About this file
This is a Request for Information/Clarification (RFI/RFC) form template used for the F-35 Fuel Stands solicitation (FA6675-25-Q-0003) at NAS Fort Worth JRB. The two-page form is divided into sections for contractor and government use, allowing contractors to submit requests for information or clarification regarding contract requirements.
The form includes fields for contract number, RFI number, subject, drawing references, and response deadlines. The second page contains a government response section and a contractor review section where the contractor must indicate if they anticipate a change order or cost increase will be required. The form must be routed through the 301 CONF/PK contracting office and Base Civil Engineering for evaluation and action. This is a standard template that does not contain any filled-in information about specific requirements or responses.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION / CLARIFICATION FORM
FOR CONTRACTOR USE ONLY
CONTRACT NO: RFI NO: DATE (YYYYMMDD)
SUBJECT: DRAWING REFERENCE/ DETAIL:
ATTACHMENT SENT UNDER SEPARATE
COVER(__)
RESPONSE NEEDED BY:
REQUEST:
PROPOSED SOLUTION (If applicable:
TO(Contracting Office): 301 CONF/PK FROM (Contractor):
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
FOR GOVERNMENT USE ONLY
FROM CONTRACTING
TO:(Base Civil Engineering):
For Evaluation and Action
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
RFI RESPONSE / CLARIFICATION (refer to page 2)
REQUEST FOR INFORMATION / CLARIFICATION FORM
RFI RESPONSE / CLARIFICATION:-
Government to complete following sections:
TO:(AF Contracting Office)
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
TO:(Contractor)
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
CONTRACTOR REVIEW
After reviewing the Government response, does the contractor anticipate A change order will be required? YES NO There will be an increase in the cost of the project? YES NO
Reviewer:
DATE (YYYYMMDD) TYPE OR PRINT NAME AND TITLE SIGNATURE:
*Contractor- return reviewed form to Contracting Officer. Should the review results in YES for either of the two questions, if any further action is required by the contractor (i.e. submission of change proporsal), they will be notified by the contracting office.