DRAINAGE AND SOIL REMEDIATION AT BROKEN TEE GOLF COURSE
Solicitation number
RFP-25-046
Issued by
Arapahoe County, Colorado

About this file

Summary: Request for Proposal #25-046

This is a Request for Proposals (RFP) issued by the City of Englewood, Colorado Parks, Recreation, Library, and Golf Department for drainage and soil remediation services at Broken Tee Golf Course. The project aims to replace, improve, and modify existing drainage systems on holes 1-6 of the championship course. Specific work items include excavation of 4,300 cubic yards of unsuitable soil to 6-inch depth; installation of 12,117 linear feet of 4-inch perforated drainpipe and 1,435 linear feet of 6-inch perforated drainpipe with pea gravel bedding; installation of 735 linear feet of 6-inch solid drainpipe; 50 twelve-inch drain inlets with cast iron grates; placement of 3,800 cubic yards of topsoil blend; finish grading and sodding of 230,000 square feet of bluegrass ryegrass turf-type sod. A recommended pre-proposal meeting and site visit is scheduled for November 5, 2025, at 2:00 PM MST at Broken Tee Golf Course. Sealed electronic proposals are due November 20, 2025, at 2:00 PM MDT. The anticipated notice to proceed delivery is mid-to-late January, with work commencing between January 15, 2026, and March 15, 2026, with substantial completion by May 1, 2026, and final completion by May 8, 2026. The initial contract term is one year from the date of execution. The City anticipates issuing an Intent to Award in December 2025.

The project utilizes a lump-sum contract structure with unit pricing for changes not to exceed plus or minus 20 percent of the total contract amount. A five percent bid bond is required, and the awarded contractor must furnish a 100 percent performance, payment, and maintenance bond within 10 days of Notice of Award. Liquidated damages of $1,600 to $2,300 per day (dependent on final pricing) apply for delays beyond the specified substantial and final completion dates. Proposals are evaluated on project understanding and management approach (35 points), project team experience and technical capability (35 points), and price proposal (30 points), with a total of 100 possible points. Prior experience in golf course construction is preferred but not required; Golf Course Builders Association of America membership or completion of at least 54 holes of new or major remodel golf course construction within the past 5 years is preferred. Contractors must comply with City of Englewood use tax of 3.8 percent and Arapahoe County Open Space use tax of 0.25 percent on construction materials. The City provides boundary and control stakes, preparation of the spoils dump site on hole #11, seeding of the berm on hole #11, and all pre- and post-plant amendments and fertilizers.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL #25-046

Page | 1

REQUEST FOR PROPOSALS

CITY OF ENGLEWOOD

DRAINAGE & SOIL REMEDIATION

BROKEN TEE GOLF COURSE

FOR

THE CITY OF ENGLEWOOD, COLORADO

RFP NO: 25-046

RFP ISSUANCE DATE: October 23, 2025

PROPOSAL DUE DATE: November 20, 2025

Page | 2

Statement of Purpose The City of Englewood's Parks, Recreation, Library, and Golf Department is seeking proposals for the Drainage and Soil Remediation Project at Broken Tee Golf Course. The project aims to replace, improve, and modify the existing drainage systems on holes 1-6 of the championship golf course.

Considerations

This City invites qualified Contractors to submit a Proposal for Drainage and Soil remediation at Broken Tee Golf Course.

It is preferred, but not required, for Contractors to have prior experience in golf course construction. The General Contractor is preferred, but not required, to be a builder member of the Golf Course Builders Association of America and/or have completed at least 54 holes of new or major remodel golf course construction under the supervision of a golf course architect within the past 5 years.

Proposals will be reviewed and evaluated using a competitive, best-value selection process described below. Proposals shall be considered from Contractors who are firmly established in the appropriate business. Contractors shall be financially sound and have the resources and ability to perform the required services in a professional and safe manner in accordance with industry standards.

Proposals in response to this Solicitation must be submitted prior to 2:00 PM MDT, November 20, 2025. Sealed proposals (electronic submissions only) will be received and accepted online via the City of Englewood’s Online Procurement System (https://www.englewoodco.gov/government/city-departments/finance/solicitation-opportunities-awards).

Solicitation Process Proposals will be evaluated and scored based on the criteria provided in this RFP. The City will consider the approach to complete the scope of work, qualifications of the project team, experience in similar work, and value of the proposed fee to complete the work.

The City may conduct interviews with short-listed firms.

Negotiations may be held with the Contractor ranked the highest by the evaluation committee based on proposal, fee, and interview (if needed). The City and the top-ranked Contractor may negotiate the details of the final contract, and City Council approval of the award may be requested. Upon Council approval, the contract will be signed, a PO set up, Notice to Proceed issued and work may begin. Should the City be unable to reach an agreement with the top-ranked Contractor, negotiations may commence with the next-ranked Contractor. This process will continue until a satisfactory contract is negotiated, or the City exercises its right to reject all proposals.

https://www.englewoodco.gov/government/city-departments/finance/solicitation-opportunities-awards

Page | 3

Project Manager

Jeremiah Stumpff, Golf Course Superintendent, will serve as the City Project Manager.

City Communications

No oral communications from the Project Manager or any other individual representing or purporting to represent the City are binding. Contractors are restricted from any and all contact with City staff and any public official of these organizations, other than the Procurement Division, regarding the project during the procurement process. A violation of this provision may result in the disqualification of the Contractor.

Questions Questions will be accepted until November 7, 2025 @ 2:00pm. Once the question period expires, the addendum will be posted on the City’s online Strategic Sourcing platform.

Verbal questions during the recommended pre-proposal meeting and site visit will be screened for applicability and, as applicable, responded to in an addendum. All questions during the procurement period must be directed in writing to:

Trudi Peepgrass, NIGP-CPP, CPPB Procurement & Contracts Manager Finance Department City of Englewood 1000 Englewood Parkway, Englewood, CO 80110 303-762-2419 tpeepgrass@englewoodco.gov

RFP Organization This RFP consists of the following:

• Section 1 – Project Overview, Background, and Goals

• Section 2 – Project Schedule and Milestones

• Section 3 – Scope of Work

• Section 4 – Proposal Submittal Requirements

• Section 5 – Proposal Evaluation and Selection

• Section 6 – Conditions for Contractors

• Drawings for Drainage and Soil Remediation Project

• Basin Detail Diagram

• Broken Tee Overview Picture

• Schedule of Values

• Attachment A – Sample Contract for Construction

Page | 4

Section 1 – Project Overview, Background, and Goals

1.1 Background

Broken Tee Golf Course in Englewood, Colorado, is a top public golf facility, originally called the Englewood Golf Course, and has been extensively redeveloped to accommodate golfers of all skill levels. The renovation involved realigning and rebuilding nine holes, adding a nine-hole Par 3, and upgrading infrastructure such as modern irrigation, drainage, and environmental protections tailored for the capped-land site.

These improvements promote both sustainability and playability while maintaining the natural beauty of the nearby river corridor.

Today, Broken Tee offers an 18-hole regulation course stretching up to 6,836 yards (par

72) and a shorter executive course perfect for practice or quicker rounds. The course features scenic views, challenging water hazards, and multiple tee options that make it suitable for both beginners and seasoned players. As one of the Denver area’s most welcoming public golf spots, Broken Tee reflects Englewood’s dedication to revitalizing community spaces with thoughtful design and long-term environmental care.

1.2 Project Overview

The Drainage and Soil Remediation Project at Broken Tee Golf Course aims to replace, improve, and modify the existing drainage systems on holes 1-6 of the championship course. Drainage work includes relocating 6 inches of unsuitable soil, installing new perforated drainage networks, upgrading catch basins, applying a new topsoil blend, finish grading, and sodding. Holes 1-6 will be closed while work is being completed.

Labor, installation, materials, and equipment to be furnished and provided by the contractor as indicated in the Schedule of Values:

• 1 - Mobilization

• 4,300 CY – Excavation to 6-inch depth and trench spoils, haul material to the dumpsite as shown on Broken Tee Overview Map.

• 12,117 LF – 4-inch perforated drainpipe with pea gravel in a minimum 12-inch by

12-inch trench.

• 1,435 LF – 6-inch perforated drainpipe with pea gravel in a minimum 12-inch by

12-inch trench.

• 735 LF – 6-inch solid drainpipe.

• 50 – 12-inch drain inlets with cast iron grates.

• 500 CY – Pea gravel for perforated drainpipe installation.

• 3,800 CY - Topsoil blend to replace excavated soil.

• 230,000 SF – Shaping and finish grading.

• 230,000 SF – Bluegrass ryegrass turf-type sod.

Page | 5

Labor, installation, materials, and equipment to be furnished and provided by the City:

• Boundary, control, and grading stakes for exact disturbance areas.

• Preparation of the spoils dump site on hole #11

• Seeding berm on hole #11

• All pre- and post-plant amendments and fertilizers.

The project will be a lump sum contract based on the approved dollar amount. Unit pricing will be used for any changes, not to exceed ±20% of the total lump sum contract amount, as directed by the City. The awarded contractor shall provide all labor and materials needed for the entire project unless otherwise specified.

The anticipated schedule for the project is to deliver the notice to proceed in mid-to-late January. The selected contractor can start anytime between January 15, 2026, and March 15, 2026, with a substantial completion date of May 1, 2026, and a final completion date of May 8, 2026.

1.3 Project Goals

The City’s objectives for delivery of the Project are as follows:

• The project includes all items shown and implied by the documents provided.

• The material and installation specifications must adhere to the City’s Schedule of

Values.

• The quantities listed in the Schedule of Values are estimated from the Contract

Drawings. The quantities provided are for the Contractor's general information and represent the main work items to be completed.

• The grading quantities provided by The City and calculations were based on the disturbance area at a 6-inch cut depth, then converted into cubic yards.

• No extra allowances will be given to the Contractor for additional earthwork they claim unless authorized through an approved Change Order.

• The Contractor shall be responsible for conducting all necessary survey work to complete the outlined tasks.

• Any work not properly located, graded for drainage, and finished may be ordered to be removed and replaced at the Contractor's expense.

• The Contractor is responsible for preserving and protecting all survey boundary and control stakes, and replacing, at their own cost, any damaged or destroyed stakes.

• Throughout these specifications, many handling and installation procedures, tools, equipment, and materials must receive approval from The City before being purchased.

• The Contractor shall, for one (1) year after the completion and acceptance of work, repair at their own expense any leaks or other failures in the irrigation system, or any deficiencies that arise in the golf course installation covered by this contract.

Page | 6

If the Contractor fails to make such repairs or adjustments, the Owner may do so and charge the Contractor for the cost.

1.4 Pre-Proposal Meeting

A recommended pre-proposal meeting will be held on Wednesday, November 5, 2025 @ 2:00pm (MST) at Broken Tee Golf Course, 2101 W Oxford Avenue, Englewood, CO 80110. Meet on the North side of the club house.

It is recommended a Contractor representative attend to understand the scope of services.

Questions raised and information provided during the pre-proposal meeting will be screened for applicability and responded to as necessary in an addendum. Oral statements may not be relied upon and will not be binding or legally effective.

Section 2 – Project Schedule and Milestones

2.1 Schedule

The City intends to proceed with comprehensive Drainage and Soil Remediation at Broken Tee Golf Course.

2.2 Project Milestones

These milestones represent the anticipated schedule for resource planning purposes and are subject to change.

Request for Proposals posted October 23, 2025 Recommended Pre-Proposal Meeting November 5, 2025 @ 2:00 pm Deadline for written questions November 7, 2025 @ 2:00 pm Proposal and fee submission due date November 20, 2025 @ 2:00 pm Anticipated Intent to Award December 2025

Section 3 – Scope of Work The Contractor will provide comprehensive labor, installation, materials and equipment as defined.

Page | 7

I. TECHNICAL SECTION – MOBILIZATION

a) This work involves mobilizing personnel, equipment, and supplies at the project site to prepare for construction. It also includes setting up the Contractor's offices, buildings, and other necessary facilities, along with all costs related to labor and operations.

b) The Equipment and Material Staging Area will be located in the back corner of the Broken Tee Clubhouse parking lot and is marked by the red circle on the Broken Tee overview map.

c) Additional equipment can be stored or staged near the entrance of the Golf Course Maintenance Facility, as indicated by the yellow circle on the Broken Tee Overview map.

II. TECHNICAL SECTION – UNDERGROUND DRAINAGE

a) The work covered by this Section of the Specifications consists of furnishing all materials, labor, and equipment for the installation of storm drainage systems, including catchments, culvert pipes, swales, diversion ditches, and perforated drainage pipe, complete in accordance with this Section of the Specifications and the applicable drawings. This work shall include grading, trenching, excavation, bedding, and backfill for all piping and drainage appurtenances.

b) Pipe and joint materials shown in the Plans and Schedule of Values will conform to the following minimum standards:

TYPE OF

PIPE

CLASS SPECIFICATION JOINTS

Corrugated Metal

16 Gauge Galvanized

AASHTO M136

AASHTO M190

AASHTO M136

AASHTO M190

Corrugated Aluminum

AASHTO M197 AASHTO M196

Polyvinyl chloride

(PVC)

Type 1, Grade 1

ASTM 1784

ASTM D3212

Corrugated Polyethylene

ASTM F-405

SCS Code 606 Couplers

Page | 8

Corrugated Polyethylene

Class III ASTM D-1248

AASHTO M252

AASHTO M294

c) Perforated drain tile as indicated shall be smooth-interior (dual-wall) polyethylene tubing.

d) Solid drain tile must be smooth-interior (dual-wall) polyethylene tubing.

e) Drain inlets shall be 12” with cast iron grates and installed as specified by the

Basin Detail that is provided.

f) Bends, elbows, tees, wyes, and other fittings shall meet the requirements of the specified type of pipe.

g) Flared end sections shall be made from the same materials as the specified pipe type. Details of fabrication and dimensions must be approved by the City before delivery to the job site.

h) Pipe bedding material for perforated drainage in greens, bunkers, and irrigated turf areas shall be 3/8" pea gravel (or an approved equivalent) for corrugated polyethylene pipe.

i) Perforated drain tubing shall be installed precisely to line and grade with the openings on the bottom, with a minimum slope of 1 percent unless directed otherwise in the field by the City.

j) Unless otherwise indicated on the Plans, culvert underdrains shall be installed on a leveling layer of pipe bedding material. The pipe shall be bedded and covered with pipe bedding material up to six (6) inches above the top of the pipe, where feasible.

k) Rock encountered within the excavation must be removed to a width equal to the outside diameter of the pipe plus 12 inches and to a depth of 6 inches below the pipe. Backfill, to the foundation elevation, can be made from approved material removed from elsewhere in the trench excavation.

l) All junctions and turns shall be constructed using wyes, tees, and bends made from the same material as the pipe.

m) The upslope ends of all underdrain pipes inside the green shall be sealed with appropriate plugs to prevent soil entry.

n) Openings in perforated PVC pipe must not exceed 1/2 inch. Pipes with larger openings will be rejected.

o) All underground utilities such as telephone, electric, water, gas, sanitary sewer, storm, tile, and drain lines, whether public or private mains or services, shall be repaired at no additional cost to the City if damaged by the Contractor.

p) All drains must be free of silt, debris buildup, or other obstructions and should be thoroughly flushed in the presence of the City.

Page | 9

q) General: The term excavation used hereinafter refers to unclassified excavation. All types of excavation, regardless of the material encountered within the project’s grading limits, shall be carried out according to the lines and grades specified by the City. Excess material from the excavation not needed for fill or backfill shall be disposed of on the site at locations designated by the City and shall be spread, shaped, or graded as directed. Excavation and backfilling shall be done in a manner and sequence that always ensures proper drainage. Grading shall be performed as needed to prevent surface water from flowing into trenches or other excavations, and any water that collects shall be pumped out or removed by other approved methods. Sheeting and shoring shall be installed as necessary to prevent surface water from entering trenches or excavations, and any accumulated water shall be removed by pumping or other approved techniques.

r) Trench excavation shall be done by open cut, and trenches shall be of the necessary width for proper pipe placement. The trench banks shall be as nearly vertical as practical. Care shall be taken not to over-excavate. No more trench length in any location shall be left open, in advance of the completed work, than is authorized or directed.

s) During excavation, materials suitable for backfilling shall be piled in an organized manner at a sufficient distance from the trench banks to prevent overloading.

t) Except as otherwise specified for wet or unstable material, backfill over depths shall be with the materials designated for filling the lower part of trenches.

When wet or unstable material is found at the bottom of the trench, as determined by the City, such material shall be removed to the required depth, and the trench backfilled to the proper grade with coarse sand, fine gravel, or other approved suitable material. Specific requirements related to particular utilities are as follows:

u) The width of the trench one foot above the top of the pipe must be such that the clear space between the pipe's barrel and the trench wall does not exceed eight inches on either side of the pipe. The width of the trench above that level should be as wide as necessary for sheeting and bracing to ensure proper work performance.

v) The bottom of the trenches shall be accurately graded to ensure uniform bearing and support for each section of the pipe on undisturbed soil throughout its entire length, except for the areas where excavation is necessary for proper sealing of the pipe joints, as specified hereafter. Depressions for joints shall be dug after grading the trench bottom, and to ensure the pipe rests on the prepared bottom along as much of its length as feasible, these depressions shall be only as long, deep, and wide as required for correctly assembling the specific type of joint.

Page | 10

w) Shoring shall be recovered in a way that prevents damage or disturbance to the work, and the excavation shall be free of forms and debris. Approved soil material shall be placed in layers no thicker than six (6) inches, unless otherwise specified, and compacted to match the density of the surrounding material. Each layer shall be spread evenly, moistened or dried by aeration when needed, to achieve the proper moisture content, and compacted uniformly using hand or machine tampers or other suitable equipment. Backfill shall be brought to final grade unless otherwise specified. Care shall be taken to avoid wedging or eccentric forces on or against any structure, and to prevent any disturbance or damage to the work.

x) Lower portion of trenches: Backfill material shall be placed in layers no thicker than six (6) inches and compacted with suitable tampers to reach a density of 90% as per AASHTO T-99, until there is a minimum cover of one (1) foot over the crown of the pipe or conduit. The backfill material in this part of the trench shall be composed of approved materials free from stones larger than three (3) inches in any dimension. However, where the pipe is coated or wrapped for corrosion protection, the backfill shall be free from stones larger than one (1) inch in any dimension.

y) Upper Portion of Trenches: The rest of the trench shall be backfilled with City-approved material that is free of stones larger than six (6) inches in any dimension. Backfill material under turfed or seeded areas shall be placed in layers no thicker than twelve (12) inches, and each layer shall be compacted to match the density of the surrounding undisturbed soil.

z) All lines shall be constructed true to line and grade as indicated. Trenching, excavation, bedding, and backfill shall be performed as specified herein before.

All pipes found to be defective or improperly laid shall be removed from construction, and the affected portion of the line shall be repaired to the satisfaction of the City at the Contractor's expense.

aa) Each pipe must be carefully inspected before installation, and any defective or damaged pipe must not be used. Adequate facilities should be available for lowering pipe sections into trenches. Pipe laying should progress upward, starting at the lower end of the pipeline. Under no circumstances should pipe be laid in water, and pipe should not be installed when trench conditions or weather are unsuitable. All pipes should be laid with the tongue end in the direction of flow.

bb) Perforated plastic pipe shall be installed to collect seepage water from areas where spring water has been exposed to the surface due to grading operations.

Excavations for trenches to hold the pipe shall start at the visible source of seepage and extend to locations designated by the City. Trenches must be at least three (3) feet deep and twelve (12) inches wide. A six (6) inch layer of pea gravel, similar to that used in green construction, shall be placed at the bottom of the trench before installing the pipe. The upper ends of the pipe shall

Page | 11 be closed off, and the trench shall be backfilled with gravel up to six (6) inches below the ground surface. Topsoil shall then be added to level the trench with the surrounding ground level.

cc) Instead of headwalls, pipe shall have flared end sections on both ends, meeting the requirements of the pipe type specified on the plans. These sections must be installed following the manufacturer's recommendations. Not all culvert or pipe runs need flared end sections.

dd) The invert of the swales shall be graded to a smooth and even grade to ensure a consistent flow of drainage with a minimum slope of one (1) percent, unless noted otherwise on the drawings. Side slopes shall be blended into existing contours to allow for proper mowing operations without scalping ridges or depressions. Material excavated from the swales shall be used as fill in adjacent areas or as directed by the City.

ee) The City shall require the Contractor to build diversion swales to prevent surface runoff from damaging tees, greens, bunkers, fairways, or other areas.

When needed, these swales will be designated by the City in the field. A change order will be necessary if this occurs.

ff) The Contractor shall take all necessary precautions to prevent any damage to existing trees, foliage, plant materials, and property outside the work areas.

gg) If the Contractor encounters material beneath the ground surface that prevents proper installation of the work as specified, he shall immediately notify the City before proceeding.

hh) All pipes and drains, at the time of final acceptance, must be free of silt, debris, or any obstructions.

III. TECHNICAL SECTION – SODDING

a) Sod must be turf type blue/rye approved by the City in writing prior to purchase.

b) The installed sod shall be cut at a height of no more than 2 inches at the time of installation.

c) Sod shall include a maximum of the top 1 inch of well-established cultured sod, primarily made up of live Kentucky Bluegrass varieties grown on loam soil, unless the City approves a different option. The sod must be free of noxious weeds, mostly free of all other weeds, and free of roots, stones, and other objectionable materials. It should withstand normal handling without breaking or tearing excessively.

d) Before cutting the sod, it shall be raked clear of debris, and the top growth shall be trimmed to the height specified in the Schedule of Values.

e) When the sod is cut, it should be moist enough to endure exposure and handling during transplanting. If needed, water the sod before cutting.

f) Water should be appropriate for irrigation and free of substances that could harm plants. Water will be supplied by the City.

Page | 12

g) Stakes used to hold the sod on slopes should be laths or shingles, 6 inches long and pointed. If this length does not provide a secure hold, a longer stake that can ensure a firm grip should be used.

h) The Contractor should understand that the finish grading of golf course construction is the most artistic and creative part of the work, and the Contractor must coordinate, cooperate, and work closely with the City to achieve the desired results.

i) The Contractor shall take all necessary precautions to prevent damage to drainage pipes, irrigation pipes, wiring, sprinkler heads, controllers, and underground valve boxes that are already installed. Any culverts or other pipes near haul roads should be ramped with sufficient earth fill if needed to prevent damage. If any damage occurs, it will be the Contractor's responsibility to repair it at his own expense.

j) All grades and contours previously established during the rough grading process will be preserved and refined. Any damage or disturbance to these grades or contours will be repaired by the Contractor.

k) The finish grading operation shall commence after the irrigation and major drainage work are completed in a specific area. The City will be notified beforehand so they can inspect all work up to that point and assist the Contractor in scheduling the finish grading.

l) Any area that has been compacted by vehicle traffic or by storing materials or equipment must be ripped, plowed, disked, and dragged to restore it to a workable, crumble-ready condition. Ripping, tilling, or otherwise loosened soil should reach a depth of 6 inches. This should be performed in at least two different directions to effectively break up the material and prevent water retention pockets in the subgrade.

m) The fairways shall be smoothed and floated using a tractor-drawn board, pipe drag, steel mat, soil surgeon, or an equivalent tool. All clods shall be thoroughly broken up, and all areas blended to match existing grades. This ensures that there are no spots that will hold water and that the surface is level enough so that a gang mower set at 1/2 inch in height will not scalp any area.

n) The Contractor shall supply a six-inch (6") topsoil layer for the areas designated on the plans to be sodded and tie-in the entire site to the existing grade.

o) If the topsoil cover has been disturbed or is less than an acceptable depth before seeding, the Contractor shall add topsoil to deficient areas to reach the minimum acceptable depth.

p) Topsoil shall be free of turf, weeds, rocks larger than one (1) inch in diameter within the top four (4) inches, concrete, roots, lime, cement, ashes, or other harmful materials, which shall be hauled to a designated area on site. Topsoil shall be natural, friable, fertile loam with characteristics of representative topsoil in the local area.

Page | 13

q) All holes, depressions, and rivulets must be filled and smoothed out. Any sticks, branches, stones, or debris on the surface that could interfere with sodding should be picked up and removed from the site.

r) The areas to be sodded shall be prepared until the soil is fully fined, mellow, at least two inches deep, disked, shaped to finish grade, and smoothed with a tractor-drawn board, pipe drag, steel mat, soil surgeon, or similar equipment.

All clods shall be thoroughly pulverized, and the entire area blended to the existing grades. This process will ensure that no spots hold water and that the surface is such that a gang mower set at 1/2 inch height will not scalp any area.

s) Areas around irrigation heads, controllers, drainage lines, caps, restricted zones near bunkers, and greens that cannot be mechanically prepared shall be manually raked and smoothed.

t) Precautions must be taken to prevent sod from drying out and from heating.

Sod that shows visible signs of heating shall not be used in the project.

u) Strips should be placed tightly against each other so that no open joints are visible. Sod should be placed without stretching.

v) Sod shall be watered and compressed into the underlying soil by rolling. The initial watering and rolling shall ensure firm contact and bonding between the sod and the soil beneath. The rolling shall produce a smooth, even surface free of humps and depressions, but shall not cause excessive compaction.

w) At the top of slopes, sod will be laid to prevent water from nearby areas from flowing freely onto greens or into bunkers, reducing silt contamination.

x) Sod adjacent to greens shall be lowered so that its top is level with the finished surface of the green. Sod that extends above the green surface will be removed by the Contractor and properly re-laid.

y) Before the finish grade and sod preparation are completed and before any grassing, the City shall be notified for inspection and approval.

IV. TOP DRESSING FOR GOLF FAIRWAY (CAPPING MATERIAL)

* 85% sand 10% Screened Topsoil 5% Comand Compost or approved equivalent.

* Mix material to be blended with Comand compost ¼” minus free of woody/bark and debris *Sand to be Athletic Sand with no more than 4% gravel retained in the #10 Sieve

Sand Material Specifications

Name Sieve Size U.S. Measure (mm)

Allowable Range

Retained Gravel 10 2.0 0% to 4%

Page | 14

Very Coarse 18 1.0 0% to 25% Coarse 35 0.5 30% to 35% Medium 60 0.25 20% to 30%

Fine 100 0.15 5% to 10% Very Fine 270 0.05 < 10%

Silt 0.002 < 5% Clay Less than 0.002 < or = 1%

USDA Agricultural Compost Class 2 TMECC

As Received

Basis Dry Matter

Basis

Method

Total Solids (%) 74.45 100.00 03.09-A Moisture (%) 25.55 0.00 03.09-A Organic Matter (%) 19.43 26.10 05.07-A Ash (%) 55.02 73.90 05.07-A Soluble Salts

1:5(MMHOS/CM) 7.77 - 04-10-A

PH 1:5 (Units) 6.81 - 04-11-A Total Nitrogen (%) 1.556 2.090 04.02-D Organic Nitrogen (%) 1.280 1.719 CALC Ammonia Nitrogen (%) 0.0079 0.011 04.02-C Ammonia Nitrogen (PPM) 78.7 105.8 04.02-C Nitrate Nitrogen (%) 0.2683 0.3603 04.02-B Nitrate Nitrogen (PPM) 2,682.7 3,603.5 04.02-B Total Phosphorus as P (%) 0.959 1.2882 04.03-A Total Phosphorus as P205 (%) 2.205 2.962 04.03-A

Total Potassium as K (%) 1.634 2.194 04.04-A Total Potassium as K20 (%) 1.960 2.633 04.04-A Carbon/Nitrogen Ratio 7 7 CALC Ammonia-N/Nitrate-N Ratio 0.0 0.0 CALC Sodium (%)

Page | 15

Additional Information

There is a 5% bid bond required for this project.

Each Bid shall be accompanied by an appropriate guarantee in the form of a Bid Bond, Certified Check or Cashier’s Check made payable to the City of Englewood in an amount of not less than 5% of the bid amount.

The awarded Contractor will be required to have ready and furnish a “Performance, Payment and Maintenance Bond” in the amount of 100% (copy attached) executed by a surety company acceptable to the City of Englewood within 10 days of Notice of Award.

Contractor Assistance: Any contractors needing support responding to solicitations may contact the Colorado Supplier Diversity Navigator at the Statewide Equity Office of Supplier Diversity Statewide Supplier Diversity Website. Services provided include assistance with responding to solicitations, interpretation of solicitation documents, technical assistance referrals, availability of resources, and bond assistance through the Construction Statewide Bond Assistance Program.

The office can be reached during normal business hours by calling 303-866-5765 or emailing DPA_SupplierDiversityHelp@state.co.us.

Sample Contract: a sample contract, which the City of Englewood intends to use with the successful contractor is attached to this RFP and identified as “Sample Contract”.

Exceptions to the contract should be identified, redlined and submitted with the contractor’s proposal. Proposed exceptions must not conflict with or attempt to preempt mandatory requirements.

City of Englewood Construction Use Tax and Arapahoe County Open Space Use Tax

Contractors and subcontractors who “build, construct or improve any building, dwelling or other structure or improvements to realty whatsoever” (Englewood Municipal Code) within the city are required to pay City of Englewood use tax and Arapahoe County Open Space use tax on any construction materials built into, incorporated or used on such projects, including building, constructing, or improving public infrastructure such as roads, sidewalks and government-owned buildings and facilities. City construction use tax and Arapahoe County Open Space use tax is collected on permits for construction materials that become part of such improvements to realty. Construction materials can be purchased exempt from city and county sales tax by providing a copy of the city building permit to suppliers. Subcontractors on projects should purchase construction materials in the same manner.

Contractors who apply for city permits are required to pay city use tax of 3.8% and county open space use tax of .25% on 50% of the contract value/price for improvements to

Page | 16 structures, and on 40% of the contract value/price of improvements other than to structures (roads, sidewalks, right-of-way improvements, for example).

Materials and supplies other than construction materials are subject to both state-collected and locally-collected retail sales taxes in effect at the place of purchase.

Examples include temporary fencing, tools, equipment purchased or rented for the project, cleaning and crew supplies and any other items that would normally be subject to regular retail sales taxes and used consumed/used by contractors and subcontractors.

Materials and supplies other than construction materials cannot be purchased exempt with a city-issued building permit.

Contractors and sub-contractors may be exempt from state-collected taxes (for example, State and RTD tax) when the material becomes part of the structure for a tax-exempt entity. The contractor must obtain an exemption certificate from the Department of Revenue to purchase the materials exempt from state-collected sales and use taxes. See https://tax.colorado.gov/sites/tax/files/documents/DR0172_2022.pdf for more detail.

Important Note: The tax-exempt status of a contractor’s customer – including the City of Englewood – does not flow through to contractors and subcontractors with respect to the payment of city and county use tax on construction materials. Contractors and subcontractors are the end-users and consumers of construction materials, and the Englewood Municipal Code clarifies that construction materials are subject to city and county use tax at the time city building permits are issued, regardless of the tax-exempt status of contractors’ customers.

Contractors and sub-contractors are required to keep records sufficient to verify that the correct amount of City use tax and Arapahoe County Open Space use tax was paid on construction materials used and consumed on permitted projects in the City. Records for permitted projects are required to be maintained for three years after the issue date of the Certificate of Occupancy and shall be made available to the City of Englewood for examination upon request.

See Englewood Municipal Code – Sections 4-4-2; 4-4-4-3; 4-4-5-1; 4-4-5-2; 4-4-5-3.

Liquidated Damages: Contractor shall pay the City $1,600 - $2,300 (dependent on final pricing as defined in the General Terms and Conditions) for each day that expires after the time specified for substantial completion until the work is complete, and $1,600.00 - $2,300 (dependent on final pricing as defined in the General Terms and Conditions) for each day that expires after the time specified for final completion until the work is finally complete. Liquidated damages will be finalized in the contract with the awarded contractor based on the final pricing per the General Terms and Conditions.

Supplemental Services

The City has, to the best of its knowledge, defined the scope and tasks to complete the work. The Contractor may propose, at its discretion, additional services beyond those

Page | 17 listed in this RFP that it feels are necessary to complete the work or add value to the project. Those additional services shall be included in the scope and fee as a stand-alone task under “Supplemental Services.” The City Project Manager must approve Supplemental Services before performing the work.

Contract Renewal The initial contract term will be for one year from the date of execution.

Section 4 – Proposal Submittal Requirements

4.1 Submittal Place and Deadline

The response must be received before the due date and time as specified in this RFP. It is the responsibility of the Contractor to ensure that electronic submittals are received prior to the closing time specified. Bids received after the date and time set for the Bid opening shall be considered non-responsive and returned un-opened to the Bidder.

Electronic submissions will only be accepted online the City of Englewood’s Online Procurement System, https://www.englewoodco.gov/government/city-departments/finance/solicitation-opportunities-awards Questions or technical difficulties should be directed to the websites’ Supplier Support Team support.ionwave@eunasolutions.com.

Submittals will be accepted until 2:00 PM on November 20, 2025.

The City of Englewood utilizes an Online Procurement System for all electronic solicitation submittals. It is the Contractor’s responsibility to ensure the submittal process is started with enough time to meet the 2:00pm deadline; for example: do not start the upload and submittal process at 1:50 pm with the expectation that your submittal will be received by the City prior to the 2:00pm deadline. If the Contractor experiences any problems, has questions or technical difficulties, PLEASE contact the Supplier Support Team, support.ionwave@eunasolutions.com. If the Supplier Support Team is unable to resolve the problem, contact the procurement agent (contact information in Introduction) by 1:45pm for a submittal resolution.

Proposals may be amended or withdrawn only by written notice prior to the Proposal opening. Amendments or withdrawals received after the Proposal opening will not be effective, and the original Proposal submitted will be considered. The Contractor agrees that its Proposal will not be withdrawn within ninety (90) calendar days following opening of the Proposals, and that during such time its Proposal will remain Contractor and irrevocable. The City reserves the right to reject any or all Proposals and to waive any technical defects in Proposals.

The City reserves the right to request clarification of information submitted and to request additional information of one or more Contractor after the Proposal Submission Due Date.

Page | 18

4.2 Submittal Format

Proposal submittals shall be clear, accurate, comprehensive, and provide specific and succinct answers to all questions and requests for information. Indirect, imprecise, or incomplete responses can serve only to the disadvantage of the proposer. Generic marketing material is discouraged. Excessive or irrelevant material will not be favorably received.

The Proposal must not exceed 10 total pages (8½ × 11 inch with 1-inch or greater margins; up to 2 pages of the total page count may be 11 x 17-inch tri-fold format; each double-sided counts as two pages), excluding the transmittal letter, index or table of contents, front and back covers, title pages/separation tabs, draft agreement acknowledgement form, and appendices.

A font similar in size to or larger than Calibri eleven-point (11-pt) shall be used.

4.3 Submittal Content

The content requirements set forth in this RFP represent the minimum content requirements for the Proposal. Additional information may be provided at Contractor’s discretion and within the available page count.

The Proposal must include, at a minimum, the following information:

• Transmittal Letter

• Company Information

• Part 1 – Experience and Technical Capability

• Part 2 – Project/Scope Understanding, Approach, and Implementation Schedule.

• Part 3 – Draft Agreement Review

• Part 4 – Schedule of Values

Transmittal Letter

Include a transmittal letter signed by an authorized representative of the Contractor who can commit the Contractor to the obligations required in the Draft Agreement. Place the transmittal letter on the Contractor’s letterhead and include the name, address, phone number, and e-mail address for the Contractor contact person. Specify who would be the Contractor’s signatory to any contract documents executed with the City. Include other information deemed relevant by the Contractor.

Proposals must be signed by an authorized corporate officer, principal, or partner (as applicable) with a signature in full. Contractors who are nonresident corporations shall furnish to the City a duly certified copy of their Articles of Incorporation from the State of Colorado Secretary of State Office along with the Proposal. Failure to promptly submit this evidence or qualification to do business in the State of Colorado may be basis for rejection of the Proposal.

The transmittal letter shall be limited to two (2) 8½ x 11-inch pages.

Page | 19

Part 1 – Contractor Experience and Technical Capability

Provide a description of the Contractor’s qualifications, experience, and technical capability. This shall include, at a minimum, the following elements:

• Provide an organizational chart for the Contractors project team, identifying all key personnel, the reporting hierarchy of staff and Contractor/Sub-Contractors, and the specific individuals responsible for coordination of the separate components of the work. Project team must include local personnel.

• Describe the roles, responsibilities, and availability of the key personnel who will be assigned to the Project.

• Identify all Sub-Contractors and describe their roles, and responsibilities. Identify the Sub-Contractors’ key personnel.

• Identify all subcontractors who will perform more than 10% of the total contract value, including their specific scope of work

Note: The identification and utilization of specific key personnel through the life of a project are important factors in the City's consideration and selection of a Contractor. Any changes in identified key personnel after the award of the Agreement must be approved by the City in writing before the change is made. Include availability of the project team to begin work as soon as possible after the selected Contract receives the Notice to Proceed.

Contractor Experience: Contractor experience refers to the demonstrated qualifications, expertise, and past performance of the vendor in providing Drainage and Soil Remediation. This includes:

• Proven experience implementing similar systems for organizations of comparable size and complexity.

• References from prior clients, preferably in the public sector or municipalities.

• Demonstrated success in delivering projects on time, within budget, and meeting performance expectations.

• Knowledge of best practices in Drainage and Soil Remediation.

Provide detailed information on the three (3) most applicable projects that have been substantially completed by the Contractors’ team members. Details shall include the following:

• Project title and contract number.

• Contractor and key personnel’s role in project.

• Owner contact information including phone number.

• Period of performance (contract start and end dates).

• Contract value.

• Summary of work performed.

• Project performance (including change order history, schedule adherence, and budget adherence).

Page | 20

• Describe any major issues or challenges presented on the project(s) and how they were resolved.

Note: Information demonstrating how the Contractor team’s key personnel have collaborated, performed, and resolved issues together on previous projects are important factors in the City's consideration and selection of a Contractor.

Key Personnel Experience: Describe specific relevant experience of each proposed key personnel providing similar details for projects as requested in Contractor Experience.

Reference Requirements: The City may contact the referenced individual(s) identified by the Contractors in Contractor Experience. The contact person(s) listed as a reference shall be someone who has personal knowledge of the Contractor’s performance during the referenced project. More than one person can be listed, but all must have knowledge of the project.

Part 2 – Project/Scope Understanding, Approach, and Anticipated Schedule

Provide a description of the Contractor’s approach to managing and delivering the scope of services contained in this RFP, and any additional issues and proposed strategies for meeting the City’s needs for the project based on Contractor’s understanding of the work, including:

• Provide a detailed project schedule showing the sequencing of drainage installation work on holes 1-6, including estimated durations for each hole's drainage work, coordination plans with golf course operations to minimize disruption to play, and specific contingency measures for weather delays while maintaining the May 8, 2026, final completion date.

• Describe your technical approach for excavating and removing unsuitable soils in active fairway areas without damaging existing irrigation lines, cart paths, or undisturbed turf, including specific equipment to be used, soil stockpiling locations, and methods for identifying and protecting existing underground utilities.

• Please provide a detailed explanation of your planned method to haul all existing soil to hole #11, including equipment and desired route.

• Explain your installation methodology for 4-inch smooth-interior dual-wall polyethylene perforated drainage pipe to achieve and maintain minimum 1% slope requirements, including survey equipment and personnel qualifications for grade

Page | 21 verification, pipe bedding procedures using washed 3/8" pea gravel, and quality control measures to prevent settlement.

• Detail your procedures for catch basin installation and modification on an active golf course, including methods for connecting to existing drainage systems, ensuring proper inverts and grades, preventing contamination during installation, and testing protocols to verify proper function before backfilling.

• Describe your finish grading techniques and equipment for achieving surfaces that can be mowed at 1/2-inch height without scalping, including methods for identifying and filling depressions that could hold water, equipment operators' experience with golf course finish grading, and procedures for blending new grades with existing contours.

• Provide your seedbed preparation method, including procedures for decompacting soils to a 6-inch depth where vehicle traffic has occurred, equipment for achieving proper soil tilth in the top 2 inches, rock removal procedures to ensure no rocks larger than 1 inch in diameter remain in the top 4 inches, and quality control measures to verify seedbed conditions before seeding.

• Describe your quality control program for ensuring drainage system functionality throughout construction, including procedures for verifying pipe grades before backfilling, preventing silt and debris accumulation in drainage lines, flushing and testing protocols before acceptance, and documentation methods for as-built conditions.

• Explain your erosion control measures during construction to prevent silt contamination of existing greens and bunkers, including specific materials and methods for protecting work areas during rain events, procedures for maintaining drainage swales during construction, and restoration plans for any erosion damage.

• Detail your warranty service capabilities for the one-year maintenance period, including response time for emergency repairs, personnel assigned to warranty work, procedures for cleaning screens, valves, vault boxes during the first 30 days, and bonding/insurance provisions to guarantee warranty performance.

• Provide your experience with coordinating work around active golf course irrigation systems, including methods for locating and marking existing irrigation lines and heads, protection measures during excavation, procedures for repairing any irrigation damage, and coordination with golf course maintenance staff for system shutdowns.

Page | 22

• Describe your capacity to complete all specified work within the compressed timeline, including the number of crews available for simultaneous operations, the equipment fleet available for the project period, the ability to increase resources if weather delays occur, and current project commitments that might affect your availability during the February to May 2026 timeframe.

• Detail your procedures for protecting existing trees designated to remain, including methods for working within branch spreads without damaging roots over 2 inches in diameter, equipment restrictions near protected trees, and your proposed penalty acceptance for any trees damaged beyond repair during construction.

• Describe your specialized equipment and techniques for working on championship golf course fairways, including low ground pressure equipment to minimize turf damage, methods for maintaining haul roads without damaging underlying drainage or irrigation, and restoration procedures for any areas damaged by construction traffic.

Part 3 – Draft Agreement Review

The Contractor understands that neither this RFP nor the Proposal shall constitute a contract with the City. No contract is binding or official until Proposals are reviewed and accepted by appointed City staff; approved through the appropriate levels of authority within the City; and an official contract is duly executed by the City.

Attachment A (Draft Agreement) of this RFP contains the proposed Contract for Construction for the Project. Proposers shall review this draft document and provide comments regarding any aspect of such document about which it has any concern, including terms that it considers ambiguous or which it believes should be modified. Such comments shall be submitted with the Proposal. The City will review all comments received and, if it deems appropriate, in its sole discretion, may modify such document.

The Draft Agreement included in the RFP is the form upon which Contractors shall base their Proposal. The comments submitted on the draft agreement will not be counted in the total page count specified above.

Part 4 - Price Proposal

A font similar in size to or larger than Calibri eleven-point (11-pt) must be used for the Price Proposal.

• Schedule of Values submitted with proposal

• Explain your understanding of the unit price contract structure and how you will track, and document actual quantities installed for payment purposes, including

Page | 23 survey methods for measuring excavation volumes, documentation procedures for installed drainage footage, and dispute resolution processes for quantity disagreements.

Appendix A – Key Personnel Resumes

Provide key personnel resumes for project team.