Request for Proposal Summary

This is a Request for Proposal issued by the City of Toledo, Ohio Department of Public Works, Division of Water Reclamation, for professional engineering services to design and support construction of the Secondary RAS SS Pumps and Valves Replacement Project (Purchase Requisition Number 10009054). The project seeks a Design Engineering Consultant to perform final design, bidding assistance, and limited construction support for the replacement of aging Return Activated Sludge pumps, suction isolation valves, and motor operators originally installed in 1969 and identified as exceeding their useful service life. The consultant will serve as the engineer of record and coordinate a multi-disciplined engineering team. The proposal submission deadline is December 15, 2026 at 1:30 PM EST, with bid opening at 2:00 PM EST the same day via Zoom. A pre-bid meeting is scheduled for December 1, 2026 at 1:00 PM EST at 3900 N. Summit Street, Building #1, Toledo, Ohio 43611, with attendance strongly encouraged. The final design must be completed within twelve months from the project kickoff meeting. Proposals must be submitted electronically through the City of Toledo's PlanetBids portal and are limited to 26 pages.

Compensation is based on direct labor hours multiplied by a factor method, with direct expenses marked up not exceeding five percent and subconsultant markups capped at three percent. The consultant must provide detailed pricing for nine tasks: Progress Meetings, Project Scheduling, Geotechnical Plan, Final Detailed Design, Bidding Services, Office Engineering During Construction, Construction Inspection, Post-Construction, and Record Plans. All pricing must be provided on the City of Toledo Price Proposal Form with hours and costs clearly itemized by task. The City's Program Management Team will provide most construction administration and inspection services; the consultant's scope includes design, permitting, commissioning, training, operations and maintenance manuals, and standard operating procedures. Disadvantaged Business Enterprise (DBE) participation is evaluated as a selection criterion, though not established as a set-aside. Proposals will be evaluated on ten criteria including background and experience, office location, familiarity with regulations, current workload, previous performance, project understanding, schedule and staffing, fees, DBE participation, and other distinguishing factors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Toledo One Government Center 640 Jackson Street Toledo, Ohio 43604

REQUEST FOR PROPOSAL

Professional Services

Secondary RAS SS Pumps and Valves Replacement Purchase Requisition Number 10009054

Issued By Department of Public Works/Division of Water Reclamation

Date Issued November 13, 2026

Response Submission Date and Time

December 15, 2026 at 1:30 PM EST

Bids will be read at 2:00 PM EST

Submit online at https://pbsystem.planetbids.com/portal/22576/portal-home Table of Contents

Introduction………………………………………...…………………………...3
Background Information……………………………………………...……4
Scope of Work ……………………...………………………………...….…....4
Deliverables……………………………………………………………..……...5
Compensation …………………...………………………………….…...……18
Form of Response ………………………………………………….….….…19
Bid Information………………………………...………………………….…..22
Required Information………………………………………….………..…23
Selection Process and Evaluation Criteria….................................24
Exhibits or other Information ………………….………………………26

Introduction As part of its Water Reclamation Plant (WRP) Improvements Program, the City of Toledo (City) is requesting proposals for professional engineering services for a Design Engineering Consultant (Consultant) to perform final design, bidding assistance, and limited construction support for the Secondary RAS SS Pumps and Valves Replacement Project (Project).

The purpose of the project is to replace, improve, and rehabilitate aging Return Activated Sludge (RAS) pumps, suction isolation valves, and motor operators that have reached or exceeded their useful service life.

These pumps and valves, installed in 1969, were identified for replacement due to exceeding the end of their useful service life. The Facility Plan also called for addition of motor operators to the isolation valves.

During this preliminary design report (PDR) development, a walk-through with the plant operators identified a list of valves and pumps that require replacement as well as the addition of motor operators to valves that are needed.

This list was broken down by priority and the highest priority valves, pumps, and motor operators were identified to be included in Tier 1 of the Bay View facility improvements. The additional pumps, valves, and motor operators identified are slated to be included in Tier 2 and Tier 3 projects.

This expanded scope as described in the PDR was identified to meet the current priorities of the maintenance, operations, and engineering staff at the WRP.

Included in the PDR is a brief description of any analysis performed and a description of the proposed improvements. Also presented, is a discussion of the construction sequence with the impact on plant operations associated with the construction and the estimated construction cost of the work.

Background Information The City has a WRP Program Management Team that is administering the plant wide capital improvements program for the City.

Some of the program projects have been identified to be performed by other Consultants and are being advertised for detailed design and construction support services that are outside of the Program Management Team.

The City’s WRP Program Management Team completed the Secondary RAS SS Pumps and Valves Replacement Preliminary Design Report (PDR) and will also be providing all other office engineering during construction services by it’s Program Construction Administration Team not identified to be performed by Consultant in this RFP.

Resident Project Representation will also be performed by the Program Construction Administration Team.

Scope of Work The Project is described herein and in the Secondary RAS SS Pumps and Valves Replacement Preliminary Design Report dated July 2, 2026 (PDR), included as Exhibit A to this Request for Proposals (RFP).

The Consultant shall be able to provide professional project management and coordinate a multi-disciplined engineering team relating to design and commissioning of the Project.

The Consultant shall be responsible for:

· acting as the engineer of record on the Project,

· performing final detailed design,

· assisting in the bidding of construction services and construction contractor (Contractor) selection,

· during construction, reviewing RFIs; recommending contractor RFPs; recommending, reviewing and preparing estimates for change orders; providing input on contractor claims and disputes; reviewing all technical submittals; and providing input on contractor conformance with the contract documents,

· attending, witnessing and evaluating startup of all improvements,

· participating in Final Inspection,

· preparing project-wide operation and maintenance manual and providing technical review of contractor provided operation and maintenance manuals,

· preparing Standard Operating Procedures (SOP’s).

· preparing conformed drawings and record plans of all improvements, and

· other services to support and manage the Project.

The Consultant shall be able to provide professional project management and coordinate a multi-disciplined engineering team relating to design and commissioning of the Project.

The Consultant shall be fully responsible for all operations of its subconsultants, and the consequences of those operations. The Consultant shall be aware at all times of the subconsultants’ location, schedule and intended operations. Any employee of the Consultant engaged in the services under this Program, including those on subcontracts, found to be unsatisfactory to the City, shall be replaced by an employee satisfactory to the City.

The scope of services follows; however, Proposers are encouraged to suggest deletions or additions within their understanding of the Project if they believe changes will improve operations, maintenance, minimize costs, ensure timely completion of the project and better achieve the project goals.

Where improvements tie in with existing facilities, require outages of existing facilities, or impact adjacent construction, plans should include sequencing plans to ensure continuous operations to meet all permit requirements of the WRP and mitigate construction impacts.

The sequencing plans shall include timing and constructability of tie-in connections to existing facilities. Any Contractor activities which impact the collection system and operations require completion of Special Plant Accommodations (SPA) forms, developed by the Division of Water Reclamation.

The design shall incorporate appropriate redundancy and flexibility, and account for all scenarios of operation and maintenance that should be continued throughout the construction of the proposed improvements. All final design elements shall be completed in accordance with ASCE, ASME, Ten State Standards, Environmental Protection Agency, and other related industry regulatory agencies.

Project designs shall proceed with continuous value engineering in mind to arrive at cost effective design solutions. This should include staged discipline reviews, reviews by professionals not involved in design production, and encouragement of design team members to ask questions and make suggestions.

Design shall address constructability, sequencing, safety, and the requirement to maintain continuous operations.

Deliverables All computer files, AutoCAD drawings and specifications shall be provided to the City at the end of the project.

All computer files (disks, tapes or other formats) provided to the City shall first be scanned for viruses using an approved virus scanning software and labeled “virus free”, indicating the date scanned, scanning software used and initialed by the person performing the scan.

Final Design The Consultant shall be responsible for all discipline-specific details to accomplish the scope as described in the Preliminary Design Report (inclusive of Process Mechanical, Piping/Plumbing, Survey, Site Civil, Structural, Electrical, Instrumentation & Controls, Safety & Security).

Electrical and Instrumentation and Control Drawings shall include one line power diagrams, process and instrumentation diagrams (P&ID), software control block descriptions, and tagging nomenclature.

The Consultant shall provide all SCADA design, HMI and screen design, and programming. SCADA system shall utilize Rockwell hardware. The Consultant shall provide P&ID’s and operational descriptions to enable SCADA system set up and programming. Where needed, the control systems design should include redundancy.

The electrical and control drawings shall be sufficiently detailed to commence programming and, after construction, for City maintenance staff to perform their tasks without additional information. All programming shall be compatible with and tied directly into the plant’s SCADA system. Consultant’s programming subconsultant shall be a local Rockwell partner with experience at the WRP.

Drawings Engineering drawings for projects shall be prepared in the latest version of AutoCAD Revit or Civil 3D format. Final Plans shall be to City of Toledo Drafting standards and layers. Title blocks, headers, etc. shall utilize the City of Toledo Water Reclamation brand guide as appropriate.

Drawings shall thoroughly depict the design and required construction including the following sheets, as appropriate: Title Sheet with appropriate signature blocks, Drawing Index, General Notes, Survey Control and Benchmark, Site Plans, Demolition Plans, Sequence of Construction, Grading Plans, Paving Plans, Piping Plan and Profile, Mechanical, Civil, Structural, Architectural, HVAC, Plumbing, Electrical, Instrumentation, Landscaping, Stormwater Pollution Prevention Plan, Details, and any other plans needed to adequately depict the required construction. All drawings shall include a consecutive sheet number over total sheets in addition to the sheet title associated with the specialization area.

The plans shall provide; proposed plans external and internal to existing structures showing routing and sizing of conduits; piping; valves; meters; and pipe sizing coordinated with existing utilities; and layout of structures, and equipment. Plans shall include plan and section views of proposed process areas with critical water elevations and control elevations indicated.

Project Progress and Communication Management The Consultant shall hold a Project kickoff meeting to review the schedule, responsibilities, communications, project understanding, requirements, and goals.

The Consultant shall hold progress meetings with the City on a monthly basis, at a minimum, the purpose of which will be to review the status and results of the work completed to date, to discuss upcoming project tasks, to review schedule, and to identify and resolve any potential conflicts or problems. Some of these meetings will also serve the purpose of design “workshops” involving plant operations and maintenance staff, where project conceptual designs and alternatives shall be presented, and input and consensus solicited from plant staff.

Additional meetings may be held periodically as necessary to supplement the progress meetings. The Consultant shall prepare specific agendas and take detailed minutes of all meetings and submit them for review to the City. The Consultant shall submit an agenda three (3) workdays in advance of the progress meetings.

Project Schedule Management The Consultant shall submit a project schedule that indicates, on a week-to-week basis, the status of the project’s design, bidding, construction and commissioning. The Consultant must use their own judgment in completing the schedule. A completed design shall take no longer than twelve (12) months from the project kick-off meeting. For purposes of this proposal, completion means that plans and specifications are ready to advertise to bid.

The Consultant shall allocate two (2) weeks for the City to review at the 60% and 90% completion stages.

The project schedule shall be updated on a monthly basis in advance of the Progress Meeting.

Changes in scope or additional work to be performed must be documented in writing and approved by the City of Toledo. The City reserves the right to cancel the services contract in the event that the selected Consultant does not meet the established schedule or intent of the project.

Permitting The selected Consultant shall prepare technical criteria and design data and complete application forms for permits or approval of the final drawings and specifications from governmental authorities that have jurisdiction to approve the project design including where applicable, but not limited to: the Ohio EPA Permit to Install (PTI) application, Ohio EPA Notice of Intent Application form (NOI), signed plans to the Ohio Environmental Protection Agency (Ohio EPA), Corps of Engineers 401/404 permits, Railroad, ODNR, ODOT, Department of Public Works Division of Building Inspection, Division of Traffic Management, Division of Code Compliance. All plan reviews and/or permit fees will be the responsibility of the City of Toledo.

The Consultant shall prepare project-specific SWP3s in accordance with the current Ohio EPA Construction General Permit and the City of Toledo requirements which includes project-specific BMPs which are not covered in the Program-wide SWP3.

The Consultant shall follow up with permitting agencies to address questions and concerns.

Opinion of Probable Construction Cost The Consultant shall provide an itemized opinion of probable project construction cost updated at the 60%, 90% and 100% stages. Cost estimates shall follow recommended practices of the Association for the Advancement of Cost Engineering using the appropriate estimate class.

Specifications The Consultant shall prepare project specifications in the Engineers Joint Contract Documents Committee General Conditions and Construction Specifications Institute Master Spec format. General and supplementary conditions, contract agreement forms, and other City forms will be provided to the Consultant by the City for incorporation into the contract documents. The City has also developed standard specification for certain items, equipment, manufacturers, etc. that it will provide to the Consultant. The specifications shall use WRP program front end and Division 1 boilerplates documents to be provided by the City and Program Management Team. Specifications shall be Division 50 format.

The design specifications shall require the Contractor to handle and dispose of all excess soils to a remote location. It shall be the responsibility of the Contractor to find an acceptable location for the soils and to do so at the expense included in their bid.

Equipment specifications shall include equipment lists including preliminary overall dimensions and weights, initial list of equipment manufacturers, and motor list/power requirements.

Bidding Services The City will advertise on the City’s website through the PlanetBids system. The Consultant shall assist the City with the issuance of contract documents, addenda and bidder notifications.

The selected Consultant shall provide four (4) copies of a Detailed Plans & Specifications and a final construction cost estimate for all work included in the contract.

The selected Consultant shall provide two (2) CD’s or flash drives with all as-bid documents in PDF format.

The Consultant shall attend and/or conduct a Pre-Bid Conference, review the project reporting procedures and other rules, and issue minutes for incorporation into an addendum.

The Consultant shall respond to bidder questions through the City administered PlanetBids portal and compose addenda as necessary to clarify or expand the bidding documents. The Consultant shall also prepare addenda to correct any discovered plan or specification deficiencies during the bid stage.

The Consultant shall assist with the evaluation of bidders and bids and make recommendations for award to the City.

Commissioning, O&M Manuals, SOPs, and Record Drawings The Consultant shall assist with commissioning and startup, prepare system-level operation and maintenance manuals and standard operating procedures, and deliver final record drawings in AutoCAD and PDF formats.

Submittals and Reviews As a part of the design development, a review of project documents will be performed at the Draft (60%) and Draft Final (90%) design levels by the City and the Program Management and Construction Management Team.

Design submittals shall be delivered to the City according to the approved project schedule. For each project review stage, the Consultant shall submit the drawings and specifications for review and comment as six hard copies (four 24” x 36” and two 11”x17”) and a digital pdf format image. The City will make the final decision on any major design decisions or equipment selection. In addition, the WRP Program Construction Administration Team will provide sequencing, logistics and constructability reviews of the design.

The 60% plans shall include all dimensions and elevations and drafts of all construction discipline drawings. The City will require fifteen (15) days for 60% design plan and specification review. The Consultant shall completely satisfy all of the City’s 60% review comments and concerns and provide a response summary.

Upon satisfactory resolution of all 60% review comments, the Consultant shall submit Draft Final (90%) complete design plans and specifications for review by the City. The 90% plans shall be considered ready to bid with only minor revisions and City comments remaining. The City will require fifteen (15) days for 90% design plan and specification review. The Consultant shall completely satisfy all City 90% review comments and concerns and provide a response summary.

Upon resolution of all review comments to the City’s satisfaction, the Consultant shall submit a digital set and six hard copies of the Final 100% plans (four 24” x 36” and two 11”x17”) and four copies of the specifications to the City. Specifications shall be submitted in a 3-ring binder and provided in digital pdf format. The final drawings shall be signed and sealed by the design engineer(s) of record responsible for the development of the design. The Consultant shall submit a title sheet tracing with an original signature, registration number, and embossed seal to the City for compliance review and City signatures.

Where improvements are located in the public right of way or involve private utilities, the Consultant shall submit two (2) sets of Draft Final (90%) plans to all private utility companies for their review, and provide the City with a memo that summarizes the disposition of all private utility company review comments.

The Consultant shall perform internal constructability, discipline review, and QA/QC to ensure quality of design plans.

The Consultant shall participate in two (2) design review meetings, corresponding to the 60%, and 90% review, with the City, and prepare and submit meeting minutes to the City for review and approval.

The Consultant shall participate in a sequencing, logistics and constructability review, led by the Program Construction Administration Team, of all Final Detailed Design.

Office Engineering During Construction The selected Consultant shall provide limited office-engineering services for the duration of the construction project.

The WRP Program Construction Administration Team will perform all other services for Construction Administration, Construction Inspection, Project Commissioning and Startup Services, Project Closeout and Warranty Period Services, Operation and Maintenance Manuals and Training, and Record Plans that are not noted to be performed by the Consultant.

These office engineering services shall include but not be limited to the following:

Construction Progress Meetings The Program Construction Administration Team will conduct the pre-construction conference and progress meetings at the project site and issue meeting minutes. The Consultant shall attend and participate in these meetings.

Requests for Information (RFIs) The Program Construction Administration Team will review and approve/recommend the Contractors’ RFIs and forward to the Consultant and the City for review and comment.

Requests for Proposal (RFP) and Change Orders The Program Construction Administration Team will document field observations and changed conditions, coordinate the timely preparation of RFPs, review the Contractors’ scope and costs, negotiate final scope and costs in conjunction with the Consultant, make recommendations to the City for approval, and process all change orders to the contract. The Program Construction Administration Team through consultation with Consultant, will inform the City of situations that may require the issuance of an RFP.

The Program Construction Administration Team will consider and evaluate the Contractors’ suggestions for modifications to work covered by the contract drawings or specifications and report their findings along with the recommendation to the City and Consultant. The Program Construction Administration Team will provide an independent cost estimate separate from that of the Contractor and Consultant, where applicable. The City will make their final decision regarding rejection or approval. The Program Construction Administration Team will distribute a written summary to all parties and prepare change order documentation as required. No contingency monies will be approved or spent without City consent.

Claims and Disputes The Program Construction Administration Team will review and evaluate the basis of any claim asserted by a Contractor relating to requests for time impacts and/or additional compensation, and make recommendations to the City regarding the resolution of any claim or dispute. The Program Construction Administration Team will render, within a reasonable time of receiving detailed information from the Contractor, a recommendation to the City in writing concerning disputes between the Contractor and the City relating to the acceptability of the work with input from the Consultant, or the interpretation of the requirements of the contract documents pertaining to the performance and furnishing of the work. All claims shall be reviewed as required by this Scope of Services and the specific language in the contract for the claim related construction project. In areas of conflicting viewpoints between the Program Construction Administration Team and Consultant, the engineer of record bears the ultimate responsibility and decision.

Contract Submittals The Program Construction Administration Team will coordinate the receipt, routing, review, and disposition of all contract submittals, including shop drawings, samples and other submittals. A submittals log, as detailed in the construction documents, shall be prepared by the Program Construction Administration Team to define required submittals by the Contractor. The Consultant shall serve as the primary reviewer for all technical submittals and the Program Construction Administration Team shall serve as a primary reviewer for site construction management submittals. The Program Construction Administration Team will forward submittals to Consultant for review, along with the Construction Administration Team’s comments relative to compliance with the project submittal requirements, project schedule and budget. The Program Construction Administration Team will coordinate with the City on select submittals that will be reviewed by the City concurrently with the Consultant reviews. Program Construction Administration Team review of submittals shall not constitute approval of safety precautions or of any construction means, methods, techniques, sequences or procedures.

Enhancements The Consultant shall provide a complete description of any tasks that they are proposing that are not mentioned above. Task hours, cost and who will perform the tasks shall also be included.

Conformed Drawings The Consultant shall prepare a conformed set of drawings and specifications incorporating changes to the documents resulting from addenda during the bidding phase for each project. These shall be submitted in electronic format (AutoCAD and pdf) and six hard copies of the drawings (four 24” x 36” and two 11”x17”) and four copies of 3-ring bound specifications.

Construction Inspection The Program Construction Administration Team will provide full time Resident Project Representation (RPR) services. The Consultant shall assist in reviewing any defects and deficiencies in the work identified by the Program Construction Administration Team.

Construction Testing The City will contract with a certified testing company to conduct material testing for each project. The material testing company will provide such tests as necessary including but not limited to: soil testing, soil moisture content, material testing, concrete design and strength tests, environmental tests, and any other testing called for by the Consultant, or normally conducted, designated or required by the City in their construction contracts.

Condemning and Reporting Non-Conforming Work The Program Construction Administration Team will condemn non-conforming work, as necessary, with input from Consultant, as appropriate and verify the construction Contractor's compliance with the technical requirements of the project. In areas of conflicting viewpoints between the Program Construction Administration Team, Consultant, the engineer of record bears the ultimate responsibility and decision.

Post-Construction Assignment Commissioning and Startup Services (CSU) The Program Construction Administration Team shall provide CSU of each of the assigned projects. CSU is the procedure of operating, testing and analyzing whether equipment, system(s), and process(es) are functioning in general as intended by design. CSU will include the following tasks with noted Consultant responsibilities:

· Verification of all documentation/submittals required for startup of a piece of equipment, system or process, including initial, intermediate and final Operation & Maintenance (O&M) Manuals; O&M data, preliminary standard operation procedures (PSOP), vendor and system training, required notices, spare parts, etc., have been received, completed, and approved by the Consultant prior to startup.

· Perform the scheduling and documentation of all required Consultant and vendor O&M training on each of the various systems, processes, and equipment item(s) included in the assigned projects, as described in the O&M Manual and Training task.

· Coordinate with City, Consultant and Contractor to schedule startup dates to minimize any interruptions to City’s daily workload and any working systems and equipment.

· Coordinate the performance of testing work and schedule testing engineers from the various equipment suppliers and Consultant for the timely and successful completion of the operational and performance tests for each of the various systems, processes, or equipment item(s) included in assigned projects.

· Coordinate professional evaluation by Consultant and City of all the operational and performance testing work required for each of the various systems, processes, or equipment item(s) included in assigned projects.

· Coordinate and document the startup and commissioning of each of the various system(s), process(s), and equipment item(s) included in assigned projects and manage the resolution of any resulting issues in coordination with the Owner, Consultant and Contractor.

· Consultant shall provide a fully functional SCADA system including programming development of screen displays, and software configuration services that comply with City control standards. Consultant’s programming subconsultant shall be a local Rockwell partner with experience at the WRP.

The selected consultant shall include in their budget, estimated hours for project commissioning and startup items.

Final Inspection The Consultant shall participate in and document the final inspection.

Manuals, Training and Procedures

Contractor Provided O&M Manuals The Program Construction Administration Team shall obtain from the Contractor O&M manuals, warranties and guarantees for materials and equipment installed in the project, including the submission of spare parts. The Program Construction Administration Team shall review initial O&M manuals and O&M data received from Contractors, following Consultant’s technical review, and prior to be returned to Contractor.

System-wide O&M Manuals In addition to the Contractor provided O&M manuals, the Consultant shall produce a system level O&M manual. The City will provide examples of acceptable system-wide O&M manuals and the Consultant shall follow the agreed upon format. The system-wide manual shall address normal and alternate operating modes and control strategies such as power-outages and wet weather. The system-wide manual should cover such items as routine maintenance, emergency maintenance, trouble shooting, instrumentation and control set points, alarms, sequence of operation, and manual/automatic modes. Tabular summaries should be used whenever possible. The manual shall contain process flow charts, schematics, and hydraulic grade lines. The system-wide O&M manual shall refer to numerous equipment-specific O&M manuals provided by the Contractors.

Draft system-wide O&M manual shall be provided to the City within three months of substantial completion of any construction contract. The City will provide comments within one month and the Consultant shall provide final system-wide O&M manual within one month of City review.

Training In addition, the Consultant shall provide system-wide training covering the topics in the system-wide O&M manual. Two training sessions for plant shift workers plus two training sessions for trade specific staff shall be required and shall be scheduled to follow individual component training required of the Contractors, sub-contractors and their vendors. The Consultant shall utilize a third-party on-line training company to produce on-line training modules compatible with existing City training software. All training shall be project specific.

The Consultant shall incorporate/populate new and adjoining existing asset data into the City’s future CMMS system along with maintenance and inspection intervals recommended in equipment O&M manuals.

Standard Operating Procedures (SOP’s) The Consultant shall produce system level SOP’s. The Consultant shall review existing WRP system-wide SOP’s and either revise them based on the new improvements or incorporate relevant information into new SOP’s. The City will provide examples of acceptable SOP’s and the Consultant shall follow the agreed upon format. The system-wide SOP’s shall provide procedures on how to startup, shutdown the process and how to operate in remote auto, remote manual and hand/manual controls. The SOP’s shall address normal and alternate operating modes and control strategies; and include instrumentation and control set points, alarms, interlocks, sequence of operation, and as applicable safety procedures.

The SOP’s shall be produced in an electronic format such that the material can be viewed on computer monitors and provided in 3 hard copies in 3 ring binders and a copy on jump drive. SOP’s should also be provided in other multi media modes, where possible, such as phone, tablet or PC applications. Draft system-wide SOP’s, or revisions to existing system-wide SOP’s shall be provided to the City within three months of substantial completion of any construction contract. The City will provide comments within one month and the Consultant shall provide final system-wide SOP’s within one month of City review.

Record Plans The Program Construction Administration Team will maintain a set of drawings indicating the as-built conditions to be utilized in preparation of record drawings by the Consultant at the conclusion of the project work. This set will be updated weekly with revisions from the RPR’s field plan mark-ups and shall be separate from the construction Contractor’s as-built drawings. The Program Construction Administration Team will coordinate and transmit submittals of information from the Contractors affecting record drawings to the Consultant for incorporation in record drawing. The Program Construction Administration Team will review the as-built drawings provided by the Contractor for general accuracy, compare Contractor’s as-built drawings to the Program Construction Administration Team’s as-built drawings and work with the Contractor to reconcile discrepancies (when applicable), and verify that the Consultant certifies the record drawings, as required. The Program Construction Administration Team will turn over the checked and reconciled Contractor as-built drawings to the Consultant for their use in preparing record drawings.

The Consultant shall submit a complete set of record drawings, incorporating all markups, into a complete AutoCAD (Revit or Civil 3D, as appropriate) file, 3 hard copies, and pdf files to the City within 30 days of the conclusion of the project, including completion and approval of all punch list items, or as directed by City.

Other services (Supplemental Service) From time to time during the course of the Package 1 projects, the City may require services beyond those set forth in this Scope of Services. The City will then issue a task order request, and the Consultant shall prepare a brief scope of services and fee estimate to accomplish the additional work.

General Conditions

Disclosure of RFP-Related Activities The Proposer agrees not to refer to the Department of Public Works or any of its Divisions in relation to this RFP and any related activities in any media form without the prior written consent of the Director of the Department of Public Works.

Applicable Taxes The selected Proposer shall be responsible for payment of all applicable federal, state, and local taxes that are in any way related to this project and its completion by the selected Proposer, including but not limited to employment taxes for its employees or agents, sales taxes, property taxes, unemployment compensation taxes, franchise taxes, and withholding taxes.

Ownership Any software (except that identified as existing and owned by the selected Proposer prior to contract award), plans and specifications, maps, drawings, digital data specifications, plots, reports, database scheme, database dictionary, and any other products and material (including copies thereof) developed for this project are the exclusive property of the City of Toledo and shall be delivered to the City in accordance with the project schedule or upon termination of the project.

The selected Proposer shall not assert or establish any right or claim under design patent or copyright laws to any of the materials created or produced specifically for, and in conjunction with this project.

The selected Proposer shall not utilize the City’s data, on other similar projects or for other customers without the prior written consent of the Director of Public Utilities.

The selected Proposer shall not utilize the City’s data, for any type of commercial, marketing, or promotional purpose (including system or process demonstrations) without the prior written consent of the Director of Public Utilities.

Insurance The City of Toledo's standard insurance requirements for professional service agreements is included in this RFP as Exhibit G. The selected Proposer shall be required to adhere to all of its clauses.

Deviations, Omissions and Conflicts It is not the intent of the City to deviate from the professional consulting services practice, and while the specifications contained in this RFP are intended to be complete in themselves, the Proposer shall consider itself to be bound by the professional consulting services practice whether or not specific reference is made thereto. The Proposer shall notify the issuing division contact noted in Section 1.2 of this RFP in writing through PlanetBids of any apparent deviations, omissions, ambiguities, or conflicts noted in this RFP which may affect the performance of this work.

Errors or Omissions in RFP Submittal The Proposer shall be responsible for all errors or omissions in its proposal. The Proposer may correct any errors and omissions in its proposal by submitting a written request by the proposal due date. This written request must be signed in the same manner and by the same person who signed the proposal and must contain instructions and page numbers for updating the original proposal.

Right to Withdraw Proposals The Proposer may withdraw its proposal by submitting a written request by the proposal due date. Proposals that are withdrawn shall be handled at the Proposer's expense, according to the instructions included in the Proposer's request to withdraw, provided such instructions are reasonable.

Effective Period of Proposal The proposal shall remain in effect for a period of at least one hundred and eighty (180) days from the proposal due date.

Proposal Liability Any and all costs incurred in responding to this RFP, including oral interviews, demonstrations or other related activities shall be the responsibility of the Proposer.

The proposal material, including supporting materials, and other information disbursed during the proposal process, will become the property of the City of Toledo.

Any material submitted with this proposal will be treated as a public document unless informed in writing by the Proposer that the Proposer considers such material to contain trade secrets under Ohio law. The City may require additional information in support of such a claim.

The City of Toledo is a public entity that must comply with certain legal requirements and internal review procedures prior to awarding any agreement. No party has the right to expect that they will be awarded an agreement with the City absent adherence to these legal requirements and review procedures. All agreements with the City of Toledo must contain the signature of the Mayor or the Mayor's duly authorized designee.

Proposers are advised that the City of Toledo will not indemnify any company or contractor so responses seeking such will be rejected. Proposers are also advised that the City of Toledo can only agree to the Laws of the State of Ohio so any responses seeking to make an agreement subject to the Laws of any other state will be rejected.

The City of Toledo reserves the right to refuse to enter into an agreement with any party unless and until all legal requirements have been adhered to and the Mayor or the Mayor's duly authorized designee executes the agreement.

In submitting a proposal, the Proposer acknowledges that the City of Toledo shall not be responsible for delays caused by errors, omissions or ambiguities on the part of the Proposer in any submission.

Safety The successful Proposer shall at all times meet or exceed all Federal, State, and City safety requirements in carrying out this project. These requirements include but are not limited to traffic control and confined space entry.

Traffic controls shall be furnished by the selected Proposer in accordance with the current “Ohio Manual of Traffic Control Devices for Streets and Highways”, and as supplemented by the City of Toledo’s Manual, which may be obtained at the Division of Transportation.

Compensation The applicant must provide a quote for the services not to exceed an amount based upon hours worked to complete the scope of work and all deliverables, including (1) a description of the type of activities to be undertaken; (2) a description of the fees to be charged for each activity; (3) the number of hours anticipated to be charged for each of the services rendered; and (4) any miscellaneous expenses, including production of documents, shall be included and estimated as applicable.

Price Proposal Form The attached Price Proposal Form shall be completed by the proposer. Total hours and cost for each task listed on the Price Proposal Form shall be provided.

Pricing Procedure The total hours for each task should as accurately as possible reflect the total effort, including that of all sub-consultants, needed to perform the complete project as outlined in this RFP. Hours in all tasks must be identified by job category for each activity and attached to the Price Proposal Form. Proposers must also indicate their company’s multiplier on direct labor without benefits or fringes and that of all major sub-consultants. All work performed by sub-consultants shall be identified by hours and cost for their respective area(s) of responsibility, and also attached to the proposer's Price Proposal Form.

Billing Procedure The successful Proposer will be awarded a contract as specified herein with a direct labor (not including benefits or fringes) times a factor method of payment. Direct expenses may be marked up by a factor not exceeding five percent. A maximum of three percent markup will be allowed on sub- Consultants. Billing will be on a monthly basis, with the Consultant submitting an invoice indicating staff hours and the appropriate hourly charges, broken down by task and project, and also indicating total hours per employee per billing period. Total hours per employee should not exceed 200 per month. Premium time will not be permitted without prior authorization from the City.

Subconsultants’ invoices shall be attached to the Consultant's invoice in the same format and shown on the Consultant's invoice as an outside reimbursable cost. Unless there is a change in scope from the original project definition, the total agreed to project cost shall not be exceeded. Any change in scope shall be brought to the attention of the City as soon as possible. Any change in scope or additional work performed must be documented in writing and approved by the City of Toledo. All invoices will be subject to audit by the City of Toledo Auditor and any funding agency audits.

Professional Services Agreement If a contract is awarded, the successful Proposer shall enter into a Professional Services Agreement with the City.

PRE-BID MEETING

There will be a pre-bid meeting held on Tuesday, December 1, 2026 at 1:00pm EST at: 3900 N. Summit Street Bldg. #1, Toledo, OH 43611. Attendance is strongly encouraged.

Form of Response A. Title Page -List the RFP title -The name of the firm -The name, title, address, telephone number, and email address of the primary contact person.

B. Letter of Transmittal Provide a letter expressly confirming that the firm fully understands the scope of services to be provided and the commitment to perform the services in a timely and cost effective manner. Responders shall indicate an anticipated timeframe to accomplish all objectives set forth in this scope of work. The firm must also commit to assigning to this scope of work professionals who have experience providing financial, performance, and management services.

Each Proposer shall submit proposals organized as described below. Proposals shall be no more than 26 total pages of information (e.g., text, photos, graphics, etc.) in length inclusive of all sections.

A page is one side of a sheet of paper with text, photos, graphics, etc. Required forms, title sheets, cover letter, and table of contents are not counted towards this total. No appendices or additional information is acceptable. Firms who fail to abide by these page limitations and submit all required information will be considered non-responsive.

C. Required Information The Proposer and any sub-Consultants/partners should provide the following information in their proposal:

Qualifications and Related Project Experience Proposer shall include a statement of the firm's qualifications to provide the requested services. The qualifications and experience statement shall include the following:

· A general background (Company Name, Address, Telephone, Ownership)

· Project Manager's and other key task managers' background, experience, and credentials

· Professional services offered and number of employees assigned to each service

· Examples of at least three similar projects that have been completed, or are at least 90% complete, within the past five years. Examples should include the project managers and key task managers included in this proposal

· A list of at least five (5) references, including name, address and telephone number of contact person for similar projects

Office Location Provide a statement of the firm's primary office location and whether a local office will be available. Include a discussion on staff accessibility for the project. Designate the office location where the primary work will be performed. Include anticipated type of work to be done at each office, including all subcontracted work. Also include the percentage (by dollar amount) of the total project work each office will handle, including all subcontracted work.

Familiarity with Local, State and Federal Regulations Provide a statement of the firm's familiarity with City of Toledo, any applicable State of Ohio, and Federal laws, regulations, or standards relevant to this type of project.

Current Workload Provide a description of the firm's current workload. Include the availability of the firm, proposed project managers, and key staff to immediately commence this project upon receipt of a Notice to Proceed.

Performance on Previous Projects Provide a list of previous contracts with the City of Toledo or other government agencies for comparable projects. Include a summary of performance for each project, the ability to meet schedule, and any savings or benefits resulting from your actions.

Understanding of Project A description in detail of the firm's understanding of the services to be provided and anticipated approach to completing the project as outlined in Section 2, "Scope of Services" and accompanying PDR. Do not merely re-state the Scope of Services. Include any considerations or evaluations which may be prudent to effectively minimize the project cost, ensure timely completion of the project, and more satisfactorily achieve the project goal. Also include any possible challenges that will be encountered and any intended or probable special techniques, services, or approaches to be used for solution. Discuss potential alternate methods. If there are certain tasks that could more easily be performed by City personnel, that would result in substantial cost savings, indicate these savings, but do not include in your cost proposal.

Staffing A list and organization chart of key personnel and subconsultants who will work on the project and their technical competence and related specialized experience. Designate the person from the primary Consultant who will manage the project.

The City fully expects that the personnel and subconsultants listed in the proposal will be assigned to the project in the event that your firm is selected. Any personnel or subconsultant changes in key positions shall be subject to advance approval by the City.

Disadvantaged Business Enterprise (DBE) Participation Include a description of any joint ventures, partnerships or subcontracts with DBEs that are certified by the City of Toledo’s Office of Diversity and Inclusion. The description should include the name of the company(s), the description of the work to be performed by the DBE and the amount and percentage of the contract that will be awarded by provider to DBEs.

Required Forms at Time of Proposal PlanetBids lists the forms and paperwork that are due with the proposal.

Other The proposal may contain any other pertinent information that the firm would like the City to consider. The proposal should list any other factors or distinguishing characteristics of the firm that would provide benefit or advantage to the City. The Proposal should list any suggested changes or improvements to the existing system.

Submission Proposals for this project can only be accepted via electronic submittal through the City of Toledo’s PlanetBids website. Bid submittals or other transmissions of information have not been completed until an email confirmation of the transmission has been issued by PlanetBids. Bids prices shall be to two (2) decimal places (i.e. $0.00). Only one (1) price per line item will be accepted with this bid.

In order to be awarded a contract, the City requires all of the following documents must be submitted with each bid your company submits in 2026 in PlanetBids:

•Letter of Transmittal
•Project Paperwork*

-Acknowledgement and Acceptance of Conditions and Contract Specifications -Living Wage Contract Addendum -Primary/Subcontractor Agreement Certificate

• City of Toledo Professional Services Agreement*

· Cost File – Price Proposal Form (Below, pg. 26) (requirements available on the “Documents” tab in PlanetBids) and *any additional items to be submitted by vendor such as cost proposal at time of bid.”

*Located on the “Documents” tab in PlanetBids

Beginning with bids advertised on or after March 13, 2026 the following documents will only need to be submitted once for your company for the duration of all contracts with the City. If any information changes, it is the company’s responsibility to notify the city and update the applicable documentation.

City Paperwork

· Vendor Registration Form, if your company is new to doing business with the city

· Business Tax Registration Form, if company is new to doing business with the city

· Child Support Affidavit, notarized

· Vendor Utility

Beginning with bids advertised on or after March 13, 2026 the following documents will only need to be submitted once for all bids your company submits in 2026. If any information changes, it is the company’s responsibility to notify the City and update the applicable paperwork.

Annual Paperwork:

· W-9

· Insurance Certificate, naming the City of Toledo as an additional insurer – requirements available on the “Documents” tab of PlanetBids

· EEO Compliance

· Debarment Certification

· Living Wage Affidavit, updated no later than February 1st

• Bureau of Workers Compensation Certificate

Bid Opening Meeting Bids will be open at 2 PM EST on the due date of this bid via Zoom Meeting at: