This request for proposal (RFP) solicits comprehensive and rapid response services to support the research programs of the National Institute of Allergy and Infectious Diseases (NIAID). The RFP seeks proposals for multiple awards of indefinite delivery/indefinite quantity contracts with a minimum total value of $2,000 and maximum of $545,452,906 over a seven-year period from May 2021 to April 2028. Services will include expanding knowledge in infectious, immunologic, and allergic diseases and developing domestic and international research capacities to respond to emerging disease threats through tasks issued under the contracts. Task orders will be competed among awardees, evaluated based on technical and cost factors specified in each task order request for proposal. The closing date for initial proposals in response to this RFP is October 1, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to Comprehensive and Rapid Response to NIAID Research Programs, newest first.
File Type Posted
DCR SP Network Overview- Amend 1.pdf PDF
Amendment 1 - 9.11.20..pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

- 1 -

SOLICITATION

SECTION A - SOLICITATION/CONTRACT FORM

1. Requisition or other Purchase Authority: Public Law 81-692, as amended

2. Request for Proposal (RFP) Number:

75N93019R00025

3. Issue Date:

July 20, 2020

4. Set Aside:

[ ] No

[X] Yes- Task Area F is reserved for Small Business Concerns- See Part IV Section L

5. Title : Comprehensive and Rapid Response to NIAID Research Programs

6. ISSUED BY:

Office of Acquisitions National Institutes of Allergy and Infectious Diseases National Institutes of Health 5601 Fishers Lane Rockville, Maryland, 20892

7. SUBMIT OFFERS TO:

See Part III, Section J, "Packaging and Delivery of the Proposal," ATTACHMENT 1 of this Solicitation.

8. Proposals for furnishing the supplies and/or services in THE SCHEDULE will be received at the place specified in, and in the number of copies specified in Attachment 1, "Packaging and Delivery of the Proposal," until 3:00pm local time on October 1, 2020. Offers will be valid for 120 days unless a different period is specified by the offeror on the Attachment entitled, "Proposal Summary and Data Record, NIH 2043.

9. This solicitation requires delivery of proposals as stated in ATTACHMENT 1, "PACKAGING AND DELIVERY OF THE PROPOSAL." If proposals are required to be delivered to two different locations, the OFFICIAL POINT OF RECEIPT for determining TIMELY DELIVERY is the address provided for the OFFICE OF ACQUISITIONS.

IF YOUR PROPOSAL IS NOT RECEIVED BY THE CONTRACTING OFFICER OR HIS DESIGNEE AT THE PLACE AND TIME SPECIFIED FOR THE OFFICE OF ACQUISITIONS, THEN IT WILL BE CONSIDERED LATE AND HANDLED IN ACCORDANCE WITH subparagraph (c)(3) of FAR Clause 52.215-1, Instructions to Offerors--Competitive Acquisition," LOCATED IN SECTION L.1. OF THIS SOLICITATION.

10. Offeror must be registered in the System for Award Management (SAM) prior to award of a contract. Offerors must access the CCR through The System for Award Management (SAM) at http://www.sam.gov

11. FOR INFORMATION CALL: Matt Lear

PHONE: 240-669-5109

e-MAIL: Matt.Lear@nih.gov

COLLECT CALLS WILL NOT BE ACCEPTED.

Offerors are strongly encouraged to submit questions regarding the solicitation by no later than 3:00pm local time on 8/21/2020 so that we can provide timely responses before proposals are due.

Callie Prassinos Contracting Officer Office of Acquisitions

DEA/NIAID/NIH/DHHS

http://www.sam.gov

RFP Number : 75N93019R00025

- 2 -

RFP TABLE OF CONTENTS

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

SECTION D - PACKAGING, MARKING AND SHIPPING

SECTION E - INSPECTION AND ACCEPTANCE

SECTION F - DELIVERIES OR PERFORMANCE

SECTION G - CONTRACT ADMINISTRATION DATA

SECTION H - SPECIAL CONTRACT REQUIREMENTS

ARTICLE H.5. GOOD CLINICAL PRACTICE TRAINING FOR NIH AWARDEES INVOLVED IN NIH-FUNDED

CLINICAL TRIALS

ARTICLE H.6. CLINICAL TRIAL REGISTRATION AND RESULTS INFORMATION SUBMISSION

ARTICLE H.7. CLINICAL TRIAL REGISTRATION AND RESULTS INFORMATION SUBMISSION PLAN

ARTICLE H.8. CERTIFICATE OF CONFIDENTIALITY

ARTICLE H.9. SINGLE INSTITUTIONAL REVIEW BOARD (sIRB)

ARTICLE H.10. PLAN FOR SINGLE INSTITUTIONAL REVIEW BOARD (sIRB)

ARTICLE H.11. INCLUSION OF WOMEN AND MINORITIES IN RESEARCH INVOLVING HUMAN SUBJECTS. . 32

ARTICLE H.13. POSTING CLINICAL TRIAL INFORMED CONSENT FORMS TO CLINICALTRIALS.GOV

ARTICLE H.14. REGISTRATION AND RESULTS REPORTING FOR APPLICABLE CLINICAL TRIALS IN

CLINICALTRIALS.GOV

ARTICLE H.15. REGISTRATION AND RESULTS REPORTING FOR APPLICABLE CLINICAL TRIALS

CLINICALTRIALS.GOV

PART II - CONTRACT CLAUSES

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J - LIST OF ATTACHMENTS

SOLICITATION ATTACHMENTS

TECHNICAL PROPOSAL ATTACHMENTS

BUSINESS PROPOSAL ATTACHMENTS

INFORMATIONAL ATTACHMENTS

PART IV - REPRESENTATIONS AND INSTRUCTIONS

SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1. GENERAL INFORMATION

a. INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION

b. NOTICE OF SMALL BUSINESS SET-ASIDE

c. NAICS CODE AND SIZE STANDARD

d. TYPE OF CONTRACT AND NUMBER OF AWARDS

e. TASK ORDERS UNDER MULTIPLE AWARD INDEFINITE DELIVERY CONTRACTS

f. LEVEL OF EFFORT

g. COMMITMENT OF PUBLIC FUNDS

h. PROMOTING EFFICIENT SPENDING

i. COMMUNICATIONS PRIOR TO CONTRACT AWARD

- 3 -

j. RELEASE OF INFORMATION

k. PREPARATION COSTS

l. SERVICE OF PROTEST

2. INSTRUCTIONS TO OFFERORS

a. GENERAL INSTRUCTIONS

1. Contract Type and General Clauses

2. Authorized Official and Submission of Proposal

3. Proposal Summary and Data Record (NIH-2043)

4. Separation of Technical and Business Proposals

5. Alternate Proposals

6. Evaluation of Proposals

7. Potential Award Without Discussions

8. Use of the Metric System of Measurement

9. Standards for Privacy of Individually Identifiable Health Information

10. Non-discrimination for Conscience, HHSAR Clause 352.270-9

11. Privacy Act - Treatment of Proposal Information

12. Selection of Offerors

13. Institutional Responsibility Regarding Investigator Conflicts of Interest

14. ROTC Access and Federal Military Recruiting on Campus

15. Certification of Filing and Payment of Taxes

16. Past Performance Information

17. Prohibition on Contractor Involvement with Terrorist Activities

18. Solicitation Provisions Incorporated by Reference

b. TECHNICAL PROPOSAL INSTRUCTIONS

1. Technical Discussions

2. Other Considerations

3. Technical Evaluation

4. Human Subjects

Notice to Offerors of Requirements, Protection of Human Subjects, HHSAR 270-4(a)

Instructions to Offerors Regarding Protection of Human Subjects

Required Education in the Protection of Human Research Participants

Inclusion of Women and Minorities in Research Involving Human Subjects

Inclusion of Children in Research Involving Human Subjects

Human Stem Cell Research

Data and Safety Monitoring in Clinical Trials

HIV Antiretroviral Treatment Trials

Registration and Results Reporting for Applicable Clinical Trials in ClinicalTrials.gov

PHS HUMAN SUBJECTS AND CLINICAL TRIALS INFORMATION FORM

5. Care of Live Vertebrate Animals

6. Research Involving Live Vertebrate Animals

7. Possession, Use and Transfer of Select Biological Agents or Toxins

8. Obtaining and Disseminating Biomedical Research Resources

c. BUSINESS PROPOSAL INSTRUCTIONS

- 4 -

1. Basic Cost/Price Information

2. Proposal Cover Sheet

3. Information Other than Cost or Pricing Data

4. Requirements for Cost or Pricing Data or Information Other than Cost and Pricing Data

5. Salary Rate Limitation

6. Small Business Subcontracting Plan

7. Mentor Protege Program, HHSAR 352.219-70

8. HUBZone Small Business Concerns

9. Total Compensation Plan

10. Other Administrative Data

11. Qualifications of the Offeror

12. Subcontractors

13. Proposer's Annual Financial Report

14. Travel Costs/Travel Policy

15. Certification of Visas for Non-U.S. Citizens

SECTION M - EVALUATION FACTORS FOR AWARD

1. GENERAL

2. COST/PRICE EVALUATION

3. HUMAN SUBJECT EVALUATION

4. LIVE VERTEBRATE ANIMALS EVALUATION

5. EVALUATION OF DATA SHARING PLAN

6. EVALUATION OF PLAN FOR SHARING MODEL ORGANISMS FOR BIOMEDICAL RESEARCH

7. TECHNICAL EVALUATION FACTORS

8. EVALUATION OF ELECTRONIC AND INFORMATION TECHNOLOGY ACCESSIBILITY- SECTION

9. PAST PERFORMANCE FACTOR

10. SUBCONTRACTING PROGRAM EVALUATION CRITERIA

- 5 -

PART I - THE SCHEDULE

THE INFORMATION SET FORTH IN SECTION A - SOLICITATION/CONTRACT FORM, HEREIN CONTAINS IMPORTANT INFORMATION FOR ANY OFFEROR INTERESTED IN RESPONDING TO THIS SOLICITATION.

ANY CONTRACT RESULTING FROM THIS SOLICITATION WILL INCLUDE IN ITS SECTION A - SOLICITATION/ CONTRACT FORM, ACCOUNTING, APPROPRIATION AND GENERAL INFORMATION APPLICABLE TO THE

CONTRACT AWARD.

THE CONTRACT SCHEDULE SET FORTH IN SECTIONS B THROUGH H, HEREIN, CONTAINS CONTRACTUAL INFORMATION PERTINENT TO THIS SOLICITATION. IT IS NOT AN EXACT REPRESENTATION OF THE CONTRACT DOCUMENT THAT WILL BE AWARDED AS A RESULT OF THIS SOLICITATION. THE CONTRACT COST OR PRICE AND OTHER CONTRACTUAL PROVISIONS PERTINENT TO THE OFFEROR (i.e., those relating to the organizational structure [e.g., Non-Profit, Commercial] and specific cost authorizations unique to the Offeror's proposal and requiring Contracting Officer Prior Approval) WILL BE DISCUSSED IN THE NEGOTIATION PROCESS AND WILL BE INCLUDED IN THE RESULTANT CONTRACT. THE ENCLOSED CONTRACT SCHEDULE IS

INTENDED TO PROVIDE THE OFFEROR WITH THE NECESSARY INFORMATION TO UNDERSTAND THE

TERMS AND CONDITIONS OF THE RESULTANT CONTRACT.

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

ARTICLE B.1. BRIEF DESCRIPTION OF SUPPLIES OR SERVICES

Contracts awarded from this solicitation shall provide the capacity and capability for a broad range of services necessary to support and conduct biomedical research in support of the NIAID mission and the management of activities specified under the Statement of Work and associated Task Orders. Services include expanding the breadth and depth of knowledge in all areas of infectious, immunologic, and allergic diseases and developing flexible domestic and international research capacities to respond appropriately to emerging and re#emerging disease threats both domestic and foreign. These capabilities will allow NIAID to rapidly and efficiently address research program needs.

ARTICLE B.2. PRICES/COSTS

a. This is a Multiple Award Indefinite Quantity contract as contemplated by FAR 16.504. The Contractor shall be reimbursed by the Government in an amount not less than a total of $2,000 (minimum) nor more than a total of $545,452,906 (maximum) for successful performance of this contract.

b. The costs set forth in this ARTICLE will cover the contract period May 1, 2021 through April 30, 2028.

c. The Government will compete and award Task Orders based on the work described in SECTION C of this contract.

d. Ordering procedures are described in The TASK ORDER PROCEDURE Article in SECTION G of this contract.

ARTICLE B.3. PROVISIONS APPLICABLE TO DIRECT COSTS

This article will prohibit or restrict the use of contract funds, unless otherwise approved by the Contracting Officer. The following is a list of items that may be included in the resultant contract as applicable. 1) Conferences & Meetings, 2) Food for Meals, Light Refreshments & Beverages, 3) Promotional Items, 4) Acquisition, by purchase or lease, of any interest in real property; 5) Special rearrangement or alteration of facilities; 6) Purchase or lease of any item of general purpose office furniture or office equipment regardless of dollar value; 7) Travel Costs including Foreign Travel; 8) Consultant Costs; 9) Subcontract Costs; 10) Patient Care Costs; 11) Accountable Government Property; 12) Printing costs; and 13) Research Funding.

- 6 -

ARTICLE B.4. ADVANCE UNDERSTANDINGS

Specific elements of cost, which normally require prior written approval of the Contracting Officer before incurrence of the cost (e.g., foreign travel, consultant fees, subcontracts) will be included in this Article if the Contracting Officer has granted his/her approval prior to contract award.

Intellectual Property

It is expected that a great majority of the products delivered under the contract will be proprietary, in part to the third party Suppliers. For the purposes of this agreement, candidate vaccines and other agents, or products ("material") includes compositions of matter, and associated information such as methods of making or using the compositions.

It is clear from the NIAID's experience that third party suppliers ("Supplier") will not provide their proprietary materials ("Material") without assurance that the intellectual property rights associated with their Material will be protected.

Accordingly, to encourage a Supplier to provide their Material for production or evaluation under this contract the Contractor agrees to this Article, which requires the Contractor and its subcontractors to provide a research use license and a commercialization license option to Subject Inventions made under the contract to the Supplier as follows:

The Contractor agrees to promptly notify the NIAID and the Supplier in writing of any Subject Inventions of the Contractor, its PI and/or any other employees or agents of the Contractor, whether patentable or not, which are conceived and/or first actually reduced to practice in the performance of work under this contract using a Supplier's Material (hereinafter "Contractor Invention"). The notice shall inform the Supplier of its right to the option set forth herein. This may be accomplished by attaching a copy of this Article to the notice.

(1) Single Supplier

With respect to Contractor Inventions resulting from the use of Material provided by one Supplier, the Contractor agrees to grant to the Supplier: (i) a paid-up nonexclusive, nontransferable, royalty-free, world-wide license to all Contractor Inventions for research purposes only; and (ii) a time-limited first option to negotiate an exclusive, world-wide royalty- bearing license for all commercial purposes, including the right to grant sub-licenses, to any Contractor Invention on terms to be negotiated in good faith by the Supplier and the Contractor, subject to the following conditions:

The Contractor will allow Supplier three (3) months from the date the Contractor sends written notice to the Supplier of the existence of a Contractor Invention (or such additional period as the Supplier and the Contractor may agree) to notify the Contractor in writing, whether or not it wants to obtain an exclusive license to the Contractor Invention.

If the Supplier fails to notify the Contractor, in a timely fashion then the Contractor's obligation to offer Supplier a license option with respect to that Contractor Invention will expire, and the Contractor will be free to dispose of its interests in such Contractor Invention in accordance with the Contractor's policies. If the Contractor and the Supplier fail to reach agreement within ninety (90) days, (or such additional period as the Supplier and the Contractor may agree) on the terms for an exclusive license for a particular Contractor Invention, then for a period of six (6) months thereafter the Contractor will not offer to license that Contractor Invention to any third party on materially better terms than those last offered to the Supplier without first offering such terms to the Supplier, in which case the Contractor will offer the Supplier a period of thirty (30) days in which the Supplier can accept or reject the offer.

(2) Multiple Suppliers

With respect to a Contractor Invention resulting from the use of Materials provided by multiple Suppliers, but which is an improvement only to a Material of a specific Supplier, the Contractor agrees to grant to that Supplier the rights described above in (1).

With respect to any Contractor Inventions resulting from the use of Material from multiple Suppliers, but that are not improvements to or specific to a single Material, the Contractor agrees to grant to each Supplier who provided Material: (i) a paid-up nonexclusive, nontransferable, royalty-free, world-wide license to all Contractor Inventions for research purposes only; and (ii) a time-limited first option to negotiate a co-exclusive, worldwide royalty- bearing license for all commercial purposes, including the right to grant sub-licenses, to all such Contractor Inventions on terms to be negotiated in good faith by each Supplier and the Contractor subject to the following conditions:

- 7 -

The Contractor will allow each Supplier three (3) months from the time the Supplier is sent written notice by the Contractor of the existence of a Contractor Invention (or such additional period as each Suppler and the Contractor may agree) to notify the Contractor, in writing, whether or not the Supplier wants to obtain a co-exclusive license to the Contractor Invention. If a Supplier fails to notify the Contractor, in a timely fashion then Contractor's obligation to offer that Supplier a license option with respect to that Contractor Invention will expire and the Contractor will continue to offer an option to a co-exclusive license to the other Suppliers as set forth herein. If there is a single other Supplier, it shall be offered an option to an exclusive license as though it were a single Supplier. If no Supplier notifies the Contractor in a timely fashion the Contractor will be free to dispose of its interests in such Contractor Invention in accordance with the Contractor's policies.

Supplier Inventions

The Contractor agrees that notwithstanding anything herein to the contrary, any invention or discovery, whether patentable or not, which is not a Subject Invention as defined in 35 USC 201(e) 1 but arises out of an intentional and unauthorized use or modification of the Supplier's Material by the Contractor and/or any other employees or agents of the Contractor, will be the property of the Supplier (hereinafter "Supplier Invention"). The Contractor will promptly notify the Supplier in writing of any such Supplier Inventions and, at the Supplier's request and expense, the Contractor will take such further action as necessary to ensure that the Supplier shall have all right, title and interest in and to any such Supplier Inventions and give Supplier any assistance reasonably necessary to obtain patents (including causing the execution of any invention assignment or other documents). The NIAID recognizes that the Contractor may also be conducting other research using the Supplier's Material under the authority of a separate agreement with the Supplier during the term of this contract; any invention arising under such separate agreement will not be subject to the terms of this provision entitled, "Supplier Inventions."

Protection of Proprietary Data

Because the Contractor will be utilizing and evaluating Materials provided to the Government by third party Suppliers, it is essential to include provisions that will protect the proprietary rights of the Suppliers. These materials generally are supplied to the Government under conditions outlined in NIAID's standard Material Evaluation Agreement (MEA) or other appropriate documents. The Contractor shall be bound by the same terms and conditions as the Government in these agreements, with respect to the proprietary and confidential nature of the information provided by the Supplier. The Contractor agrees that its PI and/or any other employees or agents of the Contractor will provide data generated under this contract exclusively to the NIAID or if directed by the NIAID to the Supplier and the FDA or other appropriate Federal agency. The Contractor understands that the NIAID may need to negotiate individual agreements with the various Suppliers to obtain Materials and that the terms of the agreements may vary. The Contractor agrees to enter into material transfer agreements with Suppliers when requested by the Suppliers as a condition for the Contractor to receive Materials. Such Agreements shall reference this contract by contract number and shall be consistent with any agreement the NIAID has entered into with the Supplier to obtain Materials. In the event the Contractor reasonably objects to the terms of the material transfer agreement, the Contractor shall promptly bring such objection to the attention of the Contracting Officer for an appropriate resolution.

"Confidential Information" is scientific, business, or financial information provided by the Supplier or the NIAID Contract Officer's Representative (COR) and marked "Confidential." Oral Disclosures of Confidential Information will be reduced to writing, marked "Confidential;" and sent to Contractor within 10 days of disclosure to be considered Confidential Information.

Confidential Information may not be revealed without written permission from the CONTRACTING OFFICER'S REPRESENTATIVE. Similarly, designated Materials are to be considered confidential. In cases where it is not clear whether information or Materials are to be considered confidential, the Contractor should contact the CONTRACTING OFFICER'S REPRESENTATIVE to obtain a determination. All materials supplied to the Contractor shall be utilized solely for contract-related research purposes and no unauthorized use or distribution of these materials shall be permitted.

Any Publication containing data generated under this contract ("Results") must be submitted for review by the CONTRACTING OFFICER'S REPRESENTATIVE and Supplier before submission for public presentation or publication. A "Publication" is defined as an issue of printed material offered for distribution or any communication or oral presentation of information, for example a manuscript or abstract. The purpose of this review is to ensure that Publications do not contain any of NIAID's or Supplier's proprietary Confidential Information and to allow Supplier

- 8 -time to file patent applications, if so desired. Contract support shall be acknowledged in all Publications of Results.

The CONTRACTING OFFICER'S REPRESENTATIVE and Supplier will review all Publications containing Results submitted to the CONTRACTING OFFICER'S REPRESENTATIVE and Supplier in a period of time not to exceed 120 calendar days from receipt of Results by both the CONTRACTING OFFICER'S REPRESENTATIVE and Supplier, and will either agree to the publication/disclosure, recommend changes and, as applicable, refer the document to the Supplier of the compound for their review. Publication of results earlier than 120 days after submission will require Supplier's written approval. When the Supplier does not consent to publication of the manuscript or abstract on the basis that Supplier's Confidential Information is included in the Publication, the CONTRACTING OFFICER'S REPRESENTATIVE shall notify the Contractor and the NIAID Contracting Officer. The CONTRACTING OFFICER'S REPRESENTATIVE is responsible for ensuring that all parties adhere to the terms and conditions of any existing Material Evaluation Agreement or other appropriate document between NIAID and the Supplier. NIAID will use its best efforts to assist and expedite the review process by the Supplier.

Should patents arise from this contract, they shall be subject to federal law governing inventions. Every patent applicant (individual or institutional) is required to provide the Government with a non-exclusive, irrevocable, paid-up license to the invention.

Invoice - Cost and Personnel Reporting and Variances from the Negotiated Budget

1. The Contractor agrees to provide a detailed breakdown on invoices of the following cost categories:

a. Direct Labor - List individuals by name, title/position, hourly/annual rate, level of effort, and amount claimed.

b. Fringe Benefits - Cite rate and amount.

c. Overhead - Cite rate and amount.

d. Materials & Supplies - Include detailed breakdown when total amount is over $1,000.

e. Travel - Identify travelers, dates, destination, purpose of trip, and amount. Cite Contracting Officer's Authorization (COA), if appropriate. List separately, domestic travel, general scientific meeting travel, and foreign travel.

f. Consultant Fees - Identify individuals and amounts.

g. Subcontracts - Attach subcontractor invoice(s).

h. Equipment - Cite authorization and amount.

i. Other Direct Costs - Include detailed breakdown when total amount is over $1,000.

j. G&A - Cite rate and amount.

k. Total Cost

l. Profit/Fee

m. Total Cost Plus Fixed Fee Monthly invoices must include the cumulative total expenses to date, adjusted (as applicable) to show any amounts suspended by the Government.

2. The Contractor agrees to immediately notify the Contracting Officer in writing if there is an anticipated overrun (any amount) of unexpended balance (greater than 10 percent) of the amount allotted to the contract, and the reasons for the variance. Also refer to the requirements of the Limitation of Funds and Limitation of Cost clauses in the contract.

35 USC 201(e): The term ''subject invention'' means any invention of the contractor conceived or first actually reduced to practice in the performance of work under a funding agreement: Provided, That in the case of a variety of plant, the date of determination (as defined in section 41(d) of the Plant Variety Protection Act (7U.S.C. 2401(d)) must also occur during the period of contract performance.

- 9 -

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

ARTICLE C.1. Statement of Work

a. Independently and not as an agent of the Government, the Contractor shall be required to furnish all the necessary services, qualified personnel, material, equipment, and facilities, not otherwise provided by the Government, as needed to perform the Statement of Work, dated May 14, 2020, attached hereto and made a part of this Solicitation (See SECTION J - List of Attachments).

b. The applicable Privacy Act System of Records Number will be specified and shall be used in any design, development, or operation work to be performed under the resultant contract. Disposition of records shall be in accordance with SECTION C of the contract, and by direction of the Contracting Officer's Representative (COR).

ARTICLE C.2. REPORTING REQUIREMENTS

All reports required herein shall be submitted in electronic format via the NIAID electronic Report Deliverable Submission (eRDS) Site, available at https://erds.niaid.nih.gov/.

All electronic reports submitted shall be compliant with Section 508 of the Rehabilitation Act of 1973. Additional information about testing documents for Section 508 compliance, including guidance and specific checklists, by application, can be found at: http://www.hhs.gov/web/508/index.html under "Making Files Accessible."

a. Technical Progress Reports

1. In addition to the required reports set forth elsewhere in this Schedule, the preparation and submission of regularly recurring Technical Progress Reports will be required in any contract resulting from this solicitation. These reports will require descriptive information about the activities undertaken during the reporting period and will require information about planned activities for future reporting periods. The frequency and specific content of these reports will be determined prior to contract award. [Note: Beginning May 25, 2008, the Contractor shall include the applicable PubMed Central or NIH Manuscript Submission reference number when citing publications that arise from its NIH funded research.]

For proposal preparation purposes only, it is estimated that one electronic version of the following reports will be required for any Task Orders issued under each of the Task Areas, as follows:

[X] Monthly [X] Annually [X] Final - Upon final completion of each Task Order

2. Summary of Salient Results

The Contractor will be required to prepare and submit, with the final report, a summary (not to exceed 200 words) of salient results achieved during the performance of the contract. This report will be required on or before the expiration date of the contract.

3. Annual Technical Progress Report for Clinical Research Study Populations

The Contractor shall submit information about the inclusion of women and members of minority groups and their subpopulations (when appropriate) for each study being performed under this http://erds.niaid.nih.gov http://www.hhs.gov/web/508/index.html

- 10 -contract. The Contractor shall submit this information in the format indicated in the attachment entitled, "" PHS Human Subjects and Clinical Trials Information Form/ Cumulative Inclusion Enrollment Report," which is set forth in SECTION J of this contract. The Contractor also shall use this format, modified to indicate that it is a final report, for reporting purposes in the final report. If the clinical study(s) involves US and non-US sites, the US sites and non-US sites should be reported on separate Cumulative Inclusion Enrollment Reports.

The first report shall be due 45 days after award. Thereafter, the report shall be due on or before the 15 day following each reporting period. The final report shall be due before the expiration of the Task Order.

In addition, the NIH Policy and Guidelines on the Inclusion of Women and Minorities as Subjects in Clinical Research, Amended, October, 2001 applies. If this contract is for Phase III clinical trials, see II.B of these guidelines. The Guidelines may be found at the following website: http://grants.nih.gov/ grants/funding/women_min/women_min.htm.

For NIH-defined Phase III Clinical Trials: Include a description of the plans for valid analysis in the study design and outcomes. This includes designing the study in a manner that potential differences, as appropriate, by sex/gender and/or racial/ethnic groups in the clinical trial protocol could be conducted. Also, provide a description of any analyses by sex/gender, race, and/or ethnicity, as appropriate, in the annual progress report and the final report. If the analysis reveals no subgroup differences, a brief statement to that effect, indicating the subgroups analyzed, will suffice. The Government strongly encourages inclusion of the results of subgroup analysis in all publication submissions. In the final report, the Contractor shall include all final analyses of the data on sex/ gender, race and/or ethnicity.

4. Reporting on Select Agents or Toxins and/or Highly Pathogenic Agents

For work involving the possession, use, or transfer of a Select Agent or Toxin and/or a Highly Pathogenic Agent, the following information shall also be included in each Annual Progress Report:

1. Any changes in the use of the Select Agent or Toxin including initiation of "restricted experiments," and/or a Highly Pathogenic Agent, that have resulted in a change in the required biocontainment level, and any resultant change in location, if applicable, as determined by the IBC or equivalent body or institutional biosafety official.

2. If work with a new or additional Select Agent or Toxin and/or a Highly Pathogenic Agent will be conducted in the upcoming reporting period, provide:

1. A list of each new or additional Select Agent or Toxin and/or a Highly Pathogenic Agent that will be studied;

2. A brief description of the work that will be done with each new or additional Select Agent or Toxin and/or a Highly Pathogenic Agent and whether or not the work is a Select Agent or Toxin restricted experiment as defined in the Select Agents Regulation 42 CFR Part 73, Section 13.b ( http://www.selectagents.gov/Regulations.html) or listed on the U.S. National Select Agents Registry restricted experiments website ( http://www.selectagents.gov/ index.html);

3. The name and location for each biocontainment resource/facility, including the name of the organization that operates the facility, and the biocontainment level at which the work will be conducted, with documentation of approval by your IBC or equivalent body or institutional biosafety official. It must be noted if the work is being done in a new location or different location.

4. For work with Select Agents performed in the U.S. provide documentation of registration status of all domestic organizations where Select Agent(s) will be used. For work with Select Agents performed in a non-U.S. country prior NIAID approval is required.

http://grants.nih.gov/grants/funding/women_min/women_min.htm http://grants.nih.gov/grants/funding/women_min/women_min.htm http://www.selectagents.gov/Regulations.html http://www.selectagents.gov/index.html http://www.selectagents.gov/index.html

- 11 -

If the IBC or equivalent body or institutional biosafety official has determined, for example, by conducting a risk assessment, that the work that has been performed or is planned to be performed under this contract may be conducted at a biocontainment safety level that is lower than BSL3, a statement to that affect shall be included in each Annual Progress Report.

If no work involving a Select Agent or Toxin and/or a Highly Pathogenic Agent has been performed or is planned to be performed under this contract, a statement to that affect shall be included in each Annual Progress Report.

b. Other Reports/Deliverables

1. Reporting of Financial Conflict of Interest (FCOI)

All reports and documentation required by 45 CFR Part 94, Responsible Prospective Contractors including, but not limited to, the New FCOI Report, Annual FCOI Report, Revised FCOI Report, and the Mitigation Report, shall be submitted to the Contracting Officer in Electronic format. Thereafter, reports shall be due in accordance with the regulatory compliance requirements in 45 CFR Part 94.

45 CFR Part 94 is available at: http://www.ecfr.gov/cgi-bin/text-idx?

c=ecfr&SID=0af84ca649a74846f102aaf664da1623&rgn=div5&view=text&node=45:1.0.1.1.51&idno=45.

See Part 94.5, Management and reporting of financial conflicts of interest for complete information on reporting requirements.

(Reference subparagraph g. of the INSTITUTIONAL RESPONSIBILITY REGARDING INVESTIGATOR FINANCIAL CONFLICTS OF INTEREST Article in SECTION H of this contract.)

2. Source Code and Object Code

Unless otherwise specified herein, the Contractor shall deliver to the Government, upon the expiration date of the contract, all source code and object code developed, modified, and/or enhanced under this contract.

HHS SECURITY AND PRIVACY LANGUAGE FOR INFORMATION AND IT PROCUREMENTS

INFORMATION AND/OR PHYSICAL SECURITY

1. Security Assessment and Authorization (SA&A)- A valid authority to operate (ATO) certifies that the Contractor's information system meets the contract's requirements to protect the agency data. If the system under this contract does not have a valid ATO, the Contractor (and/or any subcontractor) shall work with the agency and supply the deliverables required to complete the ATO within the specified timeline(s) within three

(3) months after contract award. The Contractor shall conduct the SA&A requirements in accordance with HHS IS2P, NIST SP 800-37, Guide for Applying the Risk Management Framework to Federal Information Systems: A Security Life Cycle Approach (latest revision).

For an existing ATO, Contracting Officer Representative must make a determination if the existing ATO provides appropriate safeguards or if an additional ATO is required for the performance of the contract and state as such.

NIH acceptance of the ATO does not alleviate the Contractor's responsibility to ensure the system security and privacy controls are implemented and operating effectively.

http://www.ecfr.gov/cgi-bin/text-idx?c=ecfr&SID=0af84ca649a74846f102aaf664da1623&rgn=div5&view=text&node=45:1.0.1.1.51&idno=45 http://www.ecfr.gov/cgi-bin/text-idx?c=ecfr&SID=0af84ca649a74846f102aaf664da1623&rgn=div5&view=text&node=45:1.0.1.1.51&idno=45

- 12 -

2. SA&A Package Deliverables - The Contractor (and/or any subcontractor) shall provide an SA&A package within 30 days of contract award to the CO and/or COR. The following SA&A deliverables are required to complete the SA&A package.

• System Security Plan (SSP) - due within 30 days after contract award. The SSP shall comply with the NIST SP 800-18, Guide for Developing Security Plans for Federal Information Systems, the Federal Information Processing Standard (FIPS) 200, Recommended Security Controls for Federal Information Systems, and NIST SP 800-53, Security and Privacy Controls for Federal Information Systems and Organizations applicable baseline requirements, and other applicable NIST guidance as well as HHS and NIH policies and other guidance. The SSP shall be consistent with and detail the approach to IT security contained in the Contractor's bid or proposal that resulted in the award of this contract.

The SSP shall provide an overview of the system environment and security requirements to protect the information system as well as describe all applicable security controls in place or planned for meeting those requirements. It should provide a structured process for planning adequate, cost-effective security protection for a system. The Contractor shall update the SSP at least annually thereafter.

• Security Assessment Plan/Report (SAP/SAR) - due 30 days after the contract award. The security assessment shall be conducted by the assessor and be consistent with NIST SP 800-53A, NIST SP 800-30, and HHS and NIH policies. The assessor will document the assessment results in the SAR.

The NIH should determine which security control baseline applies and then make a determination on the appropriateness/necessity of obtaining an independent assessment. Assessments of controls can be performed by contractor, government, or third parties, with third party verification considered the strongest. If independent assessment is required, include statement below.

Thereafter, the Contractor, in coordination with the NIH shall conduct/assist in the assessment of the security controls and update the SAR at least annually.

• Independent Assessment - due 90 days after the contract award. The Contractor (and/or subcontractor) shall have an independent third-party validate the security and privacy controls in place for the system(s). The independent third party shall review and analyze the Security Authorization package, and report on technical, operational, and management level deficiencies as outlined in NIST SP 800-53. The Contractor shall address all "high" deficiencies before submitting the package to the Government for acceptance. All remaining deficiencies must be documented in a system Plan of Actions and Milestones (POA&M).

• POA&M - due 30 days after contract award. The POA&M shall be documented consistent with the HHS Standard for Plan of Action and Milestones and NIH policies. All high-risk weaknesses must be mitigated within 30 days and all medium weaknesses must be mitigated within 60 days from the date the weaknesses are formally identified and documented. The NIH will determine the risk rating of vulnerabilities. Identified risks stemming from deficiencies related to the security control baseline implementation, assessment, continuous monitoring, vulnerability scanning, and other security reviews and sources, as documented in the SAR, shall be documented and tracked by the Contractor for mitigation in the POA&M document. Depending on the severity of the risks, NIH may require designated POAM weaknesses to be remediated before an ATO is issued.

Thereafter, the POA&M shall be updated at least quarterly.

3. Contingency Plan and Contingency Plan Test - due 60 days after contract award. The Contingency Plan must be developed in accordance with NIST SP 800-34, Contingency Planning Guide for Federal Information Systems, and be consistent with HHS and NIH policies. Upon acceptance by the System Owner, the Contractor, in coordination with the System Owner, shall test the Contingency Plan and prepare a Contingency Plan Test Report that includes the test results, lessons learned and any action items that need to be addressed.

Thereafter, the Contractor shall update and test the Contingency Plan at least annually.

- 13 -

• E-Authentication Questionnaire - The contractor (and/or any subcontractor) shall collaborate with government personnel to ensure that an E-Authentication Threshold Analysis (E-auth TA) is completed to determine if a full E-Authentication Risk Assessment (E-auth RA) is necessary. System documentation developed for a system using E-auth TA/E-auth RA methods shall follow OMB 04-04 and NIST SP 800-63, Rev. 2, Electronic Authentication Guidelines.

Based on the level of assurance determined by the E-Auth, the Contractor (and/or subcontractor) must ensure appropriate authentication to the system, including remote authentication, is in-place in accordance with the assurance level determined by the E-Auth (when required) in accordance with HHS policies.

4. POSITION SENSITIVITY DESIGNATIONS

All Contractor (and/or any subcontractor) employees must obtain a background investigation commensurate with their position sensitivity designation that complies with Parts 1400 and 731 of Title 5, Code of Federal Regulations (CFR). The following position sensitivity designation levels apply to this solicitation/contract:

[ ] Level 6: Public Trust - High Risk. Contractor/subcontractor employees assigned to Level 6 positions shall undergo a Suitability Determination and Background Investigation (MBI).

[ ] Level 5: Public Trust - Moderate Risk. Contractor/subcontractor employees assigned to Level 5 positions with no previous investigation and approval shall undergo a Suitability Determination and a Minimum Background Investigation (MBI), or a Limited Background Investigation (LBI).

[X] Level 1: Non-Sensitive. Contractor/subcontractor employees assigned to Level 1 positions shall undergo a Suitability Determination and National Check and Inquiry Investigation (NACI).

PLEASE NOTE: THE POSITION SENSITIVITY DESIGNATION WILL BE REVIEWED AND DETERMINED AT THE

TASK ORDER LEVEL.

1. HOMELAND SECURITY PRESIDENTIAL DIRECTIVE (HSPD)-12

Roster-

1. The Contractor (and/or any subcontractor) shall submit a roster by name, position, e-mail address, phone number and responsibility, of all staff working under this acquisition where the Contractor will develop, have the ability to access, or host and/or maintain a government information system(s). The roster shall be submitted to the COR and/or CO within fourteen (14) calendar days after the effective date of this contract. Any revisions to the roster as a result of staffing changes shall be submitted within seven (7) calendar days of the change.

The COR will notify the Contractor of the appropriate level of investigation required for each staff member. An electronic template, "Roster of Employees Requiring Suitability Investigations," is available for contractor use at:

https://ocio.nih.gov/aboutus/publicinfosecurity/acquisition/Documents/SuitabilityRoster_10-15-12.xlsx.

2. If the Contractor is filling a new position, the Contractor shall provide a position description and the Government will determine the appropriate suitability level. Upon receipt of the Government's notification of applicable Suitability Investigations required, the Contractor shall complete and submit the required forms within 30 days of the notification.

3. Upon receipt of the Government's notification of applicable Suitability Investigations required, the Contractor shall complete and submit the required forms within 30 days of the notification.

4. The Contractor shall notify the Contracting Officer in advance when any new personnel, who are subject to a background check/investigation, will work under the contract and if they have previously been the subject of national agency checks or background investigations.

https://ocio.nih.gov/aboutus/publicinfosecurity/acquisition/Documents/SuitabilityRoster_10-15-12.xlsx

- 14 -

5. All contractor and subcontractor employees shall comply with the conditions established for their designated position sensitivity level prior to performing any work under this contract. Contractors may begin work after the fingerprint check has been completed.

6. Investigations are expensive and may delay performance, regardless of the outcome of the investigation. Delays associated with rejections and consequent re-investigations may not be excusable in accordance with the FAR clause, Excusable Delays - see FAR 52.249-14. Accordingly, the Contractor shall ensure that any additional employees whose names it submits for work under this contract have a reasonable chance for approval.

7. Typically, the Government investigates personnel at no cost to the Contractor. However, multiple investigations for the same position may, at the Contracting Officer's discretion, justify reduction(s) in the contract price of no more that the cost of the additional investigation(s).

8. The Contractor shall include language similar to this "HHS Controlled Facilities and Information Systems Security" language in all subcontracts that require subcontractor personnel to have the same frequency and duration of (1) physical access to an HHS-controlled facility; (2) logical access to an HHS-controlled information system; (3) access to sensitive HHS data/information, whether in an HHS-controlled information system or in hard copy; or (4) any combination of circumstances (1) through (3).

9. The Contractor shall direct inquiries, including requests for forms and assistance, to the Contracting Officer or designee.

10. Within 7 calendar days after the Government's final acceptance of the work under this contract, or upon termination of the contract, the Contractor shall return all identification badges to the Contracting Officer or designee.

5. CONTRACT INITIATION AND EXPIRATION

1. General Security Requirements- The Contractor (and/or any subcontractor) shall comply with information security and privacy requirements, Enterprise Performance Life Cycle (EPLC) processes, HHS Enterprise Architecture requirements to ensure information is appropriately protected from initiation to expiration of the contract. All information systems development or enhancement tasks supported by the contractor shall follow the HHS EPLC framework and methodology or and in accordance with the HHS Contract Closeout Guide (2012).

HHS EA requirements may be located here: https://www.hhs.gov/ocio/ea/documents/proplans.html

2. System Documentation- Contractors (and/or any subcontractors) must follow and adhere to NIST SP 800-64, Security Considerations in the System Development Life Cycle, at a minimum, for system development and provide system documentation at designated intervals (specifically, at the expiration of the contract) within the EPLC that require artifact review and approval.

3. Sanitization of Government Files and Information- As part of contract closeout and at expiration of the contract, the Contractor (and/or any subcontractor) shall provide all required documentation in accordance with the NIH Media Sanitization and Disposal Policy to the CO and/or COR to certify that, at the government's direction, all electronic and paper records are appropriately disposed of and all devices and media are sanitized in accordance with NIST SP 800-88, Guidelines for Media Sanitization.

4. Notification- The Contractor (and/or any subcontractor) shall notify the CO and/or COR and system ISSO within fifteen days before an employee stops working under this contract.

5. Contractor Responsibilities Upon Physical Completion of the Contract- The contractor (and/or any subcontractors) shall return all government information and IT resources (i.e., government information in non-government-owned systems, media, and backup systems) acquired during the term of this contract to the CO and/or COR. Additionally, the Contractor shall provide a certification that all government information has been properly sanitized and purged from Contractor-owned systems, including backup systems and media used during contract performance, in accordance with HHS and/or NIH policies.

https://www.hhs.gov/ocio/ea/documents/proplans.html

- 15 -

6. The Contractor (and/or any subcontractor) shall perform and document the actions identified in the NIH Contractor Employee Separation Checklist https://ocio.nih.gov/aboutus/publicinfosecurity/acquisition/Documents/ Emp-sep-checklist.pdf when an employee terminates work under this contract within 2 days of the employee's exit from the contract. All documentation shall be made available to the CO and/or COR upon request.

6. Contractor Non-Disclosure Agreement (NDA)- Each Contractor (and/or any subcontractor) employee having access to non-public government information under this contract shall complete the NIH non-disclosure agreement https://ocio.nih.gov/aboutus/publicinfosecurity/acquisition/Documents/Nondisclosure.pdf , as applicable. A copy of each signed and witnessed NDA shall be submitted to the Contracting Officer (CO) and/or CO Representative (COR) prior to performing any work under this acquisition.

7. Vulnerability Scanning Reports The Contractor shall report the results of the required monthly special vulnerability scans no later than 10 days following the end of each reporting period. If required monthly, this report may be included as part of the Technical Progress Report. Otherwise, this report shall be submitted under a separate cover on monthly basis.

8. Government Access for Security Assessment. In addition to the Inspection Clause in the contract, the Contractor (and/or any subcontractor) shall afford the Government access to the Contractor's facilities, installations, operations, documentation, information systems, and personnel used in performance of this contract to the extent required to carry out a program of security assessment (to include vulnerability testing), investigation, and audit to safeguard against threats and hazards to the confidentiality, integrity, and availability of federal data or to the protection of information systems operated on behalf of HHS, including but are not limited to:

1. At any tier handling or accessing information, consent to and allow the Government, or an independent third party working at the Government's direction, without notice at any time during a weekday during regular business hours contractor local time, to access contractor and subcontractor installations, facilities, infrastructure, data centers, equipment (including but not limited to all servers, computing devices, and portable media), operations, documentation (whether in electronic, paper, or other forms), databases, and personnel which are used in performance of the contract.

The Government includes but is not limited to the U.S. Department of Justice, U.S. Government Accountability Office, and the HHS Office of the Inspector General (OIG). The purpose of the access is to facilitate performance inspections and reviews, security and compliance audits, and law enforcement investigations. For security audits, the audit may include but not be limited to such items as buffer overflows, open ports, unnecessary services, lack of user input filtering, cross site scripting vulnerabilities, SQL injection vulnerabilities, and any other known vulnerabilities.

2. At any tier handling or accessing protected information, fully cooperate with all audits, inspections, investigations, forensic analysis, or other reviews or…

This is the start of the file's text. The full file is on GovTribe.