RFP 20_1377 Turnkey Schedule B - Pricing Oden Visitor Center.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
Addendum 3 -DNR- Turnkey Solar Panels at Oden Visitor Cente
Solicitation number
RFP-751-200000001377-4
Issued by
Emmet County, Michigan

About this file

This is a pricing schedule template (Schedule B) from the Michigan Department of Natural Resources for RFP 20_1377, concerning a Renewable Energy Systems Pilot Program at the Oden Fish Hatchery Visitor Center. The document outlines the pricing submission requirements for a solar power system installation project, requiring bidders to provide detailed information about proposed solar arrays, including system specifications, power capacity, and estimated energy production.

The pricing schedule requires bidders to submit comprehensive turnkey pricing that includes all development and installation costs, annual operation and maintenance fees, remote monitoring subscription costs, and pricing for an educational kiosk. Bidders must specify installed capacity in both kWAC and kWDC, estimated annual energy production in kWh, Year One savings, and 25-year lifetime savings projections. The document offers quick payment terms with a bidder-specified discount for early payment. All prices must be arrived at independently without consultation with other contractors, and multiple proposals from the same contractor must be exclusive of each other.

View the file

Other files

File Type Posted
Exhibit 4 Visitor Center Photos for bid_Page_11.jpg JPG image
Exhibit 4 Visitor Center Photos for bid_Page_09.jpg JPG image
Exhibit 4 Visitor Center Photos for bid_Page_05.jpg JPG image
RFP 20_1377 Turnkey Schedule A - Statement of Work Oden Visitor Center.docx DOCX document
Exhibit 4 Visitor Center Photos for bid_Page_10.jpg JPG image
Exhibit 4 Visitor Center Photos for bid_Page_03.jpg JPG image
Exhibit 4 Visitor Center Photos for bid_Page_08.jpg JPG image
RFP 20_1377 PPA Schedule C - Land Lease Agreement.docx DOCX document
Exhibit 4 Visitor Center Photos for bid_Page_01.jpg JPG image
Exhibit 4 Visitor Center Photos for bid_Page_06.jpg JPG image
Exhibit 2.Oden Energy Data.Visitor Center.xlsx XLSX spreadsheet
Exhibit 3.Example Utility Bill.Visitor Center.pdf PDF
Exhibit 4 Visitor Center Photos for bid_Page_07.jpg JPG image
Exhibit 4 Visitor Center Photos for bid_Page_02.jpg JPG image
Exhibit 1.Oden Visitor Center PV Map.pdf PDF
RFP 20_1377 Turnkey Proposal Instructions-Oden Visitor Center Confidential Treatment Form-Vendor Questions Worksheet.docx DOCX document
Exhibit 4 Visitor Center Photos for bid_Page_12.jpg JPG image
Exhibit 4 Visitor Center Photos for bid_Page_04.jpg JPG image
RFP 20_1377 Turnkey Oden Visitor Center standard_contract_terms.docx DOCX document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Enter company name here.

STATE OF MICHIGAN

Request For Proposal No. XXXXXXX Renewable Energy Systems Pilot Program Oden Fish Hatchery Visitor Center Department of Natural Resources

SCHEDULE B

PRICING

1. The Contractor must provide a pricing schedule for the proposed Contract Activities using the table as included in this Schedule B. The pricing schedule should be submitted in a modifiable format (e.g.. Microsoft Word or Excel); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.

2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State.

3. The Contractor is encouraged to offer quick payment terms. The number of days must not include processing time for payment to be received by the Contractor's financial institution.

Quick payment terms: ________ % discount off invoice if paid within ________ days after receipt of invoice.

4. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.

5. If the Contractor submits multiple proposals for the same project, each proposal shall be exclusive of the other(s).

6. Oden Fish Hatchery Visitor Center:

Column A - Bidders should enter a descriptive name for each project proposal (e.g., Oden Visitor Center– 100% of annual power use) Column B – indicate the type(s) of solar arrays to be used in the proposal Column C – indicate the estimated installed power capacity of the proposed solar PV system, in kilowatts-AC.

Column D -- indicate the estimated installed power capacity of the proposed solar PV system, in kilowatts-DC.

Column E – indicate the estimated annual energy quantity produced by the proposed solar PV system in kilowatt hours (KWh).

Columns G - Enter a turn key price for the proposed system reflecting all costs for development and installation of the system through start-up of power generation (e.g, site preparation, design, permits, studies required, installation, interconnection, post-installation proof of performance testing).

Column H – Enter a proposed annual price for operation and maintenance based on one visit per year for standard O&M including site visit to analyze whether it is producing the amount of power as designed, solar array cleaning, check electrical systems and inverters, and any warranty repairs, as needed.

Column I -- Enter clarifying assumptions for inclusions and exlusions for the O&M price provided.

Column J – Provide a cost for ongoing subscription costs for remote monitoring.

Column K -- Enter estimated Year One savings for the proposed system as detailed in the Contractor’s proposal (see Schedule A, Section 1.2.3, Proposal Requirements) Column L -- Enter estimated lifetime savings for the proposed system as detailed in the Contractor’s proposal (see Schedule A, Section 1.2.3, Proposal Requirements) Column N - Enter price for an educational kiosk that would display energy generation for public.

Column M - Enter comments and describe assumptions for each Turnkey price proposal. Please also add any additional pertinent information

Oden Visitor Center

Schedule B - Pricing - Turnkey - Oden Fish Hatchery Visitor Center
System InformationTurnkey Price & Assumptions
Proposal NameProject Type (e.g., ground mount)Installed Capacity - (in kWAC)Installed Capacity - (in kWDC)Estimated Year One Energy Produced at Meter (kWh)Turnkey Price Solar at Completion ($)Annual Price For Operation & Maintenance ($/yr)Explain high level what is and is not included in priceData Plan and Cost for Internet Access if not included in turnkey purchaseYear One Solar Savings ($)25-year Solar Savings ($)Digital Kiosk for public viewing ($)Comment
InstructionsBidder InputBidder InputBidder InputBidder InputBidder InputBidder InputBidder InputBidder InputBidder InputBidder InputBidder InputBidder Input

File details come from the government source that posted it. Updated .