RFP_PR_26_003_FoundersOakParkPlayground_Carte.pdf

PDF 370 KB Posted

Attached to
Cartersville - Founders Oak Park Playground
Solicitation number
PE-60899-NONST-2026-000000074
Issued by
Barrow County, Georgia

About this file

This Request for Proposals (RFP PR-26-003) is issued by the City of Cartersville, Georgia, seeking qualified playground designers and manufacturers to design, supply, and install playground equipment for Founders Oak Park, a pocket park being created as part of the City Hall redevelopment project. The project centers on creating a distinctive playground inspired by the legacy of the historic Founders Oak Tree, which was planted over 175 years ago at the city's founding. The playground design should feature a primary tower-style play structure serving as the focal point, complementary structures for younger children ages 2-5, and various play components including motion-based elements, balance and climbing features, and sensory play opportunities. The design must incorporate inclusive and accessible play features compliant with ASTM, CPSC, and ADA standards, along with rubberized safety surfacing, seating areas, shade structures, and thematic elements honoring the oak tree's legacy. Questions are due by Wednesday, May 13, 2026, with the City's responses provided by Friday, May 15, 2026. Proposals must be submitted by Monday, June 1, 2026, at 2:00 PM EST to the City Office Building at 1 N Erwin Street, Cartersville, Georgia 30120, with selection and contract award anticipated for Thursday, June 4, 2026. The playground installation is scheduled for months 13-16 of the City Hall construction project, which began in late February/early March 2026 with anticipated completion in approximately 13 months.

The vendor will be responsible for providing the conceptual design, equipment specifications, cost proposal, supply and installation of playground equipment and surfacing, and coordination with City staff and the City Hall project team. Site preparation, including grading and base preparation, will be completed by the general contractor, while the playground vendor coordinates equipment specifications and installation requirements with the City. The proposal will be evaluated based on design creativity and theme integration (35%), play value and inclusivity (25%), quality and durability of equipment (20%), and cost and overall value (20%). Submissions must include one printed copy and a digital copy on a USB drive in a sealed package. No specific budget amount is stated in the RFP. The City reserves the right to reject any or all proposals and select the proposal that best serves the City's interests.

View the file

Other files

File Type Posted
CityHall_PhasedPlan.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RequestforProposals
FoundersOakParkPlayground

RFP: PR-26-003

ProposalsDue:
Monday,June1,2026

2:00 PM EST

Issued by

City of Cartersville, Georgia

Questionsshouldbedirectedviaemailto:
FreddyMorgan–fmorgan@cartersvillega.gov
AssistantCityManager
1NErwinStreet,Cartersville,GA30120
CC:LoganBagley–lbagley@cartersvillega.gov
PublicRelations&CommunicationsManager

Introduction

TheCityofCartersvilleisseekingproposalsfromqualifiedplaygrounddesignersand
manufacturerstodesign,supply,andinstallplaygroundequipmentforFoundersOakPark,
anewpocketparkbeingcreatedaspartoftheCityHallredevelopmentproject.
TheplaygroundwillserveasatributetothehistoricFoundersOakTree,whichwasplanted
whenthecitywasfoundedmorethan175yearsago.Whilethetreehasreachedtheendof
itslifeandmustberemovedforsafetyreasons,theCityintendstohonoritslegacyby
transformingthespaceintoawelcomingparkforfamiliesandchildren.
Theselectedfirmwillhelpcreateauniqueplaygroundexperienceinspiredbythecharacter
andlegacyoftheoaktreewhileprovidinganengagingandinclusiveplayenvironmentfor
thecommunity.
ProjectBackground
FoundersOakParkislocatedadjacenttotheCityHallredevelopmentprojectand
historicallycenteredaroundtheFoundersOakTree.Thetree,plantedatthetimeofthe
City’sfounding,haslongservedasasymboliclandmarkwithinthecommunity.
Duetoageandsafetyconcerns,thetreewillberemovedaspartoftheCityHall
redevelopment.TheCityplanstocommemoratethelegacyofthetreebycreatingasmall
pocketparkandplaygroundthatcelebratesthesite’shistorywhileprovidinganengaging
andinclusiveplayenvironment.
ProjectGoals
•CreateadistinctiveplaygroundinspiredbythelegacyoftheFoundersOakTree
•Designawelcomingandinclusiveplayspaceforchildrenandfamiliesofallabilities
•Provideavarietyofplayexperiencesthatencourageimagination,movement,and

exploration

•Incorporateseating,shade,andgatheringareasforfamiliesandcaregivers
•Createacohesivedesignthatreflectsthenaturalcharacterandstoryofthesite
PlaygroundDesignConcept
TheCityenvisionsaplaygroundcenteredaroundaprimarytower-styleplaystructure
designedforchildrenofallages.Thisstructurewillserveasthefocalpointofthe
playgroundandreferencetheform,strength,andpresenceoftheoriginaloaktree.
Thisprimarystructureshouldofferarangeofplayopportunitiesincludingclimbing,
exploration,andelevatedplayelementsappropriateforawiderangeofages.

Additional play elements may include:

•Acomplementaryplaystructuredesignedspecificallyforyoungerchildrenages2–5
•Motion-basedplaycomponents
•Balanceandclimbingelements
•Interactiveorsensoryplayfeatures
•Ground-levelplayopportunities
Designsshouldcreateafun,welcomingenvironmentwithafreshandcohesivelook,
offeringamoderntakeontheoaktreethroughformandcharacter,andcreatingaplayful
spacethattiesbacktothestoryofthesite.
InclusivePlay
TheCityencouragesdesignsthatsupportinclusiveandaccessibleplay.Theplayground
shouldprovideopportunitiesforchildrenofvaryingabilitiesanddevelopmentalstagesto
playtogether.
Designconsiderationsshouldinclude:
•Accessibleplaycomponents
•Sensory-richplayexperiences
•Ground-levelplayopportunities
•Accessiblecirculationwithintheplayground
•Opportunitiesforcaregiversandfamilymemberstocomfortablyengageinthespace
AdditionalParkElements
Inadditiontoplaygroundequipment,proposalsmayincluderecommendationsfor
complementaryparkfeaturessuchas:
•Seatingareasandbenches
•Shadestructuresorshadeelements
•Gatheringspacesforfamilies
•ThematicelementsthatreinforcethestoryoftheFoundersOakTree
Theseelementsshouldsupporttheusabilityandcomfortoftheparkwhilemaintainingthe
overallthemeofthesite.
ProjectTimelineandCoordination
ConstructionofthenewCityHallfacilitybeganinlateFebruary/earlyMarch2026andis
anticipatedtobecompletedinapproximately13months.
OnceCitydepartmentsrelocatetothenewfacility,theexistingCityHallbuildingwillbe
demolishedandworkwillbegininthatarea.InstallationoftheFoundersOakPark
playgroundwilloccurduringthisphaseoftheproject(months13-16).
TheselectedplaygroundvendorwillbeexpectedtocoordinatewiththeCityandtheCity
Hallprojectteamtoensuredeliveryandinstallationalignswiththeoverallconstruction

schedule.

SiteWorkResponsibilities
Sitepreparationandgeneralsiteworkfortheplaygroundareawillbecompletedbythe
generalcontractorfortheCityHallproject.
Thisworkmayincludegrading,basepreparation,utilities,andothersiteimprovements
necessarytopreparetheplaygroundareaforequipmentinstallation.
Theawardedplaygroundvendorwillberesponsibleforcoordinatingequipment
specificationsandinstallationrequirementswiththeCitytoensurecompatibilitywiththe
preparedsiteconditions.
PlaygroundSurfacing
Theplaygrounddesignmustincluderubberizedsafetysurfacingappropriateforthe
proposedequipmentandcompliantwithapplicableplaygroundsafetystandards.
Theselectedvendorwillberesponsiblefor:
•Providingtherubberizedsurfacingsystem
•Coordinatinglayoutandfallzonerequirements
•Installationoftherubberizedsurfacing
•Ensuringsurfacingmeetsapplicablesafetystandardsandmanufacturerspecifications

Surfacing should complement the overall design theme of the playground.

ScopeofServices
Theselectedfirmwillbeexpectedtoprovide:
•Conceptualplaygrounddesign
•Proposedequipmentandplaycomponents
•LayoutandsiteintegrationbasedonCity-providedplans
•Productspecificationsandsafetycompliancedocumentation
•Costproposalforequipmentandrelatedcomponents
•Supplyandinstallationofrubberizedplaygroundsafetysurfacing
•CoordinationwithCitystaffandtheCityHallprojectteamduringdesignand

implementation

AllplaygroundequipmentandsurfacingmustcomplywithapplicableASTM,CPSC,andADA
accessibilitystandards.
ProposalRequirements
Proposalsshouldinclude:
•Conceptualdesignorvisualexamplesillustratingtheproposedplaygroundapproach
•Descriptionofproposedplaystructuresandequipment
•Productspecificationsandmaterialsinformation
•Estimatedcostforequipmentandrelatedcomponents
•AproposedprojecttimelinebasedontheCity-providedprojectschedule,demonstrating
thevendor’sabilitytomeetanticipateddeliveryandinstallationtimeframes
•Photographsofsimilarplaygroundprojectscompletedbythevendor
•Referencesfromcomparableprojects

Attachments

ThefollowingmaterialsareincludedwiththisRequestforProposalsandshouldbeusedby
proposerswhenpreparingtheirsubmissions:
AttachmentA–Siteplanwithapproximatedimensionsoftheplaygroundsite
AttachmentB–PhasedconstructionplanforoverallCityHallproject
Thesedocumentsprovidethelayout,dimensions,andcontextfortheFoundersOakPark
playgroundareaandshouldbereferencedwhendevelopingproposedplaygrounddesigns
andequipmentlayouts.
SelectionCriteriaandScoring
DesignCreativityandThemeIntegration–35%
EvaluationofhowwelltheproposeddesigncapturesthespiritoftheFoundersOakTree
andcreatesamemorableandengagingplayenvironment.
PlayValueandInclusivity–25%
Evaluationofthevarietyofplayopportunities,accessibility,andabilitytosupportchildren
andfamiliesofvaryingagesandabilities.
QualityandDurabilityofEquipment–20%
Evaluationofmaterials,craftsmanship,safetystandards,andlong-termdurabilityofthe
proposedequipment.
CostandOverallValue–20%
Evaluationoftheoverallcostoftheproposalandthevalueprovidedrelativetothedesign
andequipmentoffered.

Total: 100%

ProjectSchedule
RFPIssued:Friday,May1,2026
QuestionsDue:Wednesday,May13,2026
City’sResponsestoQuestions:Friday,May15,2026
ProposalsDue:Monday,June1,2026@2:00PMEST
SelectionandContractAward:Thursday,June4,2026
SubmissionInstructions
Proposalsmustbereturnedinasealedpackagemarkedontheoutsidewith“Requestfor
Proposal–CityofCartersvilleFoundersOakParkPlayground”andthecompanyname.
Eachsubmissionmustincludeone(1)printedcopyoftheproposalaswellasadigitalcopy
onaUSBdrive.

Proposals should be delivered to:

CityOfficeBuilding
1NErwinStreet
Cartersville,Georgia30120
AdditionalInformation
TheCityofCartersvillereservestherighttorejectanyorallproposalsandtoselectthe
proposalthatbestservestheCity’sinterests.

File details come from the government source that posted it. Updated .