RFP_1220380_2_ Addendum No_ 1 (1).pdf

PDF 498 KB Posted

Attached to
RFP/DOT/2308-1220380-2, 1, Traffic Signal Enhancement Program - Phase II
Solicitation number
PE-66062-NONST-2024-000000112
Issued by
Fulton County, Atlanta City, Georgia

About this file

This document is an Addendum No. 1 to a Request for Proposals (RFP) issued by the City of Atlanta Department of Procurement for the Traffic Signal Enhancement Program - Phase II, Project No. RFP/DOT/2308-1220380-2. The addendum provides responses to questions from potential proponents and updates the requirements for the Phase II submission. The proposal due date remains 3/7/2024 by 2:00 P.M. EST. The project does not involve any bridge design, and cost estimates will be requested from the top-scored consultant during the negotiation phase. Shortlisted firms should submit their technical and past performance responses through the ATL-Cloud system, following the guidelines on page limits and formatting. The Phase II response requires the submission of Appendix A (OCC Requirements), technical response, and past performance response.

The addendum clarifies that there are no bridges in the project scope, which is focused on traffic signal and ITS design. Pricing information is not required at the time of the Phase II submittal, as the Department of Procurement will reach out to the top-scored consultant during the negotiation phase to request a cost estimate. No other salient pricing, funding, or contracting details are provided in this addendum.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF ATLANTA

DEPARTMENT OF PROCUREMENT

SUITE 1900

55 TRINITY AVENUE, SW

ATLANTA, GA 30303

(404) 546-1000

Excellence in VALUE CREATION through Partnership, Collaboration, and Innovation

Rev. 8.24.23

Andre Dickens

Mayor

Jaideep Majumdar

Chief Procurement Officer

M E M O R A N D U M

TO: Potential Proponents

FROM: Malik Gill, Category Specialist

CC:

Brandon Paulk, Category Lead/Manager

Courtney A. Hunt, Deputy Category Director

RE: Notice of Addendum No. 1 Memo for – RFP/DOT/2308-1220380-2/Traffic Signal

Enhancement Program – Phase II

DATE: 2/21/2024

Dear Potential Proponents / Bidders:

Attached is one (1) copy of Addendum Number No. 1 which is hereby made a part of the above referenced project.

ADDENDUM NO. 1

This Addendum No. 1 form is a part of the Request for Proposals (“RFP”) and modifies the original solicitation package as noted below and is issued to incorporate the following:

• Responses to questions

• Updated requirements for Phase II submission

DocuSign Envelope ID: A70401B3-74AC-48E4-94F6-A005717F6710

Addendum Memo

Rev. 8.24.23

The Proposal due date HAS NOT been modified and Proposals are due on 3/7/2024 and should be time stamped into the system no later than 2:00 P.M. EST.

**All other pertinent information is to remain unchanged**

All questions and inquiries concerning this project should be directed to Category Specialist, Malik Gill ; via e-mail: mgill@atlantaga.gov.

Attachment(s) mailto:mgill@atlantaga.gov

Project Name and Project Number: RFP/DOT/2308-1220380-2,1: Traffic Signal Enhancement Program Phase II Date: February 21, 2024

Questions and Responses The following questions and /or clarifications were requested by various proponents:

1. Question

Item 1.a. in the Notice to Selected Finalist notes unique approaches, “including the approach to successful bridge design.” Will the City confirm whether bridge design is needed for this project?

Response There is no Bridge Design in this project. It involves only Traffic Signal and ITS design.

2. Question

Will cost be required at the time of submittal for the Technical Response and

Past Performance Response?

Response No, Not Required. DOP will reach out to the Top Scored consultant in

Negotiation Phase, for Cost Estimate.

3. Question

How and where should shortlisted firms submit their Technical Response and

Past Performance Response?

Response The responses should be submitted in ATL-Cloud as they were submitted in Phase I.

4. Question

Can firms use 11x17 pages for any maps or graphics?

Response Submittals must be typed on standard (8½” x 11”) paper. The pages should be numbered; however, submittal pages will be counted by section to determine compliance with page limits. Page counts will be determined by pages with print on them, not by the physical piece of paper. Each

Statement of Qualifications shall be prepared simply and economically as indicated above. Colored displays and promotional materials are not desired. Emphasis must be on completeness, relevance, and clarity of content.

5. Question

Which forms should be submitted with the Phase II response?

Project Name and Project Number: RFP/DOT/2308-1220380-2,1: Traffic Signal Enhancement Program Phase II Date: February 21, 2024

Response Phase II requires submittal of Appendix A (OCC Requirements), technical response and past performance response.

6. Question If any forms are required, should they be submitted with the Phase II response or as a separate document

Response Please see the response to Question #5.

7. Question Under A. Technical Approach, Section 1.a. asks, “Provide any unique technical approaches your firm offers to fulfilling the scope of services, and/or management of the project, including the approach to a successful bridge design.” There are no bridges in the scope, as this is a traffic signal design project. Please clarify what the City wants addressed in

Section 1.a.

Response Please see the response to Question #1.

Blank Page

2024-02-21T11:40:53-0800
Digitally verifiable PDF exported from www.docusign.com

File details come from the government source that posted it. Updated .