This request for proposal (RFP) solicits design-build services for distress box replacements at the West Palm Beach VA Medical Center. The contractor will replace existing emergency call boxes on the property with new call boxes featuring video capability. The project involves design, demolition of existing call boxes, and replacement with video call boxes including installation of radios, cameras, power, cabling, and programming into the VA network. The contractor must provide all labor, materials, tools, equipment, and design-build services necessary to complete the project. Phase I proposals are due on July 22, 2022. This requirement is set aside exclusively for verified Service-Disabled Veteran-Owned Small Businesses. The awarded contract will have a period of performance of 180 days from notice to proceed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment Pkgs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________
(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24822R0105
X
07-01-2022
548-22-146
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
8875 Hidden River Pkwy Suite 525 Tampa FL 33637
Stacy Figlinski (813) 940-2788
Project Title: Distress Box Replacement; Project Number: 548-22-146 Project Location: West Palm Beach VAMC, 7305 N. Military Trail, West Palm Beach, FL, 33410
Magnitude of this construction project is between $1,000,000.00 and $5,000,000.00.
NAICS is 236220 Commercial and Institutional Building Construction, Size Standard of $36.5M. Service Code Z1DA.
Project Description: Provide all labor, materials, tools and equipment, and design-build services necessary for design and construction of a project titled "Distress Box Replacement". The project involves demo of current distress boxes and provides new boxes with cameras and radios.
The location is the West Palm Beach VA Medical Center.
This solicitation will be evaluated on a Trade-Off basis. As stated elsewhere in this solicitation, this procurement is a two (2) Phase Design/Build IAW FAR Part 36.3. One solicitation will be issued covering both phases. In Phase I proposals will be evaluated to determine which offerors will submit proposals in Phase II. Block 13 A refers to Phase 1 Proposals.
This requirement is set-aside for Vendor Information Portal(VIP) certified, Service-Disabled Veteran Owned Small Businesses (SDVOSB) Vendor verification for SDVOSB can be found here at https://www.vetbiz.va.gov/
WPB VAMC is a smoke free facility. Contractors, in order to enter the WPB VAMC campus you must have picture ID. All contractors are required to wear a face covering (covering nose and mouth per CDC guidelines) while on property. All contractors will be screened at the entrance of the property. A series of questions will be asked and temperature taken.
AT THE TIME OF PROPOSAL SUBMISSION, interested contractors MUST be actively registered in the following databases.
System for Award Management: https://www.sam.gov Vet Biz: https://www.vetbiz.gov
10 180
X X 52.211-10
X
10:00 AM EDT
07-22-2022
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
36C248
Department of Veterans Affairs Network Contracting Office 8 (NCO 8)
8875 Hidden River Pkwy Tampa FL 33637
Financial Services Center
P.O. Box 149971 Austin TX 78714-9971
Stacy Figlinski
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
REQUEST FOR PROPOSAL
PART I – GENERAL INFORMATION
PART II – PROPOSAL PREPARATION AND EVALUATION INFORMATION
PART III - AWARD
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.215-5 FACSIMILE PROPOSALS (OCT 1997)
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014)
2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS (MAY 2014)
2.6 52.228-1 BID GUARANTEE (SEP 1996)
2.7 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
(FEB 2021)
2.8 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)
2.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND
VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)
2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
2.13 PARTNERING
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2022)
(JUL 2020) (DEVIATION)
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (NOV 2021)
GENERAL CONDITIONS
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS (DEC 2014)
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE,
AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER
COVERED ENTITIES (NOV 2021)
4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING
RESPONSIBILITY MATTERS (OCT 2018)
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984) ALTERNATE I (APR 1984)
4.5 52.219-14 LIMITATIONS ON SUBCONTRACTING (SEP 2021)
4.6 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(SEP 2021)
4.7 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)
4.8 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL
LABOR RELATIONS ACT (DEC 2010)
4.9 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR
FEDERAL CONTRACTORS (OCT 2021) (DEVIATION)
4.10 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)
4.11 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.12 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.13 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN
2020)
4.14 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)
4.15 VAAR 852.215-70 SERVICE-DISABLED VETERAN-OWNED AND VETERAN-
OWNED SMALL BUSINESS EVALUATION FACTORS (OCT 2019)
4.16 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (OCT 2019)
4.17 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND
COMPLIANCE (JUL 2018)
4.18 VAAR 852.219-75 SUBCONTRACTING COMMITMENTS MONITORING AND
COMPLIANCE (JUL 2018)
4.19 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
4.20 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)
4.21 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.22 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)
ALTERNATE I (APR 2019)
4.23 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT
ADMINISTRATION (OCT 2020)
4.24 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) .. 58
4.25 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
4.26 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN
2008)
4.27 IT CONTRACT SECURITY
DESIGN BUILD SPECIFICATIONS
4.28 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES
4.29 OWNERSHIP OF ORIGINAL DOCUMENTS
4.30 RETENTION OF REVIEW DOCUMENTS
4.31 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED
PLANNING INFORMATION
4.32 COORDINATION WITH MEDICAL CENTER
4.33 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR
ATTACHMENTS
ATTACHMENT 1 - RELEASE OF CLAIMS
REQUEST FOR PROPOSAL
SOLICITATION NO. 36C24822R0105
ISSUE DATE: July 1, 2022 - PHASE I PROPOSAL DUE DATE: July 22, 2022 at 10:00 AM EST
PROJECT NUMBER: 548-22-146
PROJECT TITLE: Design Build – Distress Box Replacements
LOCATION: West Palm Beach VAMC, 7305 N. Military Trail, WPB FL 33410
PROJECT SUMMARY: Contractor is to replace existing Emergency Call Boxes on the property with new call boxes with video capability. The project involves design, demolition of existing call boxes and replacement with video call boxes. Installation includes radios and programming into VA network. The cameras shall be installed and all necessary power, cabling, programming will be operational on the VA Network. Project includes installation of necessary racks, network switches and other support hardware.
PURPOSE: The objective of this project is to provide new and updated call boxes across the WPB VAMC Campus.
OFFICE ISSUING THIS REQUEST:
Department of Veterans Affairs Network Contracting Office (NCO) 8 8875 Hidden River Pkwy. Suite 560 Tampa, FL 33637 Contracting Officer: Stacy Figlinski Email: Stacy.Figlinski@va.gov Phone: (813) 940-2788
PART I – GENERAL INFORMATION
1. All references to “Bid” or “Bidder” shall be understood to mean “Offer” or “Offeror”.
2. DEFINITIONS
a. Design-Build (D/B) as defined by the Department of Veterans Affairs (VA) is the procurement by the Government, under one contract, with one firm or joint venture (JV) as identified in your basic contract, for both design and construction services for a specific project.
b. Contracting Officer Representative (COR): The COR responsible for administering contracts under the immediate direction of the Contracting Officer.
c. Design Build Contract: This term, as used herein, refers to the Contract to perform the design and construction of the project.
d. Contractor: This term, as used herein, refers to the contractor under this contract or the D/B team.
e. AE: This term, as used herein, refers to the Architect-Engineer firm(s)that are a part of the D/B team, also referred to as D/B/AE.
3. MAGNITUDE OF CONSTRUCTION: Between $1,000,000.00 and $5,000,000.00.
4. Site Visit: An organized site visit will be held during the Phase II proposal period.
5. OFFER ACCEPTANCE PERIOD: Offers providing less than one-hundred and twenty (120) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
6. REQUESTS FOR INFORMATION: Requests for Information (RFIs) shall be submitted by the prime contractor, through email to the Point of Contact listed above. No telephone RFIs will be accepted. The cutoff for submission of RFIs for Phase I is July 11, 2022 at 10:00 AM EST.
Phase I RFI’s should address Phase I evaluation factors only. If Phase II questions are asked, they will be deferred until Phase II. Responses will be provided in one document in a Question & Answer format to all offerors through a solicitation amendment.
8. SPECIFICATIONS AND DRAWINGS: All applicable specifications and drawings will be provided electronically along with the Request for Proposal. No hard copies will be made available to proposing contractors.
9. SDVOSB Verification – The Government will review VetBiz (https://www.vip.vetbiz.gov/) to confirm SDVOSB status verification for the submitted proposal. Evaluations will be performed on proposals submitted by verified SDVOSBs only. Subsequent confirmation of SDVOSB verification status will be performed for the apparent awardee.
10. LIMITATIONS ON SUBCONTRACTING (Reference Contract Clause FAR 52.219-14 for further information): By submission of an offer and execution of a contract, the Offeror agrees that in performance of the contract, the concern will perform at least fifteen (15) percent of the cost of the contract, not including the cost of materials, with its own employees.
11. FUNDS: Funding is available for this acquisition.
12. BONDS (Reference Contract Clause FAR 52.228-15 for further information on applicability):
A payment and performance bond shall be provided. The penal sum shall be one-hundred percent (100%) of order price. Bonds and other payment protection shall be provided within 10 calendar days of award of the Contract. Notice to proceed will not be issued until the Contractor provides sufficient bonding to cover the work being performed.
13. OFFER GUARANTEE (BID BOND) (SUBMIT WITH YOUR PRICE PROPOSAL): Per FAR Clause 52.228- 1-Bid Guarantee, the amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less. NOTE: A scanned copy of the original is acceptable with the original sent by mail.
14. WAGE DETERMINATION: Wages for all contractors and subcontractors must comply with Davis Bacon Wage Determinations. The current determination is General Decision FL20220220 06/03/2022. Be advised the determination that is current at the time of the Contract award is the determination that will apply for the project. Current determinations are always available at: http://www.sam.gov/.
15. CONTRACT PERFORMANCE PERIOD: 180 calendar days after receipt of written Notice to Proceed performed in concurrent or sequential phases as indicated or required.
16. Work Element No. 1 (Design Build Effort Required): Contractor shall develop project design documentation including drawings, specifications, design analysis etc. representative of a 30% and 95%, completion stages. The (95%) review submission packages will incorporate the final review comments from the (30%) review. Upon completion of design, and upon acceptance by the Government, construction execution shall commence and be completed in accordance with contract requirements.
PART II – PROPOSAL PREPARATION AND EVALUATION INFORMATION
1. This RFP addresses both the Phase One and Phase Two proposal requirements. Do not submit the pricing information requested in Phase II with the Phase I proposal.
2. The Phase I proposals will be evaluated to determine which offerors will be invited to submit Phase II technical and price proposals.
3. A maximum of five (5) most highly rated Phase I proposals will be invited to submit a Phase II proposal.
4. Prospective vendors shall provide their proposal in any of the following formats: .pdf, .docx, or .doc to the issuing office address identified above. The proposal shall be provided via email to Stacy.Figlinski@va.gov. The technical proposal shall address each of the evaluation criteria.
a. During Phase II, the price proposal shall be provided as a separate file from the technical proposal. The price proposal shall include a copy of the vendor VETBIZ registration information, a copy of the vendor SAM.GOV registration information, and a price sheet with pricing on the statement of items. While there is no page limit to the price proposal, it shall also be on 8 ½” x 11” pages, when printed. The statement of items shall be filled out in its entirety.
5. Technical Proposal Format: Technical Proposal shall address all information requested and will then be evaluated against the stated factors. The following format shall be used:
PHASE I
1. GENERAL INFORMATION:
a. Cover Page with Solicitation Number, Project Title
b. Signed offer/Acknowledgement of Amendments
c. Copy of current vetBiz.gov SDVOSB certification
6. TECHNICAL PROPOSAL REQUIREMENTS
Phase I
Factor I – Specialized Experience and Capability
The offeror is required to submit the completed example projects outlined below. The completed example projects, which demonstrate your firms experience and capability, are to be recent and relevant to this requirement.
Recent is defined as a contract completed within the last seven years.
Relevant is defined as all of the following: 1) A DB project involving electrical work of the same or similar type required in this RFP; 2) Work conducted in an active healthcare environment;
and 3) Contracts which are $750,000.00 or greater.
A total of four (4) example projects shall be provided as stated below:
1. Provide two recent and relevant example projects demonstrating the offeror’s project management experience and capability as a prime contractor. A prime contractor is defined as the firm appearing within block 14 of the completed 1442.
2. Provide two recent and relevant example projects demonstrating capability of the firm (subcontractor) that will be performing the Distress Box replacements.
Example projects can be provided as: (Prime/Prime) + (Sub/Sub) = 4; (Prime/Prime) + (Prime- Self Perform/Prime-Self Perform) =4
Self-performed projects demonstrating your firm’s capability may be used to respond to the Government’s request for two example projects demonstrating recent and relevant construction capability of the firm (subcontractor). These project examples must be identified as self-perform.
Example projects submitted are to demonstrate a firm’s experience and capability and must be recent and relevant as defined above. The offeror must explain how the work performed by the proposed firm in the example project is relevant to the proposed acquisition within attachment J.
Only attachment J should be used to provide the example project’s written information.
Prospective contractors are to complete Experience Information Sheet, Attachment J, sections a though o.
Formatting and Other Restrictions The submission is limited to 20, 8-1/2” x 11” pages in total.
Factor II - Contractor Team and Personnel
The offeror is required to submit a narrative or organizational chart outlining the proposed contractor team. The narrative and/or organizational chart must identify any subcontractor with a portion of work estimated to be valued at $250,000.00 dollars or greater and shall be identified as such on the contractor team narrative or chart. Identify the subcontractor’s estimated overall value of the work and their primary work activities for this project. The team responsible for replacing the emergency call boxes shall be identified on the chart or within the narrative.
Please identify your firm as self-perform in the response’s narrative and/or organizational chart if your firm is responsible for replacement of the emergency call boxes. Offeror shall submit resumes for their proposed project manager and site supervisor. The resumes should demonstrate experience and qualifications commensurate with managing and executing a $750,000.00 or greater DB requirement in a healthcare environment.
Formatting and Other Restrictions The submission does not have a page limitation.
Factor III – Past Performance
The Government will survey PPIRS (Past Performance Information Retrieval System) for each prime contractor which meet the definition of relevant and recent (as defined in Factor II above).
In the event, multiple rated contracts exist in PPIRS which meet the defined criteria the most recent two projects will be used. The contracting officer’s knowledge or that of the technical team may be used in past performance evaluations.
Offerors without relevant PPIRS records can provide references for their past performance.
Offerors shall use attachment H titled “Past Performance Questionnaire”.
Formatting and Other Restrictions The submission does not have a page limitation.
Phase II
Factor IV - Schedule
The offeror is required to submit a proposed progress schedule in a time scaled bar graph format. The horizontal axis will be scaled for time beginning with the Notice to Proceed and concluding with contract completion. The vertical axis will show the milestones and major portions of the contract work. All schedule items will show a start date and a completion date.
The detailed schedule will indicate specific tasks with dates for each step of the process including:
(1) Design Period: The design period sub periods (i.e., first and second reviews, other meetings, internal QUALITY ASSURANCE /QUALITY CONTROL plan reviews, etc.).
(2) Construction Period: Mobilization; Demolition method and sequencing; Excavation; Structure Completion; Exterior finishing; Procurement and installation of equipment; Provisions for overtime or shift work; Timing of relocation of existing equipment; Site utilities, roadway realignment; and temporary rerouted medical center vehicular and pedestrian routes, Tests and final inspection.
(3) General Project Delivery Schedule and Narrative - Show relationships between construction document development/completion (including required review activities) and construction activities.
(4) The Offeror shall specify how much allowance has been made for bad weather in the schedule, the days of the week and the hours of construction operations during each phase of the work, and the percentage of contract completion that will be achieved at the end of each month of the contract.
(5) The Offeror will provide a written commitment as to the time frame (number of days after receipt of the notice to proceed) within which the Offeror will guarantee completion. The maximum anticipated completion of this project (including design and construction of the entire project) shall be indicated on the submitted schedule.
Formatting and Other Restrictions The submission does not have a page limitation
Factor V - Technical Approach
The offeror shall submit a narrative description of how they intend to approach the scope of the work. The description shall include a written narrative of the planned phasing so that the facility remains operational while the construction is occurring. The narrative will also detail how the contractor intends to prepare the site, complete construction and return the site to original condition. Narrative shall explain how the project will be accomplished to ensure minimal interruptions with daily hospital operations and patient care.
Formatting and Other Restrictions The submission for each contractor is limited to a total of seven, (7) 8-1/2” x 11” pages.
Factor VI - Price Proposal The Government will evaluate price based on the total price. Contractor is to complete Attachment F. Total price consists of the basic requirement.
The price proposal shall show direct and indirect project price break down. The price breakdown shall reflect the Base proposed items using at a minimum the following cost element:
(1) Labor (Direct & Indirect),
(2) Materials, Material Markups, Materials overhead,
(3) Equipment
(4) Subcontractor Cost
(5) Travel
(6) Other Direct Costs
(7) Overhead expenses
(8) Indirect Cost
(9) General & Administrative (G&A) expenses
(10) Profit
Technical Evaluations - All technical factors when combined are more important than cost or price.
Cost Proposal - Offerors are advised that if the technical proposals are essentially equal, award will be made on the basis of the lowest cost.
PART III - AWARD
a. The Government will evaluate proposals submitted in response to this solicitation which meet the requirements that have been provided in Parts I and II above.
b. This procurement will be a single award on a best value basis resulting from this solicitation to the responsible offeror.
c. The six (6) factors are Specialized Experience and Capability; Contractor Team and Personnel; Past Performance; Schedule; Technical Approach; Price.
Factors 1 through 5 are equal in importance and when combined are more important than price.
(2) Award may be made without discussions, except for minor clarifications.
LIST OF ATTACHMENTS:
A. Statement of Work B. 01 00 00 General Requirements Specifications C. 01 42 19 Reference Standards Specifications D. Pre-award Safety Sheet E. 01 33 23 Shop Drawings Product Data and Samples F. Price Sheet G. 01 32 16.16 Network Analysis Schedules (DB Only) H. Past Performance Questionnaire I. Sample Letter of Commitment J. Experience Information Sheet K. West Palm Beach VAMC Map L. Site Plan Call Boxes
M. General Decision Number: FL20220220 06/03/2022 (Palm Beach County) N. Limitations on Subcontracting
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBE
R
DESCRIPTION OF
SUPPLIES/SERVIC
ES
QUANTIT
Y
UNI
T UNIT PRICE AMOUNT
1.00 JB ________________
Contractor is to replace existing Emergency Call Boxes on the property with new call boxes with video capability. The project involves design, demolition of existing call boxes and replacement with video call boxes. Installation includes radios and programming into VA network. The cameras shall be installed and all necessary power, cabling, programming will be operational on the VA Network. Project includes installation of necessary racks, network switches and other support hardware.
Contract Period: Base POP Begin:
POP End:
PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z1DA - Maintenance of Hospitals and Infirmaries
GRAND TOTAL ________________
Minimum Required Equipment Specifications
Fixed Camera Specific Needs/Salient Characteristics:
Image Sensor CMOS Megapixel Sensor Progressive Scan Lightfinder 2.0 Forensic WDR HDTV 1080p video up to 120fps Day/Night Functionality Varifocal Lens Compression – zipstream, H.264 profile, H,265, Motion Jpeg
Audio – Supported, two-way audio, full duplex audio System integration – axis camera application platform Network POE class 3 or 4 Compatible with milestone software
PTZ Camera Specific Needs/Salient Characteristics:
Image Sensor CMOS Megapixel Sensor Progressive Scan Lightfinder 2.0 Forensic WDR HDTV 1080p video up to 120fps Day/Night Functionality Varifocal Lens For PTZ – Mechanical Pan/tilt, Pan = 360 endless, Tilt = 180, optical zoom 32, digital zoom 12 Compression – zipstream, H.264 profile, H,265, Motion Jpeg Audio – Supported, two-way audio, full duplex audio System integration – axis camera application platform Network POE class 3 or 4
Compatible with milestone software
See attached document: Attachment Pkgs.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE
AND BONDS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
2.1 52.215-5 FACSIMILE PROPOSALS (OCT 1997)
(a) Definition. "Facsimile proposal," as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via facsimile machine.
(b) Offerors may submit facsimile proposals as responses to this solicitation. Facsimile proposals are subject to the same rules as paper proposals.
(c) The telephone number of receiving facsimile equipment is: .
(d) If any portion of a facsimile proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document—
(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal;
(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and
(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timeliness, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.
(e) The Government reserves the right to make award solely on the facsimile proposal.
However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.
(End of Provision)
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—
SECONDARY SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO
ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
(FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
% 6.9 %
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
(End of Provision)
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.6 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
2.7 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID
GUARANTEE) (FEB 2021)
(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.
(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.
(End of Provision)
2.8 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Hand-Carried Address:
Network Contracting Activity 8 (NCA 8)
8875 Hidden River Pkwy Tampa FL 33637 Mailing Address:
Department of Veterans Affairs
Network Contracting Activity 8 (NCA 8)
8875 Hidden River Pkwy Tampa FL 33637
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
2.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I
(FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
(c) Participants will meet at—
2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY
REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
FAR
Number
Title Date
52.204-7 SYSTEM FOR AWARD MANAGEMENT OCT 2018
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE
REPORTING
AUG 2020
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE
ACQUISITION
NOV 2021
52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION OCT 1997
2.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED
AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC
2009)
Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.
(End of Clause)
2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.
(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.
PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:
Deputy Assistant Secretary for Acquisition and Logistics, Risk Management Team, Department of Veterans Affairs 810 Vermont Avenue, N.W.
Washington, DC 20420 Or for solicitations issued by the Office of Construction and Facilities Management:
Director, Office of Construction and Facilities Management 811 Vermont Avenue, N.W.
Washington, DC 20420
2.13 PARTNERING
(a) In order to most effectively accomplish this contract, the Government proposes to form a cohesive partnership with the Contractor and its subcontractors. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project, done right the first time, within the budget and on schedule.
(b) This partnership will be totally voluntary. The focus of partnering is to build cooperative relationships with the private sector and avoid or minimize disputes and to nurture a more collaborative ethic characterized by trust, cooperation and teamwork. Partnering is defined as the creation of a relationship between the owner and contractor that promotes mutual and beneficial goals. It is a non-contractual, but formally structured agreement between the parties.
The ultimate goal is the elimination of the "us" versus "them" thinking, and formation of a "we" mentality for the benefit of the project.
(c) Any cost associated with effectuating this partnership will be agreed to by both parties and will be shared equally with no change in contract price.
FAR
Number
Title Date
852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE
RESOLUTION
OCT 2018
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN
2022) (JUL 2020) (DEVIATION)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.
(2) The small business size standard is $39.5 Million.
(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204–7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (d) applies.
[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.
(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations— Representation.
(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.
(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.
(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .