This document is a Request for Proposal (RFP) issued by the Minnesota Department of Natural Resources (DNR) Operations Services Division (OSD) and the Division of Parks and Trails (PAT) for Phase 1 Engineering Services to reconstruct the Green Lake County Park 5 and Green Lake Rush Brown Water Accesses in Kandiyohi County. The scope of work includes preliminary engineering, construction document preparation, and bidding assistance for the two water access sites. The goals are to provide a high-quality user experience, comply with stormwater and accessibility requirements, and incorporate best practices for aquatic invasive species. Responses are due by 2:00 PM Central Time on July 12, 2024, and the contract term is anticipated to be from August 2024 to November 2026, with potential extensions.

The RFP outlines the required proposal content, including a work plan, qualifications and experience, and cost detail. Proposals will be evaluated based on the work plan (40%), qualifications and experience (30%), and cost detail (30%). Preference points may be awarded for targeted group, economically disadvantaged, and veteran-owned businesses. The State reserves the right to negotiate with the highest-scoring respondent and make a single award or multiple awards, whichever is in the best interest of the State.

View the file

Other files

File Type Posted
RFP_Attachments.docx DOCX document
Sample_Contract.docx DOCX document
Green_Lake_County_Water_Accesses-_Master_Roster.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of Minnesota Department of Natural Resources

REQUEST FOR PROPOSAL

Green Lake County Park 5 and Green Lake Rush Brown Public Water Accesses Reconstruction SWIFT Event # 2000015925 Date Posted: June 13, 2024

· Responses must be received not later than 2:00 PM, Central Time, July 12, 2024

· Late responses will not be considered

Minnesota’s Commitment to Diversity and Inclusion The State of Minnesota is committed to diversity and inclusion in its public procurement process. The goal is to ensure that those providing goods and services to the State are representative of our Minnesota communities and include businesses owned by minorities, women, veterans, and those with substantial physical disabilities. Creating broader opportunities for historically under-represented groups provides for additional options and greater competition in the marketplace, creates stronger relationships and engagement within our communities, and fosters economic development and equality.

To further this commitment, the Department of Administration operates a program for Minnesota-based small businesses owned by minorities, women, veterans, and those with substantial physical disabilities. For additional information on this program, or to determine eligibility, please call 651-296-2600 or go to the Office of Equity in Procurement home page, at www.mn.gov/admin/oep.

SPECIAL NOTICE: This is a request for proposal. It does not obligate the State of Minnesota to award a contract or complete the proposed program, and the State reserves the right to cancel this solicitation if it is considered in its best interest.

Your firm was selected from the Real Estate and Construction Services Master Roster of design firms interested in working on State construction projects. This RFP requests a proposal from your firm for the above referenced project. If your firm is selected, RECS will then send a contract to you for signature.

This Solicitation requires proposals to be submitted through the SWIFT Supplier Portal. Please note the security changes below that may impact responders from submitting a timely response.

SWIFT SUPPLIER PORTAL SECURITY CHANGES

There are new security measures that the Minnesota Management and Budget implemented on October 16, 2022. It is a new multi-factor authentication (MFA) to enhance the security of the State of Minnesota Supplier Portal. MFA is an authentication method that requires bidders and suppliers provide two verification factors to log into the SWIFT Supplier Portal. The goal of MFA is to create a layered defense that makes it more difficult for unauthorized system access to occur.

For information about these changes, please refer to the SWIFT Supplier Portal Multi-Factor Authentication FAQ document.

If you have not done so already, please make sure to log into the SWIFT Supplier Portal as soon as possible to get this authentication set up early so there are no issues when submitting a response to an RFP.

You are strongly encouraged to set your MFA during business hours of 8:00 A.M. to 4:00 P.M., Central Time, Monday through Friday. You may experience delay setting your MFA after hours.

TABLE OF CONTENTS

Solicitation Content

SECTION 1 – INSTRUCTIONS TO RESPONDERS4
SECTION 2 – SUMMARY OF SCOPE5
SECTION 3 – PROPOSAL INSTRUCTIONS AND ADDITIONAL INFORMATION8
SECTION 4 – PROPOSAL CONTENT9
SECTION 5 – EVALUATION PROCEDURE AND CRITERIA10
SECTION 6 – SOLICITATION TERMS11

Solicitation Attachments

· Attachment A: Responder Declarations

· Attachment B: Exceptions to State's Terms and Conditions

· Attachment C: Cost Detail

· Attachment D: Responder Forms

· Veteran-Owned Preference Form

· Workforce and Equal Pay Declaration Page

Sample Contract

· Exhibit A: Contract Terms

· Exhibit B: Insurance Requirements

· Exhibit C: Specifications, Duties, and Scope of Work

· Exhibit D: Pricing

SECTION 1 – INSTRUCTIONS TO RESPONDERS

Steps for Completing Your Response
Follow the steps below to complete your response to this Solicitation:

Step 1: Read the solicitation documents and ask questions, if any Step 2: Write your response Step 3: Submit your response

Incomplete Submittals
A response must be submitted along with any required additional documents. Incomplete responses that materially deviate from the required format and content may be rejected.

STEP 1 – READ THE SOLICITATION DOCUMENT & ASK QUESTIONS, IF ANY

How to Ask Questions

The contact person for questions is:

Charles Schuman, Contract Officer Department of Natural Resources charles.schuman@state.mn.us Questions should be emailed to the contact seven days prior to event close.

Other personnel are not authorized to answer questions regarding this Solicitation.

STEP 2 – WRITE YOUR RESPONSE

The Response Content section is in this link to Section 4. Prepare a written response and supply all requested content. Responses should address the requested information and documents detailed in Section 4. DO NOT INCLUDE Non-Public/Trade Secret data (as defined in this link to Minn. Stat. § 13.37).

Review, sign, and include the Responder Declarations with your response.

STEP 3 –SUBMIT YOUR RESPONSE

Where to Send Your Response

All responses to this solicitation (termed an “Event” within SWIFT) must be submitted through SWIFT using the Supplier portal (https://mn.gov/supplier). Training and documentation on how to submit your response is available through the Supplier portal link above. Fax, e-mail, and printed responses will not be accepted or considered. All costs incurred in responding to this solicitation will be borne by the responder.

Late responses will not be considered. Responses received after End Date above will not be considered, even if errors or delays were caused by issues outside of responders’ control. If you need assistance please contact the SWIFT Vendor Assistance Helpline at 651-201-8100, Option 1, and then Option 1.

By submitting a response, your company is making a binding legal offer for the period of time set forth below in Section 6, Conditions of Offer.

SECTION 2 – SUMMARY OF SCOPE

Procurement Overview and Goals.

The Minnesota Department of Natural Resources (DNR) Operations Services Division (OSD) and the Division of Parks and Trails (PAT) request proposals for Phase 1 Engineering Services to perform all work necessary to prepare construction plans and specifications for the reconstruction of the Green Lake County Park 5 and Green Lake Rush Brown Water Accesses in Kandiyohi County.

Phase 2 Bidding and Construction Administration Services will include bidding assistance and construction contract administration for Green Lake County Park 5 Water Access.

Phase 3 Bidding and Construction Administration Services will include bidding assistance and construction contract administration for Green Lake Rush Brown Water Access.

Note: One Consultant Contract will be awarded for the Phase I Engineering Services for both Green Lake County Park 5 and Green Lake Rush Brown Water Accesses. Upon completion of the Phase I Engineering Services, it is the State’s intent to request a proposal from the contractor and negotiate the engineering fees for the Phase 2 and Phase 3 Engineering Services, with the Phase I contractor.

Both sites are currently functioning water accesses requiring improvements to accommodate larger vehicles and trailers, potential subgrade correction, improved permanent stormwater management, aquatic invasive inspections area, accessible parking and routes, and boat ramp preplacement. The County Park 5 Water Access consists of two parcels one owned by Kandiyohi County and the other by the State of Minnesota. The Rush Brown access consists of multiple parcels with Kandiyohi County and State of Minnesota ownership.

The goals are to provide:

· A high-quality user experience to safely launch, park and retrieve watercraft.

· Comply to the extent reasonable and practical with stormwater permitting, considering Middle Fork Crow River Watershed District rules and DNR’s minimum impact design standards (MIDS) for stormwater management.

· Incorporate DNR best practices for aquatic invasive species.

· Comply with Department of Justice’s ADA Standards for Accessible Design.

Sample Tasks and Deliverables.

The intent is to complete preliminary engineering and construction documents concurrently for both projects. All deliverables identified within the scope of services and related construction documents for both water accesses. Such as, but not limited to:

Preliminary Engineering A. Project Kickoff

· Meet with the project team and walk the sites.

B. Site Assessments for Both Water Access

· Collect and draw boundary, topographic, bathymetry, and utility survey.

· Complete a geotechnical investigation.

· Complete a wetland delineation report and TEP concurrence (Rush Brown site only).

C. Conceptual Design

· Prepare conceptual design (30%) documents for review by the DNR project team.

· Include layout and stormwater plans.

· Provide SHP files of the estimated construction limits to be for archeology and resource reviews.

· Coordinate with the Middle Fork Crow River Watershed District

· Lead one Conceptual Review meeting with the DNR Project Team

· Allow twelve (12) business days for review by the DNR project Team. The DNR shall provide one (1) written set of comments to the consultant.

Construction Documents D. 60% Construction Document Submittal

· Virtually meet with DNR project manager as necessary to discuss design, grading, and standard details.

· Include removal & erosion control, layout, grading, stormwater, ramp details, pavement sections, LED solar light detail, stormwater pollution prevention plans, and planting plan.

· Consolidate all conceptual design review comments and results of permit review into a final construction document set.

· Provide a Civil 3D grading plan with proposed grading surface for use by DNR to incorporate into HEC-RAS modeling.

· Provide 60% stormwater management report.

· Provide SHP files of the estimated construction limits to be used for archeology and resource reviews.

· Prepare a detailed unit price cost estimate.

· Provide a complete index of all specification sections.

· Coordinate with the Middle Fork Crow River Watershed District as needed.

· Lead one 60% construction document review meeting with the DNR Project Team

· Allow twelve (12) business days for review by the DNR project Team. The DNR shall provide one (1) written set of comments to the consultant.

E. 95% Construction Document Submittal

· Virtually meet with DNR project manager as necessary to discuss construction documents and permit application information.

· Consolidate all 60% design review comments and results of permit review into a final construction document set.

· Plan set to include all sheets, details, and notes.

· Provide a Civil 3D grading plan with proposed grading surface for use by DNR to incorporate into HEC-RAS modeling.

· Provide 95% stormwater management report.

· Provide 95% Operation and Maintenance Manual for stormwater infrastructure.

· Provide SHP files of the estimated construction limits to be for archeology and resource reviews.

· Prepare final detailed unit price cost estimate that will also be used for bidding.

· Provide final specification sections. The DNR will provide Division 00 and 01 sections.

· Coordination Middle Fork Crow River Watershed District as needed.

· Provide information necessary to complete all permit applications. The DNR will apply for permits using information provided by the consultant.

· Lead one 95% construction document review meeting with the DNR Project Team

· Allow twelve (12) business days for review by the DNR project Team. The DNR shall provide one (1) written set of comments to the consultant.

F. Final Construction Documents

· Virtually meet with DNR project manager as necessary to discuss construction documents and permit application information.

· Consolidate all 95% design review comments and results of permit review into a final construction document set.

· Separate Project Manual documents (to allow different bid dates) shall include signed project plans by a registered professional(s) in the State of Minnesota and specifications.

· Provide final detailed unit price cost estimate that will also be used for bidding.

· Project Manual shall be signed and delivered in PDF format.

· All electronic design files shall be available upon request.

· Provide a complete construction staking xls table for both sites.

· Provide final stormwater management report.

· Provide Operation and Maintenance Manual for stormwater infrastructure.

G. Services and Documentation Provided by DNR

· Standard DNR details for water accesses, however consultant may need to modify these details.

· AutoCAD Civil 3D 11x17 title block.

· Specification Division 00 and 01 sections.

· Cost estimating/bidding spreadsheet.

· U.S. Army Corps of Engineers No-Rise Certificate and DNR Public Waters Work Permit.

· Archeology field work and State Historic Preservation Office coordination.

· No-Rise analysis and modeling

· Overall project schedule(s).

· Construction bid advertising.

Anticipated Project Design Schedule.

· Notice to Proceed/Executed ContractAugust 1, 2024
· Survey complete and remaining due diligence in-progress/completeSeptember 10, 2024
· Concept (30%) submittalOctober 1, 2024
· 60% Construction document submittalNovember 1, 2024
· 95% Construction document submittalDecember 2, 2024
· Bid documents completeJanuary 2, 2025

Phase 2 and Phase 3 Bidding and Construction Administration Services:

Upon completion of the Phase I Engineering Services, it is the State’s intent to request a proposal from the contractor and negotiate the engineering fees for the Phase 2 and Phase 3 Bidding, Construction Contract Administration, Construction Quality Control, and Final Construction Documentation with the Phase I contractor. When requested, the proposal presented for Phase 2 and Phase 3 Services shall include fees as follows:

Note: award of this contract for phase 1 engineering services does not obligate the state to award phase 2 or phase 3 services to the engineering firm selected to provide phase 1 engineering services.

SECTION 3 – PROPOSAL INSTRUCTIONS AND ADDITIONAL INFORMATION

1. Anticipated Contract Term.

The term of this contract is anticipated to be from August 2024 to November 2026, with the option to extend up to an additional two years in increments determined by the State.

Question and Answer Instructions.

All questions should be submitted no later than the date and time listed in Section 1, Instructions to Responders. The State is not obligated to answer questions submitted after the question due date and time.

Only personnel listed above are authorized to discuss this solicitation with responders. Contact regarding this solicitation with any personnel not listed above could result in disqualification. This provision is not intended to prevent responders from seeking guidance from state procurement assistance programs regarding general procurement questions.

If a Responder discovers any significant ambiguity, error, conflict, discrepancy, omission, or other deficiency in the solicitation, please immediately notify the contact person detailed above in writing of such error and request modification or clarification of the document.

Additional Tasks or Activities.

Responders are encouraged to propose additional tasks, activities, or goods above and beyond the scope of what is requested in this solicitation if they will substantially improve the results of this procurement. Any costs associated with these additional tasks, activities, or goods should be clearly marked and separated from costs associated with the tasks, activities, or goods specifically requested under this solicitation. Because cost is a factor in the evaluation of responses to this solicitation, failure to separate costs for additional tasks, activities, or goods may result in those costs being included in a responder's cost proposal and result in a lower cost score for that proposal.

SECTION 4 – PROPOSAL CONTENT

Please submit the following information:

Work Plan. Responder should provide a description of the deliverables to be provided by the Responder along with a detailed work plan that identifies the major tasks to be accomplished and be used as a scheduling and managing tool, as well as the basis for invoicing. This document should NOT list cost detail. If cost detail is included in this document, the State may disqualify the proposal as non-responsive. Responder should provide a statement of the objectives, goals, and tasks to show or demonstrate the Responder's view and understanding of the nature of the contract, and what makes the Responder uniquely suited for this work.

Qualifications and Experience. Responder should provide an outline of background and experience with examples of similar work done by the Responder and a list of personnel who will conduct the project, detailing their training, and work experience. Resumes or other information about project personnel should not, if possible, contain personal telephone numbers, home addresses, or home email addresses. If it is necessary to include personal contact information, please clearly indicate in the response that personal contact information is being provided.

Cost Detail. Complete and submit Attachment C, “Cost Detail,” attached to this solicitation.

Submit all requested documentation, including, but not limited to, the following documents:

1. Attachment A: Responder Declarations

2. Attachment B: Exceptions to State's Standard Terms and Conditions

3. Attachment C: Cost Proposal

4. Attachment D: Responder Forms

a. Veteran-Owned Preference Form

b. Workforce and Equal Pay Declaration Page

DO NOT INCLUDE Non-Public/Trade Secret data (as defined by Minn. Stat. § 13.37).

SECTION 5 – EVALUATION PROCEDURE AND CRITERIA

The State will conduct an evaluation of responses to this Solicitation. The evaluations will be conducted in three phases:

Phase 1 - Review responses for responsiveness and pass/fail requirements.

Phase 2 - Evaluate responses.

Phase 3 - Select finalist(s)

1. Phase 1 – Responsiveness and Pass/Fail Requirements The purpose of this phase is to determine if each response complies with mandatory requirements. The State will first review each proposal for responsiveness to determine if the Responder satisfies all mandatory requirements. The State will evaluate these requirements on a pass/fail basis.

Mandatory Requirements. The following will be considered on a pass/fail basis:

· Responses must be received by the due date and time specified in this RFP.

Phase 2 - Evaluate Responses Only those responses found to have met Phase 1 criteria will be considered in Phase 2.

The factors and weighting on which responses will be evaluated are:

1. Work Plan for Deliverables400 points
2. Qualifications and Experience300 points
3. Cost Detail300 points
1000 points
4. Preference Points (if applicable)120 points (in addition to 1,000 available)

Preference points are described under Solicitation Terms and will be applied to the total score after points have been awarded.

Phase 3 - Select Finalist(s) Only those responses that have been evaluated under Phase 2 shall be eligible for Phase 3.

The State will make its selection based on best value, as determined by this evaluation process. The State reserves the right to pursue negotiations on any exception taken to the State’s standard terms and conditions. In the event that negotiated terms cannot be reached, the State reserves the right to terminate negotiations and begin negotiating with the next highest scoring responder or take other actions as the State deems appropriate. If the State anticipates multiple awards, the State reserves the right to negotiate with more than one Responder.

It is anticipated that the evaluation and selection will be completed by the end of July 2024.

SECTION 6 – SOLICITATION TERMS

1. Competition in Responding The State desires open and fair competition. Questions from responders regarding any of the requirements of the Solicitation must be submitted in writing to the Solicitation Administrator listed in the Solicitation before the due date and time. If changes are made the State will issue an addendum.

Any evidence of collusion among responders in any form designed to defeat competitive responses will be reported to the Minnesota Attorney General for investigation and appropriate action.

Addenda to the Solicitation Changes to the Solicitation will be made by addendum with notification and posted in the same manner as the original Solicitation. Any addenda issued will become part of the Solicitation.

Data Security - Foreign Outsourcing of Work is Prohibited All storage and processing of information shall be performed within the borders of the United States. This provision also applies to work performed by subcontractors at all levels.

Joint Ventures The State allows joint ventures among groups of responders when responding to the solicitation. However, one responder must submit a response on behalf of all the others in the group. The responder that submits the response will be considered legally responsible for the response (and the contract, if awarded).

Withdrawing Response A responder may withdraw its response prior to the due date and time of the Solicitation. For solicitations in the SWIFT Supplier Portal, a responder may withdraw its response from the SWIFT Supplier Portal. For solicitations done any other way, a responder may withdraw its response by notifying the Solicitation Administrator in writing of the desire to withdraw.

After the due date and time of this Solicitation, a responder may withdraw a response only upon showing that an obvious error exists in the response. The showing and request for withdrawal must be made in writing to Solicitation Administrator within a reasonable time and prior to the State’s detrimental reliance on the response.

Rights Reserved The State reserves the right to:

· Reject any and all responses received;

· Waive or modify any informalities, irregularities, or inconsistencies in the responses received;

· Negotiate with the highest scoring Responder[s];

· Terminate negotiations and select the next response providing the best value for the State;

· Consider documented past performance resulting from a State contract may be considered in the evaluation process;

· Short list the highest scoring Responders;

· Require Responders to conduct presentations, demonstrations, or submit samples;

· Interview key personnel or references;

· Request a best and final offer from one or more Responders;

· The State reserves the right to request additional information ; and

· The State reserves the right to use estimated usage or scenarios for the purpose of conducting pricing evaluations. The State reserves the right to modify scenarios, and to request or add additional scenarios for the evaluation.

Samples and Demonstrations Upon request, Responders are to provide samples to the State at no charge. Except for those destroyed or mutilated in testing, the State will return samples if requested and at the Responder’s expense. All costs to conduct and associated with a demonstration will be the sole responsibility of the Responder.

Responses are Nonpublic during Evaluation Process All materials submitted in response to this Solicitation will become property of the State. During the evaluation process, all information concerning the responses submitted will remain private or nonpublic and will not be disclosed to anyone whose official duties do not require such knowledge. Responses are private or nonpublic data until the completion of the evaluation process as defined by Minn. Stat. § 13.591. The completion of the evaluation process is defined as the State having completed negotiating a contract with the selected responder. The State will notify all responders in writing of the evaluation results.

Trade Secret Information Responders must not submit as part of their response trade secret material, as defined by Minn. Stat. § 13.37.

In the event trade secret data are submitted, Responder must defend any action seeking release of data it believes to be trade secret, and indemnify and hold harmless the State, its agents and employees, from any judgments awarded against the State in favor of the party requesting the data, and any and all costs connected with that defense.

The State does not consider cost or prices to be trade secret material, as defined by Minn. Stat. § 13.37.

A responder may present and discuss trade secret information during an interview or demonstration with the State, if applicable.

Conditions of Offer Unless otherwise approved in writing by the State, Responder’s cost proposal and all terms offered in its response that pertain to the completion of professional and technical services and general services will remain firm for 180 days, until they are accepted or rejected by the State, or they are changed by further negotiations with the State prior to contract execution.

Award Any award that may result from this solicitation will be based upon the total accumulated points as established in the solicitation. The State reserves the right to award this solicitation to a single Responder, or to multiple Responders, whichever is in the best interest of the State, providing each Responder is in compliance with all terms and conditions of the solicitation. The State reserves the right to accept all or part of an offer, to reject all offers, to cancel the solicitation, or to re-issue the solicitation, whichever is in the best interest of the State.

Requirements Prior to Contract Execution Prior to contract execution, a responder receiving a contract award must comply with any submittal requests. A submittal request may include, but is not limited to, a Certificate of Insurance.

Targeted Group, Economically Disadvantaged Business, Veteran-Owned and Individual Preference Unless a greater preference is applicable and allowed by law, in accordance with Minn. Stat. § 16C.16, businesses that are eligible and certified by the State as targeted group (TG) businesses, economically disadvantaged (ED) businesses, and veteran-owned businesses will receive points equal to 12% percent of the total points available as preference.

For TG/ED/VO certification and eligibility information visit the Office of Equity in Procurement website at https://mn.gov/admin/business/vendor-info/oep/ or call the Division’s Helpline at 651.296.2600.

Reciprocity State shall comply with Minn. Stat. § 16C.06, subd. 7, as that applies to a non-resident vendor. This paragraph does not apply for any project in which federal funds are expended.