RFI Government responses - 573-18-600 Reno Stairwells RFIs.docx

DOCX document 37 KB Posted

Attached to
Y1DA--FY22: NRM Tier 2 (PROJ: 573-18-600) BB - Renovate Stairwells
Solicitation number
Not on record
Issued by

About this file

This document contains responses to questions from bidders on a renovation of hospital stairwells project for the Department of Veterans Affairs. Key details include that the solicitation number is not listed, the project involves renovating stairwells at the VA Gainesville hospital to address issues like accessibility, fire protection and code compliance. The scope of work includes demolition, new walls, doors, finishes, lighting and mechanical work. The response date for proposals has been extended to an unspecified date. The contractor will be responsible for safety plans, scheduling, disposal of hazardous materials and coordination between different areas of the hospital. Finishes will vary between stairs and full clarification is provided in addendums. The selected contractor may propose working on multiple stairs concurrently subject to approval and must coordinate with other projects.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA GAINESVILLE Renovation of Hospital Stairwells 573-18-600 BIDDER RFIs

ALL DRAWINGS AND OTHER RELATED DOCUMENTS ARE INCLUDED IN THE LINK BELOW

https://drive.max.gov/share/2225a89efe4b44a9

11/15/2022
RESPONSE BY
QUESTION
QUESTION FROM
DATE
RESPONSE
RESPONSE DATE
VA
1. Can you provide the Environmental Report (Asbestos Report)?
Milicon
11/08/2022
The asbestos report is available and attached as part of the bid documents
12-05-2022
VA
2. Is the coordination of the SOW by Stairwell or by Floors?
Milicon
11/08/2022
Generally, the coordination of the schedule and sequence will be developed by the stairwell. There may be limited situations, however, where the VA may request a stairwell to be delivered in multiple stages to accommodate life safety needs.
12-05-2022
VA
3. Who would provide the contingency plan if there were an Emergency, and we are currently working on an emergency exit stairwell?
Milicon
11/08/2022
The contractor is responsible to coordinate with the VA Safety Officer to provide an alternate means of egress during the execution of activities that impede the utilization of a particular stairwell. The contractor is responsible to provide the proper signing and labeling of temporary routes of evacuation depending on the work implemented by the stairwell. Refer to spec SECTION 01 58 16 and any other information under the plans, specifications, or the TIL.
12-05-2022
VA
4. Will the VA provide specialized keys and fobs, or would we need a VA Chaperone all the times?
Milicon
11/08/2022
VA will provide a construction KEY according to the planned work by the contractor as needed.
12-05-2022
VA
5. Does this project overlap with other projects throughout the hospital? Same scope different projects?
Milicon
11/08/2022
There is no overlap planned as part of the plans and specifications of this project. Nevertheless, the contractor shall consider any coordination with other projects VA is managing in the surrounding areas. This scope is intended to stand alone, and additional stairwell projects with similar scopes are not anticipated at this time.
12-05-2022
VA
6. Can we get the color marked plan that was shown on the walkthrough on November 3rd, 2022?
Milicon
11/08/2022
The color-marked floor plan utilized during the site visit is included as a reference only. It is not intended that this color-marked floor plan supersede any bid document
12-05-2022
TMM
7. Are the finishes (Painting, flooring, lighting, etc.) all the same for the interior stairs?
Milicon
11/08/2022
Refer to Bid Documents including Drawings A601, A602, A603, and A604 and related information included in Addendum.
12-05-2022
VA
8. Stair #54 is blocked; will the renovation keep this stair blocking entrance from everyone?
Milicon
11/08/2022
The works at stair No. 54 will be according to the plans and specifications.
12-05-2022
VA
9. Stair #17 (Outdoor Stair) was partially frame and some drywall was installed, is this going to be done under a different project or it should be included on the SOW?
Milicon
11/08/2022
The ongoing works planned for Stair No.17 are not expected to overlap the works for this project, meaning that the works will be according to the plans and specifications.
12-05-2022
VA
10. What is the preferred containment plan that the VA will prefer on interior, exterior stairs, and mechanical room?
Milicon
11/08/2022
The containment plan shall be in full compliance with the plans and specifications. Refer to the spec SECTION 01 35 26 and the latest reference under the VA Technical Information Library (TIL).
12-05-2022
VA
11. Would this project allow to work on weekends and nighttime?
Milicon
11/08/2022
There will be certain activities that have to be done after working hours or on weekends according to previous coordination with the VA.
12-05-2022
VA
12. Is any of the stairs by any Mental Health Ward that need additional clearances to work?
Milicon
11/08/2022
While it is not the intent to limit access to the stairwells adjacent to the Mental Health Area, patient activities within this zone may necessarily restrict the construction activities that occur outside in a limited way access to the building and the areas require continuous coordination with the VA.
12-05-2022
VA
13. If there is any unforeseen situation on a stair, will the GC be able to start another stair while the issue resolves? Or will the project stop?
Milicon
11/08/2022
The contractor is responsible to develop the project schedule and sequence of the work. Such a schedule can be changed in coordination with the COR depending on circumstances that impede the sequence as planned.
12-05-2022
VA
14. Can the GC work on multiple stairs at the same time? Or one at a time?
Milicon
11/08/2022
The Contractor may propose to escalate the schedule by working on multiple stairwells at a time, but approval will be on a case-by-case basis subject to approval by the VA.
12-05-2022
VA
15. On Stairs in Mechanical Rooms most of the surrounding areas are covered by Mold, would this need to be remediated?
Milicon
11/08/2022
There is no need to remediate mold in the mechanical rooms.
12-05-2022
VA
16. On Mechanical Rooms most of the ductwork is rusted, damaged, or covered with mold, would this need to fix under the SOW of this project? Or leave as it is?
Milicon
11/08/2022
There is no need to remediate mold in the mechanical rooms.
12-05-2022
TMM
17. What are we doing with old fixtures? Are they garbage or do we turn them in to the hospital?
Milicon
11/08/2022
Dispose of demolished materials as indicated in the Bid Documents including Specification Section 02 41 00 – Demolition.
12-05-2022
TMM
18. Can we use an alternative to what's on the plans for the fixtures ?
Milicon
11/08/2022
Products other than those listed as Design Basis products and/or Scheduled in the Bid Documents may be provided if they meet the salient characteristics of the specific products indicated.
12-05-2022
TMM
19. Do we have to mark the circuit on the light fixture?
Milicon
11/08/2022
Circuit markings on fixtures is not required by the Specifications.
12-05-2022
TMM
20. None of the fixtures have a circuit number. Are we working them hot?
Milicon
11/08/2022
No, Contractor will need to trace the circuit and turn off the prior doing work.
12-05-2022
TMM
21. A.01, A.02, and A.03 show Stair 18 as alternate 5 (there may be other references to “alternate 5”). No alternate 5 exists in the solicitation. Please clarify
Blue Cord
11/14/2022
Specification Section 01 00 00, Paragraph 1.3 has been revised by Addendum to include Alternate No. 5.
12-05-2022
TMM
22. Stairs 1, 9, 10, and 11 are shown on various A.0x sheets as being on specific alternates; however, some stairs are on multiple alternates per the solicitation. Please clarify which supersedes.
Blue Cord
11/14/2022
Contractor bids should follow Bid Items as indicated in Specification Section 01 00 00, Article 1.3.
12-05-2022
VA
23. File “J.09 Attachment 09 – Past Performance Survey [3 Pages].pdf” is the same document as “J.10 Attachment 10 – Letter of Commitment Key Subcontractors [1 Page].pdf”. Please provide the correct document.
Blue Cord
11/14/2022
WILL UPLOAD CORRECT FORM

PLEASE OMMIT ATTACHEMENT 10 & 11 FROM THE REQUIREMENTS

12-05-2022

TMM
24. Please confirm the finish schedules are correct as supplied at A601 through A604 and not missing information. Specifically, there are many stairs showing “N/A” or “-“. As just two examples: Stairs 17 & 18 do not show any finishes for walls, yet these stairs are getting entirely new walls constructed.
Blue Cord
11/14/2022
Clarifications for finishes indicated on Drawings A601 – A604 are included in Addendum.
12-05-2022
TMM
25. Please clarify “P” (with no number) finish code on the finish schedule at A601.
Blue Cord
11/14/2022
Clarifications for finishes indicated on Drawing A601 are included in Addendum.
12-05-2022
TMM
26. Please provide finish details for Stair 41; it does not appear on any finish schedule.
Blue Cord
11/14/2022
Clarifications for finishes indicated on Drawing A601 are included in Addendum.
12-05-2022
TMM
27. Please clarify the different meanings indicated by “EX”, “N/A”, and “-“ on the finish schedule. We assume “EX” to mean “existing to remain as-is”, “N/A” to mean “not applicable, the surface does not exist to finish”, and “-“ to mean “existing to remain as-is.”
Blue Cord
11/14/2022
Abbreviation for “EX” is indicated on Drawing G0.2 in ARCHITECTURAL ABBREVIATIONS. Abbreviation for “N/A” has been added to Drawing G0.2 by Addendum.
12-05-2022
TMM
28. On the finish schedule, please clarify if “RF1” has the same meaning as “RF” and if “RB1” has the same meaning as “RB”.
Blue Cord
11/14/2022
Clarifications for finishes indicated on Drawings A601 – A604 are included in Addendum.
12-05-2022
TMM
29. Corner guards are called out on the finish schedule. Where are these to be used?
Blue Cord
11/14/2022
Corner guards have been deleted. Clarifications for finishes indicated on Drawings A601 – A604 are included in Addendum.
12-05-2022
TMM
30. Remark 2 on A602 does not appear on the finish schedule itself. There are two lifts shown in the drawings (stairs 19 & 43). Please clarify which, as the drawings do not indicate which is the “generator room”.
Blue Cord
11/14/2022
Remark 2 Added to Stair 19-0 on revised Drawing A602 included in Addendum.
12-05-2022
TMM
31. Lift shown at 2/A43.1 is drawn in black, indicating this is a new item. All notes on A43 indicate this is an existing lift. Please clarify.
Blue Cord
11/14/2022
Notes provided on this Drawing clearly identify existing items to remain. No change to Bid Document is required or provided.
12-05-2022
TMM
32. Please provide jamb, head, and sill details for door 17-0.
Blue Cord
11/14/2022
Door 17-0 will be an existing door assembly being installed by a separate project currently under construction.
12-05-2022
TMM
33. Please provide spec for hardware set E8 used only on door 17-0.
Blue Cord
11/14/2022
Door 17-0 will be an existing door assembly being installed by a separate project currently under construction.
12-05-2022
TMM
34. Please provide the frame type for door 8-0PB2.
Blue Cord
11/14/2022
Clarification for frame type is indicated on revised Drawing A613 included in Addendum.
12-05-2022
TMM
35. CN5 for 1/A7.1 indicates door 7-0PB2 is an existing door, frame, and hardware to remain, but the door is shown dashed, indicating to be demolished. 7-0PB2 on 4/A7.1 is shown dark, indicating a new door, frame, and hardware. The door schedule on A613 indicates the door is existing to remain with a new frame and hardware. Please clarify.
Blue Cord
11/14/2022
Clarification for door is indicated on revised Drawing A7.1 included in Addendum.
12-05-2022
TMM
36. CN2 for 2/A8.1 indicates door, frame & hardware for 8-0PB1 are all to be demolished. CN2 for 5/A8.1 states to replace the door, frame, and hardware as scheduled. The door schedule on A613 indicates the door is existing to remain with a new frame and hardware. Please clarify.
Blue Cord
11/14/2022
Clarification for door is indicated on revised Drawing A8.1 included in Addendum.
12-05-2022
VA
37. Please provide the “existing conditions report” indicated in section 02 83 33.13 for the locations of lead-based paint requiring removal and disposal.
Blue Cord
11/14/2022
The lead-based report is available and attached as part of the bid documents.
TMM
38. Please provide a specification section for signage (division 10).
Blue Cord
11/14/2022
Clarification for signage is indicated on revised Drawings A701 and A702 included in Addendum.
12-05-2022
VA
39. Please extend the bid date to December 13, 2022.
Blue Cord
11/14/2022
Bid Date was extended by previous Addendum.
12-05-2022
VA
40. Is this project tax-exempt?
Blue Cord
11/14/2022
No, this project is not tax-exempt.
12-05-2022
VA
41. Due to the instability in our current economy with price escalations and procurement issues, please change the contract type to a Fixed-Price with Economics Price Adjustments pursuant to FAR 16.203.
Blue Cord
11/14/2022
This procurement will be Firm Fixed Price
12-05-2022
VA
42. Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?
Blue Cord
11/14/2022
The project superintendent can be the SSHO. The person must meet the minimum qualifications required as per specifications and the TIL for both roles. This person must be full time at the project site.
12-05-2022
VA
43. If no to the question above, will the SSHO need to be full-time for this project?
Blue Cord
11/14/2022
Refer to the response to question 42.
12-05-2022
VA
44. Will the government clarify if there is a separate LOS form offerors must submit, in addition to the VAAR 852.219-77 form requested under paragraph (j), or if only the VAAR 852.219-77 form (provided as an attachment) is required?
Blue Cord
11/14/2022
The LOS FORM IS NO LONGER REQUIRE
12-05-2022
VA
45. We were unable to visit the roof areas during the site visit, can photos of those areas be provided?
Blue Cord
11/14/2022
The contractor can coordinate with the COR for additional site visits. Sent an email to Jorge.MoralesLopez@va.gov
12-05-2022
VA
46. Is there an established sequence for the project or can that be determined by the awarded contractor?
Blue Cord
11/14/2022
The project schedule and sequence must be developed by the contractor contingent on the coordination and approval of the VA COR.
12-05-2022
VA
47. Will the contractors be allowed to occupy multiple stairwells at a time?
Blue Cord
11/14/2022
The project schedule and sequence must be developed by the contractor contingent on the coordination and approval of the VA COR.
12-05-2022
VA
48. Will a laydown area be provided for the contract to store dumpsters and materials? If so, where will this laydown area be located in proximity to the buildings?
Blue Cord
11/14/2022
The VA will not provide a laydown area. The contractor has to coordinate to deliver materials and equipment according to the daily need per the means and method.
12-05-2022
TMM
49. Note J on sheet G0.2 indicates that scaled layout and coordination drawings will be provided prior to the start of any work. Please identify who will be responsible to provide these drawings.
Blue Cord
11/14/2022
Architectural General Note J has been deleted from Drawing G0.2 by Addendum.
12-05-2022
TMM
50. Note K on sheet G0.2 indicates that “PATCH AND REPAIR ALL DAMAGED SURFACES AS NEEDED TO INSTALL NEW WORK.” Will limits to this damaged surface be provided? This statement is vague and leaves subjective limits to the scope.
Blue Cord
11/14/2022
Design intent of Architectural General Note K is indicated as intended.
12-05-2022
TMM
51. Door 12-4 indicated a new Card Reader will be required; however, no locations are shown on the electrical drawings. Are we to assume this location already has a reader installed and we are providing a new device?
Blue Cord
11/14/2022
Remark 1 has been deleted has been deleted from Door 12-4 indicted on Drawing A614 by Addendum.
12-05-2022
TMM
52. On Sheet E55.1 it indicates that we are to provide a card reader and access control for the space. Is this to be connected into any door hardware? If not, please provide intent.
Blue Cord
11/14/2022
New work notes on E55.1 state where to route access control to and what type of system they are being added to.
12-05-2022
TMM
53. On multiple electrical sheets, it is indicated that we are to provide additional hardware in the control panel “For a complete and operational system” Can you please provide details to what is currently installed or provide a list of required hardware?
Blue Cord
11/14/2022
If this is in reference to the access control work shown this equipment is Lenel. The contactor will need to get the Lenel representative who supports this facility to give them a quote to do the work referenced on the drawings.
12-05-2022
TMM
54. Sheet E17.1 indicates that panel R.EQ2 is to be installed under a separate project. Please confirm this panel will be installed before commencement of this solicitation.
Blue Cord
11/14/2022
This project is currently under construction.
12-05-2022

END OF RFIs RECEIVED 11/15/2022