VIRTUAL INDUSTRY DAY

RFI

QUESTIONS AND ANSWERS

1. The project is unrestricted—is that 100%? Are there any assets set aside to encourage/acquire the use of SB, DBE, 8(2), etc?

-- The TYAD Army Family Housing Project will be changing to an 8a competitive acquisition.

2. Will layout/stakeout be completed by design team, or is that on the contractor?

-- The construction contractor will be responsible for laying out / staking out the Army Family Housing construction area.

3. What are the buildings to be demolished currently being used for?

-- The buildings to be demolished are currently used as Army Family Housing units.

a. If unoccupied, is there an option/desire to solicit/award the site demo work ahead of the development work?

-- Demolition of the existing buildings will remain as part of the scope of work for the Army Family Housing construction contract.