RFP 601 Administrative Document - Amended 1.docx

DOCX document 104 KB Posted

Attached to
Property Damage Claims Management
Solicitation number
601
Issued by
Idaho

About this file

This is an amended Request for Proposal (RFP) issued by the State of Idaho Division of Purchasing on behalf of the Idaho Transportation Department (ITD) for Property Damage Assessment and Recovery Event 601. The RFP seeks proposals for a vendor to manage property damage claims on ITD's behalf, responding through insurance channels to recover compensation for damages to state property including interstates, state highways, signs, guardrails, lighting, signals, roadways, bridges, drainage structures, noise walls, retaining walls, fencing, and camera systems. The pre-proposal conference was held on June 18, 2025, from 9:00 a.m. to 10:00 a.m. Mountain Time, with the deadline to submit written questions set for June 25, 2025, at 11:59:59 p.m. Mountain Time. The RFP closing date is noted in the IPRO header document, with public opening the following business day. The contract term is one year initially, with an anticipated total contract term of five years upon mutual written agreement for renewals, extensions, or amendments. The evaluation will be conducted by technical proposal committees, with top scoring offerors potentially invited to oral presentations via Microsoft Teams.

The cost proposal evaluation is based on an administrative percentage rate per claim, with the lowest rate receiving all 200 available cost points. The maximum dollar fee per claim may not exceed $10,000. Offerors must provide a fully burdened administrative percentage rate including all operating and personnel expenses, overhead, salaries, administrative expenses, travel, and profit. Historical pilot program data from calendar years 2022-2023 indicates ITD processed 1,036 total claims with 794 claims recovered, recovering approximately $4.2 million of $6.2 million in total claims. Offerors must meet mandatory minimum requirements including three years of experience providing similar services to other state Departments of Transportation, current licensure as Idaho insurance adjusters for staff working directly with insurance companies, and provision of SOC 2 audit reports for data centers located in the continental United States. No set-asides are identified in this procurement. Proposals will be evaluated on a 1,200-point scale comprising mandatory submission requirements, business information (150 points), organization and staffing (250 points), scope of work (400 points), oral presentations (200 points), and cost proposal (200 points).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF IDAHO

DIVISION OF PURCHASING

FOR THE

IDAHO TRANSPORTATION DEPARTMENT

REQUEST FOR PROPOSAL

PROPERTY DAMAGE ASSESSMENT AND RECOVERY

EVENT 601

Amended 1 – 7/15/2025

TABLE OF CONTENTS

RFP ADMINISTRATIVE INFORMATION1
1 OVERVIEW2
2QUESTIONS3
3INSTRUCTIONS FOR SUBMISSION OF PROPOSAL5
4.PROPOSAL FORMAT7
5.PROPOSAL REVIEW, EVALUATION, AND AWARD8
6.MANDATORY SUBMISSION REQUIREMENTS11
7.BUSINESS INFORMATION12
8.ORGANIZATION AND STAFFING13
9.SCOPE OF WORK15
ATTACHMENT 1 – PRE-PROPOSAL CONFERENCE REGISTRATION FORM21
ATTACHMENT 2 – OFFEROR QUESTIONS22
ATTACHMENT 3 – MODIFICATION AND EXCEPTION FORM24
ATTACHMENT 4 – COVER FORM25
ATTACHMENT 5 – COST PROPOSAL27
APPENDIX A – IDAHO TERMS AND CONDITIONS BACKGROUND AND LIMITATIONS28

RFP ADMINISTRATIVE INFORMATION

RFP Title:

Property Damage Assessment and Recovery

RFP Project Description:

The Division of Purchasing (DOP) is seeking proposals on behalf of the Idaho Transportation Department (ITD), to identify and investigate on State property damages.

RFP Lead:

Kevin Jarrett, Buyer Email: Kevin.Jarrett@adm.idaho.gov Phone: 208-332-1615

Submitting electronically via IPRO:
Electronic Submission:

IPRO IOGIN

Pre-Proposal Conference Date/Time:

Wednesday, June 18th from 9:00 a.m. to 10:00 a.m. Mountain Time

Deadline to Receive Questions:

Wednesday, June 25th at 11:59:59 p.m. Mountain Time

RFP Closing Date:

See IPRO Header Document

Public Opening Date:

The following business day after closing

Initial Term of Contract and Renewals:

The Contract term shall be one (1) year. Upon mutual, written agreement, the Contract may be renewed, extended or amended. The anticipated total Contract term is five (5) years.

EVENT 601 PROPERTY DAMAGE CLAIM MANAGEMENT
2

1 OVERVIEW

1.1. Purpose

The Idaho Division of Purchasing (DOP), on behalf of the Idaho Transportation Department (ITD), is seeking a vendor to respond on ITD’s behalf, through insurance channels ITD’s claim of property damage by third party negligence. In doing so, privileged information should be exchanged in order to process an insurance claim or claim against damager and recover compensation for all property damage which includes Labor and Materials by means of insurance or private party. State Property includes all Idaho Interstates and State Highways. The damage recovery process will have an initial claim and includes the start to end processing of all damage claims as assigned by ITD. Recovery should include but not limited to the following in State Right Of Way or property owned and operated by Idaho Transportation Department, highway signs, guardrail, street lighting, street signals, public roadway, bridges, drainage structures, noise walls, retaining walls, fencing and highway camera systems.

1.2. Background Information

ITD ran a pilot program as a concessions contract, historical claims information below:

Calendar Year (CY) 2022 Total Claims – 560 Total Claims Recovered – 473 Total Claim Amount - $3,924,456 Total Claim Amount Recovered to date – $2,955,808

CY – 2023 to date Total Claims – 476 Total Claims Recovered – 321 Total Clam Amount - $2,291,621 Total Claim Amount Recovered to Date - $1,281,391

1.3. Resulting Contract

If the State awards a contract from this Solicitation, it will do so by issuing a Contract document from the State’s eProcurement system, IPRO POWERED BY LUMA, which will be an acceptance of the successful offer. The Contract will be comprised of that contract document; this RFP, including any incorporated documents; the successful Proposal, including any clarifications requested by the state of Idaho (State); and an artifact formalizing any requirements agreed upon through contract discussions or negotiations, if applicable.

The following documents are incorporated into this RFP as if set out in their entirety, whether or not they are attached in IPRO POWERED BY LUMA:

· Solicitation Instructions for Vendor

· Standard Contract Terms and Conditions

If not attached in IPRO POWERED BY LUMA, the documents may be found on the “Information for Vendors” page of DOP’s website, www.purchasing.idaho.gov. If multiple versions of any of these documents are available on the website, the version in effect on the day the RFP was issued shall apply.

2.

2 QUESTIONS

2.1. Restrictions on Communications

From the issue date of this RFP, until a contract is awarded, or the RFP is cancelled, vendors are prohibited from communications regarding this RFP with the ITD staff, evaluation committee members, or other associated individuals, except the Division of Purchasing.

2.2. Pre-Proposal Conference

A non-mandatory pre-proposal conference will be held at the time indicated in Section 1, page 1 of this RFP. This will be your opportunity to ask questions, over teams, with the ITD staff. All parties interested are invited to participate by attending the conference via Teams. Those choosing to participate must pre-register to receive meeting details by submitting the completed Attachment 1 - Pre-Proposal Conference Registration Form via email to the RFP Lead. Parties interested are asked to register by Tuesday, June 17th at 5:00 p.m. Mountain Time. Any oral answers given by the State during the pre-proposal conference are unofficial and will not be binding on the State.

2.3. Questions

2.3.1. This solicitation is issued via the State’s e-Procurement system, IPRO POWERED BY LUMA. The RFP Lead is the only contact for this Solicitation. All correspondence must be in writing. In the event that it becomes necessary to revise any part of this RFP, amendments will be posted at IPRO. It is the responsibility of parties interested in this RFP to monitor IPRO for any updates or amendments. Any oral interpretations or clarifications of this RFP must not be relied upon. All changes to this RFP will be in writing and must be posted to IPRO to be valid.

2.3.2. Questions or other correspondence must be submitted in writing to the RFP Lead (see contact information in the RFP Administrative Information, page 1). QUESTIONS MUST BE RECEIVED BY 11:59:59 P.M. MOUNTAIN TIME ON THE DATE LISTED IN THE RFP ADMINISTRATIVE INFORMATION.

2.3.3. Written questions must be submitted using Attachment 2 - Offeror Questions. Official answers to all written questions will be posted on IPRO POWERED BY LUMA as an amendment to this RFP, DO NOT SUBMIT QUESTIONS VIA IPRO.

2.4. Vendor Proposed Modifications and Exceptions to Requirements, Terms, and Conditions

2.4.1. Vendors must submit any proposed modifications to the requirements, terms, or conditions of the RFP on Attachment 2 - Offeror Questions prior to the deadline to submit questions. Questions regarding these requirements must contain the following:

· The rationale for the specific requirement being unacceptable to the party submitting the question (define the deficiency).

· Recommended verbiage for the State’s consideration that is consistent in content, context, and form with the State’s requirement that is being questioned.

· Explanation of how the State’s acceptance of the recommended verbiage is fair and equitable to both the State and to the party submitting the question.

2.4.2. In the event that a Proposal contains modifications or exceptions to any Solicitation requirements, terms, or conditions which are not addressed during the question and answer period, they must be identified and submitted on Attachment 3 - Modification and Exception Form and must contain the same information outlined in Section 2.4.1, above. The State will not consider any modifications or exceptions that are not identified specifically on Attachment 3.

2.4.3. The State has sole discretion to determine if the modifications or exceptions submitted by an Offeror would result in a material change or otherwise threaten the integrity of the procurement process. See Appendix A - Idaho Terms and Conditions Background and Limitations. Pursuant to IDAPA 38.05.01.084.e, the State may only negotiate non-material modifications or exceptions. Modifications or exceptions which the State determines to be material, or which otherwise threaten the integrity of the procurement process, will not be accepted or negotiated. In the event that the Offeror has conditioned its Proposal on the State’s acceptance or negotiation of its proposed modifications or exceptions, and the modifications or exceptions are deemed material, the Offeror will be given the opportunity to retract the proposed modifications or exceptions from its Proposal. Failure to do so will result in the Offeror’s Proposal being found non-responsive, after which it will receive no further consideration.

2.4.4. Non-material modifications or exceptions may be discussed with the apparent successful Offeror, at the discretion of the State; however, the State shall have the right to reject any and all such modifications and/or exceptions, or to call an end to such discussions, and to instruct the Offeror to amend its Proposal and remove the modifications and/or exceptions. Failure to do so may result in the State finding the Proposal non-responsive.

2.4.5. Except as otherwise provided within the Solicitation, the State will not consider modifications or exceptions to the requirements, terms, or conditions which are proposed after the RFP Closing Date.

3 INSTRUCTIONS FOR SUBMISSION OF PROPOSAL

3.

3.1. General Instructions

3.1.1. Proposals must be submitted electronically, as detailed below. Except as otherwise addressed in this solicitation, all submission materials must be submitted at the same time. If multiple submissions are received, only the latest timely submission will be considered.

3.1.2. Alternate proposals are not allowed.

3.1.3. All electronic files must be in Microsoft Word or Excel format; the only exception is for financials, brochures, or other information only available in an alternate format.

3.1.4. It is mandatory to submit your Proposal electronically via IPRO POWERED BY LUMA, all Offerors participating in this Solicitation must establish an account in the IPRO system, as it is necessary in order to process and/or award the resulting Contract(s). Establishing an account is free and only takes a few minutes.

3.2. Trade Secrets

Paragraph 28 of the Solicitation Instructions to Vendors describes trade secrets to “include a formula, pattern, compilation, program, computer program, device, method, technique or process that derives economic value, actual or potential, from not being generally known to, and not being readily ascertainable by proper means by other persons and is subject to the efforts that are reasonable under the circumstances to maintain its secrecy.” In addition to marking each page of the document with a trade secret notation (as applicable; and as provided in Paragraph 28 of the Solicitation Instructions to Vendors), Offerors must also:

3.2.1. Identify with particularity the precise text, illustration, or other information contained within each page marked “trade secret” (it is not sufficient to simply mark the entire page). The specific information you deem “trade secret” within each noted page must be highlighted, italicized, identified by asterisks, contained within a text border, or otherwise clearly delineated from other text/information and specifically identified as a “trade secret.”

3.2.2. Provide a separate document entitled “List of Redacted Trade Secret Information” which provides a succinct list of all trade secret information noted in your Proposal; listed in the order it appears in your submittal documents, identified by Page #, Section #/Paragraph #, Title of Section/Paragraph, specific portions of text/illustrations; or in a manner otherwise sufficient to allow the State’s procurement personnel to determine the precise text/material subject to the notation. Additionally, this list must identify with each notation the specific basis for your position that the material be treated as exempt from disclosure and how the exempting the material complies with the Public Records Law.

3.2.3. Submit a redacted copy of the Proposal with all trade secret information removed or blacked out. The redacted copy must be submitted electronically, with the word “redacted” in the file name.

3.3. Electronic Submission

3.3.1. Electronically submitted Proposals must be submitted through IPRO POWERED BY LUMA When submitting through IPRO, enter your Cost in IPRO as “$0.01,” and UPLOAD YOUR TECHNICAL PROPOSAL, SEPARATE COST PROPOSAL, AND ALL OTHER REQUIRED SUBMITTAL ITEMS. Remember to submit an additional redacted version of the proposal if you have identified trade secrets.

3.3.2. Vendors are strongly encouraged to begin the process of submitting the response far enough in advance of the End Time to allow for resolution of technical difficulties. Be advised that the state is not responsible for a Vendor’s failure to timely submit a responsive submission due to any technical or technological difficulties. See IDAPA 38.05.01.61.02.

3.3.3. Submitting via IPRO POWERED BY LUMA, be advised that the Offeror for Proposal evaluation and award purposes is the entity profile under which the Proposal is submitted in IPRO, which must be the same legal entity presented in the uploaded response materials. If the entity identified on the state supplied Signature Page differs from the entity under which you submit your Proposal in IPRO, the information provided on the Signature Page prevails.

3.3.4. Offerors are further advised to upload response materials with descriptive file names, organized and consolidated in a manner which allows evaluators to efficiently navigate the Offeror’s response; as the State will print uploaded documents for evaluation in the manner received via IPRO.

4. PROPOSAL FORMAT

1.

2.

3.

These instructions describe the format to be used when submitting a Proposal. The format is designed to ensure a complete submission of information necessary for an equitable analysis and evaluation of submitted Proposals. There is no intent to limit the content of Proposals.

4.1. Table of Contents

Include a table of contents in the Technical Proposal identifying the contents of each section, including page numbers of major Sections.

4.2. Format

Proposals shall follow the numerical order of this RFP beginning with Section 6 and continuing through the end of the applicable RFP Attachments, including all mandatory submission items detailed in Section 6 and identified throughout the RFP. Proposal sections and subsections must be identified with the corresponding numbers and headings used in this RFP. In your response, restate the RFP section and/or Section, followed with your response.

Offerors are encouraged to use a different color font, bold text, italics, or other indicator to clearly distinguish the RFP section from the Offeror’s response. Except for brochures, financials, work samples, or other similar submission items, all electronic Proposals must be submitted in Microsoft Word or Excel, and must not be locked. Offerors are strongly cautioned against including website links or imbedded documents in the Proposal; the State will not be responsible for the RFP Lead or any evaluator’s failure to consider information outside of or imbedded in the Proposal.

4.3. Evaluation Codes

(M) Mandatory Response - failure to respond to any (M) section, or to comply with any mandatory specification or requirement, will render Offeror’s Proposal non-responsive and no further evaluation will occur.

(ME) Mandatory and Evaluated Response - failure to respond to any (ME) section, or to comply with any mandatory specification or requirement in an (ME) section, will render Offeror’s Proposal non-responsive and no further evaluation will occur. Offeror must respond to these sections as directed; points will be awarded based on predetermined criteria.

(E) Evaluated Response - a response is desired and will be evaluated. If Offeror cannot meet the requirement, or chooses not to respond for any reason, zero (0) points will be awarded for the section. If Offeror responds, points will be awarded based on predetermined criteria.

Note: Offerors are directed to IDAPA 38.05.01.074.03.a, as well as IDAPA 38.05.01.091.05, which allow the designated State official to waive minor informalities as well as minor deviations. The State also reserves the right to seek clarification on any (M), (ME), or (E) requirement.

5. PROPOSAL REVIEW, EVALUATION, AND AWARD

4.

5.1. Overview

The objective of the State in soliciting and evaluating Proposals is to ensure the selection of a firm or individual that will produce the best possible results for the funds expended.

5.1.1. All Proposals will be reviewed first to ensure that they meet the Mandatory Submission Requirements of the RFP as addressed in Sections noted with an (M) or (ME). Any Proposal(s) not meeting the Mandatory Submission Requirements will be found non-responsive.

5.1.2. Evaluation Criteria

Technical Proposal:

Mandatory Submission RequirementsPass/Fail
Business Information150 points
Organization and Staffing250 points
Scope of Work400 points
Presentations200 points
Cost Proposal200 points
TOTAL POINTS1,200 points

5.2. Technical Proposal

5.2.1. The Technical Proposal will be reviewed first on a “pass” or “fail” basis to determine compliance with those requirements listed in the RFP with an (M) or (ME). All Proposals which are determined by the State, in its sole discretion, to be responsive in this regard will continue in the evaluation process outlined in this Section.

5.2.2. The Technical Proposal will be evaluated and scored utilizing one (1) or more Technical Proposal Evaluation Committee(s).

5.2.3. The scores for the Technical Proposal will be normalized as follows: The Technical Proposal with the highest raw technical score will receive all available Technical Points: 800 points. Other Proposals will be assigned a portion of the maximum available Technical Points, using the formula:

800 X raw score of technical Proposal being evaluated highest raw technical score.

5.3. Oral Presentations

5.3.1. Following evaluation of Technical Proposals, the State may, in its sole discretion, invite up to three (3) top scoring Offerors to provide presentations. The State reserves the right to invite as many Offerors as it deems appropriate, based on the Technical Proposal evaluation scores. The State also reserved the right to invite additional Offerors to provide presentations after the initial round, in its sole discretion.

5.3.2. Presentations will take place remotely via Microsoft Teams or another virtual meeting platform.

5.3.3. The scores for the Oral Presentations/Demonstrations will be normalized as follows: The Oral Presentation/Demonstration with the highest raw score will receive all available Oral Presentation/Demonstration Points: 200 points. Other Offerors will be assigned a portion of the maximum available Oral Presentation/Demonstration Points, using the formula:

200 X raw score of Oral Presentation/Demonstration being evaluated highest raw oral presentation/demonstration score.

5.3.4.

5.4. Cost Proposal

5.4.1. The Cost Proposal will only be opened and evaluated for Offerors who received the top three technical scores.

5.4.2. The scores for the Cost Proposal will be normalized as follows: The cost evaluation will be based on the “Administrative percentage rate per claim” entered on Attachment 5 – Cost Proposal. The Administrative percentage rate per claim will be multiplied by ten thousand ($10,000) dollars to give a monetary value that can be evaluated. The Proposal with the lowest administrative percentage rate per claim proposed will receive all available Cost Points: 200 points. Other Proposals will be assigned a portion of the maximum available Cost Points using the formula:

200 X lowest administrative percentage rate per claim (multiplied by $10,000) Cost proposal being evaluated.

5.5. Responsibility

Pursuant to IDAPA 38.05.01.081, the RFP Lead may, in the State’s sole discretion, require the apparent high point Offeror to provide documentation to demonstrate its responsibility. The RFP Lead may request documentation including, but not limited to: credit or financial reports, and references. Failure to provide requested documentation may result in the Offeror being deemed non-responsible. Nothing herein shall prevent the State from using other means to determine Offeror’s responsibility.

5.6. Award

Award of Contract will be made to the responsive, responsible Offeror whose Proposal receives the highest number of total normalized points.

6. MANDATORY SUBMISSION REQUIREMENTS

The technical proposal begins with the mandatory items identified in this list and the following sections. NOTE: THIS CHECKLIST IS PROVIDED AS A COURTESY ONLY; OFFERORS ARE RESPONSIBLE FOR SUBMITTING ALL MANDATORY SECTIONS, ATTACHMENTS, SUBMITTAL ITEMS, ETC., REGARDLESS OF WHETHER THEY ARE IDENTIFIED IN THIS LIST.

☐ (M) Signature Page: All Proposals must be submitted with a state supplied Signature Page, attached separately in IPRO POWERED BY LUMA. For electronically submitted Proposals, submit a completed, scanned signature page. Your ORIGINAL Signature Page should be included at the FRONT of your ORIGINAL Technical Proposal

☐ (M) Cover Form: Complete, sign, and submit Attachment 4, Cover Form.

☐ (M) Acknowledgement of Amendments: If the RFP is amended, the Offeror must acknowledge each amendment with a signature on the acknowledgement form provided with each amendment. Failure to return a signed copy of each amendment acknowledgement form with the Proposal may result in the Proposal being found non-responsive. See IDAPA 38.05.01.52.

☐ Section 7: Provide response to all (M) and (ME) sections, and any other required submittal items.

☐ Section 8: Provide response to all (M) and (ME) sections, and any other required submittal items.

☐ Section 9: Provide response to all (M) and (ME) sections, and any other required submittal items.

☐ (ME) Cost Proposal: Provide your cost information on the form provided in Attachment 5, Cost Proposal. Submit the Cost Proposal in a separately uploaded file or separately sealed envelope.

☐ Redacted copy of Technical Proposal and list of Trade Secret redactions, as detailed in Section 3.2.

☐ Review the required types and levels of insurance—these are mandatory requirements. If you do not already have the required types and levels of insurance, you are strongly encouraged to contact your insurance representative to find out if you will be able to obtain the required insurance. (The Offeror should not purchase additional insurance in reliance of being awarded a contract). If you are awarded a Contract, failure to provide proof of the required insurance will be grounds for termination of the Contract.

7. BUSINESS INFORMATION

By submitting a Proposal in response to this RFP, the Offeror agrees to comply with all (M) and (ME) requirements.

7.1. (ME) Damage Claims Recovery Services Experience Describe in detail your knowledge and experience in providing services similar to those required in this RFP. Include the Offeror’s business history, description of current service area, and customer base. Specifically address the following mandatory evaluated minimum requirements if you are proposing Damage Claims Recovery services:

7.1.1. The Offeror must have a minimum of three (3) years of experience providing these services to other State Departments of Transportation (DOT), as described in this RFP. Describe how you meet this requirement using specific examples.

7.1.2. Provide one (1) example of a successful claims action from start to finish providing payment to the DOT.

7.1.3. Provide your firm’s qualifications to deliver claims services.

7.2. (ME) Demonstrated Success Provide specific data demonstrating previous percentage of success with successful claims.

7.3. (E) Customer Satisfaction Over the last ten (10) years, approximately what percentage of customers have chosen to remain with your company when given an option (e.g. exercising option renewals, extending agreements, selecting your company again upon re-solicitation, etc.)

7.4. (ME) Client History Offerors must provide two to three (2-3) brief client histories that illustrate the Offeror’s ability and experience with property damage assessment and recovery claims. Provide a list of current and former clients for whom the Offeror has worked on similar projects.

7.5.

8. ORGANIZATION AND STAFFING

Describe your qualifications to successfully meet the requirements of the RFP by providing a detailed response to the following:

8.1. (ME) Point of Contact Identify the person who will be the dedicated Point of Contact if Offeror is awarded a contract. Provide a description of the proposed Point of Contact experience and qualifications, and licenses.

8.2. (ME) Key Personnel and Qualifications Provide a list of key management, customer service and other roles to be used in the fulfillment of this Contract (in addition to the Point of Contact). Provide role descriptions, license certifications, including requisite qualifications and experience of the person(s)/role(s) identified, as well as an explanation of how the person in that role will contribute to the project. Your response should demonstrate the extent to which you have the expertise to accomplish the Scope of Work.

8.3. (ME) Organization Provide an organizational chart identifying key management, customer service, and other personnel to be used in the fulfillment of this contract.

8.4. (M) Changes in Key Personnel The Contractor must notify DOP and ITD, in writing, when there is a change in Key Personnel directly providing services under the contract. Any staff identified as key personnel in Section 8.2 must have a backup who is properly trained and qualified to act as a fully functioning replacement in the temporary absence of the key person. Key personnel must be assigned for term of the contract barring circumstances outside the control of the Contractor such as death or disability. Should any key personnel choose to leave for another reason (e.g., higher pay, job dissatisfaction) their replacement must be equal or superior in qualifications, is subject to ITD approval, and must be provided within thirty (30) calendar days of their known departure.

8.5. (ME) Training/Licensed/Certified Describe how your company keeps claims recovery personnel current and knowledgeable regarding current insurance claims practices and tort law on behalf of self-insured entities, and ensures licensures are current.

8.6. (M) Subcontractors If you intend to utilize subcontractors, describe the extent to which they will be used; how will they comply with Contract requirements, including confidentiality. Include each position providing service and provide a detailed description of how the subcontractors are anticipated to be involved under the Contract. Include a description of how the Offeror will ensure that all subcontractors and their employees will meet all Scope of Work requirements. All subcontractors must be approved in writing by the ITD Contract Monitor. NOTE: The information provided for subcontractors, if any, will be evaluated as part of Section 8.2, Key Personnel and Qualifications.

If you do not intend to utilize subcontractor(s), provide a statement to that effect.

8.7. (ME) Quality Control Describe your company’s quality control process including online website(s), Uploading sites etc. to ensure claims processing, information, invoicing, collections, and reporting are accurate.

9. SCOPE OF WORK

By submitting a Proposal in response to this RFP, the Offeror agrees to comply with all (M) and (ME) requirements.

All sections of the Scope of Work (SOW) are required contract services. Use this Proposal outline as part of your response to the RFP. Keep in mind, the evaluators will be scoring your Proposal based on the methodologies proposed and the completeness of the response to each item listed below. You must describe in detail how you will meet each requirement marked (M) or (ME) below. Include personnel, proposed timelines, confidentiality processes, methodologies, and any pertinent information that will be required from the Agency in order to achieve full compliance with all tasks and deliverables.

9.1. ITD Responsibilities

Idaho Transportation Department will be responsible for:

9.1.1. To commit to continual improvement to the recovery process with monthly or quarterly review via conference call or virtual meeting environments available to both parties;

9.1.2. To designate a point of contact for each district, and ITD headquarters, to handle communication with awarded Contractor about damage claims and monthly reports;

9.1.3. To meet with the Contractor on an annual basis to review the results and processes of the contract and to identify ways to improve both the process and results;

9.1.4. Providing all estimated costs, repair invoices, and any other associated costs.

9.1.5. ITD reserves the right to recall or withdraw any claim from being pursued for any reason, without prior notice.

9.2. (ME) General

9.2.1. Contractors staff that work directly with insurance companies must be currently licensed adjustors in the State of Idaho. Contractor must provide a copy of said licenses to ITD.

9.2.2. Contactor must keep transcripts of all phone calls as a record of transaction and communication and be available to ITD upon written request within five (5) business days. The Contractor must keep transcripts for at least six (6) months after a claim is resolved.

9.2.3. The contactor along with ITD must identify the damaging party or company responsible for ITD owned property damage. Using the Police Report (whether obtained by contractor OR ITD). The contractor will work on behalf of ITD and create a claim based on information from the Police Report. The contractor will identify available insurance coverage for each claim and file all claims with assessed value of one hundred ($100.00) dollars or more.

9.2.4. The Contractor must have an independent audit of its Data Centers prior to each renewal period and at a minimum of once per year, at its expense, and upon written request from the State must provide an un-redacted version of the audit report to the designated State representative no later than thirty (30) calendar days after the report is published. A Service Organization Control (SOC) 2 audit report is required, or, the State may, in its sole discretion, approve another audit type upon Contractor request. In addition, the State must have the right to inspect the Data Centers used by the Contractor to support the Contract, subject to reasonable restrictions imposed by Contractor, within ten (10) calendar days of written notice to Contractor, or such other timeframe as may be mutually agreed upon by the parties. Data Centers must be located in the continental United States.

Describe in detail how you will meet requirements 9.2.1 – 9.2.5. 9.1.1 – 9.1.5.

9.3. (ME) Reports

9.3.1. The contactor must provide ITD monthly and annual reporting using the State of Idaho Fiscal Year reporting period (July 1 through June 30) that includes but are not limited to new claims filed with insurance or private parties including the date, summary of new files opened, with estimates for repair received by ITD, summary of settled/closed claims with recovered amount and date with administration or any fee’s separated, filtered by District, open cases nearing the statute of limitations, settlement negotiated and approved by ITD, and any additional reports agreed upon written amendment between Contractor and ITD and DOP.

9.3.1.1 Monthly Summary Report to provide an overview of ITD claims and the status of their files in the claim recovery process.

9.3.1.2 Monthly Activity Report which shows amount paid by district and claim type, and to include year-to-date totals.

9.3.1.3 Open Claim Report identifies and lists all open files and their status and description broken down by ITD district.

9.3.1.4 Unbilled report lists all files not invoiced and broken down by ITD district

9.3.1.5 Payment report matches the statement on a monthly basis.

9.3.1.6 Compliant Log identifying all complaints from entities Contractor is seeking funds from and be available to ITD on Contractors web site or provided to ITD via email during the course of the claim.

9.3.1.7 Annual Actuary Reporting must assure work conforms to appropriate practices. Actuary Reporting must be submitted to ITD at least thirty (30) to sixty (60) days before renewal. To include but not limited to the following, measuring individual claims submitted by ITD for recovery of Damaged Real Property using Police Report Identification numbers, Date of Loss, Date of estimates for repair submitted by ITD, Amount of Estimate, Amount with percentage of Contractor Fee, Claim recovery total, Date of recovery, (recovery meaning payment) Negotiated Claims, Negotiated claim amount with ITD consent, type of damage, monthly payments made to ITD from recoveries including fee breakdown, Claims nearing statute of limitations, claims in legal.

9.3.1.8 Contractor must schedule with ITD a virtual monthly meeting to review reports with ITD headquarters and all Districts.

9.3.1.9 Contractor’s web site must at a minimum have the ability to search claims by Police Report Number or Date of loss or both.

Provide examples of each report with 9.3.1

9.4. (M) Contactor must provide ITD access to online web portal. The portal must provide ITD access to claims status (but not limited to) using and agreed upon claim number unique to each Police Report for the ease of reporting and ensuring both parties stay updated on the claim’s status and progress, ability to upload Police Reports, Photo’s or other information necessary to contribute to a successful recovery. Status Notes on each claim to include dates and any other details on each particular claim by the Contractor’s Adjustors.

9.5. (ME) Contractor must accept claims submitted via secure data file transfer.

Provide an explanation of how and what secure data file transfer you will be utilizing for 9.5.

9.6. (M) Contactor must accept damage claims in the following ways: Police Reports uploaded by ITD using agreed secure data upload, emails containing a Police Report Number and Existing claims, not yet invoiced, ITD will work to make all police reports available to the contractor for expedient claim processing.

9.7. (ME) Pre-Invoicing Contactor must:

9.7.1 Obtain necessary damaging party information via police reports or data centers previously reported to obtain damaging party information from redacted Police Reports.

9.7.2 Endeavor to obtain all means necessary for identifying the damaging party’s insurance carrier, including but not limited to documented phone calls, email, personal contacts.

9.7.3 Evaluate and verify all necessary information has been collected on behalf of ITD, to process an accurate property damage claim through insurance companies or private parties.

9.7.4 Contactor is responsible for filing all municipality claims, where the municipality damages ITD property, with the appropriate municipality. Contractor must follow appropriate statutory requirement to recover a claim.

9.7.5 Request police reports and fire reports on applicable files noting damage within thirty (30) business days.

9.7.6 All correspondence must include claim number and police report number. Make all necessary effort to obtain any and all missing information. Attempt including but not limited to documented phone calls, email, personal contact to obtain Certificates of Insurance (COI) from municipality permits.

Describe in detail how your company will meet the requirements within 9.7. Provide examples of a pre-invoice packet.

9.8. (ME) Billing

9.8.1 Contactor must update the status of a claim through the invoicing cycle as follows:

9.8.1.1 Once damage costs are deemed final, process claims through the invoicing program within five (5) business days. Submit a letter of intent on official company letter head to invoice for all approved claims within five (5) business days.

9.8.1.2 Ensure all claims are complete prior to invoicing.

9.8.1.3 Add to each invoice an administrative percentage provided in Attachment 5 Cost Proposal.

9.8.1.4 Accurately assemble all supporting documentation based on the information provided by ITD.

9.8.1.5 Submit notice of intent to file a claim immediately upon identification of responsible party.

9.8.1.6 Make all necessary effort to obtain any and all missing information.

Provide an example of invoices including documentation including 9.8.1.1 – 9.8.1.5. Provide your company’s efforts to obtain any and all missing information as in 9.8.1.6.

9.9. (ME) Insurance Contractor must:

9.9.1 Process all applicable insurance claims through Contractors licensed insurance adjusters.

9.9.2 Update the demographic statistics of the claim through the insurance processing lifecycle.

9.9.3 Process all insurance claims and assign a licensed adjuster within ten (10) business days of completion of the pre-invoice process.

9.9.4 Submit subrogation packages to the damaging party’s insurance carrier.

9.9.5 Attempt to obtain Certificates of Insurance (COI) from municipality permits.

9.9.6 Attempt recovery on all uninsured motorist claims using Contractor licensed adjusters.

Provide a detailed explanation of your insurance claim process for 9.9

9.10. (ME) Recovery Process Contractor must:

9.10.1 Update the status of the claim throughout the recovery process cycle using online portal and monthly reporting by contractor to be sent to designee.

9.10.2 Require payment in full for all liable parties, whether Paid in Full or Partial Payments made.

9.10.3 The contractor will identify available insurance coverage for the claim, submit ITD documentation for damage repair costs, and /or negotiate recovery on all claims.

9.10.4 Identify levels of any information needed to support the recovery and, interact with ITD personnel as needed, process payments for insured and uninsured motorists, identify processes and procedures that increase the likelihood of recovery at one hundred percent (100%) of damage cost of the repair, and associated costs.

9.10.5 Negotiate a settlement for damages and cost up to twenty-five percent (25%) of the gross invoice amount before written authorization from ITD is required. All settlements over twenty-five percent (25%) must be approved in writing by ITD prior to acceptance. Contractor fees will be reduced proportionally by the settlement amount when payment is received.

9.10.6 Utilize internal quality assurance process to review claim for compliance and progression of the recovery process for open claims aged greater than ninety (90) calendar days.

Provide a detailed explanation of your recovery process meeting all requirements within 9.10

9.11. (ME) Pre-Legal Process Contractor must:

9.11.1 Process claims with an invoiced value between five hundred ($500.00) and two hundred thousand dollars ($200,000.00) that remain unrecovered after one hundred eighty (180) calendar days from the date of invoice to an affiliated non-litigation attorney for the following process:

9.11.1.1 Identified damager must be sent a letter indicating damage claim is owing and that said claim may be escalated for further action if not paid.

9.11.1.2 Pre-legal attorney firm must perform follow-up phone calls and monitoring until claim is paid or all avenues for recovery are exhausted. This process must last a maximum of ninety (90) calendar days.

9.11.1.3 Pre-legal attorney firm must provide documentation after ninety (90) days that they have been reaching out to claimant and/or insurance provider.

9.11.1.4 Following the pre-legal process, if unrecovered after ninety (90) days, the claim must be returned to ITD for litigation evaluations.

Provide an explanation of your Pre-Legal Process 9.11

9.12. (M) Financial Remittance Contractor must:

9.12.1 Acknowledge funds received by the Contractor in regard to ITD claims pursuant to the Contract and must be designated payable to ITD, must be property of ITD and must be held “in trust” on behalf of ITD.

9.12.2 Recover and disburse funds referenced in this Contract.

9.12.3 Remit all payments, minus Contractors fees as permitted by this agreement.

9.12.4 Net remit payments to ITD by the fifth (5th) day of each month from the prior calendar Month’s claims.

9.12.5 Net remit payment to ITD via Electronic Funds Transfer (EFT).

9.12.6 Accept the following payment methods: EFT, Telephonic, Mail.

9.12.7 Accept the following forms of payments: Check, Money Order, Debit Card, EFT. Transactional costs associated with Credit Card payments must be covered by the Contractor.

9.12.8 Accept the following types of payments: Paid in Full, Settled in Full, Partial Payment.

Provide a statement that the vendor meets this requirement.

9.13. (M) Proposed Fees and Pricing Contactor must:

9.13.1 Provide your administrative percentage cost per property damage recovery on Attachment 5 - Cost Proposal.

9.13.2 Maximum dollar fee per claim must not exceed ten thousand dollars ($10,000.00).

9.13.3 Administrative percentage must be added to the total cost of damage repair costs in order for ITD to recover an amount as close to one hundred percent (100%) of damage repair costs as possible.

9.14. (ME) Training

9.14.1 Training must be virtual (i.e. teams, zoom, etc.) interactive and live.

9.14.2 Initial Training must be for up to two (2) ITD employees for each District 1 – 6 and Headquarters for a total of fourteen (14) trainees, others as needed/requested.

9.14.3 Provide hourly rate for additional training if needed for new hires, ITD will request training as needed for vendors online web portal per cost provided in Attachment 5 – Cost Proposal (this rate will be used for contractual training rates and not for award purposes).

Provide your comprehensive training and support for usage of claims management software.

ATTACHMENT 1 – PRE-PROPOSAL CONFERENCE REGISTRATION FORM

EVENT 601 PROPERTY DAMAGE CLAIM MANAGEMENT

PRE-PROPOSAL CONFERENCE
Wednesday, June 18th from 9:00 a.m. to 10:00 a.m. Mountain Time
Idaho Transportation Department
Event 601

PROPERTY DAMAGE CLAIM MANAGEMENT

Oral Information: Questions concerning an RFP must be directed in writing to the RFP Lead in the time period prescribed in the RFP document. Vendors are cautioned against relying on any verbal information, and do so at the Vendor’s sole risk. The RFP may only be amended by written documentation posted to the state’s eProcurement System, IPRO POWERED BY LUMA.

Potential Offerors choosing to participate in the Pre-Proposal Conference must pre-register by submitting this completed form, via e-mail, to the RFP Lead at Kevin.Jarrett@adm.idaho.gov. After the RFP Lead receives your form and the registration deadline passes, you will be provided with phone conferencing and meeting details. Please indicate in the appropriate column if your attendance will be by phone. Attendees are asked to register for the Pre-Proposal Conference no later than 5 p.m., Mountain Time on Tuesday, June 17th.

PLEASE PRINT:

Name
Company
Email Address

ATTACHMENT 2 – OFFEROR QUESTIONS

EVENT 601 PROPERTY DAMAGE CLAIMS MANAGEMENT

Instructions:

DO NOT IDENTIFY YOUR NAME OR YOUR COMPANY’S NAME OR PRODUCT NAMES OF INTELLECTUAL PROPERTY IN YOUR QUESTIONS.

ADD ROWS BY HITTING THE TAB KEY WHILE WITHIN THE TABLE AND WITHIN THE FINAL ROW.

The following instructions must be followed when submitting questions using the question format on the following page.

1. DO NOT CHANGE THE FORMAT OR FONT. Do not bold your questions or change the color of the font.

1. Enter the RFP section number that the question is for in the “RFP Section” field (column 2). If the question is a general question not related to a specific RFP section, enter “General” in column 2. If the question is in regards to a State Term and Condition or a Special Term and Condition, state the clause number in column 2. If the question is in regard to an attachment, enter the attachment identifier (example “Attachment 1”) in the “RFP Section” (column 2), and the attachment page number in the “RFP page” field (column 3).

1. Do not enter text in the “Response” field (column 5). This is for the State’s use only.

1. Once completed, this form is to be e-mailed per the instructions in the RFP. The e-mail subject line is to state the RFP number followed by “Questions.” DO NOT SUBMIT QUESTIONS VIA IPRO.

EVENT 601 PROPERTY DAMAGE CLAIM MANAGEMENT

Question
RFP Section
RFP Page
Question
Response

ATTACHMENT 3 – MODIFICATION AND EXCEPTION FORM

Instructions: Complete this form and submit prior to the questions due date if you are proposing modifications or taking exception to any of the requirements, terms, or conditions included in the RFP, including any documents incorporated by reference (such as the Standard Contract Terms and Conditions.) See RFP Section 2.4 for a full explanation of the process surrounding vendor-proposed modifications and exceptions.

Offerors must specifically address any and all proposed modifications and exceptions. Blanket requests to negotiate requirements, terms, or conditions will not be considered. Offerors must provide an explanation as to why the requirement, term, or condition should be considered non-material. Offeror must also provide a reason for the proposed modification or alternative language, specifically addressing the issues itemized in RFP Section 2.4.1.

The determination of materiality will be made at the State’s sole discretion. Non-material modifications or exceptions may be negotiated with the apparent successful Offeror, at the discretion of the State, and as otherwise provided in RFP Section 2.4.4.

RFP Section
RFP Requirement, Term, or Condition
Reason Requirement, Term, or Condition Should be Considered Non-Material
Proposed Modification, Alternative, or Exception
Reason for Proposed Modification, Alternative, or Exception
Response

ATTACHMENT 4 – COVER FORM

(M) Attachment 4, Cover Form must be completed, signed, and submitted with your Proposal. Failure to complete and submit this form may result in your Proposal being deemed non-responsive.

Instructions: The Technical Proposal must include a signed copy of this cover form. Copy and paste this form onto your company letterhead, or include the following information: Offeror’s company name, mailing address, phone number, fax number, e-mail address, and name of Offeror’s authorized signer. The cover form must include the RFP Number and Title and must be signed by an individual authorized to commit the Offeror to the contents of the Proposal.

Requirement
Response
Offeror’s corporate or other legal entity status
☐ Corporation

☐ Limited Liability Corporation (LLC) ☐ Limited Liability Partnership ☐Sole Proprietorship ☐ Other (specify)

Offeror’s Tax Identification Number

EIN:

Offeror’s DUNS Number

DUNS:

Is Offeror a legal entity with the legal right to contract?

☐ Yes ☐ No

Other than modifications/exceptions identified on Attachment 3, in compliance with Section 2.4 of this RFP, does Offeror accept, and is Offeror willing to comply with, the requirements of this RFP and attachments, including but not limited to those identified in Section 1.4 and the Special Terms and Conditions in Appendix?

☐ Yes ☐ No

Is Offeror in compliance with applicable equal employment regulations?

☐ Yes ☐ No

Does Offeror affirm that it has not employed any company or person other than a Bona fide employee working solely for the Offeror or a company regularly employed as its marketing agent, to solicit or secure the Contract, and that it has not paid or agreed to pay any company or person, other than a Bona fide employee working solely for the Offeror or a company regularly employed by the Offeror as its marketing agent, any fee, commission, percentage, brokerage fee, gifts, or any other consideration contingent upon or resulting from the award of the Contract.?

☐ Yes ☐ No

Does Offeror understand and agree that for breach or violation of the above term, the State has the right to annul the Contract without liability or, in its discretion, to deduct from the offered price the amount of any such fee, commission, percentage, brokerage fee, gifts, or contingencies.

☐ Yes ☐ No

Firm(s) and/or staff responsible for writing the Proposal

Names:

Does Offeror affirm that it is not currently suspended, debarred, or otherwise excluded from federal or state procurement and non-procurement programs?

Note: vendor information is available at https://sam.gov.

☐ Yes ☐ No

Does the Offeror affirm that the Proposal will be firm and binding for ninety (90) calendar days from the Proposal opening date?

☐ Yes ☐ No

Does Offeror warrant that it does not knowingly and willfully employ persons who cannot legally work in this country; and that Offeror takes steps to verify that it does not hire persons who have entered our nation illegally or cannot legally work in the United States; and that any misrepresentation in this regard or any employment of persons who have entered our nation illegally or cannot legally work in the United States constitutes a material breach and will be cause for the imposition of monetary penalties up to five percent (5%) of the Contract price, per violation, and/or termination of the Contract?
☐ Yes ☐ No

Signed By:

Printed Name:

Date:

ATTACHMENT 5 – COST PROPOSAL

(ME) Attachment 5, Cost Proposal must be completed and submitted with your Proposal. The Offeror must provide a fully burdened administrative percentage rate which must include, but not be limited to, all operating and personnel expenses, such as: overhead, salaries, administrative expenses, travel, profit, and supplies. The percentage rate will be multiplied by ten thousand ($10,000) dollars to give a monetary value for evaluation purposes.

Description
Percentage Rate

Administrative percentage rate per claim

The Offeror must provide a fully burdened hourly rate which must include, but not be limited to, all operating and personnel expenses such as overhead, salaries, administrative expenses, profit, and supplies. Training will be provided virtually, no travel expenses will be needed or paid.

Description
Hourly Rate

Additional training

Company Name: _ Name of Individual submitting bid:

Phone: Fax:

E-mail:

APPENDIX A – IDAHO TERMS AND CONDITIONS BACKGROUND AND LIMITATIONS

Idaho…