order to evaluate each response fairly. The school system may, during the course of the evaluation process, request additional information to supplement and/or clarify the information provided.
Proposals will be evaluated in light of the material and substantiating evidence presented in the proposal, and not on the basis of what is inferred.
Any exceptions taken to the terms and conditions of this RFP must be clearly identified. If no exceptions are listed, it will be concluded that the proposer will meet, in every detail, the conditions stipulated in this RFP.
Proposals may be modified or withdrawn by written notice received prior to deadline for receipt of proposals. A proposal also may be withdrawn in person by a proposer or his authorized representative, provided his identity is made known and he signs a receipt for the proposal, but only if the withdrawal is made prior to the deadline set for receipt of proposals.
The proposal form (Attachment 5) shall be signed by such an officer, member, or person as is duly authorized to bind the CM to a contract.
Each respondent shall provide the school system with six (6) copies of his/her response. Begin each section and subsection as described herein on a separate page. Number the pages in each section consecutively. Each page shall have the name of the respondent indicated clearly across the bottom of each page.
Submission of a response authorizes the school system to make inquiries concerning the respondent and its officers to any persons or firms deemed appropriate by the school system.
Questions that arise prior to the proposal submittal date shall be submitted in writing to both the school system and the architect.
Proposal Format
Firm History & Information (25%)
Briefly describe your firm’s organizational structure and history. Include the following information:
• Cover letter [limited to two (2) letter-size pages] at the beginning of the proposal. The cover letter shall include a project title, CM information (including name, address, e-mail address, and telephone and fax number), names, email addresses and telephone and fax numbers of persons authorized to provide any clarifications required. The letter should express your organizations commitment to the following topics:
• Why you believe your firm is aptly suited to perform Construction Management services for
CCSS.
• What specific qualities/attributes you and your firm possess that would enable you to meet the school system’s educational specifications and high expectations of service in a superior manner.
• Identify specific instances where other school districts have benefited as a result of your association with their construction program.
• Comment on your firm’s qualifications, including general information and brief history of the firm, including a chronology of the firm’s origin through its current status and any changes in ownership or locale since its inception.
• Furnish an organizational chart for your firm specifically indicating those who will be involved in this program, the length of time that the current management team has been with the firm and the amount of involvement that senior management will devote to this project.
• Provide a compliance letter from your bonding company showing consent to provide 100%
Performance and Payment Bonds for your services as a Construction Manager.
• Each respondent shall provide a certificate of insurance detailing their firm’s present coverage and limits. Insurance agent shall certify that they are licensed to perform business in the State of
Georgia. The certificate of insurance should be addressed to CCSS and be dated within 30 days of the bid date.
Relevant Experience/References (25%)
Provide a list of all relative and similar projects completed in the past ten (10) years within the State of Georgia. Also identify the four (4) most recently completed Construction Management at Risk projects on the list. Include the following information:
• Project name and location
• General description (new construction, addition, renovation)
• Project delivery method
• Project’s original budget and final cost
• Percentage of change orders
• Project’s total square footage
• Project’s cost per square foot (indicate if $/sf includes sitework)
• Project start and completion dates
• Scheduled duration vs. actual completion time
• Individuals within your firm who were involved in the project.
• Owner’s contact information
• Project architect’s contact information
Project Approach (10%)
Provide a brief outline and description of your firm’s approach for this project. The description should include, at a minimum, your approach to the following topics:
1. Pre-Construction Services
a. Constructability Review
b. Cost Control
c. Generating Bidder Interest
d. Subcontractor and Material Supplier Qualifications
e. Value Engineering
2. Schedule Control
a. Include a preliminary schedule for this project including pre and post construction activities.
b. Schedule Recovery
3. Budget
a. Change Order Management
4. Safety Program
5. Quality Control
6. Post Completion Activities
Briefly describe your greatest concern regarding delivery of this project.
Fee Structure (40%)
Contractor shall stipulate a percentage fee for General Conditions on Attachment 2, and a percentage fee for Overhead and Profit on Attachment 3. Submit Attachments 2 and 3 and the completed “Contractor Cost Proposal Summary”, in a separate sealed envelope with your proposal.
Fees for General Conditions not itemized in the schedule of values and Overhead and Profit shall be billed as a percentage of the total project completion.
Attachment 1
ESTIMATED WORK CATEGORIES
Selective Demolition
Sitework, Grading, Storm Drainage, Erosion Control, Grassing, Tree Protection
Termite Control
Site Concrete & Asphalt Paving
Chain Link Fence
Cast-in-place Concrete
Cast Stone and Unit Masonry
Structural & Miscellaneous Steel
Metal Stair & Railing
Rough Carpentry
Architectural Woodwork
Building Insulation
PVC and/or Metal Roofing
Hollow Metal Doors & Frames
Wood Doors
Fiberglass Reinforced Doors
Aluminum Windows & Storefronts Overhead Coiling Doors
Door Hardware Glass & Glazing Drywall /Acoustical Ceiling
Hard Tile
Resilient Flooring & Carpet
Painting and Joint Sealant
Signage
Manufactured Canopy Covers Toilet and
Bath Accessories
Door (Dock) Bumpers
Metal Roof and Wall System
Plumbing, Site Utilities
Fire Protection
HVAC
Electrical System (Including low voltage systems)
Attachment 2
CONSTRUCTION MANAGEMENT SERVICES
FEE STRUCTURE
PROJECT COST MATRIX
All items marked Pre-Con or Const. Services must be included in your fee if you seek payment for these items. However, it is not required that you provide each item. The GM/GC will use its common practices to determine which items are necessary for the execution of the work.
Carroll County School System
Transportation and Maintenance Facility
Office Expense In Pre- Const.
Services
Construction Management
Services within fee
Cost of Work
Owner
CM Field Office, Furniture & Furnishings X
Office Supplies - Preconst. X
Office Supplies X
Field Office Equipment & Maintenance X
Owner/Arch Office, Equipment & Utilities
X
Jobsite Radios/Beepers/Cell phones X
Copy Machine & Maintenance – Preconst.
X
Copy Machine & Maintenance X
Computers, Usage, Software &
Maintenance – Preconst.
X
Computers, Usage, Software & Maintenance
X
Fax Machine & Service X
Field Office Telephone X
Long Distance - Preconst. X
Long Distance/Local, All X
Office Janitorial X
Postage & Expressage - Preconst. X
Postage & Expressage X
Plans & Specifications ( All printing of plans and specifications)
X
Scheduling Expenses X
Construction Photos & Supplies X
Personal Relocation Expenses and Temporary Housing
X
Job Travel, All X
Project Meetings X
Construction Trade Training Programs X
Record Drawings (As Built) X
Advertising (for bids) X
Messenger/Runner/Courier X
Audit (If Required) X
Records Storage X
Public Information Program X
Testing, Inspection & Quality Control In Pre- Const.
Services
Construction Management
Services within fee
Cost of Work
Owner
Testing Laboratory Services X
Soils Testing & Inspection X
Concrete Testing & Inspections X
QC/QA Manager X
Provide NPDES storm water monitoring and maintenance of sediment control associated with construction activity.
Include all fines incurred from authorities having jurisdiction.
X
Taxes/Insurance/Fees In Pre- Const.
Services
Construction Management
Services within fee
Cost of Work
Owner
File and obtain permits from authorities having jurisdiction. Coordinate and schedule inspection. (Fees to authorities having jurisdiction shall be paid by the Owner)
X
Building Permits Fees X
Special Permits, Licenses, Fees X
Utility Connection Fees X
Operational Permits X
Easements X
Impact Fees X
Builder’s Risk Insurance X
Insurance Deductibles X
Owner’s & Contractor’s Protective
Insurance X
General Liability & Umbrella Insurance for Project
X
Miscellaneous Insurance X
Sales, Use and Gross Receipts Taxes X
Performance & Payment Bonds (bonding of subcontractors will not be allowed without owner and architect approval.)
X
Cost of Temporary Services. Cost if temporary and permanent services .
Includes electrical, water, sanitary, and security until owner takes beneficial occupancy.
X
OHSA, Fines, and Penalties incurred X
Construction Managers own legal fees and expenses
X
Construction Management Labor In Pre- Const.
Services
Construction Management
Services within fee
Cost of Work
Owner
Payroll Tax Fringes on Division of labor X X
Worker’s Compensation Insurance X X
Pre-const. Management Labor X
Const. Management Labor X
Safety Officer X
General Conditions Labor
Coordinate post-completion activities, including the assembly of guarantees, manuals, closeout documents, training, and the Owner’s final acceptance.
X
Conduct, record, and complete preliminary deficiency list prior to issuance of Architect’s deficiency list.
Coordinate and monitor the resolution of all deficiency items.
X
Coordinate, monitor and resolve all warranty complaints and latent deficiencies to the satisfaction of the Owner and the Using Agency during the one-year general warranty period.
X
Fees In Pre- Const.
Services
Construction Management
Cost of Work
Owner
Services within fee
CM Fees (Separately proposed)
Legal Fees X
Construction Equipment & Tools In Pre- Const.
Services
Construction Management
Services within fee
Cost of Work
Owner
Engineering equipment including transits and levels
X
Field Engineering X
Layout Crew, and Exterior X
Engineering Supplies X
Layout/Batterboards X
Licensed Survey Layout, Baseline, and benchmarks
X
Site Surveys & Soils Reports X
Temporary Sanitation Facilities X
Temporary storage and protection of materials including Owner purchased items with approved purchase orders.
X
Dump trucks, rubber tire loaders, sweeps, small tools, and supplies, including dump fees for site clean up, general site and ongoing site and job cleanup.
X
Provide portable construction heat and lighting as required.
X
Financially responsible for all utilities to the project until the authority having jurisdiction provides temporary permit/certificate of occupancy.
X
Permanent Construction In Pre- Const.
Services
Construction Management
Services within fee
Cost of Work
Owner
Trade Contract Cost X
Self-Perform Labor & Materials X
Materials Incorporated into the Work X
Corrective Work : Punch list work and warranty work within the “cost of work” coordinating all corrective work during construction and after Owner’s acceptance shall be within construction management services. It is the CM/GC responsibility within the fee to complete any item not performed by subcontractor.
X
Total General Conditions: _______% (please do not extend % beyond 2 decimal points)
Attachment 3
CONSTRUCTION MANAGEMENT SERVICES
FEE STRUCTURE
Overhead and Profit* % (Please do not extend % beyond two decimal points)
Alternates and Change Orders
1. Any CM fee for alternates accepted by the Owner shall be paid using the percentage stipulated herein.
2. Change Orders will only be considered on Owner requested changes and unforeseeable conditions. For all executed change orders (changes in the work), the contract sum and CM Fee shall be as specified in AIA A201
– 2017 General Conditions, Article 7. Delete from paragraph 7.3.7 the words “the Agreement, or if no such amount is set forth in the agreement, a reasonable amount” and insert the following paragraph 7.3.7.6 and subparagraphs .a, .b, .c, .d, .e and .f to 7.3.7:
A. 7.3.7.6 In paragraphs 7.3.3 and 7.3.7, the allowance for overhead and profit combined, included in the total cost to the Owner shall be based on the following:
1. 7.3.7.6.a For the Construction Manager, for any work performed by his forces, that percentage for overhead and profit as stated in the Construction Manager at Risk Proposal Form.
2. 7.3.7.6.b For the Construction Manager, for any work performed by his subcontractors, that percentage for overhead and profit as stated in the Construction Manager at Risk Proposal Form.
3. 7.3.7.6.c For each subcontractor involved, for any work performed by his own forces, fifteen percent (15%) of the subcontractor’s cost.
4. 7.3.7.6.d Overhead and profit is to be applied to only those costs identified in paragraphs 7.3.7.1 thru 7.3.7.5.
5. 7.3.7.6.e In order to facilitate checking and verification of change order proposals for both increases and decreases in the contract amount, all change order proposals shall be accompanied by a complete cost breakdown of the items in 7.3.7.1 thru 7.3.7.5 for both the Construction Manager and the subcontractors.
6. 7.3.7.6.f The only allowable mark-up for the cost of changes in the Work shall be for overhead and profit as stated in subparagraphs 7.3.7.6.a, 7.3.7.6.b and 7.3.7.6.c.
Attachment 4
CARROLL COUNTY SCHOOL SYSTEM
SAMPLE RATING CHART
Project:
Company X Company Y Company Z
Item Description % Rank/Score Rank/Score Rank/Score
1. Firm History & Capability 25%
2.
Relevant
Experience/References
25%
3.
Project Approach
10%
4.
Total Project Fee*
40%
TOTAL
100%
*For evaluation purposes, Total Project Fee is based on:
((General Conditions %) + (O/H & Profit %)) x (Construction Budget).
Attachment 5
CERTIFICATION OF INFORMATION PROVIDED
The information provided herein is accurate to the best of my knowledge and can be accepted by the recipient as a true representation of:
Firm Name:
Signed: ____
Position:
Date:
Other files
| File | Type | Posted |
|---|---|---|
| Award Information | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .