RFP for CMAR services for the Construction of a New Municipal Animal Shelter
Solicitation number
RFP # 2026-02
Issued by
Tarrant County, Texas

About this file

This is an RFP packet for Construction Manager at Risk (CMAR) services issued by the City of Saginaw, Texas for the preconstruction and construction of a new Municipal Animal Shelter. The solicitation follows a one-step CMAR selection process in accordance with Texas Government Code Chapter 2269, Subchapter F, and requests both qualifications and proposals from qualified candidates. Sealed proposals consisting of seven hard copies and one PDF file on a USB flash drive must be submitted to Lee Howell, Assistant City Manager, at Saginaw City Hall, 333 W. McLeroy, Saginaw, Texas 76179, with a submission deadline of 11:30 a.m. CST on December 3, 2026. Late submittals will not be accepted. All proposal packages must be marked with the firm's name and RFP number 2026-02.

The RFP packet does not specify pricing terms, set-asides, incumbent information, funding amounts, or other financial details within the document summary provided. Additional information regarding evaluation criteria, insurance requirements, bonding, project budget parameters, and other contract performance terms would be contained within the full RFP documentation.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSAL (RFP)

FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES

FOR THE CONSTRUCTION OF A

NEW MUNICIPAL ANIMAL SHELTER

RFP # 2026-02

CITY OF SAGINAW, TEXAS

November 2026

GENERAL INFORMATION:

The City of Saginaw, Texas (“City”) is accepting proposals for a Construction Manager at Risk

(CMAR) team member to provide preconstruction and construction services for its new Municipal

Animal Shelter. The City will be using a one-step CMAR selection process in accordance with

Texas Government Code Chapter 2269, Subchapter F, and this solicitation requests both qualifications and proposals from qualified candidates, as determined by the City. Sealed proposals from CMARs consisting of seven (7) hard copies and one (1) PDF file format on a USB flash drive, addressed to Lee Howell, Assistant City Manager, will be received at the Saginaw City

Hall, 333 W. McLeroy, Saginaw, Texas 76179 until 11:30 a.m. CST on December 3, 2026. Late submittals shall not be accepted. All packages to be marked with the firm’s name and RFP #

2026-02

The City reserves the right to reject any and all proposals and re-solicit for new proposals, or to reject any and all proposals and temporarily or permanently abandon the project. The City makes no representations, written or oral, that it will enter into any form of agreement with any respondent to this RFP for any project and no such representation is intended or should be construed by the issuance of this RFP. By submitting proposals in response to this RFP, the respondent accepts the evaluation process and acknowledges and accepts that determination of the “most qualified” firm(s) will require subjective judgments by the City. Respondents acknowledge and accept that any costs incurred from the respondent’s participation in this RFP process shall be at the sole risk and responsibility of the respondent. Respondents submit qualifications and proposals at their own risk and expense. The City will initially evaluate all proposals based upon evaluation criteria stated below or as may be in the City’s best interest in this Request for Proposal. After initial evaluation of all submitted proposals, the City may shortlist at least (2) two respondent candidates for consideration, and may request the short-listed proposals to participate in an interview to discuss their ability to perform the Services and the

Work as described in the Contract.

The schedule for this procurement process is currently as follows, and is subject to change by the

City at its sole discretion:

Announcement

November 13, 2026 RFQ publicly advertised (1st Notice)

November 20, 2026 RFQ publicly advertised (2nd Notice)

December 3, 2026 Qualifications and proposals due by 11:30 a.m.

December 7, 2026 Selection committee meets to short-list CMAR finalists

Week of December 7, 2026 Interviews with short-listed candidates if necessary

Week of December 14, 2026 Interviews with short-listed candidates if necessary

January 19, 2026 Contract approval by City Council (tentative)

PROJECT INFORMATION:

The building will be to replace a city animal shelter with new, modern building(s) that meet the current and future needs of our city. The proposed shelter facility is estimated to be approximately 10,000 square feet, and anticipated to include; kennel housing and indoor and outdoor recreation space for dogs, cats, or other domestic animals, lobby, reception, and public viewing adoption areas, exam, quarantine, and isolation rooms, staff office space, work areas, file and storage areas, get-to-know spaces, conference rooms; customer service area; book, periodicals, video, and audio browsing space; study rooms, and staff work areas including offices and lounge. The current budget for the design and construction is $15,000,000. The City is currently in negotiation with Quorum Architects, Inc., (“Architect”) to design the project. The facility will be designed to be located, along with parking and outdoor public gathering spaces, on the proposed site of a vacant 5-acre tract in the 1100 block of Defiel St. The current schedule is for the design of the facility to be completed in in the fall of 2027 and construction to begin as soon as possible afterward.

SCOPE OF WORK:

Preconstruction Services: The CMAR will work with the Architect and the City during the design process to ensure the feasibility and constructability of the building. The CMAR will also be responsible for cost estimates during both the schematic and design development phases of the project. The CMAR will work with the Architect and City to ensure that the cost of construction of the Project is within the estimated Construction Budget through the selection of construction systems and materials, detailed CSI format cost estimating, scheduling, and other means. The

CMAR will also review the project schedule and identify critical path and long lead items. Upon the completion of the design development phase and prior to the completion of the 100% set of construction documents, the CMAR will submit a proposal of a Guaranteed Maximum Price

(GMP) for the construction of the Project, which is within the City’s Construction Budget.

Bidding Services: Should the City exercise its option, the CMAR will serve as General Contractor to complete all work for the bidding and construction of the project. The CMAR will be responsible for coordination of all bids, advertisement and solicitation, bid procurement, selection of sub-consultants or trade contractors as outlined in Texas Government Code Chapter

2269. CMAR will also be responsible for issuance of pre-purchase orders for long lead items, if required.

Construction Services: Should the City exercise its option, the CMAR will serve as General

Contractor to complete all work for the construction of the Project. The scope of Construction services will be determined based on the final Drawings and Specifications and may include, but not be limited to, one or more of the following areas of work: site clearing, excavation, fill, select fill and backfill; site utilities; concrete sidewalks, paving and roadway / parking lot work, rough and finish grading, topsoil and grass planting; fencing and gates, site lighting, retaining wall construction, landscape installation, irrigation, concrete piers, concrete slab-on-grade, concrete masonry (CMU) interior walls, cast stone lintels, limestone and plaster exterior veneer, concrete floor topping, masonry, structural steel or wood frame (columns and joists), metal or wood roof deck, metal wall and roof panels, miscellaneous metals and metal fabrications; rough and finish carpentry, millwork and casework; damp proofing and waterproofing, caulking and sealants, thermal insulation, flashing and sheet metal, metal soffit panels, metal roofing, modified bitumen roofing; other roofing, wood doors, metal doors and frames, aluminum doors and frames, glass and glazing, finish architectural hardware, acoustical ceilings, resilient flooring and base, carpeting, tile or wood flooring, metal studs and support systems, gypsum drywall, painting and special floor coatings, interior and exterior signage; metal louvers and miscellaneous specialties;

furnishings and appliances; equipment and specialty equipment; sound enhancement systems;

fire protection; lightning protection; telecommunications, audio / visual and security systems and mechanical, plumbing and electrical systems, and any other requirements set out in the Contract

Documents.

The work does not include inspection services, and the materials testing services necessary for

City’s acceptance of the Project, which will be performed under a separate contract with an independent provider engaged directly by the City.

EVALUATION CRITERIA:

Evaluation scores will be based on the below scoring criteria.

• Respondent’s Qualifications and Experience

• Respondent’s Estimating and Cost Control Measures

• Respondent’s Quality Control and Commissioning Program

• Respondent’s Warranty Program

• Respondent’s Pricing and Delivery Proposal

FORMAT RESPONSE TO RFP:

The submitted response to this RFP should be as concise as possible while adhering to the format and information requirements described below. Please limit your response to a maximum of twenty (20) single sided pages or ten (10) double-sided pages, excluding the cover letter, resumes and attachments such as photographs or other exhibits. Attachments are limited to five (5) pages. Font size of 11 or larger is required. The cover letter should include a point of contact and contact information including an email address and phone number.

The submitted response shall be divided into the following sections and shall include at a minimum the following information:

Section 1 – Qualifications and Experience

a. The CMAR’s successful and cost-effective experience and expertise with animal shelter projects of similar size, scope, and budget.

b. The CMAR’s capability to provide the resources, including funding, equipment and staffing, necessary to meet the project requirement.

c. The CMARs proposed project personnel as shown in a project organizational chart and including their qualifications and construction experience on similar projects as evidenced by their resumes.

d. The CMAR’s recent experience with project cost estimates, as well as project budget and schedule adherence.

e. The CMAR’s safety record supported by accurate and verifiable data.

f. The CMAR’s reference letters indicating the quality of previous work on similar projects and satisfaction from customers.

Section 2 – Estimating and Cost Control Measures

Describe your project estimating system for developing the Guaranteed Maximum Price (GMP)

Proposal and how you will monitor and track these costs during the procurement and payment process, including contingencies you will propose in the GMP, and how these contingencies will be managed through the completion of the project.

Section 3 – Quality Control and Commissioning Program

Describe how your quality control team will measure the quality of the construction and commissioning performed by trade contractors on this project, and how will you address non-conforming work. Section 4 – Warranty Program

Describe how you will measure the quality of service provided to the owner for this project and describe your warranty service support philosophy and warranty service implementation plan for this project.

Section 5 – Pricing and Deliver Proposal

a. Preconstruction Fee: For all preconstruction phase services including pre-planning, cost estimating, scheduling, value engineering, constructability reviews. Provide an itemized list of services and a total lump sum cost.

b. General Conditions: Proposed not to exceed costs for general conditions to accommodate onsite staff. Provide a proposed itemized worksheet of general conditions assuming a project schedule of 18 months.

c. Construction Phase Service Fees: Identify a construction phase service fee as a percentage of the construction budget for all home office expenses and any other expenses not included in the general conditions, including all overhead and profit.