RFP-717526.pdf
PDF 585 KB Posted
- Attached to
- RFP Installation of 500 KV Bus Supports
- Solicitation number
- 717526
- Issued by
- Benton County, Washington
About this file
RFP-717526: Installation of 500 kV Bus Supports at Columbia Generating Station
This Request for Proposal (RFP) is issued by Energy Northwest, a Joint Operating Agency and Municipal Corporation in Washington State, for the installation of 500 kilovolt (kV) bus supports at Columbia Generating Station in Richland, Washington. The project addresses a design deficiency resulting in support structure failures and requires excavation, foundation preparation, concrete pouring, anchor and rebar installation, exothermic welding of grounds, and cable management across four locations within the facility's Protected Area. A mandatory bid walk is scheduled for July 29, 2026, at 11:00 a.m. local time at Building No. 26 (Deschutes Conference Room) of the facility. Bidders must submit questions by August 5, 2026, at 1:00 p.m., and proposals are due by August 19, 2026, at 1:00 p.m. to Robert Mendez, Contracts Lead (rdmendez@energy-northwest.com). Work must be completed within a 28-day work window and is subject to liquidated damages provisions if not completed on schedule. The contract will be awarded to a single qualified contractor based on weighted evaluation criteria: General Qualifications (10%), Commercial Qualifications (10%), Technical Qualifications (45%), and Price (35%).
All work performed in Washington State is subject to prevailing wage requirements under RCW chapter 39.12, with rates effective March 1, 2026, available on the Washington State Department of Labor & Industries website. Bidders must be licensed contractors in Washington State and must comply with the Inflation Reduction Act (IRA) prevailing wage requirements, whichever is higher. Contractors are required to submit a Performance and Payment Bond equal to 100% of the total contract sum (excluding sales tax), file certified payroll reports with L&I, and maintain a 5% retainage until final project approval by three Washington State agencies. Apprentice utilization requirements of 15% apply if the total proposal price exceeds $1,500,000. The contract includes incentive payments for safety, schedule adherence, quality, and compliance (A.C.E.M.A.N. criteria), with specific liquidated damages for delays, injuries, operational events, and rework. Contractor personnel must obtain Unescorted Access certification through Energy Northwest's credentialing process, which may require up to 40 hours per person, and must comply with security restrictions, cyber security procedures, and site-specific safety and health plan requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL NO. 717526
Procurement Quality Level: 0
FOR
INSTALLATION OF 500 KV BUS SUPPORTS
AT
COLUMBIA GENERATING STATION
MANDITORY BID WALK July 29, 2026
QUESTIONS DUE BY August 5, 2026
PROPOSAL DUE BY August 19, 2026
RFP No. 717526
Pursuant to Revised Code of Washington (RCW) §43.52.565, Energy Northwest, a Joint Operating Agency and Municipal Corporation in the State of Washington, is soliciting competitive proposals from qualified Proposers to install the 500 Kilovolt (kV) bus supports for Columbia Generating Station (Columbia).
Work performed in Washington State only: Work performed by craft personnel (i.e. laborers, millwrights, pipefitters and boilermakers, etc.) in the State of Washington are subject to prevailing wage requirements pursuant to RCW chapter 39.12. If the Work will be performed in Washington State, Bidders must be a licensed contractor in Washington State to submit a proposal on this procurement.
Energy Northwest makes no guarantee as to any actual or minimum amount of Work to be performed. Work is directed at the sole discretion and benefit of Energy Northwest.
Energy Northwest reserves the right, without qualification, to select any proposal as a basis for negotiation, to reject all proposals and to exercise its discretion and apply its judgment with respect to any proposal submitted. This Request for Proposal (RFP) does not commit Energy Northwest to pay any costs incurred in connection with any proposal, or to contract for any Work. There is no commitment on the part of Energy Northwest to accept the lowest priced proposal or any conditions imposed by a Bidder as a requirement of acceptance of their proposal. The proposal to be accepted shall be at the sole discretion of Energy Northwest.
Information submitted to Energy Northwest in response to this RFP becomes public record under the Revised Code of Washington. Without exception by the presenting Party, the information is subject to public disclosure pursuant to the Washington State Public Records Act.
Energy Northwest may unilaterally release or exempt information from public disclosure. In the event a Bidder seeks to withhold information from public disclosure, it shall hold Energy Northwest harmless from any damages or costs, including attorney’s fees and statutory awards imposed by any court or regulatory authority. Energy Northwest shall not be liable for any inadvertent public disclosure of information, despite the exercise of reasonable care.
Bidders shall thoroughly examine and be familiar with the RFP documents. Submittal of a proposal shall constitute an acknowledgement upon which Energy Northwest may rely that the Bidder has thoroughly examined and is familiar with these documents. Failure or neglect to receive or examine these documents shall in no way relieve Bidder from any obligation with respect to the proposal or these documents. No claim for additional compensation is allowed for lack of knowledge of the RFP documents.
This RFP is comprised of:
• Section I – Bid Submission Format and Content
• Section II – Contractor Selection Procedure
• Section III – Statement of Work
• Section IV – Cost Proposal Form
• Section V – Sample Document
• Exhibit “A” – OSHA Statistical Report [required with Cost Proposal Form]
• Exhibit “B” – Certification of Compliance with Wage Payment Statutes [required with Cost Proposal Form]
• Exhibit “C” - Proposed Subcontractors
• Exhibit “D” – Final Statement and General Release
• Attachment(s)
MANDTORY BID WALK
Examination date: July 29, 2026, 11:00am (local time, Richland WA). The Contracts Lead will provide further details and required forms to be completed to those who are interested in participating. Contact Robert Mendez, Contracts Lead at rdmendez@energy-northwest.com for further information.
Arrangements will be made by Energy Northwest to allow prospective Bidders access to the site for the purpose of making preliminary inspections. Availability of and access to the Site is otherwise limited; therefore, the Bidders are advised to plan their inspections and preliminary measurements for the date specified.
Date: July 29, 2026
Time: 11:00am (local time, Richland WA)
Location: Energy Northwest
Columbia Generating Station 76 N. Power Plant Loop
Richland, WA 99354
Meeting Room: Building No. 26 – Deschutes Conference Room No. 1-247
Bidders attending the mandatory site examination shall bring required personal protective equipment (PPE), including a hard hat, safety glasses and safety shoes containing upper leather or steel/composite toes. Energy Northwest will not be providing any PPE.
Essential information: Energy Northwest allows each Bidder to send a maximum of two representatives to the site tour that will include areas in the Protected Area. Bidder shall submit the “Energy Northwest Visitor Log” form provided by the Procurement Specialist for each person attending the examination of site to John Hagfelt via email at jahagfeldt@energy-northwest.com by July 22, 2026, no later than 12:00pm (local time, Richland WA) to coordinate access to the Protected Area.
Bidders, do not sign the form prior to submitting the document. The form is signed at the Protected Area security checkpoint.
Bidders who do not submit the form will not be authorized to participate in the portion of the Site tour within the Protected Area.
Bidder shall satisfy itself concerning the nature and the location of the Work, the general and local conditions, particularly those affecting transportation, disposal, handling and storage of materials, availability of labor and applicable wage rates, water and electric power, roads, climate conditions and seasons, and physical conditions at the actual work site and project area as a whole, the equipment and facilities needed preliminary to and during Work prosecution, and all other matters which can in any way affect the Work or the cost thereof.
mailto:rdmendez@energy-northwest.com mailto:jahagfeldt@energy-northwest.com
Failure of the Bidder to acquaint itself with all available information shall not relieve Bidder of the responsibility for properly estimating both the difficulties and the costs of successfully performing the Work.
RFP QUESTIONS AND RESPONSES
This is an opportunity to seek clarification or information regarding the requirements of this RFP.
The Bidder shall submit questions via email to the Contracts Lead (if necessary) no later than 1:00pm (Local time Richland, Washington) on August 5, 2026. Questions after this date may not receive a response.
Robert Mendez, Contracts Lead Phone No. 509.372.5380 rdmendez@energy-northwest.com
The Contracts Lead will provide answers to the questions via an Addendum to all Bidders.
Addendums will be emailed directly to all Bidders who attend the mandatory bid walk and will be posted on the Energy Northwest website.
PROPOSAL DUE DATE
Submit proposals to Robert Mendez, Contracts Lead no later than 1:00pm (Local time Richland, WA.) on August 19, 2026. Proposals shall be submitted by email at rdmendez@energy-northwest.com.
RFP SECTION I
PROPOSAL SUBMISSION FORMAT AND CONTENT
Bidders should submit all information necessary for Energy Northwest to evaluate the proposal in accordance with the prerequisites, technical and commercial evaluation factors set forth in this RFP.
Only those proposals which meet these requirements will be given further consideration.
A. PURPOSE
Energy Northwest will utilize the following guidelines in the selection of Bidders.
1. The purpose of the selection will constitute an objective and impartial procedure in that all interested Bidders are evaluated against the same criteria.
2. The criteria utilized in evaluating prospective Bidders shall relate to the competence and qualifications of the Bidders being considered so that the Bidders selected shall constitute the best qualified of those considered in the sole judgment of Energy Northwest.
3. The procedures employed shall ensure that companies owned by women and minorities are provided with full and equitable opportunity for participation in the selection process.
B. PROCEDURE
1. Energy Northwest shall publish in a newspaper of statewide and/or local circulation an announcement inviting all interested Bidders to indicate their interest in submitting a proposal for the Work described in the RFP. The announcement will state a date by which proposals and supporting documentation must be received.
a. RFP Questions and Responses: This is an opportunity to seek clarification or information regarding the requirements of this RFP. Submit questions via email to the Contracts Lead no later than 1:00pm (Local time Richland, WA) on August 5, 2026. Questions after this date will not receive a response. The Contracts Lead will provide answers to the questions via an Addendum to all Bidders.
b. Proposal Due Date: Submit proposals to the Contracts Lead no later than
1:00pm (Local Time Richland, WA) on August 19, 2026, Proposals shall be submitted by email to rdmendez@energy-northwest.com.
2. Proposals received by the stated due date and time will undergo a structured, multi-phase evaluation conducted by Energy Northwest. Each proposal will be evaluated against predefined criteria using a pass/rejection methodology and a quantitative, weighted scoring model. Bidders must provide sufficient detail in their submissions to allow evaluators to accurately assess, based on the methodology below, Bidder’s overall responsiveness in areas of technical knowledge, experience, management, staff and schedule as outlined in RFP Section II.
a. Mandatory qualifications will be evaluated on a pass/rejection basis. Failure to meet any mandatory requirement will result in automatic rejection of the proposal. A passing score will equal three points.
b. Commercial qualifications will be evaluated on a yes/no basis. Consistent with scoring methodology, a “yes” response will receive three points and a “no” response will receive one point.
c. Technical qualifications reflect factors other than price, as authorized under
RCW §43.52.565. Evaluators will assign a raw score from 0 to 5 for each technical evaluation criterion. Scores will reflect the demonstrated quality, completeness, clarity, and responsiveness of Bidder’s proposal to the requirements outlined in RFP Section II.
i. Score of 5 – Significantly exceeds requirements outlined; with superior, verifiable value; minimal risk; compelling differentiators and outcomes (e.g., proven results, innovative yet feasible approach, quantified benefits, exceptional references, robust risk mitigation, high quality experience). If pricing is related, this score may be used to differentiate Bidders as determined by Energy Northwest.
ii. Score of 4 – Exceeds requirements outlined; presents clear, credible solutions; lower risk; well-documented, tailored approach (e.g., strong methodology, strong risk mitigation, relevant experience, measurable performance commitments). If pricing is related, this score may be used to differentiate Bidders as determined by Energy Northwest.
iii. Score of 3 – Meets minimum requirements with adequate detail;
manageable risk; demonstrates reasonable understanding; may lack differentiators (e.g., clear plan, standard approach, baseline compliance, typical references, limited innovation). If pricing is
iv. Score of 2 – Marginal response; some requirements addressed but with notable gaps; moderate to high risk; limited detail; questionable feasibility without clarification. If pricing is related, this score may be used to differentiate Bidders as determined by Energy Northwest.
v. Score of 1 – Deficient response; major deficiencies resulting in low probability of successful performance; vague plan; significant misalignment with scope; failure to address critical risks. If pricing is
vi. Score of 0 – Does not meet requirements. Proposal may be considered unresponsive and not eligible for award consideration based on this criterion (e.g., missing required sections, failure to submit required forms, excessive or unacceptable exceptions).
d. Weighted Scoring Calculation. Each technical criterion is assigned a weighting factor expressed as a percentage of the total available points.
For each criterion, the raw score (0–5) assigned by evaluators will be multiplied by the applicable weighting factor to produce the criterion’s weighted score. The sum of all weighted scores will constitute the Bidder’s total technical score used to determine ranking and competitive range.
Score Formula: Raw Score (0–5) × Criterion Weight = Weighted Score
e. Evaluator Criteria. Energy Northwest will evaluate proposals using the weighted criteria listed below. Bidders are responsible for providing comprehensive, detailed responses for each criterion to ensure accurate scoring and full consideration.
Evaluation Criteria Weighted Average%
General Qualifications 10%
Commercial Qualifications 10%
Technical Qualifications 45%
Price 35%
3. Based on the proposals submitted and evaluated, Energy Northwest may elect to perform Bidder interviews. All Bidders which have submitted a proposal that are deemed to be responsible will be provided with an opportunity for an interview.
Interviews may be held remotely, or in person at the sole discretion of Energy Northwest. Bidders will receive more information regarding how to prepare for the interview if selected to participate.
4. After completion of the interviews, Energy Northwest may either choose the Bidder deemed to be qualified, responsive, responsible, and most advantageous to perform the required Work or Energy Northwest may provide an opportunity for Bidders to submit a Best and Final Office (BAFO).
5. After the submittal of a BAFO, if requested, there will be no further opportunity for clarification, refinement, and/or discussions. Energy Northwest will review and evaluate the BAFOs. Energy Northwest will select the Bidder whose proposal is in the best interest of and most advantageous for Energy Northwest if any.
6. Bidder shall thoroughly examine and be familiar with the BAFO documents. Submittal of a BAFO shall constitute an acknowledgement upon which Energy Northwest may rely that the Bidder has thoroughly examined and is familiar with these documents. Failure or neglect to receive or examine these documents shall in no way relieve Bidder from any obligation with respect to the proposal or these documents. No claim for additional compensation will be allowed, which is based on lack of knowledge of the BAFO documents.
7. Energy Northwest reserves the right, without qualification, to select any BAFO as a basis for negotiation, to reject all BAFO’s and to exercise its discretion and apply its judgment with respect to any BAFO submitted. This BAFO does not commit Energy
Northwest to pay any costs incurred in connection with any BAFO, or to contract for any Work. There is no commitment on the part of Energy Northwest to accept the lowest priced BAFO or any conditions imposed by a contractor as a requirement of acceptance of their BAFO. The BAFO to be accepted shall be at the sole discretion of Energy Northwest.
8. Information submitted to Energy Northwest in response to this BAFO becomes public record under the Revised Code of Washington. Without exception by the presenting Party, the information is subject to public disclosure pursuant to the Washington State Public Records Act. Energy Northwest may unilaterally release or exempt information from public disclosure. In the event a proposer seeks to withhold information from public disclosure, it shall hold Energy Northwest harmless from any damages or costs, including attorney’s fees and statutory awards imposed by any court or regulatory authority. Energy Northwest shall not be liable for any inadvertent public disclosure of information, despite the exercise of reasonable care.
C. WRITTEN BID PROTEST PROCEDURES
A. Purpose: These protest procedures are included in this RFP to provide a prompt, fair and equitable administrative remedy to all Bidders regarding alleged substantive errors or omissions in the RFP or regarding any decision by Energy Northwest to award the Contract, to declare a Bid non-responsive, or to find a Bidder not responsible.
B. Form of Protest: In order to be considered, a protest shall be in writing and shall include: (1) the name, street address, telephone, fax number and email address of the aggrieved party and/or their authorized representative; (2) the RFP title and number under which the protest is submitted; (3) the economic interest of the aggrieved party in the Contract to be awarded under the RFP; (4) a detailed description of the specific grounds for the protest and any supporting documents;, (5) the specific ruling or relief requested; and (6) evidence that all persons with a financial interest in the procurement have been given notice of the protest or if such persons are unknown, a written statement to that effect. In the event the protesting party asserts the responsibility of any other Bidder as a ground for protest, it must address in detail the specific responsibility criteria identified in the particular RFP and, absent such specific responsibility criteria, the matters addressed in chapters 39.04 and
39.06 RCW pertaining to Bidder and/or Subcontractor responsibility. The transmittal envelope must clearly identify the RFP number on its face and be labeled as a “Bid Protest.” No protest will be considered by Energy Northwest if all Bids are rejected or if the protest is received after award of the Contract as contemplated by this RFP.
The protest shall be provided to Energy Northwest, General Counsel at Kootenai Building, MD 1020, 76 North Power Plant Loop, Richland, Washington 99354;
Attention: Esther Andrews; 509.377.6020.
C. Timing:
1. Prior to Bid Opening or Due Date: Protests based on the specifications or other terms in the RFP Documents which are apparent on the face of said documents must be received by Energy Northwest no later than 10 calendar days prior to the date established for submittal of Bids. Protests based on other circumstances must be received by Energy Northwest within five calendar days after the protesting Bidder knows or should have known of the facts and circumstances upon which the protest is based. In no event shall a protest be considered if all Bids are rejected or after award of the Contract.
2. After Bid Opening and Prior to Award: Within two full business days (the equivalent of 16 business hours) after the advertised date and time of Bid opening, as amended (Saturday, Sunday, and legal holidays excluded), any party planning to protest must file a written notice of such intention with the Energy Northwest General Counsel. If no notice is received by the Energy Northwest General Counsel within the two business days, all eligible protestors will be considered to have waived their right to protest. Notice of intention must stipulate (1) name, address, and phone number of the aggrieved party; (2) the RFP number and title under which the protest is submitted; and (3) the intended grounds for the protest.
The complete protest, prepared according to the criteria set forth herein (and consistent with the criteria set forth in subsection I.16.B above), must be received by the Energy Northwest General Counsel within two business days (16 business hours) after the date and time of receipt of the notice of protest.
After the two business days have passed from Bid opening date/time, Energy
Northwest will proceed as follows:
If a notice of intent to protest was filed with the Energy Northwest General Counsel during the two business days following Bid opening, the Energy Northwest General Counsel’s may make the following determination:
a. Suspend the award decision to allow consideration of the protest before award is made; or
b. Declare intent to award and wait a minimum of two business days (sixteen business hours as defined above) before entering into a contract. Written notice of intent to execute a contract shall be met by either one of the following methods: (1) public posting by Energy Northwest with a named intent to award indicated on the posted tabulation, made public or accessible to the public by telephone and/or posting on the Energy Northwest internet location designated for Bid results; or (2) an Energy Northwest memorandum request to authorize award to the apparent successful Bidder. The first memorandum request submitted either to the Energy Northwest Executive Board (if applicable) or official or employee with delegated approval authority shall be considered notice of intention to award.
After Bid opening, only Bidders that submitted a Bid, subcontractors, or others that can show a substantial economic interest in the Bid award and who are aggrieved, are eligible to protest. After Bid opening, protests are limited to issues related to Bid opening, evaluation of the Bids, and intention to award decisions, and are further limited to those items that were not known or could not have been reasonably known prior to Bid opening. Such issues that were known or should have reasonably been known must have been protested prior to Bid opening and are no longer eligible as an issue of protest.
Only protests stipulating an issue of fact concerning the following subjects shall be considered:
▪ A matter of bias, discrimination or conflict of interest on the part of the evaluator;
▪ Errors in computing the score or Bid Price upon which award decisions are based; or
▪ Non-compliance with procedures described in the solicitation for the opening and award itself.
D. Review by Energy Northwest:
1. Energy Northwest shall promptly consider the protest based on the written submittal. In its sole discretion, Energy Northwest may give notice of the protest to other interested parties, including other Bidders. Energy Northwest reserves the right to resolve or to attempt to resolve any protest that concerns the form or content of the solicitation and which protest was received before the Bid due date or Bid opening through written addenda to the Bid documents.
2. Energy Northwest may, in its sole discretion, elect to hold a hearing regarding the protest. A hearing will not, however, generally be held unless Energy Northwest believes it would be helpful to the resolution of the Protest. At the hearing, the aggrieved party will be given a reasonable opportunity to present relevant evidence and to make legal arguments. Other interested parties may also be given the opportunity to do so. The hearing will generally be recorded, and Energy Northwest will maintain an official record of all documentary evidence presented at the hearing. Energy Northwest will issue a written final decision on any submitted Protest. In making its decision, Energy Northwest may consult with others and consider information relating to the protest from any source, including other interested parties. A copy of the final decision will be provided to the aggrieved party, and any other party as may be required, by either: (i) personal service; (ii) facsimile; or, (iii) email, with telephonic confirmation.
3. The determination by Energy Northwest will either:
a. Find the protest lacking in merit and uphold Energy Northwest’s action; or
b. Find only minor technical or harmless errors in Energy Northwest’s acquisition process and determine Energy Northwest to be in substantial compliance and therefore reject the protest; or
c. Find merit in the protest and pursue correction including correcting the errors and reevaluating the Bids, and/or reissuing the solicitation to begin a new process; or
d. Make other findings and determine other courses of action, as appropriate.
E. Stay of Award of the Contract: Energy Northwest will stay award of the Contract for two business days following the issuance of its final decision. The term “business day” shall mean any day on which Energy Northwest is open for regularly conducted business.
F. Appeal: Any appeal must be filed within two business days of the determination being delivered by the Energy Northwest General Counsel to the aggrieved party. An appeal must be in writing and submitted to the Energy Northwest General Counsel.
The written statement of appeal must provide a substantial basis for an appeal, based on the information submitted as part of the original protest. New information or basis of protest will not be considered during the appeal process. This shall be the final appeal provided to the protestor. The protest shall be considered by the Energy Northwest General Counsel who shall consider all facts and issues and shall issue a final decision on behalf of Energy Northwest. If the aggrieved party appeals the decision, then the subsequent determination by the Energy Northwest General Counsel shall be final and conclusive. The notice shall be provided to Energy Northwest General Counsel at Kootenai Building, MD 1020, 76 North Power Plant Loop, Richland, Washington 99354; Attention: Esther Andrews, Senior Vice President/Chief Compliance Officer; 509.377.6020.
G. Strict Compliance: Strict compliance with these protest procedures is essential in furtherance of the public interest. Any aggrieved party that fails to comply strictly with these protest procedures is deemed, by such failure, to have waived and relinquished forever any right or claim with respect to alleged irregularities in connection with the solicitation or award of the Contract.
RFP SECTION II
PROPOSAL SUBMISSION FORMAT AND CONTENT
In order to facilitate evaluation of Bidders proposal, Energy Northwest requires that Bidder responses be formatted to the following outline. Failure to comply with this format and omission of the requested content may be cause for Bidders proposal rejection without consideration.
A. MANDATORY QUALIFICATIONS
1. The following are mandatory requirements and will be evaluated on a pass/rejection basis. Failure to meet any mandatory requirement will result in automatic rejection of proposal.
a. Bidder must attend the mandatory Bid walk.
b. Bidder has completed and signed the signed Cost Proposal Form.
c. Pursuant to chapter 5.50 RCW verifying under penalty of perjury, the Bidder shall complete, sign and submit the Exhibit “B” - Certification of Compliance with Wage Payment Statutes with the RFP Documents.
B. COMMERCIAL QUALIFICATIONS
All items will be evaluated on a yes/no basis. Consistent with scoring methodology, a “yes” response will receive three points and a “no” response will receive one point.
1. Pursuant to RCW 39.04.350, Bidder must meet the following Bidder responsibility criteria to be considered a responsible Bidder. Bidder shall:
a. Declare on the Cost Proposal Form, Bidder’s current certificate of registration number as a contractor in compliance with RCW 39.04.350 (RCW 18.27 general contractor, RCW 18.106 plumbing, RCW 70.87 elevator), which must be in effect at the time of RFP due date.
b. Declare on the Cost Proposal Form, Bidder’s current Washington Unified
Business Identifier number.
c. Declare on the Cost Proposal Form, the Bidder has Industrial Insurance
(workers’ compensation) coverage for the Bidder’s employees working in Washington State, as required in Title 51 RCW.
d. Declare on the Cost Proposal Form, the Bidder has a Washington Employment Security Department number, as required in Title 50 RCW.
e. Declare on the Cost Proposal Form, the Bidder has a Washington
Department of Revenue state excise tax registration number, as required in Title 82 RCW.
f. Declare on the Cost Proposal Form, has Bidder been disqualified from performing Work on any state or federal contracts as detailed in RCW §39.12.065 (3).
g. Declare on the Cost Proposal Form, Bidder has received Prevailing Wage and Public Works training or is exempt. Use the web address below to learn more about Contractor Training.
h. Declare on the Cost Proposal Form, Bidder has not been found out of compliance with apprenticeship utilization requirements.
3. Pursuant to RCW §39.04.350 (2), responsive and qualified Bidder shall provide the following supplemental Bidder’s data for proposal evaluation. Bidder shall:
a. Declare on the Cost Proposal Form, the Bidder has thoroughly reviewed the specifications, laws and ordinances governing the Work contemplated.
b. Declare on the Cost Proposal Form that the Bidder shall complete the Work within the work window of 28 days. Work not completed by work window shall be subject to the Liquidated Damages provision in Appendix “B” of the Contract Document.
c. Declare on the Cost Proposal Form that Bidder has reviewed and acknowledges the Liquidated Damages provision in Appendix “B” of the Contract Document.
d. Declare on the Cost Proposal Form, Bidder has performed similar Work for a nuclear power generating facility.
e. Declare on the Bid Form, Bidder has thoroughly reviewed the requirements of the Inflation Reduction Act.
f. Declare on the Bid Form, does Bidder have a record of Nuclear Regulatory
Commission (NRC) violations.
1. If the Bidder does have violations, Bidder shall submit on a separate document these violations. This document shall include but not limited to.
i. Dates,
ii. Descriptions,
iii. Corrective actions,
iv. Status.
2. In the case of Bidder having NRC violations, failure to provide this document may result in the bid being deemed non‑responsive.
g. Bidder has submitted a completed 2026 W-9 form?
h. Declare on the Cost Proposal Form if Bidder has submitted exceptions to Energy Northwest’s Appendix “D” – General Provisions. Energy Northwest will not engage in a lengthy negotiation of the General Provisions.
Extensive or material exceptions will result in Bidder’s proposal being declared non-responsive. Exceptions thereto must be clearly defined in “track changes” in the MS WORD documents (Appendix “D”) supplied by Energy Northwest. Any exception taken must have a comment in the document describing why the exception is being submitted.
i. Declare on the Bid Form, Bidder has previously negotiated terms with
Energy Northwest in which they intend to utilize in the course of this Work.
If previously negotiated terms are already in place, mark “No” on the Bid Form for above question and “Yes” on the Bid Form for this question.
C. TECHNICAL QUALIFICATIONS
Evaluators will assign a raw score from 0 to 5 for each technical evaluation criterion.
Scores will reflect the demonstrated quality, completeness, clarity, and responsiveness of Bidder’s proposal to the requirements outlined in RFP Section I.
1. Pursuant to RCW §43.52.565, technical qualifications reflect factors other than price.
a. Equivalent experience: Bidder shall submit a minimum of three recent or current customers (nuclear power generating facilities, or Federal Government projects (Department of Defense, Department of Energy, Corps of Engineers, or other Utilities) where similar Work was performed. Include the following:
i. Customer name
ii. City and State
iii. Contact person(s)
iv. Phone number and email address
v. Date work was performed
b. Key Personnel: Provide the names and resumes of the actual supervisors that will be assigned to this Work. The Energy Northwest team wants commitment and predictability from the Bidder that the listed supervisors will be onsite to direct the Work.
c. Rate Sheet: Provide a rate sheet for (to be attached separately as an Excel document) to support the Work, the labor rates shall include but are not limited to:
1. Supervisor(s),
2. Laborers,
3. Teamsters,
4. Electricians
5. Cement Masons,
6. Iron Workers,
7. Carpenters,
8. Contractor shall include the labor rates for any other craft or supervision needed to support the Work, and
9. Labor sheet shall include overtime and double time rates if applicable.
d. Means and Methods: Provide a preliminary approach and schedule for the maintenance work described in this RFP. Outline may include: planning and preparation, work order reviews, work order walkdowns, mobilization, in-processing, implementation, performance, contingency, completion, reporting and exit.
e. Occupational Safety & Health Administration (OSHA) Statistical Report:
Bidder shall submit the completed OSHA safety statistics report, Exhibit “A”, showing Bidder safety performance for the past five years. This report should only include statistics for the business division of Bidder’s company that will be performing Work at Columbia. If the Bidders’ company is not required to report to OSHSA per OSHA standards 1904.1(a) (1), the Bidder shall identify this on Exhibit “A”, failure to properly identify this on Exhibit “A” could deem the Bidder as unresponsive.
Note: If Bidder’s Experience Modification Rate (EMR) or Total Recordable Incident Rate (TRIR) rating exceeds 1, their Bid may be removed from consideration upon further evaluation by Energy Northwest’s Industrial Safety department. This evaluation will review the data and weigh it against other criteria (experience, previous successful work performed, number of workers/hours worked, etc.).
f. Project Schedule: Bidder shall submit a Level 1 project schedule. Schedule shall detail activities to be performed by the Contractor containing mobilization, training, walk downs, field implementation, and demobilization.
g. Proposed Subcontractors: Proposer shall complete and submit the Proposed Subcontractor form, Exhibit “C”, indicating the Subcontractors who may perform any portion of the Work. Subcontractors may be limited to the amount of scope and value and must be registered to work in the State of Washington and meet the same requirements as the Contractor.
Pursuant to RCW §39.30.060, if the Total Proposal Price is $1,000,000 or more, Bidder shall submit as part of the proposal:
i. Within one hour after the published proposal submittal time, the names of the Subcontractors with whom the Bidder, if awarded the contract, will subcontract for performance of the Work of: HVAC (heating, ventilation, and air conditioning); plumbing as described in chapter 18.106 RCW; and electrical as described in chapter 19.28 RCW, or to name itself for the Work; or
ii. Within 48 hours after the published proposal submittal time, the names of the Subcontractors with whom the Bidder, if awarded the contract, will subcontract for the performance of the Work of structural steel installation and rebar installation.
iii. Failure to provide those listings or list multiple subcontractors in the same category, unless tied to specified bid alternates, will render the bid nonresponsive and void.
h. Declare on the Bid Form, Bidder has submitted a sample Site-Specific Safety and Health Plan (SSSHP).
i. At a minimum, the SSSHP shall address the following items:
• Safety roles, responsibilities and expectations for employees and Subcontractors.
• Safety orientation process. How will the Bidder train their personnel to Energy Northwest standards and expectations?
• Proactive steps to prevent injuries (including walkdowns, observations, using Human Performance (HU) tools such as Take 2, Job Hazard Analysis/Job Safety Analysis).
• Safety event and near miss reporting and documentation (follow ISPM-1, document on Contractor’s forms, complete Condition Reports).
• Process for pre-job briefs, Take 2 and HU tools to be used.
• Process for safety inspections and supervisor and peer safety observations and coaching.
• Process for implementation of industrial safety operating experience and lessons learned.
• Process for working on or near asbestos, lead, Polychlorinated Biphenyls (PCB), silica and other health hazards.
• Critical work processes requiring Lock Out Tag Out, fall protection, confined space, hot work and high hazard lifts (and other Industrial Safety high risk activities).
D. TOTAL PROPOSAL PRICE
1. Prevailing wage requirements:
a. Labor provided for Work at Columbia is subject to Washington State prevailing wage requirements. Prevailing wage rates can be found on the LNI website at the following address:
https://lni.wa.gov/licensing-permits/public-works-projects/prevailing-wage-rates/
b. It shall be the sole legal and contractual obligation of the Bidder to determine the correct labor categories and wage rates when preparing its proposal for this Work as of the effective date of March 1, 2026, and if necessary, contact Labor & Industries’ (L&I) Industrial Statistician for information.
Labor provided under any Contract awarded hereunder is subject to Washington State prevailing wage rates. The Bidder awarded this Work must file an intent to pay and affidavit of wages paid as required by RCW §39.12.040 and Washington Administrative Code (WAC) §296-127-026. Pursuant to L&I Law Booklet, sole proprietors must file the intent and affidavit. There is no exemption from the requirement to file the forms. Prevailing wage rates can be found on the Washington State Department of L&I website at the following address.
Note: False filings of forms may result in penalties and sanctions under RCW §39.12.050. Failure to pay appropriate wages may result in penalties and sanctions under RCW §39.12.065. Energy Northwest will not be liable for any resulting difference in prevailing wages paid by the Contractor or Subcontractors.
c. Pursuant to chapter 39.12 RCW, Contractor shall submit certified payroll reports at least once a month to L&I using the L&I online system.
E. PERFORMANCE AND PAYMENT BOND
1. Pursuant to RCW §39.08.30, Contractor shall provide the performance and payment bond on Energy Northwest Form No. 715, provided by Energy Northwest, prior to starting any public work. To ensure compliance with the terms of the Contract Documents, the Contractor shall furnish a performance and payment bond in an amount equal to 100% of the total Contract Sum, excluding Washington State sales tax.
2. Cost of the performance and payment bond shall be invoiced separately and include supporting documentation. No markup of the cost of the performance and payment bond is authorized.
3. The release of the bond is initiated once the Work is completed.
https://lni.wa.gov/licensing-permits/public-works-projects/prevailing-wage-rates/
F. GENERAL PRESIDENTS' PROJECT MAINTENANCE AGREEMENT
General Presidents' Project Maintenance Agreement (GPPMA) is used at Columbia for Energy Northwest personnel. Bidder shall maintain labor harmony with local trade unions.
RFP SECTION III
STATEMENT OF WORK
A.1 INTRODUCTION
A. Energy Northwest, a joint operating agency and municipal corporation, operates Columbia Generating Station (Columbia), a nuclear power generating facility with a boiling water reactor.
B. Contractor shall install 500 kV bus supports to resolve a design deficiency, which resulted in support structure failures. These bus supports need excavations, grounding and foundation pours in four locations.
A.2 SCOPE OF WORK
A. The Scope of Work is intended to give an overview of the Work and is not inclusive of all the Work necessary to complete the project. Specific information is available during the Examination of Site, in the drawings and other documentation available from the Technical Representative or designee.
B. The Site location is 76 North Power Plant Loop, Richland, WA 99354, a nuclear power plant location. The Work shall be performed inside the Protected Area of Columbia.
Note: Contractor shall use the above address when determining the appropriate tax rate in accordance with Section B.10.
C. Work includes but is not limited to the following:
1. Excavate, form and pour the foundations for four new 500kV Bus Supports.
2. The installation of anchors, rebar, and tie ins to existing Deluge piping foundations will need to be performed.
3. Exothermic welding of grounds shall be performed. Grounds shall be welded from the ground grid and stubbed up by the new concrete pedestals.
4. Grounds in the new excavations shall need to be extended in some cases so that they will not be in the new foundations.
5. While excavating, it may uncover some direct burial cable for 120VAC lighting circuits.
6. Excavations shall need to be performed using a vacuum truck.
7. See the Attachments for further details.
D. Work hours may be increased based upon Columbia needs. Any changes to the hours or schedule will be agreed upon by both parties.
A.3 SCHEDULE OF WORK
The actual dates are subject to change based on the Columbia operational schedules.
Technical Representative or designee will coordinate actual start dates with the Contractor.
A.4 REFERENCES AND ATTACHMENTS
Contractor shall review all Attachments included with the RFP. Upon Contract award additional electronic drawings can be requested from the Technical Representative or designee. For access to these files please email jahagfeldt@energy-northwest.com.
A.5 ENERGY NORTHWEST’S RESPONSIBILITIES
A. Provide project layout, Site coordination and work schedule.
B. Provide Technical Representative or designee to coordinate work activities.
C. Provide temporary power as needed.
D. Provide the rock/ballast and soil as needed to cover the new foundations
E. Provide the decision regarding Contractor mobilization based on current Energy
Northwest maintenance schedules. Energy Northwest will notify the Contractor in a timely manner of delays or schedule changes.
F. Provide drawings, and other information as necessary to complete the Work.
A.6 CONTRACTOR’S RESPONSIBILITIES
A. Provide a single point of contact for the duration of the Work.
B. Assist the Technical Representative or designee in the development of the final implementation schedule.
C. Mobilize equipment and personnel required for the Work in a well-organized manner.
Ensuring the Work is successful in regard to quality workmanship, cost efficiency and schedule adherence.
D. Follow all safety rules, including wearing required personal protective equipment as defined by Energy Northwest, or the Contractor’s safety program, whichever is more stringent.
E. Provide reports requested by Energy Northwest for inspections and/or Work performed may include but are not limited to, detailed descriptions, photos, videos and sketches for the Technical Representative’s or designee’s review and approval.
F. Report of findings that include drawings, pictures, videos, or other documented resources.
mailto:jahagfeldt@energy-northwest.com
G. Demobilize personnel and equipment following successful acceptance of the Work by the Technical Representative or designee.
A.7 CONTRACTOR’ PERFORMANCE EXPECTATIONS
A. Perform the Work within budget.
B. Perform the Work on schedule.
C. Provide a weekly Work activity report.
D. Perform the Work with no rework.
E. Perform the Work with no injuries.
F. Cleanup work area daily.
A.8 CONTRACTOR’S DELIVERABLES
A. Contractor shall complete the work in accordance with the Contract document.
B. Contractor shall provide a complete construction schedule to the Technical Representative or designee.
C. Prior to the first payment the Contractor shall provide the required prevailing wage intent and performance and payment bond to Melinda Soto at mjsoto@energy-northwest.com.
D. Prior to Final Payment Contractor shall submit the prevailing wage affidavit to the Melinda Soto at mjsoto@energy-northwest.com. This document shall verify compliance with Washington State labor laws and ensure that all wages paid under the Contract reflect the prevailing wage standards applicable to the scope of work.
A.9 QUALITY ASSURANCE
A. Contractor shall be familiar with all features of the job site that may affect the execution of the Work. It is the expectation of Energy Northwest that all Contractors perform at or exceed industry standards and uphold all the safety standards.
B. All activities performed by the Contractor on Energy Northwest property shall be subject to the Quality Assurance (QA) requirements of Energy Northwest.
C. Hold points and inspection points noted in work orders are times in the Work process that Work must stop until and inspection is complete and the inspector has approved the Work. If the inspector approves the Work, the Work can continue. If the inspector does not approve the Work, the Work will need to be stopped and repaired.
D. Contractor is responsible for all costs associated with delays not specifically allowed in this document and costs to remediate a condition not caused by Energy Northwest.
Examples include: time necessary to obtain chemical permits for chemicals not mailto:mjsoto@energy-northwest.com mailto:mjsoto@energy-northwest.com previously identified by the Contractor, material procurement, and delays and costs associated with hazardous waste spills such as hydraulic fluid to the ground.
RFP SECTION IV
COST PROPOSAL FORM
(Do not modify the form)
NOTE: ALL SECTIONS MUST BE FILLED IN.
NAME OF BIDDER:
(Full Legal Company Name)
Mandatory Qualifications YES NO
Bidder has attended the mandatory Bid walk?
Bidder has completed and signed the Cost Proposal Form?
Bidder has submitted the completed and signed Exhibit “B” - Certification of Compliance with Wage Payment Statutes?
Commercial Qualifications (Responsible) YES NO
Current certificate of registration number as a contractor:
Washington State Unified Business Identifier (UBI) number:
Bidder has Industrial Insurance (workers’ compensation) coverage for the Bidder’s employees working in Washington?
Washington Employment Security Department number:
Revenue state excise tax registration number:
Bidder has not been disqualified from performing work on any state or federal contract?
Bidder has completed the required Contractor Training or is exempt?
Bidder has reviewed and acknowledged the Washington State Apprentice Utilization
Requirement language and has not been found out of compliance?
Commercial Qualifications (Responsive & Qualified) YES NO
Bidder has thoroughly reviewed the specifications, laws and ordinances governing the
Work contemplated?
Bidder can perform the Work within the required work window?
Bidder has thoroughly reviewed the Liquidated Damages provision in Appendix “B”?
Bidder has performed similar Work for a nuclear power generating facility?
Bidder has thoroughly reviewed and acknowledges the IRA language?
Bidder has any NRC violations? If yes, please provide a list on a separate document.
Bidder has submitted a completed 2026 W-9 form (Taxpayer Identification Number and
Certification)?
Bidder submitted exceptions to General Provisions in Appendix “D?
Bidder has previously negotiated terms with Energy Northwest in which they intend to utilize in the course of this Work?
Technical Qualifications YES NO
Bidder has submitted equivalent experience?
Bidder has submitted their Key Personnel?
Bidder has submitted a rate sheet?
Bidder has submitted their Means and Methods for the Work?
Bidder has submitted a completed OSHA statistical report Exhibit “A”?
Bidder has provided a level 1 project schedule?
Bidder has submitted their proposed subcontractors Exhibit “C”?
Bidder has submitted their SSSHP?
Additional Information Declare
Number of Addendums received and have been considered in preparing this Bid.
The Price above shall be interpreted as the Contract Price upon Contract Award. Payment shall be made in accordance with the schedule of values rates submitted by the Bidder.
BIDDER NAME:
STREET ADDRESS:
CITY, STATE & ZIP CODE:
PHONE NO.:
EMAIL ADDRESS:
BY:
(Type or Print Name)
TITLE:
SIGNED:
DATE:
Bidder affirms that by signing this Proposal Cost Form, Bidder clearly understands the Scope of Work as described in the RFP documents and any published addendums. Bidder has the required resources to complete the Work in the designated duration. Bidder affirms that by signing this Bid Form they have the authority as an authorized signer for their company.
Note: Failure to sign the Proposal Form above shall result in rejection of the RFP.
Description Total Proposal Price
Installation of 500 KV bus supports
(Price does not include sales tax)
RFP SECTION V
SAMPLE CONTRACT
ENERGY NORTHWEST
76 North Power Plant Loop Richland, WA 99354 Phone: 509.372.5000 and
Company Address Phone hereinafter referred to as “Contractor”, hereby agree as follows:
1. INTRODUCTION
Inserted from the RFP.
2. PERIOD OF PERFORMANCE
Period of performance is to begin on the Contract signing date and continue to or until terminated in accordance with Appendix “D”.
3. INCORPORATED DOCUMENTS
• Appendix “A” - Statement of Work
• Appendix “B” - Special Provisions
• Appendix “C” - Schedule of Payments
• Appendix “D” - General Provisions
• Attachments & Exhibits
• RFP No. 717526 and Addendum(s)
Attachments, drawings, papers or specifications annexed or referred to herein shall be deemed as part of this Contract.
4. CONSIDERATION
A. Compensation for Work performed shall be per the price set forth in Appendix “B” of the Contract. Energy Northwest shall authorize the Contractor to perform specific tasks by means of a Contract.
B. Energy Northwest makes no guarantee as to any actual or minimum amount of Work to be done. Energy Northwest reserves the right to suspend or terminate any authorized Contract in accordance with Appendix “D” of the Contract or to extend the Contract beyond the initial term by issuance of an Amendment in accordance with Appendix “D” of the Contract to complete any Work already initiated and/or authorized under the original term and scope of the Contract.
5. NOTICES
Any notice or other communication under this Contract given by either Party shall be sent via email to the email address listed below, or mailed, properly addressed and stamped with the required postage, to the intended recipient at the address and to the attention of the person specified below and shall be deemed served when received and not mailed.
Either Party may from time to time change such address by giving the other Party notice of such change.
Technical Representative Contractor Name: Name:
Phone: Phone:
Email: Email:
For commercial questions please contact Robert Mendez, at 509.372.5380 or email rdmendez@energy-northwest.com.
Contractor shall submit an emergency contact in which this person is available 24/7 in the case of a true emergency (no “trunk line” phone numbers, only direct contact information).
Energy Northwest shall use the following provided emergency contact information solely for the purpose of facilitating immediate communication in the event of an emergency related to Contractor’s personnel during the performance of this Contract.
Contractor Emergency…
This is the start of the file's text. The full file is on GovTribe.