Summary

This Request for Competitive Sealed Proposals (RFP 742-27-255-2) is issued by the University of Texas Permian Basin for the selection of a general contractor to perform infrastructure modernization work at the J. Conrad Dunagan Library. The 80,000 square-foot, two-story building, constructed in 2000, requires significant upgrades including passenger elevator modernization and code compliance, fire sprinkler head replacement throughout both levels with five-year pipe inspection, HVAC equipment replacement with distribution, controls, variable frequency drives, chill water pumps and piping, electrical upgrades including an emergency generator and transfer switch (bid as an alternate), and restroom renovation with new fixtures and drainage/supply systems. Additional scope includes aluminum curtain wall system restoration with mullion/gasket/sealant replacement, building management system upgrades with controllers and networking equipment, and coordination of all life safety requirements. A non-mandatory pre-submittal conference with guided library tour is scheduled for December 8, 2026, at 1:00 PM CST at the library foyer. Proposals are due by January 12, 2027, at 2:00 PM CST and must be submitted as three separate electronic PDF files or one paper copy to Alaneisha (Ally) Duke at the Office of Purchasing, with questions due by December 17, 2026, at 5:00 PM CST via the UTPB bid site.

The lump-sum contract will be awarded to the proposer offering the best value based on scored evaluation criteria totaling 100 points, with pricing weighted at 60 points and qualifications, safety, warranty, project planning, execution plan, and past performance on representative and University of Texas System projects comprising the remaining 40 points. The architect's estimated construction cost is $4,054,000, with a total project cost of $4,700,000; proposals must include five percent (5%) contractor's contingency and $250,000 owner's construction contingency in the base bid. Respondents must submit a Veteran Heroes United in Business (VetHUB) Historically Underutilized Business Subcontracting Plan, as the University of Texas System has determined that subcontracting opportunities are probable for this contract valued above $100,000. Performance and payment bonds in the amount of one hundred percent (100%) of the contract price are required within ten calendar days of best value selection. The University reserves the right to reject any and all proposals, divide the project into multiple parts, or abandon the project. Liquidated damages are established at $500 per calendar day for failure to achieve substantial completion by the contractual deadline.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR COMPETITIVE SEALED PROPOSALS

FOR A GENERAL CONTRACTOR

UNIVERSITY OF TEXAS PERMIAN BASIN

J. CONRAD DUNAGAN LIBRARY INFRASTRUCTURE MODERNIZATION

RFP No.: 742-27-255-2

PROPOSALS DUE TUESDAY, JANUARY 12, 2027, 2:00 PM CST

Prepared By:

Alaneisha (Ally) Duke, Assistant Director of Purchasing Office of Purchasing 4901 E. University Blvd

Mesa Building, Room 3162 Odessa, TX 79762

432-552-2791 duke_a@utpb.edu Issued: November 16, 2026

TABLE OF CONTENTS

Section 1 - General Information and Requirements

1.1 General Information

1.2 Public Information

1.3 Type of Contract

1.4 Clarifications and Interpretations

1.5 Submission of Proposals

1.6 Point-Of-Contact

1.7 Evaluation of Proposals

1.8 Owner’s Reservation of Rights

1.9 Acceptance of Evaluation Methodology

1.10 No Reimbursement for Costs

1.11 Pre-Submittal Conference

1.12 Eligible Respondents

1.13 Historically Underutilized Business Submittal Requirements

1.14 Certain Proposal and Contract Prohibited

1.15 Sales and Use Taxes

1.16 Certification of Franchise Tax Status

1.17 Required Notices of Worker’s Compensation Insurance Coverage

1.18 Delinquency in Paying Child Support

1.19 Certification Required by Texas Governor Executive Order GA-48

Section 2 - Executive Summary

2.1 Historical Background

2.2 Mission Statement

2.3 Project Description, Scope and Budget

2.4 Project Planning Schedule

2.5 Project Budget

Section 3 - Submittal Requirements For Statement of Proposals

3.1 Respondent’s Ability To Provide Construction Services

3.2 Qualifications of Construction Team

3.3 Respondent’s Past Performance on Representative Projects

3.4 Respondent’s Past Performance on U.T. System Projects

3.5 Respondent’s Project Planning and Scheduling for This Project

3.6 Respondent’s Execution Plan, Quality Control and Commissioning Program for this Project

3.7 Respondent’s Project Safety Program for This Project

3.8 Respondent’s Warranty and Service Support Program for This Project

3.9 Respondent’s Pricing and Delivery Proposal

Section 4 - Format of Proposals

4.1 General Instructions

4.2 Page Size, Binding, Dividers and Tabs

4.3 Table of Contents

4.4 Pagination

Section 5 – Proposal Documents:

5.1 Definition

5.2 Ownership and Temporary Use of Documents

5.3 Electronic Distribution and Receipt

5.4 Proposal Documents on File

5.5 Attachments

Request for Competitive Sealed Proposals

UNIVERSITY OF TEXAS PERMIAN BASIN

J. CONRAD DUNAGAN LIBRARY INFRASTRUCTURE MODERNIZATION

RFP No.: 742-27-255-2

SECTION 1 – GENERAL INFORMATION AND REQUIREMENTS

1.1 GENERAL INFORMATION: The University of Texas Permian Basin (“Owner”) is soliciting Competitive Sealed Proposals (“Proposals”) for selection of a General Contractor firm for the Geoscience Relocation and Science and Technology Building Renovation (“Project”), in accordance with the terms, conditions, and requirements set forth in this Request for Competitive Sealed Proposals.

1.1.1 This Request for Competitive Sealed Proposals (“RFP”) is the only step for selecting a General Contractor for the Project as provided by Texas Education Code §51.783(d). The RFP provides the information necessary to prepare and submit Competitive Sealed Proposals for consideration and ranking by the Owner.

1.1.2 The Owner may select the Proposal that offers the “best value” for the institution based on the published selection criteria and on its ranking evaluation. The Owner may first attempt to negotiate a contract with the selected offeror. The Owner may discuss with the selected offeror options for a scope or time modification and any price change associated with the modification. If the board is unable to reach a contract with the selected offeror, the Owner may formally end negotiations with that offeror and proceed to the next “best value” offeror in the order of the selection ranking until a contract is reached or all proposals are rejected.

1.2 Public Information: All information, documentation, and other materials submitted in response to this solicitation are considered non-confidential and/or non-proprietary and are subject to public disclosure under the Texas Public Information Act (Texas Government Code, Chapter 552.001, et seq.) after the solicitation is completed.

1.2.1 The Owner strictly complies with all statutes, court decisions, and opinions of the Texas Attorney General with respect to disclosure of RFP information.

1.3 Type of Contract: Any contract resulting from this solicitation will be in the form of the Owner’s Standard General Contractor Agreement, a copy of which is included in the Proposal Documents.

1.3.1 The work will be awarded under as a Lump-Sum contract to the Respondent offering the “best value” to the Owner.

1.4 CLARIFICATIONS AND INTERPRETATIONS: Any clarifications or interpretations of this RFP that materially affect or change its requirements will be issued by the Owner as an Addendum. It is the responsibility of all respondents to obtain this information in a timely manner. All such Addenda issued by the Owner before the proposals are due as part of the RFP, and respondents shall acknowledge receipt of each Addendum to the RFP and/or the Bid Documents in its Proposal.

1.4.1 ALL QUESTION SUBMITTALS WILL BE DUE: THURSDAY, DECEMBER 17, 2026, AT 5:00 PM CST. via the UTPB bid site: https://vendors.planetbids.com/portal/74570/portal-home

1.4.2 No oral explanation in regard to the meaning of the Proposal Documents will be made and no oral instructions will be given before the award of the contract. Discrepancies, omissions or doubts as to the meaning of Drawings and Specifications shall be communicated in writing to the Project Architect for interpretation. Any interpretation made will be in the form of an Addendum, which will be forwarded to all known plan holders and its receipt by the respondent shall be acknowledged on the Respondent’s Pricing and Delivery Proposal Form.

1.4.3 Respondents shall consider only those clarifications and interpretations to the Drawings and Specifications that the Project Architect issues by Addenda five (5) calendar days prior to the submittal deadline. Interpretations or clarifications in any other form, including oral statements, will not be binding on the Owner and should not be relied on in preparing Proposals.

1.5 SUBMISSION OF GENERAL CONTRACTOR PROPOSALS:

1.5.1 PROPOSAL DEADLINE: The Owner will receive General Contractor Proposals until Proposal Deadline: Tuesday, JANUARY 12, 2027, 2:00 PM CST

1.5.2 Office of Purchasing will accept General Contractor Proposals, Execution of Offer Letters (EOOs), and VetHUB Subcontracting Plans (HSP’s) on paper or electronically.

1.5.3 Number of Copies

Proposer must submit either (a) or (b) :

(a) ONE (1) complete paper copy of its Proposal, Qualifications, Execution of Offer Letters (EOOs), and separate VetHUB Subcontracting Plans (HSP’s).

(b) Submit ONE (1) electronic copy of the Proposal with included Qualifications, ONE (1) separate electronic copy of the Execution of Offer Letters (EOOs), and ONE (1) separate electronic copy of the VetHUB Subcontracting Plans (HSP’s).

Please be aware that these files may be printed by the Owner.

Please limit each file required by Section 4 to 15 GB (Editor confirm file size limitation and if upload site will accept limitation) per file and follow File Naming Protocol as under:

· File Name: CompanyName_RFP_Proposal

· File Name: CompanyName_EOO_Response

· File Name: CompanyName: HSP Response Please do not use these characters in the file name ~ " # % & * : < > ? / \ { | }.

If any file cannot be successfully uploaded on first attempt, try again. If there is a system error on second attempt, contact the Point-of-Contact identified in Section 1.6 of this RFP

General Contractor Proposals shall be addressed to the Point-of-Contact identified in 1.6 of this RFP. Any General Contractor Proposals posted to the link above after the deadline will not be accepted. The Respondents may verify receipt of its General Contractor Proposal by reaching out to the Point-of-Contact in 1.6 of this RFP. During these forthcoming electronic RFP submissions, The University of Texas System cannot be held responsible for all possible contingencies. In the event the Respondent has any issues with connectivity and/or technology, The University of Texas System reserves the right to proceed with the selection of a General Contractor.

After the HSP’s are received (refer to 1.5.3) and deemed responsive by the University of Texas Permian Basin, then all properly submitted General Contractor Proposals will be considered.

1.5.4 Submission

Proposals must be received by the University on or before the Submittal Deadline (ref. Section 1.5.1) and delivered to:

Alaneisha (Ally) Duke Assistant Director of Purchasing Office of Purchasing

4901 E. University Blvd

Mesa Building, Room 3162 Odessa, TX 79762

Email to duke_a@utpb.edu

OR

UTPB bid site: https://vendors.planetbids.com/portal/74570/portal-home

1.5.5 Proposals or VetHUB Subcontracting Plans that are received late will be considered non-responsive.

1.5.6 The Owner will not acknowledge or receive Proposals or VetHUB Subcontracting Plans by any other means other than those identified in 1.5.2.

1.5.7 Properly submitted Proposals and VetHUB Subcontracting Plans will not be returned to the respondents.

1.6 POINT-OF-CONTACT: The Owner designates the following person, as its representative and Point-of-Contact for this RFP. Respondents shall restrict all contact with the Owner and direct all questions regarding this RFP, including questions regarding terms and conditions, to the Point-of-Contact person.

Alaneisha (Ally) Duke, Assistant Director of Purchasing University of Texas Permian Basin

Office of Purchasing

4901 E. University Blvd

Mesa Building, Room 3162 Odessa, TX 79762 Phone: 432-552-2791 E-Mail: duke_a@utpb.edu

1.6.1 The Owner designates the following as its Architect/Engineer representative regarding questions about the technical Drawings and Specifications.

Parkhill Architects

800 S. Polk Street

Amarillo, TX 79101

Attention: Melissa Walker

1.7 EVALUATION OF PROPOSALS: The evaluation of the Proposals shall be based on the requirements described in this RFP. All properly submitted Proposals will be reviewed, evaluated, and ranked by the Owner.

1.7.1 SCORED CRITERIA

Scored Criteria
Max Points
1.7.1.1 Respondent’s Ability to Provide Construction Services
5
1.7.1.2 Qualifications of the Construction Team
5
1.7.1.3 Respondent’s Past Performance on Representative Projects
8
1.7.1.4 Respondent’s Past Performance on U.T. System Projects
4
1.7.1.5 Respondent’s Project Planning and Scheduling for this Project
8

1.7.1.6 Respondent’s Execution Plan, Quality Control and Commissioning Program for this Project

1.7.1.7 Respondent’s Project Safety Program for this Project
4
1.7.1.8 Respondent’s Warranty and Service Support Program for this Project
4
1.7.1.9 Respondent’s Pricing and Delivery Proposal
60
Total Possible Points
100

1.8 OWNER’S RESERVATION OF RIGHTS: The Owner may evaluate the Proposals based on the anticipated completion of all or any portion of the Project. The Owner reserves the right to divide the Project into multiple parts, to reject any and all Proposals and re-solicit for new Proposals, or to reject any and all Proposals and temporarily or permanently abandon the Project. Owner makes no representations, written or oral, that it will enter into any form of agreement with any respondent to this RFP for any project and no such representation is intended or should be construed by the issuance of this RFP.

1.9 Acceptance of Evaluation Methodology: By submitting its Proposals in response to this RFP, the Respondent accepts the evaluation process and acknowledges and accepts that determination of the “best value” Respondent will require subjective judgments by the Owner.

1.9.1 The Owner reserves the right to consider any Proposal “non-responsive” if the Base Proposal Cost is determined to be unreasonable or irresponsible in relation to the other submitted Proposals and/or the Owner’s estimate of the construction cost.

1.10 no reimbursement for costs: Respondent acknowledges and accepts that any costs incurred from the respondent’s participation in this RFP process shall be at the sole risk and responsibility of the respondent. Respondents submit Proposals at their own risk and expense.

1.11 PRE-SUBMITTAL CONFERENCE (Non-Mandatory): A pre-submittal conference will be held at the time and location described below.

TUESDAY DECEMBER 8, 2026 at 1:00 PM CST The University of Texas Permian Basin 4901 E. University Blvd.

J. Conrad Dunagan Library Foyer

Odessa, TX 79762

Campus Map: Campus Map and Building Directory - The University of Texas Permian Basin | UTPB There will be no virtual meeting option available.

1.11.1 A guided tour of the J. Conrad Library will be included as part of the conference agenda. This may be the only opportunity for potential respondents to view the Project site(s) before the submittal of Proposals. Attendance at the pre-submittal conference is optional.

1.12 Eligible Respondents: Only individual firms or lawfully formed business organizations may apply (This does not preclude a respondent from using consultants.) The Owner will contract only with the individual firm or formal organization that submits a Proposal.

1.13 HISTORICALLY UNDERUTILIZED BUSINESSES SUBMITTAL REQUIREMENTS: It is the policy of The University of Texas System, and each of its component institutions, to promote and encourage contracting and subcontracting opportunities for Historically Underutilized Businesses (VetHUB) in all contracts. Accordingly, the Office of Capital Projects (OCP) has adopted Exhibit H, Policy on Utilization of Historically Underutilized Businesses (included in the Proposal Documents). The Policy applies to all contracts with an expected value of $100,000 or more. If OCP determines that subcontracting opportunities are probable, then a VetHUB Subcontracting Plan is a required element of the Proposals. Failure to submit a required VetHUB Subcontracting Plan will result in rejection of the Proposals.

1.13.1 STATEMENT OF PROBABILITY: The University of Texas System, Office of Capital Projects (OCP), has determined that subcontracting opportunities are probable in connection with this procurement solicitation. Therefore, a VetHUB Subcontracting Plan (HSP) is required as a part of the respondent's Proposal. The respondent shall develop and administer a HSP as a part of the respondent's Proposal in accordance with the OCP Policy on Utilization of Historically Underutilized Businesses (VetHUB), Exhibit H.

1.13.2 Refer to Exhibit H, Policy on Utilization, Historically Underutilized Business and the Summary of Requirements for a detailed list of attachments required with the Proposals.

1.13.3 The “Statement of Probability” determines the probability for subcontracting opportunities. This determination will clarify which attachments, detailed in Figure 1, will be required to be completed and returned.

1.14 CERTAIN PROPOSALS AND CONTRACTS PROHIBITED: Under Section 2155.004, Texas Government Code, a state agency may not accept a proposal or award a contract that includes proposed financial participation by a person who received compensation from the agency to participate in preparing the specifications or request for proposals on which the proposal or contract is based. All vendors must certify their eligibility by acknowledging the following statement, "Under Section 2155.004, Government Code, the vendor certifies that the individual or business entity named in this bid or contract is not ineligible to receive the specified contract and acknowledges that this contract may be terminated and payment withheld if this certification is inaccurate." If a state agency determines that an individual or business entity holding a state contract was ineligible to have the contract accepted or awarded as described above, the state agency may immediately terminate the contract without further obligation to the vendor. This section does not create a cause of action to contest a proposal or award of a state contract.

1.15 SALES AND USE TAXES: Section 151.311, Tax Code, as amended effective October 1, 1993, permits the purchase free of state sales and use taxes of tangible personal property to be incorporated into realty in the performance of a contract for an improvement to realty for certain exempt entities that include The University of Texas System. The section further permits the purchase tax-free of tangible personal property (other than machinery or equipment and its accessories and repair and replacement parts) for use in the performance of such a contract if the property is "necessary and essential for the performance of the contract" and "completely consumed at the job site." In addition, the section permits the purchase tax-free of a tangible service for use in the performance of such a contract if the service is performed at the job site and if "the contract expressly requires the specific service to be provided or purchased by the person performing the contract" or "the service is integral to the performance of the contract."

1.16 CERTIFICATION OF FRANCHISE TAX STATUS: Respondents are advised that the successful respondent will be required to submit certification of franchise tax status as required by State Law (H.B. 175, Acts 70th Leg. R.S., 1987, Ch. 283, p. 3242). The Respondent further agrees that each subcontractor and supplier under contract will also provide a certification of franchise tax status.

1.17 REQUIRED NOTICES OF WORKERS' COMPENSATION INSURANCE COVERAGE: The Texas Workers' Compensation Commission has adopted a new rule, 28 TAC, sec. 110.110, relating to REPORTING REQUIREMENTS FOR BUILDING OR CONSTRUCTION PROJECTS FOR GOVERNMENTAL ENTITIES. The rule applies to all building or construction contracts advertised for bid on or after September 1, 1994. The rule implements sec. 406.096, Texas Labor Code, which requires workers' compensation insurance coverage for all persons providing services on a building or construction project for a governmental entity. The requirements of the rule are set forth in Article 6 of the Uniform General Conditions.

1.18 DELINQUENCY IN PAYING CHILD SUPPORT: Under Section 231.006, Family Code, the vendor or applicant certifies that the individual or business entity named in this contract, bid, or application is not ineligible to receive the specified grant, loan, or payment and acknowledges that this contract may be terminated and payment may be withheld if this certification is inaccurate.

1.19 Certification Required by Texas Governor Executive Order GA-48: Pursuant to Executive Order GA-48 of the Governor of Texas effective November 19, 2024, Contractor certifies that it and, if applicable, any of its holding companies or subsidiaries, is not:

a. Listed in Section 889 of the 2019 National Defense Authorization Act (NDAA); or

b. Listed in Section 1260H of the 2021 NDAA; or

c. Owned by the government of a country on the U.S. Department of Commerce's foreign adversaries list under 15 C.F.R. § 791.4; or

d. Controlled by any governing or regulatory body located in a country on the U.S. Department of Commerce's foreign adversaries list under 15 C.F.R. § 791.4.

[NOTE: Executive Order GA 48 states that a public institution of higher education cannot enter into a new contract, contract extension, or contract renewal for a good or service with any company that meets any of the above-listed criteria. However, if the public institution of higher education can sufficiently demonstrate that (a) the good or service is necessary for the institution of higher education to fulfill a core function that directly benefits Texans and (b) the good or service can only be provided by an entity that meets one of the above-listed criteria, then the public institution of higher education may enter into a new contract, contract renewal, or contract extension with such an entity for no more than one year from November 19, 2024, and never thereafter.]

SECTION 2 – EXECUTIVE SUMMARY

2.1 HISTORICAL BACKGROUND:

Our Mission and History - The University of Texas Permian Basin | UTPB

2.2 MISSION STATEMENT:

As a regional, comprehensive institution, The University of Texas Permian Basin serves a diverse community of students from the region, the state, and beyond. Through excellence in student-centered teaching, learning, research, and public service, the University cultivates engaged citizens and impacts lives while advancing technology and the public interests of West Texas

2.3 PROJECT DESCRIPTION AND SCOPE:

The University of Texas Permian Basin J. Conrad Dunagan Library was constructed in 2000. The

Library’s infrastructure is more than 26 years old now and certain components are in need of significant upgrading. The 80,000 square foot two-story building has a single two-stop elevator which requires modernization and code compliance. The building is fully sprinklered, but the sprinkler heads all need to be changed out (both levels), as well as upgrades to fire alarm panels.

The HVAC equipment has reached the end of its useful life and requires replacement, including distribution and controls, VFD’s, chill water pumps and piping. Electrical upgrades will include adding an emergency generator and transfer switch (will be bid as an Alternate). Restrooms will be upgraded to include new fixtures and associated drainage and supply.

Scope of Work

Work of Project consists of the renovation of restrooms, break room, restoration of aluminum curtain wall system including mullion/gasket/sealant replacement, and replacement of existing passenger elevator cab in existing shaft to meet applicable code and accessibility requirements. Work includes coordination of all life safety requirements for the new cab and all elevator control systems. Fire protection work includes fire sprinkler head replacement throughout the building and 5-year fire pipe inspection. Mechanical work includes the following: upgrading and replacing the building management system, including controllers for identified HVAC equipment and systems, the associated wiring infrastructure, enclosures, power supplies, and networking equipment; refurbish air handlers, including new variable frequency drives, and new HVAC equipment as shown. Electrical work includes light fixtures at restrooms, exterior light fixtures, exterior lighting control system, and associated electrical work to support new elevator cab and HVAC work.

2.4 PROJECT PLANNING SCHEDULE:

The following anticipated dates are for planning purposes only (if there is a conflict between the dates below and the Proposal Form, the duration shown on the Proposal Form shall govern). The contractual dates required by the Owner of the “best value” respondent will be identified in the executed agreement.

· Owner conducts Pre-Submittal Conference Refer to Section 1.11

· Owner receives Request For Competitive Sealed Proposals Refer to Section 1.5

· Owner receives Proposals/VetHUB Subcontracting Plan Refer to Section 1.5

· Owner executes Agreement

TBD

· Owner issues Notice to Proceed for Construction

TBD

· General Contractor achieves Substantial Completion

TBD

· General Contractor achieves Final Completion

TBD

2.5 PROJECT BUDGET:

The architects estimated construction cost is $4,054,000. The Total Project Cost (TPC) is $4,700,000. Please include five-percent (5%) Contractor’s Contingency in your Base Bid. Please include $250,000 Owner’s Construction Contingency in your Base Bid.

SECTION 3 – REQUIREMENTS FOR COMPETITIVE SEALED PROPOSALS

Respondents shall carefully read the information contained in the following criteria and submit a complete statement of Proposals to all questions in Section 3 formatted as directed in Section 4. Incomplete Proposals will be considered non-responsive and subject to rejection.

3.1 CRITERIA ONE: Respondent’s Ability To Provide Construction Services

3.1.1 Provide the following information on your firm for the past five (5) fiscal years:

Volume

· Annual number, value and percent change of contracts in Texas per year;

· Annual number, value and percent change of contracts nationally per year;

Revenues

· Annual revenue totals and percent change per year;

Bonding

· Total bonding capacity;

· Available bonding capacity and current backlog;

3.1.2 Attach a letter of intent from a surety company indicating your firm’s ability to bond for the entire construction cost of the project. The surety shall acknowledge that the firm may be bonded for each stage/phase of the project, with construction cost of no less than the combined base and alternate proposal costs stated in CRITERIA nine: Respondent’s Pricing and Delivery Proposal. Bonding requirements are set forth in Article 17 of the Agreement and Article V of the Uniform General Conditions.

3.1.3 Identify if your firm is currently for sale or involved in any transaction to expand or to become acquired by another business entity? If so, please explain the impact both in organization and company direction.

3.1.4 Provide details of any past or pending litigation, or claims filed, against your firm that may affect your performance under a Contract with the Owner.

3.1.5 Identify if your firm is currently in default on any loan agreement or financing agreement with any bank, financial institution, or other entity? If so, specify date(s), details, circumstances, and prospects for resolution.

3.1.6 Does any relationship exist by relative, business associate, capital funding agreement, or any other such kinship between your firm and any Owner employee, officer or Regent? If so, please explain.

3.2 CRITERIA TWO: QUALIFICATIONS OF CONSTRUCTION TEAM

3.2.1 Provide resumes of the Respondent’s team that will be directly involved in the Project, including, as applicable, Project Managers and Superintendents.

3.2.2 Describe the proposed Project assignments and lines of authority and communication for each team member to be directly involved in the Project.

3.2.3 Identify the Mechanical, Electrical and Plumbing Subcontractors included as part of this proposal, including their experience with similar projects, the number of years with the firm, and their city(s) of residence.

3.3 CRITERIA THREE: Respondent’s PERFORMANCE ON PAST REPRESENTATIVE PROJECTS

3.3.1 Identify and describe the Respondent’s experience with providing Construction Services that are most related to this project within the last five (5) years. List the projects in order of priority, with the most relevant project listed first. Provide the following information for each project listed:

· Project name, location, contract delivery method, and description

· Color images

· List proposed team members who worked on project

· Initial and Final construction cost, including change orders

· Final project size in gross square feet

· Type of construction (new, renovation, or expansion)

· Actual Notice To Proceed, Substantial Completion, and Final Payment dates for Construction Services

· Name of Project Manager (individual responsible to the Owner for the overall success of the project)

· Name of Project Superintendent (individual responsible for coordinating the day to day work)

· Names of Mechanical, Plumbing and Electrical Subcontractors References (for each project listed above, identify the following):

· The Owner’s representative who served as the day-to-day liaison during construction, including telephone number and email address.

· Architect/Engineer’s name and representative who served as the day-to-day liaison during construction, including telephone number and email address.

· Length of business relationship with the Owner.

References shall be considered relevant based on specific project participation and experience with the respondent. The Owner may contact references during any part of this process. The Owner reserves the right to contact any other references at any time during the RFP process.

3.3.2 Identify a maximum of three (3) completed projects, of any type, for which your firm has received an award for construction excellence from a recognized organization and provide descriptive information for each.

3.4 CRITERIA Four: Respondent’s PAST PERFORMANCE ON U.T. SYSTEM PROJECTS

3.4.1 Identify and describe the Respondent’s experience with providing Construction Services on University of Texas System projects within the last five (5) years.

If the respondent has not previously provided Construction Services for The University of Texas System, then identify and describe the respondent’s past performance on Construction projects for “major” institutions of higher education (or similar) within the last five (5) years. Projects may repeat with Section 3.3.

In either case above, provide the following information for each project listed:

· Project name, location, contract delivery method, and description

· Color images

· List proposed team members who worked on project

· Initial and Final construction cost, including change orders

· Final project size in gross square feet

· Type of construction (new, renovation, or expansion)

· Actual Notice To Proceed, Substantial Completion, and Final Payment dates for Construction Services

· Name of Project Manager (individual responsible to the Owner for the overall success of the project)

· Name of Project Superintendent (individual responsible for coordinating the day to day work)

· Names of Mechanical, Plumbing and Electrical Subcontractors

3.5 CRITERIA FIVE: RESPONDENT’S Project PLANNING AND scheduling FOR THIS PROJECT

3.5.1 Using the Project Planning Schedule in the Part 2.4 of this RFP and identify specific critical process, phases, milestones, approvals, and procurements anticipated. Clearly identify the 10% Total Project Float required during the Construction Phase.

3.5.2 Describe what you perceive are the critical Construction issues for this Project and state how those have been addressed in the Critical Path Method (CPM) Milestone schedule you have submitted for this Project.

3.5.3 Identify the schedule assumptions that are included in your Critical Path Method (CPM) schedule submitted for this Project.

3.5.4 Describe your approach to assuring timely completion of this project, including methods for schedule recovery, if necessary. From any three (3) of the projects listed in response to Section 3.3 or 3.4 of this RFP, provide examples of how these techniques were used, including specific scheduling challenges/requirements and actual solutions.

3.5.5 Describe your plan, if any, for improving the Project schedule provided in Part 2.4 of this RFP for achieving Substantial and Final Completion. In doing so:

3.5.5.1 Respondent shall describe any impact on quality of services, materials or workmanship that may occur.

3.5.5.2 Respondent shall state it understands by submission of its Proposal that any other time durations required of the Project will not be revised.

3.5.1 Describe your experience with replacing underperforming subcontractors and what you did to mitigate schedule impacts created by their replacement. Identify any projects listed in response to Section 3.3 and 3.4 of this RFP where this occurred

3.5.2 This Project will occur in a building that will remain occupied during construction, describe your plan to phase construction to minimize impact to the occupants in the existing building.

3.5.3 Describe the anticipated steps necessary to maintain operation of the occupied building during construction.

3.6 CRITERIA SIX: RESPONDENT’S EXECUTION PLAN, quality control AND COMMISSIONING prOGRAM FOR THIS PROJECT

3.6.1 Provide your proposed Site Utilization Plans, Contractor Site Access and Limits of Construction.

3.6.2 Describe your approach to pre-planning and coordinating inspections and approvals with the Owner’s work force/consultants and other AHJ entities, including but not limited to, Texas Department of Licensing and Regulation, State Fire Marshall, etc.

3.6.3 Provide the name(s) of the Project and Information Management System(s) you will utilize during construction and describe the benefits each system will provide this Project. Include examples of the deliverables each system will generate (i.e. logs, reports, records, tracking/monitoring lists etc.). Furthermore, address how each these systems will:

3.6.3.1 Create, track, complete and close out of contractor produced punch lists.

3.6.3.2 Incorporate 3rd party punch lists and how those items are tracked by various stakeholders and closed out by their respective authors.

3.6.3.3 Deficiency tracking/resolution and progress reporting to the Owner.

3.6.3.4 Inspection tracking and compliance sign off by various stakeholders.

3.6.3.5 Document and monitor pre-functional and functional test progress and compliance sign off by various stakeholders.

3.6.4 Describe your quality control program and address:

3.6.4.1 Methods used to measure and ensure quality control during construction and how you will proactively address non-conforming Work.

3.6.4.2 How you will confirm the Work is compliant with all aspects of the Project requirements and that you have fulfilled all of your obligations as the General Contractor prior to requesting the Owner or its consultant’s participation in inspections, testing, commissioning or development of punch lists.

3.6.5 Describe your plans and processes for vetting of potential Change Proposals for legitimacy, contractual compliance, accuracy, and timeliness prior to notifying the Owner of the potential change and subsequently presenting Change Proposals for Owner review.

3.6.6 Describe how and when you intend to facilitate mock-ups for Owner’s approval into the Project.

3.6.7 Describe your understanding of the Owner’s requirement for, Certification of No Asbestos Containing Materials or Work and identify how this will be managed on this Project.

3.6.8 Describe your procedures for implementing industry’s “best practices” as defined by the Construction Industry Institute and similar organizations for:

· Front End Planning

· Establishing and tracking project objectives

· Partnering & Team Building

· Dispute Prevention and Resolution

· Cost tracking

· Change (order) management systems

· Lessons Learned

· Materials Management

· Preparing for and coordinating inspections

· Punch list development, tracking, completion, and secure signoff by various parities

· Total quality management for each phase, including close-out and commissioning.

· Zero Accidents Techniques

3.6.9 Describe your experience in constructing high performance buildings achieving LEED certification of Silver or higher. Explain the methods used to ensure compliance with best green building practices for construction of sustainable facilities. For any combination of three (3) projects listed in response to Section 3.3 or 3.4 of this RFP, provide examples of how these methods were used and the degree of success achieved.

3.6.10 State if your Proposal for this Project includes contractor produced Building Information Models (BIM) for coordination of work and subsequent production of shop drawings. Identify each sub-contractor / trade and any self-performed work that is included in the Proposal and state the minimum BIM Level of Detail / Development (i.e. Level 200, 300, 400, 500) to be provided by each trade.

3.6.11 Outline the process you intend to utilize during construction for continuously maintaining accurate, professionally drafted electronic As Built / Record Documents for turn over to the design team and the Owner.

3.6.12 Describe your approach to coordinating and facilitating Owner installed work. Examples include: audio/visual systems, telecom racks/switches, security systems/equipment, door hardware/card readers, lab equipment, parking access/controls equipment, furnishings etc.

3.6.13 Describe your approach to pre-planning and coordinating inspections and approvals with the Owner’s work force and consultants.

3.6.14 Describe your approach to coordinating inspections and approvals with the State Fire Marshall regarding approval of fire/life safety systems.

3.6.15 Describe your approach to coordinating inspections and approvals with the Texas Department of Licensing and Regulation for conveying systems.

3.6.16 Describe your approach to coordinating inspections and approvals with the Texas Department of Licensing and Regulation regarding Texas Accessibility Standards.

3.6.17 Describe how you have maintained security during the construction of an occupied facility listed in Section 3.3 or 3.4 of this RFP.

3.6.18 Describe your experience dealing with congested campuses/site conditions for any project listed in Section 3.3 or 3.4 of this RFP.

3.6.19 Describe your plans for infection control in an occupied, fully functional hospital facility.

3.6.20 Describe your approach for mitigating noise/vibration, dust/fume/odor/moisture/temperature transmission into adjacent occupied space.

3.6.21 Describe your approach to Total Building Commissioning, specifically addressing Fire Alarm & Security Systems to ensure completion of all pre-functional, functional, systems integration and training activities prior to the contractual substantial completion date. From any three (3) projects listed in response to Section 3.3 or 3.4 of this RFP, provide examples of how these techniques were successfully implemented to the satisfaction of the Owner.

3.6.22 Provide any other details regarding special services, products, advantages, or other benefits offered to the Owner by the Respondent that are included as part of this Proposal. If any of the special services, products, advantages, or other benefits are in “addition to” clearly state which items are an additional service to the Proposal.

3.7 CRITERIA SEVEN: RESPONDENT’S ABILITY TO MANAGE CONSTRUCTION SAFTY RISKS AND PROJECT safety program FOR THIS PROJECT The vision of the University of Texas System and this Institution is to prevent workplace injuries / incidents on all construction projects. We consider this a core value within our organization and attach maximum importance to this Criteria in the evaluation.

3.7.1 Briefly explain your firm’s understanding of the 2013 Uniform General Conditions Article 7 Construction Safety (Ref. Exhibit B) and indicate how your project safety program will align with the specification. * Note – Generic statements such as “have read and understand the safety specification” or “will comply” are not acceptable responses.

3.7.2 Briefly describe your firm’s approach to anticipating, recognizing, and controlling construction safety risks.

3.7.3 Detail your firm’s Safety Department structure. Identify the highest-ranking person and job title for the Department. Provide the reporting line for the safety professional team member(s) on the construction project.

3.7.4 Describe the safety performance and insurance claims history information and weighting that your firm will or has used in the submission and selection process for subcontractors that will be used on the project. Indicate when/if your firm would perform any work beyond project management.

3.7.5 For all projects that your firm has managed or co-managed in the most recent five (5) year period, list and describe all incidents that reached any of the following levels of severity:

3.7.5.1 Any occupational illness or injury that resulted in any project worker’s death or total/permanent disability.

3.7.5.2 Any occupational illness or injury that resulted in any project worker’s hospital stay of three (3) or more days.

3.7.5.3 Explosion, fire, or water damage that claimed 1% or more of a project’s construction value.

3.7.5.4 Failure, collapse, or overturning of a project structure, scaffold, excavation, crane, or motorized equipment when any project workers were present on the project site.

3.7.6 List any OSHA citations that your firm has been issued during the most recent five (5) year period. Indicate the current status or final outcome for each citation.

3.7.7 Indicate your firm’s North American Industry Classification System (NAICS) code used to determine your firm’s Experience Modification Rate (EMR). Provide your annual EMR for each of the most recent five (5) year period.

3.7.8 Indicate your firm’s annual OSHA Recordable Incident (RI) Rate for all work performed for each of the most recent five (5) year period.

3.7.9 Indicate your firm’s annual OSHA Days Away from Work (DAFW) Rate for all work performed for each of the most recent five (5) year period.

3.7.10 Indicate your firm’s annual OSHA Day Away, Restricted, or Transfer (DART) Rate for all work performed for each of the most recent five (5) year period.

3.7.11 Briefly indicate how your firm will support the onsite Safety when safety issues arise. What level of corporate safety will periodically audit the project and how often? How often is it anticipated that the Corporate Safety Officer / Director will periodically audit the project?

3.7.12 Provide the signature of the Respondent’s Corporate Safety Officer / Director attesting to CRITERIA SEVEN responses.

3.8 CRITERIA EIGHT: RESPONDENT’S Warranty AND Service Support PROGRAM FOR THIS PROJECT

3.8.1 Describe your warranty service support philosophy and warranty service implementation plan for this Project.

3.8.2 Describe how you will measure the quality of service provided to the Owner for this Project.

3.8.3 Provide reference letters from three (3) Owners (other than U.T. Permian Basin) identified in Sections 3.3 OR 3.4 of the previously issued RFP that describe your response to, and performance on, warranty services AFTER substantial completion.

3.9 CRITERIA nine: Respondent’s Pricing and Delivery Proposal AND EXECUTION OF OFFER

3.9.1 Complete and submit the “Respondent’s Pricing and Delivery Proposal and Execution of Offer” included with the RFP Documents.

SECTION 4 – FORMAT of PROPOSALS

4.1 General Instructions

4.1.1 Proposals shall be prepared simply and economically, providing a straightforward, concise description of the respondent's ability to meet the requirements of this RFP. Emphasis shall be on the quality, completeness, clarity of content, responsiveness to the requirements, and an understanding of Owner's needs.

4.1.2 Electronically submitted Proposals shall be searchable .pdf and a MAXIMUM OF SIXTY (60) PRINTABLE PAGES. Minimum eleven (11) point font size shall be used. The cover, table of contents, VetHUB Subcontracting Plan (Section 1.13), and Execution of Offer do not count as printed pages.

4.1.2.1 Proposals shall be submitted to the location(s) identified in Section 1 as three (3) separate files 1) Proposal with included Qualifications, 2) Execution of Offer, 3) VetHUB Subcontracting Plan.

4.1.3 Respondents shall carefully read the information contained in this RFP and submit a complete response to all requirements and questions as directed. Incomplete Proposals will be considered non-responsive and subject to rejection.

4.1.4 Proposals and any other information submitted by respondents in response to this RFP shall become the property of the Owner.

4.1.5 Proposals that are qualified with conditional clauses, alterations, items not called for in the RFP documents, or irregularities of any kind are subject to rejection by the Owner, at its option.

4.1.6 The Owner makes no representations of any kind that an award will be made as a result of this RFP. The Owner reserves the right to accept or reject any or all Proposals , waive any formalities or minor technical inconsistencies, or delete any item/requirements from this RFP when deemed to be in Owner's best interest.

4.1.7 Proposals shall consist of answers to questions identified in Section 3 of the RFP. It is not necessary to repeat the question in the Proposals; however, it is essential to reference the question number with the corresponding answer.

4.1.8 Failure to comply with all requirements contained in this Request for Proposals may result in the rejection of the Proposals.

4.2 PAGE SIZE, BINDING, DIVIDERS, AND TABS:

4.2.1 Electronically submitted Proposals shall be capable of being printed by the Owner on letter-size (8-1/2” x 11”) paper, portrait orientation.

4.2.2 Additional attachments shall NOT be included with the Proposals. Only the responses provided by the Respondent to the questions identified in Section 3 of this RFP will be used by the Owner for evaluation.

4.3 TABLE OF CONTENTS:

4.3.1 Submittals shall include a “Table of Contents” and give page numbers for each part of the Proposal.

4.4 PAGINATION:

4.4.1 Number all pages of the submittal sequentially using Arabic numerals (1, 2, 3, etc.); the Respondent is not required to number the pages of the HUB Subcontracting Plan.

SECTION 5 – PROPOSAL DOCUMENTS:

5.1 DEFINITION: Proposal Documents include the Proposal Requirements and the Contract Documents. The Proposal Requirements consist of the Request for Competitive Sealed Proposals for General Contractor, the Proposal and HSP Form, and other sample proposal and contract forms. The proposed Contract Documents consist of the Form of Agreement between the Owner and Contractor, Performance and Payment Bonds, Uniform General Conditions for Building Construction Contracts, VetHUB Utilization Policy (Exhibit ‘E’), other forms and documents identified in the Agreement, Drawings, Specifications, and all Addenda issued prior to receipt of Proposals, and Change Orders issued after execution of the Contract.

5.2 OWNERSHIP AND TEMPORARY USE OF DOCUMENTS: Proposal Documents prepared by the Owner, Project Architect and its consultants, or other consultants retained by the Owner for the Project that describe the Work to be executed are instruments of service and shall remain the property of their authors. Any party accessing or receiving the Proposal Documents shall not use the documents on any other projects nor shall the Proposal Documents be used, altered, disseminated, or transmitted for any other purposes. Regardless of means of receipt or possession Proposal Documents shall not be retained in any form by any party in any location more than 90 calendar days from their original issuance by The University of Texas Permian Basin.

5.3 ELECTRONIC Distribution AND RECEIPT: Proposal Documents are provided by the University of Texas Permian Basin. By accessing/receiving these documents, the accessor/receiver is confirming to The University of Texas Permian Basin it is a legal business entity authorized to do business in the State of Texas and is in good standing with the Texas Comptroller of Public Accounts. The accessor/receiver further agrees to abide by the Ownership and Temporary Use of Documents provided for in this Request for Proposal.

5.4 PROPOSAL Documents ON FILE:

Proposal Documents are accessible for download at UTPB bid site: https://vendors.planetbids.com/portal/74570/portal-home Construction Drawings are available for download at:

https://general.utpb.edu/rfp/742-27-255-2/

5.5 ATTACHMENTS:

EXHIBIT A – Standard Agreement Between Owner and Contractor

EXHIBIT B – 2013 Uniform General Conditions for University of Texas System Building Contracts EXHIBIT C – Drawing, and Specifications

EXHIBIT D - Respondent’s Pricing and Delivery Proposal and Execution of Offer EXHIBIT E – Policy on Utilization Veteran Heroes United in Businesses (VetHUB)

EXHIBIT A

Sample Standard Agreement Between Owner and Contractor (included herein by reference - see Exhibit A Attachment)

EXHIBIT B

2013 Uniform General Conditions for University of Texas System Building Construction Contracts (included herein by reference - see Exhibit B Attachment)

EXHIBIT C

Drawings and Specifications https://general.utpb.edu/rfp/742-27-255-2/

EXHIBIT D

RESPONDENT’S PRICING AND DELIVERY PROPOSAL

RFP No.:

742-27-255-2 Project Name:

J. CONRAD DUNAGAN LIBRARY INFRASTRUCTURE MODERNIZATION

From:

Respondent’s Name:

Mailing Address:

City, State, Zip Code:

Phone Number:

To:

Alaneisha (Ally) Duke Assistant Director of Purchasing Office of Purchasing

4901 E. University Blvd

Mesa Building, Room 3162 Odessa, TX 79762 Having carefully examined the Uniform General Conditions for University of Texas System Building Construction Contracts (UGC), the Plans and Specifications and addenda thereto, as prepared by JSA Architects, Inc, the Project Architect/Engineer on this Project, as well as the premises and all the conditions affecting the work, the undersigned proposes to furnish all labor, materials, and equipment necessary to achieve Substantial Completion of the work in accordance with the Contract Documents for the following sum (Amount shall be shown in both written and figure form. In case of discrepancy between the written amount and the figure, the written amount will govern):

1.1 BASE PROPOSAL COST:

DOLLARS ($

1.1.1 OWNER’S SPECIAL CASH ALLOWANCE: The above Base Proposal Cost includes the following Owner’s Special Cash Allowance(s) for work to be done within this contract under the supervision of the General Contractor and/or the Subcontractors. Each allowance shall be listed on the Contractor's Contract Price Breakdown as a portion of the total contract amount, and each shall be expended only upon direction of the Owner. This is a lump sum amount from which changes are to be paid in accordance with the Changes section of the Uniform General Conditions for University of Texas System Building Construction Contracts. Any unused amount will be deducted from the Contract Price by Change Order.

1.1.1.1 NONE AT THIS TIME

DOLLARS ($ 0.00)

1.1.1.2 NONE AT THIS TIME

1.1.1.3 NONE AT THIS TIME

1.1.2 OWNERS CONSTRUCTION CONTINGENCY: The Base Proposal Cost shall include an Owner’s Construction Contingency in an amount equal to ten percent (10%) of the Base Proposal Cost. The Owner’s Construction Contingency shall be separately identified in the Respondent’s Proposal and included in the Total Proposal Cost. The Owner’s Construction Contingency is established for the Owner’s use for unforeseen conditions, changes in the Work, or other project costs authorized by the Owner during construction. The contingency is not a guaranteed payment to the Contractor and shall be expended only upon written authorization by the Owner and in accordance with the Contract Documents and the Uniform General Conditions.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .