RFI - Questions and Answers 6-25-2020.pdf
PDF 89 KB Posted
- Solicitation number
- PANNAD-20-P-0000-000642-RFI
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VIRTUAL INDUSTRY DAY
RFI
QUESTIONS AND ANSWERS
1. The project is unrestricted—is that 100%? Are there any assets set aside to encourage/acquire the use of SB, DBE, 8(2), etc?
-- The TYAD Army Family Housing Project will be changing to an 8a competitive acquisition.
2. Will layout/stakeout be completed by design team, or is that on the contractor?
-- The construction contractor will be responsible for laying out / staking out the Army Family Housing construction area.
3. What are the buildings to be demolished currently being used for?
-- The buildings to be demolished are currently used as Army Family Housing units.
a. If unoccupied, is there an option/desire to solicit/award the site demo work ahead of the development work?
-- Demolition of the existing buildings will remain as part of the scope of work for the Army Family Housing construction contract.
File details come from the government source that posted it. Updated .