RFB-SLRDC Steel Cell Flooring Retrofit-SC-21-B-26.pdf
PDF 562 KB Posted
- Solicitation number
- 146975
- Issued by
- Spartanburg County, South Carolina
About this file
Summary: Steel Cell Flooring Retrofit - Sumter-Lee Regional Detention Center
This is a Request for Bid (RFB) document issued by South Carolina for the Sumter-Lee Regional Detention Center Steel Cell Flooring Retrofit project (RFB-SLRDC Steel Cell Flooring Retrofit-SC-21-B-26). The project involves retrofitting steel cell flooring at the detention facility. Bidders are required to submit sealed bids by the specified due date, with the contract award anticipated following the bid opening and evaluation process. A pre-bid site visit and bidders' conference are scheduled to allow prospective bidders to inspect the facility, review project conditions, and obtain clarification on project requirements and specifications.
The RFB establishes pricing requirements for all flooring retrofit materials, labor, equipment, and related work necessary to complete the project according to specifications. Bid submissions must include detailed cost breakdowns and proposed timelines for completion. The contract will be awarded to the lowest responsible and responsive bidder meeting all technical and qualification requirements. Funding for this detention center improvement project is provided through South Carolina state appropriations or facility operational budgets. Bidders must comply with all applicable state procurement regulations, bonding requirements, and performance standards for public works projects in South Carolina.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Floor Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 6, 2026
INVITATION TO BID
The Sumter County Purchasing Department is soliciting separate sealed bids from qualified vendors for the following project:
Sumter Lee Regional Detention Center Steel Cell Flooring Retrofit
INVITATION # SC-21-B-26
Bids will be received until 3:00 PM November 3, 2026, in the Sumter County Purchasing Department Conference Room located at The Sumter County Administration Building 13 E Canal Street, Sumter, South Carolina 29153.
Plans and bid documents may be obtained from the Sumter County Purchasing page at https://www.sumtercountysc.gov/departments/j_- _r/purchasing/open_solicitations_and_bid_opportunities.php or directly to the Planet Bids portal at https://vendors.planetbids.com/portal/82907/bo/bo-search . Interested bidders need to ensure they register through the site to be a vendor. Documents may also be obtained from the following; however, the Planet Bids portal is the preferred method:
Sumter County Purchasing Department 13 East Canal Street 2nd Floor Administration Building Sumter, South Carolina 29150 Email: rgalloway@sumtercountysc.gov Phone: (803) 436-2329
The County of Sumter reserves the right to reject any or all bids. The County of Sumter reserves the right to waive any or all technicalities.
Mandatory Pre-bid Meeting October 21, 2026 at 10:00 AM
Sumter Lee Regional Detention Center 1250 Winkles Road
Sumter, South Carolina 29153
INFORMATION FOR BIDDERS
1. RECEIPT AND OPENING OF BIDS
Sumter County, South Carolina (herein called the “Owner”) invites bids on the forms attached hereto, all blanks of which must be appropriately filled in. Bids will be received by the Owner in the Sumter County Purchasing Department Conference Room and will be publicly opened and read aloud. The envelope containing the bids must be sealed, addressed to Sumter County Purchasing Department, located at the Sumter County Administration Building 13 E.
Canal Street, Sumter, South Carolina, 29153 and designated as Bid for “Sumter Lee Regional Detention Center Flooring Retrofit”. The Owner may consider informal any bid not prepared and submitted in accordance with the provisions hereof and may waive any informalities. The Owner may reject any and all bids. The Owner reserves the right to negotiate with the lowest, responsive Bidder. Any bid may be withdrawn prior to the above scheduled time for the opening of bids or authorized postponement thereof. Any bid received after the time and date specified shall not be considered. No bidder may withdraw a bid within 60 days after the actual date of the opening thereof.
2. PREPARATION OF BID
Each bid must be submitted on the prescribed form. All blank spaces for bid prices must be filled in ink or typewritten.
Bids which are incomplete, unbalanced, conditional or obscure, or which contain additions not called for, erasures, alterations, or irregularities of any kind, or which do not comply with the information for Bidders, may be rejected at the option of the Owner.
The correct total amount bid for the completed work is defined as the correct sum total of the amounts bid for the individual items in the Bid. The correct amount bid for each unit price item is defined as the correct product of the quantity listed for the item by the unit price bid.
If submitting in person or by mail, each bid must be submitted in a sealed envelope bearing on the outside the name of the Bidder, Bidder’s address, Contractor’s License Number, and the name of the project for which the bid is submitted. If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope addressed as specified above.
Electronic submission of bid is permitted as well through the Planet Bids portal https://vendors.planetbids.com/portal/82907/bo/bo-search with required attachments included in this bid package.
3. SUBCONTRACTS
The bidder is specifically advised that any person, firm, or other party to whom it is proposed to award a subcontract under this contract must be acceptable to the Owner. A list of subcontractors must be provided with the bid form.
4. MODIFICATION
Any bidder may modify his bid by written or telegraphic communication (which then shall include facsimile transmission) at any time prior to the scheduled time for receipt of bids, provided such telegraphic communication is received by the Owner prior to closing time, and provided further the Owner is satisfied that a written confirmation of the telegraphic modification over the signature of the Bidder was mailed prior to the closing time. The telegraphic communication should not reveal the bid price but should provide the addition or subtraction or other modification so that the final prices or terms will not be known by the Owner until the sealed bid is opened. If written confirmation is not received within two days from the closing time, no consideration will be given to the telegraphic modification.
5. METHOD OF BIDDING
The Owner invites the following bid (s): lump sum.
6. QUALIFICATION OF BIDDER
The Owner may make such investigations as he deems necessary to determine the ability of the Bidder to perform the work, and the Bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the Owner that such Bidder is properly qualified to carry out the obligations of the contract and to complete the work contemplated therein. Conditional bids will not be acceptable. Each bidder may be required to furnish the following information after the bid opening (negative or “not applicable” responses and explanation therefore required):
(A) Professional Qualifications
1. The number, experience, and professional qualifications of the company personnel that will be directly and indirectly involved with this project.
2. Range of company services available to clients.
3. Company history, including date firm was established.
4. Availability of advisory staff and proximity of firm to job site.
5. Company philosophy regarding customer service.
(B) Prior Specific Experience on This Type Project
1. Documentation of experience in working in a Detention Center
(C) Time Frame to Start
1. Successful bidder will begin project on the date set by the
County and the Vendor.
(D) Time Frame to Complete: December 31, 2026, or an agreed upon date.
(E) Sub-Contractors and Specialty to be Utilized on Project
Respondents should identify Sub-Contractors, address, and specialty.
(F) References
1. Provide references for projects of similar size and scope of work (preferably 3 of each)
2. Provide specific mailing address, contact person, and
Telephone number (s) of each reference.
While a response is required for the information requested above, the requested information does not constitute requirements for a Bidder to be deemed “qualified” but shall be considered along with other information by Owner in making such determination.
7. BID SECURITY OR BOND
Each bid must be accompanied by cash, certified check of the Bidder, or a bid bond prepared on the form of bid bond attached hereto, duly executed by the Bidder as principal and having as surety thereon a surety company approved by the Owner, in the amount of five percent (5%) of the bid. Such cash, checks, or bid bonds will be returned to all except the three lowest Bidders within three days after the opening of bids, and the remaining cash, checks, or bid bonds will be returned promptly after the Owner and the accepted Bidder have executed the contract, or, if no award has been made within 30 days after the date of the opening of bids, upon demand of the Bidder at any time thereafter, so long as he has not been notified of the acceptance of his bid.
8. LIQUIDATED DAMAGES FOR FAILURE TO ENTER INTO CONTRACT
The successful Bidder, upon his failure or refusal to execute and deliver the contract and bonds required within ten (10) days after they have received notice of the acceptance of their bid, shall forfeit to the Owner, as liquidated damages for such failure or refusal, the security deposited with his bid. Liquidated damages will be assessed at $100.00 per day.
1. TIME OF COMPLETION AND LIQUIDATED DAMAGES
Bidder must agree to commence work on or before a date to be specified in a written “Notice to Proceed” of the Owner and to fully complete the project within the number of consecutive calendar days thereafter as indicated on the Bid Form for each consecutive calendar day thereafter as hereinafter provide in General Conditions. Bidder must agree also to pay as liquidated damages, the sum of $100.00 for each consecutive day thereafter as hereafter provided in the Scope of Work. Deadline for completion is December 31, 2026, or an agreed upon date acceptable to the Owner and the successful contractor..
2. CONDITIONS OF WORK
Each Bidder must inform himself fully of the conditions relating to the scope of the project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of his obligation to furnish all material and labor necessary to carry out the provisions of his contract.
Insofar as possible, the Contractor in carrying out his work must employ such methods or means as will not cause any interruption of or interference with the work of any other contractor.
3. ADDENDA AND INTERPRETATION
No interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any Bidder orally. Each request for such interpretation should be in writing, addressed to the Sumter County Purchasing Department 13 East Canal Street, Sumter, South Carolina 2915 or via email Email address is rgalloway@sumtercountysc.gov . To be given consideration, the request must be received by 4:00 pm on October 15, 2026. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the contract documents.
4. PERFORMANCE BOND
Simultaneously with his delivery of the executed contract, the Contractor shall furnish a surety bond or bonds as security for faithful performance of this contract and for the payment of all persons performing labor on the project under this contract, as specified in General Conditions included herein. The surety on such bond or bonds shall be a duly authorized surety company, bond shall be countersigned by an agent residing in South Carolina, and the said surety shall be satisfactory to the Owner, The Performance and Payment Bond shall be in the amount of 100% of the contract amount.
5. POWER OF ATTORNEY
Attorneys—in—Fact who sign bid bonds or contract bonds must file with each bond a certified and effectively dated copy of their power of attorney.
6. NOTICE OF SPECIAL CONDITIONS
Attention is particularly called to those parts of the contract documents and specifications, which deal with the following:
(a.) Insurance requirements
7. LAWS AND REGULATIONS
The Bidder’s attention is directed to the fact that all applicable State Laws, municipal ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout, and they will be deemed to be included in the contract the same as though herein written out in full. City/County of Sumter Business license will be required to perform this work and must be acquired within 5-7 days of the award of the contract. Project only and/or annual renewal business licenses will both meet this requirement.
8. METHOD OF AWARD
The contract, if awarded, will be awarded to the lowest responsive bidder deemed qualified by the Owner.
9. OBLIGATION OF BIDDER
At the time of the opening of bids, each Bidder will be presumed to have inspected the site and to have read and be thoroughly familiar with the plans and contract documents, including all addenda. The failure or omission of any Bidder to examine any form, instrument or document shall in no way relieve any Bidder from any obligation in respect to his bid.
18. CERTIFICATE OF INSURANCE
A. Certificates of insurance to be provided by the successful bidder at his own expense and shall be included in the return bid package. The insurance shall be written on an Occurrence basis and shall remain in effect without interruption for the duration of the Project, until final payment, or while correcting, removing, or replacing defective work, whichever is later.
B. The certificates shall apply to the Agreement by indicating the Project and naming the Owner as an “Additional Insured”, or by attachment of a policy amendment.
C. The insurance shall be written and so listed on the certificate for coverage not less than the following limits, or greater if required by law:
1. Commercial General Liability:
a. General Aggregate $1,000,000
2. Business Automobile Liability: (including all owned, non-owned and hired vehicles):
a. Combined Single Limit $1,000,000
3. Worker’s Compensation:
a. State Statutory
b. Employer’s Liability $100,000 per accident
D. All required insurance shall be written such that the Insured is the
Proposer.
19. CERTIFICATION REGARDING ILLEGAL IMMIGRATION
By signing your bid, the contractor certifies that you will comply with the applicable requirements of Title 8, Chapter 14 of the South Carolina Code of Laws and agree to provide to the State upon request any documentation required to establish either: (a) that Title 8, Chapter 14 is inapplicable to you and your subcontractors or sub-subcontractors; or (b) that you and your subcontractors of sub-subcontractors are in compliance with Title 8, Chapter 14.
Pursuant to Section 8-14-60, “A person who knowingly makes or files any false, fictitious, or fraudulent document, statement, or report pursuant to this chapter is guilty of a felony and, upon conviction, must be fined within the discretion of the court or imprisoned for not more than five years, or both.” You agree to include in any contracts with your subcontractor’s language requiring your subcontractors to (a) comply with the applicable requirements of Title 8, Chapter 14, and (b) include in their contracts with the sub-subcontractors language requiring the sub-subcontractors to comply with the applicable requirements of Title 8, Chapter 14.
BID FORM
Date: __________________________
BID OF ________________________________________________________
(Hereinafter called “Bidder”), a South Carolina corporation doing business as
TO: Sumter County Sumter County, South Carolina (hereinafter called “Owner”)
Gentlemen:
The bidder in compliance with your invitation for bids for the “Sumter Lee Regional Detention Center Flooring Retrofit”. , having examined the plans and specifications with related documents and the site of the proposed work, and being related documents and the site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed project, including the availability of materials and labor, hereby proposes to furnish all labor, material, labor and supplies to construct the project in accordance with the Contract Documents, within the time set forth therein, and at the prices stated below. These prices are to cover all expenses incurred in performing the work required under the Contract Documents, of which this bid is a part.
Bidder acknowledges receipt of the following addendum:
Bidder agrees to perform all the duties outlined in “Scope of Work” Described in the specifications and shown on the plans for the following lump sum price:
Lump Sum Amount in Numbers
Lump Sum Amount in Words
The above sum price shall include all labor, material, removal, overhead, profit, insurance, mobilization, etc., to cover the finished work of the several kinds called for.
Bidder understands that the Owner reserves the right to reject any or all bids and to waive any informality in the bidding.
The Bidder agrees that this bid shall be good and may not be withdrawn for a period of 60 calendar days after the scheduled closing time for receiving bids.
Upon receipt of written notice of the acceptance of this bid, Bidder will execute the formal contract attached within 10 days and deliver a Surety Bond or Bonds (100% of total bid amount of Lump Sum) of the General Conditions. The bid security attached in the sum of
____________________________Dollars_________________________Cents
($____________________) is to become the property of the Owner in the event the contract and bond are not executed within the time above set forth, as liquidated damages for the delay and additional expense to the Owner caused thereby.
Respectfully submitted:
BY: _____________________________________
SEAL (IF BID IS BY A CORPORATION)
Business Address
Lump sum for the complete scope of work Pricing for steel repairs per square foot $______________ per sq ft Flooring system manufacturer and product designation:
Proposed flooring system thickness __________________ Estimated project duration __________________________ Estimated project schedule _________________________ Warranty information attached References for comparable industrial, correctional or detention facility projects within the State of South Carolina or another surrounding state References to have contact name and telephone number in the blanks
BID BOND: KNOW ALL MEN BY THESE PRESENTS, that we, the undersigned as Principal, and as Surety are hereby held and firmly bound unto as Owner in the penal sum of for the payment of which, well and truly to be made, we hereby jointly and severally bind ourselves, our heirs, executors, administrators, successors, and assigns. Signed, this day of . The conditions of the above obligation is such that whereas the Principal has submitted to a certain Bid attached hereto and made a part hereof to enter into a contract in writing, for the
1250 Winkles Road, Sumter, South Carolina 29150
NOW THEREFORE,
(a) If said Bid shall be rejected, or in the alternate,
(b) If said Bid shall be accepted and the Principal shall execute and deliver a contract in the Form of Contract attached hereto (properly completed in accordance with said Bid) and shall furnish a bond for his faithful performance of said contract, and for the payment of all persons performing labor or furnishing materials in connection therewith and shall in all other respects perform the agreement created by the acceptance of said Bid, then this obligation shall be void, otherwise the same shall remain in force and effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder, shall, in no event, exceed the penal amount of this obligation as herein stated. The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its bond shall be in no way impaired or affected by any extension of the time within which the Owner may accept such Bid; and said Surety does hereby waive notice of any such extension.
IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals, and such of them as are corporate seals to be hereto affixed and these presents to be signed by their proper officers, the day and year first set forth above.
______________________________________(L.S.)
Principal
Surety
By: __________________________________________
(SEAL)
IMPORTANT: Surety companies executing BONDS must appear on the Treasury Department’s most current list (Circular 570 as amended) and be authorized to transact business in the State where the project is located.
PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS: that
(Name of Contractor)
(Address of Contractor) a Corporation, hereinafter called Principal, and
(Name of Surety) (Address of Surety) hereinafter called Surety, are held and firmly bound unto ___________________
(Name of Owner)
(Address of Owner) hereinafter called Owner, in the penal sum of ____________________________ __________________________($_______________________________) in lawful money of the United States, for the payment of which sum will and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered into a certain contract with the Owner, dated the ___________of _______________, 20______, a copy of which is hereto attached and made a part hereof for the construction of:
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions and agreements of said contract the Owner, with or without notice to the Surety, and if he shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save harmless so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.
PROVIDED, FURTHER, that the said surety, for value received hereby stipulates and agrees that no change, extension of time to be performed thereunder or the specifications accompanying the same shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.
PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of which shall be deemed an original, this the _______day of ________________, 20_____.
Principal
(Principal) Secretary
(SEAL) By __________________________
(Address) Witness as to Principal
(Address) (Surety)
ATTEST: By __________________________
(Surety) Secretary
(SEAL)
Witness as to Surety (Address)
NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute bond.
NOTE: Bond must be countersigned by a South Carolina resident agent.
PAYMENT BOND
KNOW ALL MEN BY THESE PRESENTS: that
(Name of Contractor)
(Address of Contractor) a Corporation, hereinafter called Principal, and
(Name of Surety)
(Address of Surety)
Hereinafter called Surety, are held and firmly bound unto ___________________
(Name of Owner)
(Address of Owner) hereinafter called Owner, in the penal sum of ___________________________
__________________________________________________________Dollars, ($_____________________) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered into a certain contract with the Owner, dated the _____________ of ___________________, 20______, a copy of which is hereto attached and made a part hereof for the construction of:
NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions, and agreements of said contract the Owner, with or without notice to the Surety, and if he shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save harmless so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.
PROVIDED, FURTHER, that the said surety, for value received hereby stipulates and agrees that no change, extension of time to be performed thereunder or the specifications accompanying the same shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.
PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.
IN WITNESS WHEREOF, this instrument is executed in three (3) counterparts, each one of which shall be deemed an original, this the _______day of_______________________, 20_______.
Principal
(Principal) Secretary
(SEAL) By
(Address)
Witness as to Principal
(Address) (Surety)
ATTEST:
(Surety) Secretary
(SEAL) By ________________________
Witness as to Surety (Address)
Scope of Work
1) Mandatory Demolition and Surface Preparation
Mechanically remove rubber from the side wall down to the raw steel so that new high-bond, rust-inhibitive epoxy primer that is specifically engineered for the steel substrate. Use a proper HD manual floor scraper or a rotary hammer with a wide, rigid scraper blade attachment.
Any leftover rubber adhesive or mastic must be removed with a mechanical grinder with a specialized diametric/cup wheel or wire wheels to strip the remaining glue until you hit bare metal.
To achieve the streel profile desired, the steel deck must be ground to clean, bright metal finish to meet SSPC-SP 10 Near – White Blast cleaning standard to ensure that the primer locks into the steel.
2) The desired retrofit option is the High-Build fluid applied polyurea system
That cures rapidly to minimize cell downtime.
Recommended replacement workflow:
a) Metal primer: Apply a high-bond, rust-inhibitive epoxy primer specifically engineered for steel substrates.
b) Base coat: Apply the seamless fluid-applied polyurea by rolling it continuously up the steel walls to 6 inches to create a completely sealed liquid-tight “bathtub” effect.
c) Topcoat: Finish with a chemical-resistant polyurea topcoat with a fine anti-slip aggregate for traction and color stability.
3) This project at the Sumter Lee Detention Center will include the retrofitting of approximately 84 total steel cells within the entire facility
The eighty-four steel cells are in the following areas of the Detention Center facility:
B – pod 56 steel cells C – pod 22 steel cell Medical G133 1 steel cells Booking area 5 steel cells A/C Control Room J/K Control Room Control Room Booking Platform
The specified fluid-applied polyurea will be a system manufactured by Freedom Chemical Corp or an equivalent product that must be approved by the Purchasing Department of Sumter County. An equivalent product spec sheet must be submitted 10 days prior to the BID OPENING. This type of system will require rapid return to service of the maximum-security steel cells. Drying time must be a matter of hours to foot traffic. A monolithic application that self-levels across the steel floor and wrap 6 inches up the cell walls ensures a liquid-tight, tamper proof seal.
4) To ensure a high-volume preparation the Contractor shall utilize HD floor scrapers/strippers to rapidly peel up the bulk of the rubber sheets and the thick mastic. After removing the rubber, the steel must be ground down to a clean profile. The Contractor shall utilize planetary diamond floor grinders equipped with specialized PCD scrapers to chew through the remaining adhesive, followed by metallic-bond diamond segments to achieve the required SSPC-SP 10 near white metal profile.
The Contractor shall use proper methods to mitigate dust created by the grinding down of rubber adhesive and steel scale. The Contractor must ensure air quality that remains compliant inside the facility. Any loose mechanical parts such as scraper blades, screws and bolts must be logged in and out at every shift change to prevent any items from entering the prison population.
The Contractor must utilize modern polyurea with low odor or 100% solids (VOC-free) along with venting of grinding on steel that will emit an odor.
The Contractor will use a phasing approach that is acceptable to the Sumter Lee Detention Center Administrative staff. The phase approach will allow the facility to operate as efficiently as possible and allow the polyurea coating contractor to work efficiently. The coating Contractor will maintain close communication with the facility staff to rotate the inmates thru out the detention facility.
5) The Contractor shall maintain strict on-site security controls. The Contractor shall keep a tool inventory log of every diamond grinding wheel, scraping blade, wrench and syringe must be etched, numbered and inventoried at the checkpoint before entering the facility and when leaving the facility. All the Contractors’ chemicals/products must be kept in a secure place during the work schedule. Any container for the rubber debris must be searched and cleared by guards before moving across security lines.
The Contractor shall coordinate removal of the flooring debris with Detention Center staff to minimize disruption to the Detention Center operations.
6) The Contractor shall provide to the County/Detention Center product data sheets for the proposed flooring system prior to installation for County approval.
Submittals shall include:
*Manufacturer and product name
*Technical data sheets
*Recommended system thickness
*Chemical-resistance information
*Slip resistance characteristics
*Surface preparation requirements
*Cure times and anticipated return-to-service time
*Maintenance and cleaning recommendations
*Safety data sheets (SDS)
*Warranty information
Otherwise approved, the flooring system shall be suitable for institutional/detention center applications and shall be installed by PERSONNEL CERTIFIED BY THE MANUFACTURER
IN HIGH BUILD FLUID APPLIED POLYUREA COATING SYSTEMS.
7) Because the project is located within an operating detention facility, the Contractor shall comply with all security procedures established by the Sumter Lee Regional Detention Center.
At a minimum:
All Contractor personnel shall comply with facility access, identification, screening and escort requirements.
The Contractor shall submit personnel information as required by the facility before workers are permitted on site.
Tools, equipment, and materials shall be controlled and accounted for in accordance with the facility requirements.
Contractor personnel shall not enter restricted areas without authorization.
Work schedules shall be coordinated with the facility administration.
The Contractor shall maintain secure separation between floor renovation and occupied portions of the facility.
No floor renovation activity shall compromise the security or normal operation of the facility.
8) Contractors shall protect all existing surfaces, equipment, doors, walls, drains, fixtures and other property that are to remain.
Any damage caused by the Contractor shall be repaired or replaced at the Contractor’s expense to the satisfaction of the Owner.
9) The Contractor shall provide continuous cleanup during the work and shall:
Remove construction debris from the work area Maintain safe access and egress Remove all masking and protective materials Clean adjacent surfaces affected by construction Leave completed flooring free of dust, debris adhesive, and other contaminants Remove all Contractor owned equipment and materials upon completion.
10) The Contractor shall correct at no cost to the Owner any area of the flooring renovation that exhibits any type of defect identified by the Owner according to the Scope of Work.
11) The Contactor shall provide a written manufacturers and an installer warranty covering defects in materials and workmanship.
The warranty shall identify the following:
Warranty period Covered materials and labor Exclusions Required maintenance procedures Procedures for submitting warranty claims
The proposed warranty shall be submitted with the Contractor’s bid or prior to execution of the work as directed by the Owner.
12) Contractor Responsibilities
The Contractor shall furnish all labor, supervision, materials, tools, equipment, transportation, temporary protection, disposal and incidentals necessary to provide a complete and operational flooring system.
The Contractor shall be responsible for field verification of dimensions and existing conditions before ordering materials or beginning work.
13) Owner Responsibilities
The Owner will:
Identify the areas included in the project (see drawings) Coordinate reasonable access to the work areas
Provide facility-specific security requirements and procedures
Review required submittals. Owner to choose MFR std colors.
Coordinate facility operations to the extent reasonably practicable
14) Bid Requirements
Contractors shall provide a detailed proposal that includes:
Lump sum for the complete scope of work Pricing for steel repairs per square foot Flooring system manufacturer and product designation Proposed flooring system thickness Estimated project duration Estimated project schedule Warranty information References for comparable industrial, correctional or detention facility projects within the State of South Carolina or another surrounding state
15) Completion Requirements:
The project shall be considered substantially complete when:
Existing rubber flooring has been removed from all designated areas
Substrates have been properly prepared Seamless industrial flooring has been completely installed and cured All required cove base, transitions and edge details are complete Deficiencies identified by the Owner have been corrected
Work areas have been cleaned Required documentation, warranties, and maintenance information have been submitted The facility can safely return to areas to normal use