RFP 2027-0002 Track Replacement Resurfacing Project.pdf

PDF 596 KB Posted

Attached to
RFP #2027-0002 Track Replacement Resurfacing Project
Solicitation number
2027-0002
Issued by
Tolland County, Connecticut

About this file

Summary

This Request for Proposals (RFP) document is issued by Plainfield Board of Education, a Connecticut public school district, soliciting sealed bids from qualified athletic-surface contractors for the renovation of the existing running track at Plainfield High School located at 105 Putnam Road, Plainfield, Connecticut. The project scope includes removal of the existing synthetic track surface, reconstruction of the asphalt base, installation of a porous polyurethane track system suitable for interscholastic competition, and installation of NFHS-compliant certified line markings with project management by an ASBA Certified Track Builder or equivalent credential. The RFP was issued on November 9, 2026, with an optional pre-proposal site meeting scheduled for November 23, 2026, at 1:00 p.m. The deadline for written questions is November 25, 2026, with district responses issued by December 3, 2026. Sealed bids are due on December 7, 2026, at 11:00 a.m. EST with public opening immediately following. Award is anticipated in December 2026. Proposal prices must remain firm for at least thirty days after the proposal opening unless a longer period is specified by the proposer. Two hard copies of complete proposals must be submitted to Plainfield Public Schools, 234 Shepard Hill Road, Plainfield, CT 06374, addressed to Superintendent Paul M. Brenton.

The base bid must be a firm, lump-sum price for the complete scope of work, with proposers responsible for independently developing costs. The district will allocate permit costs and may negotiate whether permits are obtained and paid by the owner or contractor; proposers must separately identify permit-related costs if applicable. Contractor qualifications must demonstrate relevant experience with at least three comparable running track projects completed within the last five years, preferably for public schools or municipalities, along with three owner references and evidence of financial capability and bonding capacity. Contractors must maintain comprehensive insurance coverage including $1,000,000 Commercial General Liability per occurrence, $1,000,000 Automobile Liability combined single limit, statutory Workers' Compensation, and $4,000,000 Umbrella/Excess Liability per occurrence, with a 100% Bid/Performance Bond required. Evaluation criteria include total base bid value, technical scope responsiveness, track system quality, experience with comparable public projects, qualifications of key personnel, references and past performance, proposed construction schedule, warranty terms, financial capacity, exceptions and exclusions, and any litigation or safety history. The district reserves the right to waive informalities, reject any proposals, negotiate with proposers, or make no award, as it determines to be in the best interest of Plainfield Public Schools.

View the file

Other files

File Type Posted
2027-0002_Nov_16_26_solicitation_doc.pdf PDF
2027-0002_Nov_13_26_solicitation_doc.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PLAINFIELD BOARD OF EDUCATION

Running Track Replacement/Resurfacing Project Bid #: 2027-0002

1. PROJECT OVERVIEW

Plainfield Public Schools (the “District” or “Board”) is soliciting sealed proposals from qualified athletic-surface contractors for the renovation of the existing running track at Plainfield High School, 105 Putnam Road, Plainfield, Connecticut. The work is intended to provide a complete, durable, competition-ready running track system, including removal of the existing synthetic surface, reconstruction of the asphalt base, installation of a porous polyurethane track system, and certified line markings.

2. PROJECT OBJECTIVES

Replace the existing track surface and reconstruct the underlying asphalt base within the existing track, high jump, and long jump footprints.

Provide a high-quality porous polyurethane paved mat structural spray track system suitable for interscholastic competition.

Provide NFHS-compliant/certified track line markings and an “as-built” striping layout drawing.

Complete the work with qualified supervision, including project management by an ASBA Certified Track Builder (CTB) or equivalent demonstrated credential.

Protect surrounding facilities and restore lawn or other areas disturbed by construction operations.

3. PROCUREMENT SCHEDULE

Milestone Date / Time

RFP Issued / Specifications Available November 9, 2026

Optional Pre-Proposal Site Meeting at PHS Track November 23, 2026 at 1:00 p.m.

Deadline for Written Questions November 25, 2026

District response / addenda issued December 3, 2026

Sealed Bids Due December 7, 2026 at 11:00 a.m. EST

Public Opening of Bids December 7, 2026 at 11:00 a.m. EST

Anticipated award December 2026

4. CONTACT AND QUESTIONS

All communications concerning this RFP shall be directed to the District contact designated below.

Proposers shall not contact Board members, school staff, consultants, or other District personnel regarding this procurement except as authorized in writing.

District Contact: Mrs. Courtney Brannon Title: Business Manager Email: BrannonC@plainfieldschools.org Telephone: (860) 564-6400

Questions shall be submitted in writing by the deadline stated in the Procurement Schedule. Responses that materially affect the RFP will be issued by written addendum and made available to all known prospective proposers.

5. PROPOSAL SUBMISSION REQUIREMENTS

The District will receive sealed proposals for the project in accordance with the schedule above. Late proposals will not be considered and may be returned unopened. The proposer assumes the risk of any delivery delay.

Submit two (2) hard copies of the complete proposal, unless the District specifies a different number before release.

Place proposals in a sealed envelope or package clearly marked “PLAINFIELD HIGH SCHOOL

TRACK REPLACEMENT / RESURFACING PROJECT – RFP #2027-0002.”

Include the proposer’s legal name and return address on the outside of the package.

Deliver proposals to: Plainfield Public Schools, 234 Shepard Hill Road, Plainfield, CT 06374, Attention: Paul M. Brenton, Superintendent.

Proposal prices shall remain firm for at least thirty (30) business days after the proposal opening unless a longer period is stated by the proposer and accepted by the District.

No oral, telephonic, emailed, or facsimile proposal will be accepted unless the District issues a written addendum expressly permitting electronic submission.

6. LEGAL AND COMPLIANCE

Freedom of Information Act: All information submitted in a bid is subject to disclosure under the Connecticut Freedom of Information Act.

Non-collusion: By submitting a bid, each bidder certifies under penalty of perjury that the prices in this bid have been arrived at independently, without collusion.

Affirmative Action: The Contractor is an Equal Opportunity Employer and shall comply with all applicable federal and state laws regarding affirmative action and equal employment opportunity.

7. ACCEPTANCE OR REJECTION OF PROPOSALS

Plainfield Public Schools reserves the right to waive informalities or technical defects; reject any or all proposals, in whole or in part; request clarification; negotiate with one or more proposers when permitted; and make an award, or make no award, as determined to be in the best interest of the District and Board. The District is not obligated to accept the lowest-priced proposal.

8. TECHNICAL SCOPE OF WORK

The successful Contractor shall furnish all labor, supervision, equipment, materials, transportation, disposal, overhead, taxes, profit, and incidentals necessary for a complete project, except for items specifically identified as Owner-provided or excluded. The base scope shall include, at minimum, the following:

A. Remove and legally dispose of the existing synthetic track surface.

B. Pulverize the existing asphalt with a traveling hammermill to approximately eight (8) inches deep at the track, high jump, and long jump areas. The landing pit is to remain. The existing asphalt has been represented as approximately three (3) inches thick; proposer shall verify field conditions.

C. Blend reclaimed pulverized asphalt with the existing gravel base and remove excess material from the site as required.

D. Rough grade and compact the base.

E. Laser grade and compact the base using equipment capable of grading track turns to ASBA tolerances. The reference proposal assumes a one percent (1%) cross slope toward the infield;

proposer shall identify any recommended or required adjustment.

F. Install a new three and one-half inch (3.5") asphalt base at the existing track, high jump, and long jump areas, in two lifts, with the footprint to remain substantially as existing unless otherwise approved in writing by the District.

G. Install a BSS-100 polyurethane paved mat structural spray system manufactured by Beynon Sports Surfaces, or an approved equal meeting or exceeding the performance characteristics of the specified system. Any proposed equal shall be clearly identified with technical data sufficient for evaluation.

H. Install NFHS-compliant/certified line markings for the completed track and event areas.

I. Restore lawn and other areas disturbed or damaged by construction equipment or access operations.

J. Provide project management by an ASBA Certified Track Builder (CTB), or provide documentation of equivalent qualifications acceptable to the District.

K. Provide an “as-built” layout drawing for striping and event markings at project closeout.

L. Maintain safe access, barricades, housekeeping, debris control, and protection of adjacent school facilities throughout construction.

9. OWNER-PROVIDED ITEMS / BASE BID EXCLUSIONS

For purposes of proposal comparability, the following allocation is based on the reference scope.

Proposers shall identify any exception or additional exclusion in the Proposal Form.

Owner will provide reasonable access for construction trucks and equipment.

Local permits are not included in the reference contractor price. The District shall confirm before award whether permits will be obtained/paid by the Owner or Contractor. Proposers shall separately identify permit-related costs if applicable.

Permanent fencing is excluded, except temporary removal/reinstallation or access work necessary for a construction entrance, unless otherwise included by the proposer.

Any work not expressly included in the proposer’s base bid must be listed as an exclusion; silence will be interpreted as inclusion when the work is reasonably necessary for a complete installation.

10. SITE CONDITIONS AND FIELD VERIFICATION

Each proposer is responsible for becoming familiar with the site and existing conditions before submitting a proposal. Dimensions, pavement thicknesses, grades, drainage conditions, access constraints, utility locations, and other field conditions shall be verified by the proposer to the extent necessary to prepare a complete proposal. Any material discrepancy or condition that could affect price or performance shall be raised during the question period.

11. MATERIALS, QUALITY, AND STANDARDS

Track surfacing shall be an IAAF/World Athletics-certified or equivalent system appropriate for the intended interscholastic use and consistent with the specified BSS-100 system or approved equal.

Line markings shall comply with applicable NFHS requirements and be installed by experienced track-layout personnel.

Asphalt, aggregate, polyurethane components, adhesives, coatings, and markings shall be new and suitable for their intended use.

Workmanship shall meet accepted industry practice and applicable ASBA tolerances and guidance.

The Contractor shall comply with applicable federal, State of Connecticut, local laws, codes, regulations, and District policies affecting the work.

12. PROJECT SCHEDULE

Each proposer shall provide its earliest available mobilization date, anticipated duration, substantial completion date, and final completion date. The successful Contractor shall coordinate all work with the District to minimize disruption to school and athletic operations.

13. WARRANTY AND CLOSEOUT

Each proposer shall state all manufacturer and contractor warranties applicable to the asphalt base, track system, coatings, markings, and workmanship. At closeout, the successful Contractor shall provide warranty documents, product data, maintenance recommendations, the as-built striping/layout drawing, final lien releases as applicable, and any other closeout documentation required by the District.

14. CONTRACTOR QUALIFICATIONS

Proposals shall demonstrate that the proposer is qualified, experienced, financially capable, and properly staffed to complete the project. At minimum, include:

Legal company name, address, telephone number, and primary contact.

Years in business and years of experience constructing or renovating synthetic running tracks.

At least three (3) comparable running track projects completed within the last five (5) years, preferably for public schools, municipalities, colleges, or similar public entities.

Three (3) owner references with contact name, telephone number, email address, project name, project value, and completion date.

Name and resume/qualifications of the proposed project manager and ASBA Certified Track Builder (CTB), if applicable.

List of major subcontractors and the portions of work they will perform.

Disclosure of pending litigation, claims, debarment, suspension, or other proceedings that could materially affect performance of the contract; state “None” if none.

Evidence of ability to obtain required insurance and any bid/performance/payment bonds required by the final RFP.

15. GENERAL CONDITIONS

A. All proposals must conform to the requirements of this RFP and all written addenda. Failure to comply may result in rejection.

B. The successful Contractor shall enter into a written contract with the District. The RFP, addenda, accepted proposal, negotiated clarifications, and required bonds/insurance may be incorporated into the final contract.

C. The Contractor shall not assign, transfer, or subcontract material obligations without prior written approval of the District. Approval of a subcontractor does not relieve the Contractor of responsibility for the work.

D. The Contractor shall be responsible for supervision, safety, means and methods, protection of persons and property, site housekeeping, and compliance with applicable laws and regulations.

E. The Contractor shall promptly report accidents, property damage, or safety incidents arising from the work to the District’s designated representative.

F. The District may inspect the work and reject work or materials that do not conform to the contract requirements.

G. Changes in the scope or contract price shall be authorized only by written change order or other written authorization issued by the District.

H. The Contractor shall maintain accurate records supporting applications for payment, changes, allowances, and reimbursable items, if any.

I. The Contractor shall be responsible for taxes, fees, licenses, and similar costs applicable to its business and work, except items expressly identified as Owner responsibilities.

J. The District may require background checks, site access controls, or conduct requirements for personnel working on school property. Contractor personnel shall comply with District safety and security procedures.

16. DEFAULT AND TERMINATION

If the Contractor fails to provide the required level or quality of work, fails to meet an agreed schedule without approved cause, abandons the work, becomes insolvent, fails to maintain required insurance or bonds, improperly assigns or subcontracts the work, or otherwise materially breaches the contract, the District may provide written notice and a reasonable opportunity to cure when appropriate. If the default is not cured, the District may terminate the contract and pursue any remedies available under the contract or law. The Contractor and its surety, if applicable, may be responsible for reasonable costs, losses, and damages incurred by the District as a result of the default.

17. FORCE MAJEURE

Neither party shall be liable for delay caused by events beyond its reasonable control, such as severe weather, catastrophe, fire, epidemic/pandemic, governmental order, war, riot, strike, or similar event, provided the affected party gives prompt notice and uses reasonable efforts to mitigate delay. The parties shall cooperate in good faith to revise the project schedule when warranted.

18. INDEMNIFICATION AND INSURANCE

Refer to Appendix G for specific insurance requirements to be referenced on the Certificate of Insurance

19. PAYMENT

The reference proposal provides for a 15% deposit upon acceptance, followed by payments based on an agreed schedule of values and completion of scheduled items on a bi-monthly basis, with the balance due upon completion. The District may accept, reject, or negotiate this payment structure in the final contract. The proposer shall submit a proposed schedule of values and payment schedule with its proposal. Payment will be conditioned on satisfactory progress, proper invoices/applications for payment, and any required lien waivers or closeout documentation.

20. PRICE BASIS

The Base Bid shall be a firm, lump-sum price for the complete scope described in this RFP, subject only to approved alternates, allowances, unit prices, or written change orders. Each proposer is responsible for independently developing its price.

21. EVALUATION AND AWARD

The District intends to award the contract to the responsible proposer whose proposal is determined to be in the best interest of Plainfield Public Schools. Evaluation may include the following factors, not necessarily in order of importance:

Total Base Bid and overall value to the District.

Responsiveness to the required technical scope and completeness of proposal.

Quality and suitability of the proposed track system and materials.

Experience with comparable public-school or municipal track projects.

Qualifications of the project manager, Certified Track Builder, and key personnel.

References and past performance, including schedule, quality, warranty response, and change-order history.

Proposed construction schedule and ability to meet the District’s required completion date.

Warranty terms and post-installation service.

Financial capacity, bonding capacity (if required), and insurance capability.

Exceptions, exclusions, proposed substitutions, and risk to the District.

Any litigation, claims, safety history, debarment, or other matters relevant to reliable performance.

Any other factor the District reasonably determines to be in its best interest.

22. PROPOSAL CONTENT / REQUIRED SUBMITTALS

Organize the proposal in the following order:

A. Signed Proposal Certification and Contractor Information form.

B. Completed Base Bid / Pricing Form, including alternates, allowances, unit prices, and exclusions.

C. Detailed technical proposal identifying the track system, manufacturer, thickness/build-up, and all proposed substitutions or equals.

D. Project schedule with mobilization, major work activities, curing periods, striping, substantial completion, and final completion.

E. Company qualifications and comparable-project experience.

F. Project team resumes and Certified Track Builder credentials.

G. Three owner references for comparable work.

H. List of subcontractors and suppliers.

I. Warranty information.

J. Insurance and bonding capability documentation, as required by the final RFP.

K. Completed Good Faith / Compliance Certification.

L. Disclosure of exceptions, exclusions, litigation, debarment, or conflicts of interest.

M. Acknowledgment of all addenda.

APPENDIX A – PROPOSAL CERTIFICATION & CONTRACTOR INFORMATION

The Contractor has read and understood the Proposal Documents, including all appendices and addenda, and the Proposal conforms to the terms and conditions of the Proposal Documents except for exceptions expressly identified in writing.

I hereby certify, as an authorized officer/representative of the company named below, that all information and material supplied to the District in connection with this proposal are complete and true to the best of my knowledge. I understand that material misrepresentation or an attempt to mislead the District may result in disqualification or termination of any resulting contract.

Company: ____________________________

Address: ____________________________

City / State / ZIP: ____________________________

Telephone: ____________________________

Email: ____________________________

Authorized Representative: ____________________________

Title: ____________________________

Signature: ____________________________

Date: ____________________________

Notary Public / Seal (if required by District): ____________________________

APPENDIX B - BASE BID / PRICING FORM

Project: Plainfield High School Running Track Replacement / Resurfacing Project Location: 105 Putnam Road, Plainfield, CT 06374

Item Description Amount 1 Base Bid - complete scope of work $________________

Permit allowance / permit cost, if Contractor-paid

Alternate / Add:

Alternate / Deduct:

Other:

TOTAL PROPOSAL (as applicable): $____________________________

Base Bid written in words: ______________________________________________________________

Proposed Track System / Manufacturer: __________________________________________________

Proposed mobilization date: __________________ Substantial completion: __________________

Number of calendar days from Notice to Proceed to substantial completion: ______________

Contractor warranty: __________________________ Manufacturer warranty: __________________

Exceptions / exclusions / clarifications (attach additional sheets if necessary):

Acknowledgment of Addenda: No. ______ Date ______ No. ______ Date ______ No. ______ Date ______

AFFIRMATIVE ACTION/EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION

In compliance with federal and state laws, regulations, and executive orders relating to equal employment opportunity and affirmative action, the undersigned certifies the following:

1. The Contractor is an Equal Opportunity Employer and does not discriminate in employment on the basis of race, color, religion, sex, sexual orientation, gender identity or expression, national origin, ancestry, age, disability, marital status, veteran status, or any other protected classification.

2. The Contractor shall take affirmative action to ensure that applicants are employed, and employees are treated during employment, without regard to the above characteristics.

3. The Contractor agrees to provide documentation of its affirmative action and equal employment opportunity practices upon request.

Contractor Information

Company Name: ________________________________________________

Address: _______________________________________________________

City / State / ZIP: _______________________________________________

Telephone: ___________________

Email: ___________________________

Authorized Representative: _______________________________________

Title: __________________________________________________________

Signature: ____________________________________ Date: ____________

Submit this signed certification with your bid or proposal.

Failure to include this document may render the submission non-responsive.

APPENDIX C - COMPARABLE PROJECTS & REFERENCES

REFERENCE 1

Owner / Agency: ____________________________

Project Name / Location: ____________________________

Scope of Work: ____________________________

Contract Value: ____________________________

Completion Date: ____________________________

Contact Person: ____________________________

Telephone: ____________________________

Email: ____________________________

REFERENCE 2

Owner / Agency: ____________________________

Project Name / Location: ____________________________

Scope of Work: ____________________________

Contract Value: ____________________________

Completion Date: ____________________________

Contact Person: ____________________________

REFERENCE 3

Owner / Agency: ____________________________

Project Name / Location: ____________________________

Scope of Work: ____________________________

Contract Value: ____________________________

Completion Date: ____________________________

Contact Person: ____________________________

APPENDIX D - PROJECT TEAM & SUBCONTRACTORS

Project Manager: __________________________________ Years with Firm: __________

ASBA Certified Track Builder (CTB): ______________________________ Credential No.: __________

Site Superintendent / Foreperson: ________________________________________________

Attach resumes and credentials for key personnel.

Subcontractor / Supplier Work / Material Approx. % of Contract

APPENDIX E - GOOD FAITH / COMPLIANCE CERTIFICATION

The undersigned, as an authorized signer for the Contractor, certifies to the best of their knowledge that:

1. No consultant, subcontractor, employee, or representative of the Contractor has given, offered, or agreed to give any improper gift, contribution, employment offer, or other inducement in connection with the award of this contract.

2. No person or entity, other than a bona fide employee or disclosed representative, has been retained on a contingent-fee basis to improperly influence the award of this contract.

3. The Contractor will comply with applicable Connecticut General Statutes and federal, state, and local nondiscrimination requirements.

4. The Contractor is not presently debarred, suspended, or otherwise prohibited from contracting by a federal, state, or local agency. If that status changes during the procurement or contract term, the Contractor will notify the District promptly.

5. This proposal is made in good faith, without fraud or collusion with any other proposer for the same work.

6. The Contractor has complied, and will continue to comply, with applicable tax, employment reporting, withholding, and other legal obligations relevant to the work.

Company: ____________________________

Authorized Representative: ____________________________

Title: ____________________________

Signature: ____________________________

Date: ____________________________

APPENDIX F - DISCLOSURES / EXCEPTIONS

Pending lawsuits, claims, administrative proceedings, or other matters that could interfere with performance of the contract (state “None” if none):

Exceptions to RFP requirements, proposed substitutions, or requested contract modifications (state “None” if none):

APPENDIX G – INSURANCE REQUIREMENTS

The School District expects each vendor to include its appropriate purchase documents in its Proposal for consideration by the School District. The following terms and conditions shall be included or incorporated into any purchase document between the School District and the selected vendor. Notwithstanding the foregoing, in the School District’s sole discretion, the required contract language may be subject to negotiation if, for example, the School District believes the Contractor’s bid includes more favorable language. For purposes of these provisions, “Contractor” means the successful vendor; and “Agreement” means the contractual document entered into between the School District and the successful vendor.

1. Insurance.

General Conditions: Within ten (10) business days of the award or notice, or prior to the start of work, whichever comes first, the contractor will provide, pay for, and maintain in full force and effect the insurance outlined here for coverage’s at not less than the prescribed minimum limits of liability. Such coverage is to remain in force during the life of the contract and for such additional time as may be required, and will cover the contractor’s activities, those of any and all subcontractors, or anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable.

A. Certificates of Insurance: The contractor will give the owner a certificate of insurance completed by a duly authorized representative of their insurer certifying that at least the minimum coverage’s required here are in effect and specifying that the liability coverage’s are written on an occurrence form and that the coverage’s will not be canceled, non-renewed, or materially changed by endorsement or through issuance of other policy(ies) of insurance without thirty (30) days advance written notice to:

Plainfield Public Schools: Business Office, 234 Shepard Hill Road, Plainfield, CT 06374. Failure of the owner to demand such certificate or other evidence of full compliance with these insurance requirements or failure of the owner to identify a deficiency from evidence provided will not be construed as a waiver of the contractor’s obligation to maintain such insurance.

B. Insurer Qualification: All insurance will be provided through companies authorized to do business in the State of Connecticut and considered acceptable by the owner, with an A.M. Best Rating of A-

/VIII.

C. Additional Insured: To the extent commercially available at no additional cost, the policy or policies providing insurance as required, with the exception of professional liability and workers’ compensation, will defend and include the owner, directors, officers, representatives, agents, and employees as additional insureds on a primary basis for work performed under or incidental to this contract.

D. Retroactive Date and Extended Reporting Period: If any insurance required here is to be issued or renewed on a claims-made form as opposed to the occurrence form, the retroactive date for coverage will be no later than the commencement date of the project and will state that in the event of cancellation or nonrenewal, the discovery period for insurance claims (tail coverage) will be at least 36 months.

E. Subcontractors’ Insurance: The contractor will cause each subcontractor employed by the contractor to purchase and maintain insurance of the types specified below. When requested by the owner, the contractor will furnish copies of certificates of insurance evidencing coverage for each subcontractor.

2. Insurance Limits and Coverage:

A. To the extent applicable, the amounts and types of insurance will conform to the minimum terms, conditions and coverages of Insurance Services Office (ISO) policies, forms, and endorsements.

B. If the contractor has self-insured retentions or deductibles under any of the following minimum required coverage’s, the contractor must identify on the certificate of insurance the nature and amount of such self-insured retentions or deductibles and provide satisfactory evidence of financial responsibility for such obligations. All self-insured retentions or deductibles will be the contractor’s sole responsibility.

C. Commercial General Liability: The contractor will maintain commercial general liability insurance covering all operations by or on behalf of the contractor on an occurrence basis against claims for personal injury (including bodily injury and death) and property damage (including loss of use). Such insurance will have these minimum limits:

Minimum Limits:

$1,000,000 each occurrence $2,000,000 general aggregate with dedicated limits per project site $2,000,000 products and completed operations aggregate $1,000,000 personal and advertising injury

1) Property damage liability arising out of the collapse of or structural injury to any building or structure due to excavation (including burrowing, filling or backfilling in connection therewith), tunneling, pile driving, cofferdam work or caisson work; or to moving, shoring, underpinning, razing or demolition of any building or structure, or removal or rebuilding of any structural support thereof.

2) Property damage liability for injury to or destruction of property arising, directly or indirectly, from blasting or explosions however caused, other than explosions of air or steam vessels, piping under pressure, prime movers, machinery or power transmitting equipment.

3) Property damage liability for injury to or destruction of wires, conduits, pipes, mains, sewers or other similar property, or any apparatus in connection therewith, below the surface of the ground, arising from and during the sue of mechanical equipment for the purpose of excavating or drilling within project limits; injury to or destruction of property at any time resulting therefrom.

D. Automobile Liability: The contractor will maintain commercial auto liability coverage for liability arising out of any auto, including owned, hired, and non-owned autos.

Minimum Limits: $1,000,000 combined single limit each accident

E. Workers’ Compensation: The contractor will maintain workers’ compensation and employer’s liability insurance. Waiver of subrogation in favor of Plainfield Public Schools shall apply.

Minimum Limits: Workers’ Compensation: statutory limit Employer’s Liability: $500,000 bodily injury for each accident

$500,000 bodily injury by disease for each employee $500,000 bodily injury disease aggregate

F. Umbrella/Excess Liability: The contractor will maintain coverage applying over the underlying

Commercial General Liability, Automobile Liability, Pollution Liability (where applicable), and Employer Liability section of the Workers Compensation coverage.

Minimum Limits: $4,000,000 per occurrence/$4,000,000 annual aggregate Coverage applies over the underlying Commercial General Liability, Automobile Liability, pollution liability (where applicable), and Employer Liability section of the Workers Compensation Coverage.

G. Professional Liability (for contractors, consultants, engineers, and other individuals/businesses providing professional services) Each Claim/Wrongful Act: $1,000,000

Annual Aggregate $1,000,000

H. Bid/Performance Bond: Include for 100% of contract cost.

Plainfield Public Schools reserves the right to amend amounts of coverage required and type of coverage’s provided based on work or service to be performed.

3. General Indemnification and Waiver of Subrogation. To the extent provided by law, Contractor agrees to indemnify, hold harmless and defend the School District, its Board and its Board members in their official and individual capacities, its successors, assignees, employees, contractors and agents from and against any and all claims, costs, expenses, damages, and liabilities, including reasonable attorney’s fees, arising out of the (i) negligent act or willful misconduct of the Contractor, its officers, directors, employees and agents; (ii) any breach of the terms of the Agreement by Contractor; or (iii) any breach of any representation or warranty by Contractor under the Agreement. Contractor, Subcontractor (s) and Supplier (s) waive all rights of subrogation against the Owner and the Owner’s insurance carriers. The Owner and the Owner’s insurance carriers retain all rights of subrogation.

File details come from the government source that posted it. Updated .