Text version

CDRL DECK 20130827

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MGMT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A001 Integrated Program Management Report Integrated Master Schedule

Baseline

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

TOTAL PRICE

DI-MGMT-81861 SOW Para 3.1.4 SFAE-AV-UH-T

INSERT

7. DD 250 REQ 9.DIST STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION IN

LT

MTHLY 30 DACA

b. COPIES

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

Final

A

N/A SEE BLK 16

Reg

Repr

16. REMARKS:

BLOCK 8 The COR will review and approve or disapprove initial baseline submittal with comments

NLT thirty (30) days after initial submittal. If disapproved the Contractor shall revise IAW comments and resubmit NLT thirty (30) days after receipt of comments. The COR will review and approve or disapprove IMS baseline revision submittals with comments NLT seven (7) days after submittal. If disapproved the Contractor shall revise IAW comments and resubmit NLT seven (7) days after receipt of comments.

BLOCK 9 Distribution D. See Enclosure 1.

BLOCK 10, 13 The Contractor shall not re-baseline any IMS activities without concurrence from the

COR. As required, the Contractor shall deliver revised IMS baseline data anytime the data is revised

NLT 30 days of revisions for COR approval. The Contractor shall deliver status against the approved

IMS baseline monthly. Revisions shall be identified in each submittal by use of “Change Bars” in

MS office, or by similar means to make revisions easily identifiable.

BLOCK 14 The Contractor shall electronically deliver the data to the COR via COR supplied e-mail address. Files over 5MB shall be delivered via AMRDEC SAFE (https://safe.amrdec.army.mil

<https://safe.amrdec.army.mil/> ) concurrent with the notification letter to COR. Files that cannot be transmitted electronically shall be mailed to the following address:

Prototype Integration Facility ATTN: UH Data Manager

5405 Fowler Road

Mark For: FMS Case TW-B-YZC Redstone Arsenal, AL 35898-5000

“WARNING – This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 reference)).”

SEE BLK 16

15. TOTAL 0 1 0

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

https://safe.amrdec.army.mil/

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A002 Technical Report-Study/Services IMS Baseline Change Report

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MISC-80508B SOW Para 3.1.4.1 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SEE BLK 16 SEE BLK 16

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

N/A

BLOCK 10, 12, 13 The Contractor shall deliver an IMS Baseline Change Report any time revisions to the baseline are made. The Contractor shall deliver IMS

Baseline Change Reports NLT seven (7) days prior to IMS baseline revision submittal (A001).

BLOCK 14 The Contractor shall electronically deliver the data to the COR via

COR supplied e-mail address. Files over 5MB shall be delivered via AMRDEC

SAFE (https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the notification letter to COR. Files that cannot be transmitted electronically shall be mailed to the following address:

5405 Fowler Road

“WARNING – This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq) or the

Export Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq. Violations of these export laws are subject to severe criminal penalties.

Disseminate in accordance with provisions of DoD Directive 5230.25

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and

Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MGMT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A003 Data Accession List

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-81453A SOW Para 3.1.5 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SEE BLK 16 30 DACA

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

16. REMARKS

BLOCK 10, 13 After first submission, review, and re-submission: the contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions.

Revisions shall be identified in each submittal by use of “Change Bars” in MS office, or by similar means to make revisions easily identifiable.

BLOCK 14 The Contractor shall electronically deliver the data to the COR via

COR supplied e-mail address. Files over 5MB shall be delivered via AMRDEC

SAFE (https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the notification letter to COR. Files that cannot be transmitted electronically shall be mailed to the following address:

5405 Fowler Road

“WARNING – This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq) or the

Export Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq. Violations of these export laws are subject to severe criminal penalties.

Disseminate in accordance with provisions of DoD Directive 5230.25

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A004 Technical Report-Study/Services Data Delivery from the DAL

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MISC-80508B SOW Para 3.1.5 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall deliver data within 30 days of

Procuring Contracting Officer (PCO) request.

BLOCK 14 The Contractor shall electronically deliver the data to the

COR via COR supplied e-mail address. Files over 5MB shall be delivered via AMRDEC SAFE (https://safe.amrdec.army.mil

<https://safe.amrdec.army.mil/> ) concurrent with the notification letter to

COR. Files that cannot be transmitted electronically shall be mailed to the following address:

Prototype Integration Facility ATTN: UH Data Manager 5405 Fowler Road Mark For: FMS Case TW-B-YZC Redstone Arsenal, AL 35898-5000

“WARNING – This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 reference)).”

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and

Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER CMAN

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A005 Contractor's Configuration Management Plan FMS Configuration

Management Plan (CMP)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-CMAN-80858B SOW Para 3.1.6 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 8 The COR will review and approve or disapprove with comments NLT thirty

(30) days after submittal. If disapproved the contractor shall revise IAW comments and resubmit NLT thirty (30) days after receipt of COR comments.

BLOCK 9 See Enclosure 1.

BLOCK 10, 12, 13 The Contractor shall deliver the initial submittal NLT 14 days prior to

SRR. The contractor shall deliver an updated list anytime the data is revised NLT 14 days from date of revision not to exceed a bi-weekly submittal. Revisions shall be identified in each submittal by use of either, “Changes Bars” in MS Office, or by similar means to make revisions easily identifiable.

BLOCK 14 The Contractor shall electronically deliver the data to the COR via COR supplied e-mail address. Files over 5MB shall be delivered via AMRDEC SAFE

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the notification letter to COR. Files that cannot be transmitted electronically shall be mailed to the following address:

5405 Fowler Road

“WARNING – This document contains technical data whose export is restricted by the

Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq) or the Export

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 reference)).”

15. TOTAL

0 1 0

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER CMAN

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A006 As Built Configuration List (ABCL)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-CMAN-81516 SOW Para 3.1.7 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10,12,13 The contractor shall deliver one ABCL NLT 30 days after final delivery (DD250).

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A007 Technical Reports – Study/Services Program Risk Management

Assessment Report

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MISC-80508B SOW Para 3.1.8 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall submit data NLT 14 Days prior to: Systems

Requirements Review (SRR), Preliminary Design Review (PDR), Critical Design Review

(CDR), Test Readiness Review (TRR), and Pre-Shipment Readiness Review (PSRR).

Revisions shall be identified in each submittal by use of “Change Bars” in MS office, or by similar means to make revisions easily identifiable.

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A008 Briefing Material SEE BLK 16

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MGMT-81605 SOW Para 3.1.9, 3.2.5.2, 3.3.4.2, 3.4.1.2, 3.5.12.2, 3.5.14.2

SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

N/A SEE BLK 16 SEE BLK 16

BLOCK 3

A008-001 Program Management Review (PMR) Program Status Briefing Material A008-002 System Requirement Review (SRR) Briefing Material

A008-003 Preliminary Design Review (PDR) Briefing Material

A008-004 Critical Design Review (CDR) Briefing Material A008-005 Test Readiness Review (TRR) Briefing Material

A008-006 Pre-Shipment Readiness Review (PSRR) Briefing Material

BLOCK 8 The COR will review and approve or disapprove with comments NLT seven (7) days after submittal. If disapproved the contractor shall revise IAW comments and resubmit NLT fourteen

(14) days following receipt of comments.

BLOCK 10, 12, 13 The Contractor shall deliver briefing material through the IPT process NLT 14 days prior to the corresponding event. COR comments on the briefing package content will be made through the IPT within 7 days of receipt. The Contractor shall deliver the final presentation updated

IAW the review event NLT 14 days after the conclusion of the event.

<https://safe.amrdec.army.mil/> ) concurrent with the notification letter to COR. Files that cannot be

5405 Fowler Road amended, Title 50, U.S.C., Sec App 2401 et seq. Violations of these export laws are subject to severe

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER SAFT

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A009 System Safety Program Plan (SSPP)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-SAFT-81626A SOW Para 3.1.10 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 8 The COR will review and approve or disapprove with comments NLT thirty (30) days after submittal. If disapproved the contractor shall revise IAW comments and resubmit NLT thirty (30) days after receipt of COR comments.

BLOCK 10, 12, 13 The Contractor shall deliver baseline plan NLT 30 days prior to Preliminary Design Review (PDR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in each submittal by use of either, “Changes Bars” in MS Office, or by similar means to make revisions easily identifiable.

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER IPSC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A010 Software Development Plan (SDP)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-IPSC-81427A SOW Para 3.2.1 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall submit initial document NLT 30 days prior to

Preliminary Design Review (PDR). The Contractor shall deliver final documentation

NLT 30 days prior to Critical Design Review (CDR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

1 1 0

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER IPSC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A011 Software Requirements Specification (SRS)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-IPSC-81433A SOW Para 3.2.2 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 4 Contractor format is acceptable.

NLT 30 days prior to Critical Design Review (CDR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBHT C. CATEGORY:

TDP TM OTHER IPSC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A012 Software Product Specifications (SPS)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-IPSC-81441A SOW Para 3.2.3 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

NLT 30 days prior to Critical Design Review (CDR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBHT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A013 Technical Reports – Study/Services Requirements Traceability

Matrix (RTM)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MISC-80508B SOW Para 3.2.4 SFAE-AV-UH-T

7. DD250 REQ 9.DIST STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall submit initial document NLT 14 days prior to

System Requirements Review (SRR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in each submittal by use of either, “Changes Bars” in MS Office, or by similar means to make revisions easily identifiable.

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER IPSC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A014 Software Design Description (SDD)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-IPSC-81435A SOW Para 3.3.1 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

NLT 30 days prior to Critical Design Review (CDR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER IPSC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A015 Interface Design Description (IDD)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-IPSC-81436A SOW Para 3.3.2 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

NLT 30 days prior to Critical Design Review (CDR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER SESS

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A016 Product Drawings/Models and Associated Lists Engineering and Installation

Drawings

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-SESS-81000E SOW Para 3.3.3 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 8 The COR will review and approve or disapprove with comments NLT thirty (30) days after submittal. If disapproved the contractor shall revise IAW comments and resubmit NLT thirty

(30) days after receipt of COR comments.

BLOCK 10, 12, 13 Thirty percent (30%) of engineering drawings and associated lists shall be released and delivered NLT 30 days prior to PDR. Ninety percent (90%) of engineering drawings and associated lists shall be released and delivered NLT 30 days prior to the Critical Design Review

(CDR). Remaining drawing releases and revised drawings shall be delivered NLT 30 days prior to

Test Readiness Review (TRR). Any time a drawing is revised, the Contractor shall submit the revised drawing within 14 days thereafter. Revisions shall be identified in the drawing change block or by similar means to make changes easily identifiable.

<https://safe.amrdec.army.mil/> ) concurrent with the notification letter to COR. Files that cannot be

5405 Fowler Road amended, Title 50, U.S.C., Sec App 2401 et seq. Violations of these export laws are subject to severe

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER SESS

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance Trainer

(BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

A017 Product Drawings/Models and Associated Lists Drawing Tree

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-SESS-81000E SOW Para 3.3.3 SFAE-AV-UH-T

7. DD 250 REQ 9.DIST STATEMENT

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

14. DISTRIBUTION

8. APP CODE SEE BLK 16 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 8 The COR will review and approve or disapprove with comments NLT thirty (30) days after submittal.

If disapproved the contractor shall revise IAW comments and resubmit NLT thirty (30) days after receipt of COR comments.

BLOCK 10, 12, 13 Thirty percent (30%) of drawing tree shall be released and delivered NLT 30 days prior to PDR. Ninety percent (90%) of drawing tree shall be released and delivered NLT 30 days prior to the Critical

Design Review (CDR). Remaining drawing tree shall be delivered NLT 30 days prior to Test Readiness Review

(TRR). Any time a drawing is revised, the Contractor shall submit the revised drawing tree within 14 days thereafter. Revisions shall be identified in the drawing tree change block or by similar means to make changes easily identifiable.

BLOCK 14 The Contractor shall electronically deliver the data to the COR via COR supplied e-mail address. Files over 5MB shall be delivered via AMRDEC SAFE (https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the notification letter to COR. Files that cannot be transmitted electronically shall be mailed to the following address:

5405 Fowler Road

“WARNING – This document contains technical data whose export is restricted by the Arms Export Control Act

(Title 22, U.S.C., Sec 2751, et seq) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 reference)).”

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A018 Technical Reports – Study/Services R&M Prediction Report

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MISC-80508B SOW Para 3.5.3 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall deliver initial data NLT 30 days prior to

Preliminary Design Review (PDR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in each submittal by use of either, “Changes Bars” in MS Office, or by similar means to make revisions

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER NDTI

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A019 Test and Evaluation Program Plan (TEPP)

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-NDTI-81284 SOW Para 3.5.6 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall deliver draft baseline plan NLT 30 days prior to

Critical Design Review (CDR). The Contractor shall deliver final plan NLT 30 days prior to Test Readiness Review (TRR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in each submittal

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER NDTI

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A020 Test Procedure

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-NDTI-80603A SOW Para 3.5.8 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall submit document NLT 30 days prior to Test

Readiness Review (TRR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in each submittal by use of either, “Changes Bars” in MS Office, or by similar means to make revisions easily identifiable.

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP

A021 Technical Report-Study/Services Acceptance Test Procedure

List

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MISC-80508B SOW Para 3.5.9 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall submit document NLT 30 days prior to Test

Readiness Review (TRR). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in each submittal by use of either, “Changes Bars” in MS Office, or by similar means to make revisions easily identifiable.

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the COR Issuing Contracting Officer for Contract/PR

No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER MISC

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

UH-60M Black Hawk Maintenance

Trainer (BHMT-M)

FMS CASE TW-B-YZC

W58RGZ-12-C-0008

Logistics Services

International, Inc.

A022 Technical Report-Study/Services Deficiency Report

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED

DI-MISC-80508B SOW Para 3.5.10 SFAE-AV-UH-T

REQUIRED

10. FREQUENCY 12. DATE OF FIRST SUBMISSION

SECT. B

8. APP CODE

D

11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

a. ADDRESSEE

Draft

BLOCK 10, 12, 13 The Contractor shall submit document NLT 15 days following

Contractor Preliminary Inspection (CPI). The Contractor shall deliver revised data anytime the data is revised NLT 30 days of revisions. Revisions shall be identified in each

(https://safe.amrdec.army.mil <https://safe.amrdec.army.mil/> ) concurrent with the

5405 Fowler Road

Administration Act of 1979, as amended, Title 50, U.S.C., Sec App 2401 et seq.

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to

Department of Defense, Washington Headquarters…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .