This is a Statement of Work (SOW) for the overhaul and testing of Marotta valves for USS Sullivan (DDG 68). The Navy requires the overhaul of nine valves total: seven RM11HB-6B Marotta valves and two RM11MA Marotta valves. The valves have failed or exceeded their Planned Maintenance Periodicity and are impacting the ship's operational readiness, particularly affecting Gas Turbine Engine operations.
The contractor shall perform a standard soft kit overhaul consisting of replacement of all soft parts (o-rings, gaskets, etc.) and comprehensive testing using Original Equipment Manufacturer (OEM) parts exclusively, per maintenance specification MRC 5510/003 36M-1. Work includes preliminary inspection and disassembly, cleaning, routine overhaul, reassembly, and rigorous testing in accordance with manufacturer specifications. If preliminary inspection reveals damaged seats or hard parts beyond the scope of soft kit overhauls, the contractor must submit a Condition Found Report (CFR) and revised quote within five business days for approval before proceeding with additional repairs. The contractor shall return all valves with permanent metal tags listing test pressure, test date, part numbers, and serial numbers. Deliverables include the CFR, overhauled and tested valves, and test reports with Certificates of Conformance. The required turnaround time is 15-30 days if all valves are received simultaneously, or 30-45 days after receipt of order if received at different times. The contractor is responsible for return transportation to the ship or designated Navy receiving point on an F.O.B. Destination basis. Payment shall be made via electronic Funds Transfer through the Wide Area Workflow system. The testing site is Moody Marine Services in Atlantic Beach, Florida, and the Point of Contact is to be determined.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| solicitation N6883626Q0026 2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
USS SULLIVANS DDG 68 requires the following: Overhaul and Testing of Marotta Valves
1.0 PURPOSE / TASK DESCRIPTION
The purpose of this Statement of Work (SOW) is to define the requirements for the overhaul (soft kits only) and testing of Marotta valves. The contractor shall provide all labor, facilities, equipment, and OEM materials necessary to return the following assets to a fully mission-capable status:
· Seven (7) each: RM11HB-6B Marotta valves
· Two (2) each: RM11MA Marotta valves Reason for repairs:
Manifolds is not operating as designed or within its operating parameter which has resulted in failure to Gas Turbine Engines impacting our operational readiness. Additionally, equipment has exceed its Planned Maintenance Periodicity (PMS) and requires a complete rebuild.
2.0 SCOPE OF WORK
2.1 The contractor shall perform a standard overhaul consisting of the replacement of all soft parts (o-rings, gaskets, etc.) and comprehensive testing. The scope of effort includes the following specific tasks:
The Government will ship the 9 valves listed in the section below to the contractor.
1. 1A/1B GTM- Model NO:RM11HB-6B, MFR P/N:283145-0003, SERIAL NO: 352
2. NR 1 GTG – Model NO:RM11HB-6B, MFR P/N:283145-0003, SERIAL NO: 342
3. 2A/2B GTM Model NO:RM11HB-6B, MFR P/N:283145-0003, SERIAL NO: 351
4. NR 2 GTG Model NO:RM11HB-6B, MFR P/N:283145-0003, SERIAL NO: 363
5. MAIN 1 HP/LP CROSS CONNECT Model NO:RM11JA-5, MFR P/N:283048-0004, SERIAL NO: M1002
6. MAIN 2 HP/LP CROSS CONNECT Model NO:RM11JA-5, MFR P/N:283048-0004, SERIAL NO: 257
7. NR 3 GTG Model NO:RM11HB-6B, MFR P/N:283145-0003, SERIAL NO: 269
8. AEB REDUCING Model NO:RM11JA-5, MFR P/N:283048-0004, SERIAL NO: M1002
9. GT WATER WASH Model NO:RM11MA-1, MFR P/N:281163-0008, SERIAL NO: 380
2.2 Preliminary Inspection and Disassembly
The contractor shall conduct preliminary testing, disassembly, and inspection of each manifold upon receipt to determine the current condition and extent of necessary repairs.
2.3 Cleaning and Routine Overhaul
The contractor shall clean and inspect all internal and external parts. All soft parts, including but not limited to o-rings and gaskets, shall be replaced. Mandatory Requirement: All replacement parts utilized in this overhaul shall be Original Equipment Manufacturer (OEM) parts exclusively.
* Maintenance shall be IAW MRC 5510/003 36M-1. See attached.
2.4 Condition Found Report (CFR) for "Over and Above" Repairs This SOW covers "soft kit" overhauls. In the event that the preliminary inspection reveals damaged or worn seats and/or hard parts, the contractor shall halt work on the affected unit. The contractor shall submit a formal Condition Found Report (CFR) and a revised quote for the additional "over and above" repairs and parts to the Technical Point of Contact (TPOC) within 5 business days of discovery. No "over and above" work shall proceed without explicit written modification by the Contracting Officer.
2.5 Reassembly and Testing
Completed manifolds shall be reassembled and rigorously tested in accordance with the latest applicable manufacturer specifications and technical manuals.
2.6 Identification and Tagging
Following successful testing, the contractor shall permanently affix a metal tag to each manifold. The tag shall clearly list:
· Test Pressure
· Date of Test
· Manifold Identification (Part Number and Serial Number)
2.7 Upon completion of the tasks above, the contractor shall return all valves to the government in the required condition as specified in this SOW.
3.0 DELIVERABLES
| Deliverable |
| Description |
| Due Date |
| Condition Found Report (CFR) |
| Report detailing required hard parts/repairs beyond standard soft kits, including a revised quote. |
| Within [5] days Five Business Days |
| Overhauled Valves |
| 9 fully overhauled, tested, and tagged Marotta valves |
| In accordance with the established Period of Performance (Section 6.0). |
| Test Reports & CoC |
| Certificate of Conformance (CoC) and individual test reports verifying compliance with manufacturer specs. |
| To be shipped concurrently with the overhauled valves. |
4.0 PLACE OF PERFORMANCE
No, testing will be conducted off-site government facility Testing Site:
Moody Marine Services 589-1 Levy Rd Atlantic Beach FL 32233 904.247.1041
5.0 PERIOD OF PERFORMANCE
The required turnaround time (TAT) for the standard "soft kit" overhaul of all 9 units is 15-30 days to accomplish if all 9 Marotta valves are received at the same time. If received at different times, 30-45 days After Receipt of Order (ARO) and receipt of the GFP at the contractor's facility.
6.0 PACKAGING, HANDLING, STORAGE, AND TRANSPORTATION (PHS&T)
All overhauled units shall be packaged to prevent damage, deterioration, and corrosion during transit and standard storage.
Responsibility for shipping the valves from USS The Sullivans (or the local warehouse) to the contractor's facility. The Government must ensure the valves are "Clean, Drained, and Safe" prior to transit.
Upon completion of the overhaul/test, the contractor must package the valves to prevent damage during the return trip. This usually requires Level A or B Preservation and packaging in accordance with MIL-STD-2073-1 (Military Packaging).
F.O.B. Destination : The Contractor is responsible for the cost and risk of transporting the overhauled valves all the way back to the ship or designated Navy receiving point.
7.0 QUALITY ASSURANCE
The contractor shall maintain a Quality Management System (QMS) adequate to ensure all testing and OEM part integration meets manufacturer specifications. A Certificate of Conformance
8.0 POINT OF CONTRACT
TBD
9.0 METHOD OF PAYMENT
WIDE AREA WORKFLOW / Payment should be made via electronic Funds Transfer (ETF)