RFP 25_014 Storm Drainage Improvements 1st Av.pdf

PDF 125 KB Posted

Attached to
RFP 25-014 Storm Drainage Improvements 1st Ave.
Solicitation number
PE-69754-NONST-2025-000000009
Issued by
Miller County, Georgia

About this file

This is an Invitation to Bid document issued by the City of Thomson, Georgia for the First Avenue Storm Drainage Improvements project (EPA CG-02D52423-0), prepared by Civil Design Solutions, L.L.C. The project scope includes removal and disposal of existing storm piping and structures, installation of approximately 750 linear feet of various size storm drain pipe including structures, construction of two stormwater detention ponds, and approximately 1,400 square yards of 1.5-inch asphalt milling and inlay. Additional work includes traffic control, clearing, earthwork, dewatering, grassing, and soil erosion and sediment controls. Sealed bids will be received until 10:00 AM on December 10th, 2025 at the Thomson-McDuffie Government Center, 210 Railroad Street, 2nd Floor, Thomson, Georgia 30824, at which time bids will be publicly opened and read aloud. The contract will be awarded as a single contract, and all work must be completed within one hundred eighty calendar days. Complete plans, specifications, and contract documents are available from Civil Design Solutions, L.L.C., 371 Main Street, Warrenton, Georgia 30828, for $100 per set (non-refundable).

Bidders must submit a bid bond or certified cashier's check in an amount not less than 10 percent of the base bid from a surety company licensed in Georgia with an "A" minimum rating. The successful bidder will be required to provide performance and payment bonds each equal to 100 percent of the contract price. All contractors performing utility contracting work must be licensed by the State of Georgia as a "Utility Contractor" and must employ a "Utility Manager" certification holder to oversee the work. Contractors must be registered with E-Verify and comply with O.C.G.A. 13-10-91 requirements for work authorization. The project is subject to Build America, Buy America Act requirements, mandating that all iron, steel, manufactured products, and construction materials be produced in the United States. Funding is provided through a grant administered by the U.S. Environmental Protection Agency. A Land Disturbing Permit is currently submitted but not yet approved. Portions of the project are located on privately owned property and will require easements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Thomson – First Avenue Drainage Improvements – EPA CG-02D52423-0

Contract Documents & Technical Specifications

Civil Design Solutions, L.L.C. 00100-1 Proj. No. 23-038

INVITATION TO BID

PART 1 - GENERAL

1.1 SEALED BIDS

Sealed bids for construction of the City of Thomson Project No. EPA CG-02D52423-0, First Avenue Storm Drainage Improvements, will be received until 10:00 AM on Friday, November 7th, 2025_ at the Thomson-McDuffie Government Center, 210 Railroad Street, 2nd Floor, Thomson, Georgia 30824, at which time and place they will be publicly opened and read aloud. Any proposal received after said time and date will not be considered by the Owner. No bid may be withdrawn after the closing time for the receipt of bids for a period of sixty (60) days.

1.2 SCOPE OF WORK

The work shall consist of, but not be limited to, furnishing all products and performing all labor necessary to perform the following construction work along First Ave and Church Street:

Removal and disposal of existing storm piping and structures. Installation of approximately 750 L.F. of various size storm drain pipe including structures. Construction of 2 stormwater detention ponds. Approximately 1,400 s.y of 1.5” asphalt milling and inlay. Also included, but not limited to, in this project are all associated items such as: traffic control, clearing, earthwork, dewatering, grassing, soil erosion and sediment controls, and any associated appurtenances.

Time allotted for completion of work is one hundred eighty (180) calendar days. All Work shall be completed in accordance with the plans and specifications. The Work will be awarded in one (1) Contract.

1.3 PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS

Plans, Specifications and Contract Documents are on file at Civil Design Solutions, L.L.C. in Warrenton, Georgia. Copies may be obtained from Civil Design Solutions, L.L.C., 371 Main Street, Warrenton, Georgia 30828, Phone: (706) 465-0900, Fax: (706) 465-0909, upon payment of $100 for each full-size set (non-refundable).

1.4 CONTRACTOR AFFIDAVIT REQUIREMENT

All bidders who will be engaged in the physical performance of services on behalf of The City of Thomson must be registered with, authorized by, and use the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91.

Furthermore, the contractor will be required to continue to use the federal work authorization program throughout the contract period and the contractor will contract for the physical performance of services in satisfaction of such contract only with subcontractors who present

Civil Design Solutions, L.L.C. 00100-2 an affidavit to the contractor with the information required by O.C.G.A. § 13-10-91(b).

1.5 CONTRACTOR LICENSE

The Scope of Work as described herein is defined as “utility contracting” in accordance with O.C.G.A 43-14-2(17) so the Contractor performing the work must provide proof of a valid license by the State of Georgia as a “Utility Contractor” and must also employ a “Utility Manager” certification holder who will have oversight of all the work. Therefore, the Contractor submitting a bid must list the license number of the Contractor(s) performing the utility contracting on the Bid Form and provide proof of a valid license and the license number shall also be written on the face of the bid envelope. See Instruction to Bidders for additional bidding requirements.

1.6 BONDS

Bids shall be accompanied by a bid bond or certified cashier’s check in an amount not less than 10% of the base bid. All bonds shall be by a surety company licensed in Georgia with an “A” minimum rating of performance and a financial strength of at least five (5) times the contract price as listed in the most current publication of “Best’s Key Rating Guide Property Liability”. Performance and Payment Bonds, each in an amount equal to 100% of the contract price shall be required of the successful bidder if contract is awarded. Each Bond shall be accompanied by a “Power of Attorney” authorizing the attorney-in-fact to bind the surety and certified to include the date of the bond.

1.7 PERMITS

The status of Federal, State and /or local permits for this project are as follows:

Permits Status A. Land Disturbing Permit Submitted – Not Approved B. NPDES GAR 100001 (Stormwater) < 1 Acre Dist. – Not Required C. Stream Buffer Variance Not Required D. GA DOT Utility Facility Encroachment Not Required E. Building Permit Not Required

1.8 RIGHTS-OF-WAY AND EASEMENTS

Portions of this project are located on privately owned property. Easements will be required for this project.

1.9 RESERVATION OF RIGHTS

Owner reserves the right to reject any or all Bids, including without limitation, the rights to reject any or all nonconforming, non-responsive, unbalanced or conditional Bids and to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by the Owner.

Civil Design Solutions, L.L.C. 00100-3

1.10 BUILD AMERICA, BUY AMERICA ACT (BABAA)

This agreement is for services related to a project that is subject to the Build America, Buy America Act (BABAA) requirements under Title IX of the Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. 177-58. Absent an approved waiver, all iron, steel, manufactured products, and construction materials used in this project must be produced in the United States, as further outlined by the Office of Management and Budget’s Memorandum M-22- 11, Initial Implementation Guidance on Application of Buy America Preference in Federal Financial Assistance Programs for Infrastructure, April 18,2022.

1.11 FUNDING SOURCES

Funding shall be provided through a Grant as administered by the US Environmental Protection Agency.

CITY OF THOMSON

OWNER

END OF SECTION

File details come from the government source that posted it. Updated .