RFP narrative.pdf

PDF 303 KB Posted

Attached to
Baconton Charter: Sports Facility
Solicitation number
PE-55407-NONST-2026-000000008
Issued by
Bacon County, Georgia

About this file

This is a Request for Proposal (RFP) narrative document for Baconton Community Charter School, a Georgia-based institution, outlining the scope of work for an athletic facility construction project. The project involves erecting a 140' x 95' steel building on a concrete foundation with customary gutters and downspouts, installing 3" of closed cell spray foam on the roof deck and gable ends, 4" of open cell spray foam on exterior walls, and sealing the perimeter with closed cell foam. The work includes installation of interior and exterior doors and windows meeting specified material requirements (steel or fire-rated wood interior doors, steel or FRP exterior doors, and double-paned insulated windows), adequate HVAC systems for each area, and buildout of a concession area, bathrooms, and classrooms using metal studs and drywall. Interior finishes include suspended grid ceilings with 2x2 and/or 2x4 tiles, VCT flooring throughout with the exception of sealed concrete flooring in the gymnasium area, commercial school-grade plumbing fixtures, customary electrical outlets and lighting, and painting to be designated at a later date. Interested parties should submit questions via email to lburkett@bccsblazers.org.

The fire suppression system must be provided as a separate quote in compliance with Title 25 of the Georgia Code, while the school will provide the fire alarm system, Ethernet infrastructure, and camera installation. No specific response date, bid due date, site visit requirements, bidder's meeting, award date, contract term, pricing terms, set asides, incumbent information, or funding sources are detailed in this scope of work document.

View the file

Other files

File Type Posted
BC Sports Facility 3_18_2026 cancellation.docx DOCX document
bid criteria.pdf PDF
drawing1.pdf PDF
drawing3.pdf PDF
drawing2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Athletic Facility

Baconton Community Charter School

Scope of Work:

Erect a 140’ x 95’ steel building on a concrete foundation per included drawing.

Install customary gutters and downspouts.

Install 3” of closed cell spray foam on the roof deck and gable ends, 4” of open cell spray foam on exterior walls, seal perimeter with closed cell foam.

Install interior/exterior doors and windows. (steel or fire-rated wood interior doors /steel or FRP exterior doors /double paned, insulated windows) per plans

Install adequate HVAC in each area.

Build out:

Concession area, bathrooms and classrooms with metal studs and drywall.

Suspended grid ceilings with 2x2 and/or 2x4 tiles and customary insulation.

VCT flooring with the exception of the GYM floor where sealed concrete will be used.

Plumb with commercial, school-grade fixtures.

Wire spaces with customary outlets and lighting.

Paint will be designated at a later date.

Fire suppression system: please provide a separate quote on FPS per Title 25 of the Georgia Code.

We will provide fire alarm system, Ethernet and camera installation.

Please submit questions by email: lburkett@bccsblazers.org