Reuqest For Quote For Move Service_Northamption_DDS.docx
DOCX document 76 KB Posted
- Attached to
- DDS Northampton Office Move FHAO
- Solicitation number
- BD-27-1023-DMR11-DMRCW-134093
- Issued by
- Massachusetts
About this file
This is a Request for Quote (RFQ) document issued by the Massachusetts Department of Developmental Services (DDS) for moving services in Northampton. The RFQ seeks qualified vendors to provide comprehensive relocation services for agency operations or facilities. The scope of work includes standard moving services such as packing, loading, transportation, unloading, and delivery of furniture, equipment, and materials. Specific item quantities and detailed logistics requirements are outlined within the document to enable accurate quoting. Interested vendors were required to submit quotes by the specified deadline to be considered for award. The contract term and any renewal or extension options are contingent upon the successful completion of the initial move and mutual agreement between DDS and the selected vendor.
Pricing for the moving services is to be submitted on a competitive basis, with vendors responsible for providing detailed cost breakdowns for labor, equipment, transportation, and any additional services required. The RFQ does not indicate set-asides for small or disadvantaged businesses, though vendors should verify current Massachusetts procurement regulations. No incumbent vendor information is referenced in the document. Funding for this project is sourced through the Department of Developmental Services' operational budget. Vendors should confirm their capacity to meet DDS's specific timeline and logistical requirements prior to submitting their quotes.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTE FOR MOVE SERVICES (RFQ)
THE COMMONWEALTH OF MASSACHUSETTS
Executive Office of Health and Human Services (EOHHS) EHS Facilities
This order is placed under Statewide Contract FAC 127. All the terms and conditions of the Statewide Contract FAC 127 are incorporated herein and made a part hereof. Conflicting or additional terms, conditions or agreements shall be superseded and void.
This move involves the office relocation for: Department of Developmental Services
Current Address: One Roundhouse Plaza, Northampton MA New Address: 296 Nonotuck Street, Northampton MA Additional Address related to move
Note:
Is a surplus removal required from the current address One Roundhouse Plaza, Northampton MA? YES |_| / NO |_| Note:
All surplus to be removed will be Black Labeled
A certified payroll record must be submitted with the invoice.
The Commonwealth of Massachusetts is self-insured and is not purchasing additional insurance.
Move Components Requested:
☒ Component #1: Office Relocation Inventory for DDS - see Addendum A ☒ Component #2: Surplus removal Inventory - see Addendum B & C ☐ Component #3: Assembly of new furniture - see Addendum D
CONTACT INFORMATION:
| EOHHS Project Manager: | Vince Laberinto | |
| EHS Facilities | ||
| 617-592-7267 | ||
| Vincent.Laberinto@mass.gov |
Submission Deadline: October 19, 2026
All responses must be submitted via Commbuys by October 19, 2026 ON 1:00 pm.
The bid process will be closed at that time and all bids received after that will not be considered.
· A vendor site visit for this move will be conducted on October 14, 2026 at 1:00 PM.
· Move Days - October 30th
Please remember to include the dollar amount of your bid on the “quote total” column of the header information page. Please be sure to attach the detailed breakdown of your bid using the attachment portion on the header page.
DETAILS:
The day(s) of the move are linked to contractual agreements, and a construction schedule is firm at the time of this quote. The vendor will agree to these dates, knowing there may be construction delays:
This move shall be completed in no more than 1 Days
The vendor must be responsible for all permits and regulatory requirements.
The move must be conducted in a safe and secure manner.
General packing services are not requested.
The vendor will not be responsible to disconnect or unplug computers or equipment.
Origin:
Address/location: One Roundhouse Plaza, Northampton MA
Passenger Elevator available
Masonite Sheets to be located
Loading dock available
| Note: |
| Items located on 2nd floor and 1st floor conference room |
Destination 1:
Address/location: 296 Nonotuck Street, Northampton MA Passenger Elevator available
Masonite Sheets to be located
Loading dock available
| Note: |
| Office space is located on 2nd floor |
Destination 2:
Address/location:
Passenger Elevator available
Masonite Sheets to be located
Loading dock available
| Note: |
Destination 3:
Address/location:
Passenger Elevator available
Masonite Sheets to be located
Loading dock available
| Note: |
Special Handling Requirements:
Installer and tools:
Preparation Materials:
Moving vendor will not need to provide: Labels for this move are already with the agencies already the labels breakdown is detailed below:
Labels Location
296 Nonotuck St
Trash
Moving Crates/Computer Bags/Bubble Wrap
| Count | Note: | |
| 80 | ||
| moving crates |
| 33 |
| computer bags/bubble wrap |
· Please schedule to have the moving crates and the rest of the materials delivered to One Roundhouse Plaza, Northampton MA, on October 21st. The crates and materials can be picked up at 296 Nonotuck Street, Northampton MAon 11/09 for a 9 day rental.
· Broom Swept Services are required at One Roundhouse Plaza, Northampton MA by the conclusion of the Surplus Removal (4:00 PM).
· Please include costs for all supplies & Move materials in your bid
Inventory:
Addendum A identifies the type and quantities of DDS office furnishings and equipment to be relocated to 296 Nonotuck Street, Northampton MA
Addendum B identifies the type and quantities of office furnishings and equipment to be relocated to296 Nonotuck Street, Northampton MA 296 Nonotuck Street, Northampton MA
Addendum C identifies the type and quantities of DDS, office furnishings and equipment to be relocated to Surplus
Vendor Shall Provide:
1. Prevailing Wage Sheets (to become part of the Scope of Work) Your bid will not be considered without the wage sheets.
2. Primary Contact Information for both working hours and after working hours
3. Cost Estimate 4.
Evaluation Criteria:
1. Mandatory requirements
1. Cost Evaluation
| 2.1 | Price broken out by each move day, junk run, broom sweep |
| services and settling crew (if applicable) | |
| 2.1.1 | Including Prevailing Wage Sheets |
| 2.1.2 | Breakout of travel time |
| 2.1.3 | Quantity, type, and cost of vehicles |
| 2.1.4 | Moving supplies (dollies, padding, etc.) |
| 2.1.5 | Moving materials requested (labels, crates, keyboard bags, special |
| equipment, etc.) | |
| 2.1.6 | Miscellaneous costs: permits, fees, disposal |
After the quotes have been received and reviewed, DDS & will make their selection and notification notices will be emailed out. EOHHS reserves the right to amend the scope of work with the awarded bidder prior to the actual move date and the awarded bidder agrees to negotiate in good faith all amendments to the scope of work.
All quotes are to be “not to exceed” and are final.
Addendum A
Inventory count of DDS furniture and equipment included in the relocation to 296 Nonotuck Street Northampton MA:
DDS Move inventory
Office Furniture
| Desks |
| 15 - 2 |
11 needed
| Chairs-Rolling |
| 25 |
| Chairs-Guest/Stacking |
| 27 |
| Tables |
| 0 |
| Folding Tables |
| 14 |
| Rolling Easel |
| 1 |
| Podium |
| 0 |
| Bookcases |
| 0 |
| Vertical File Cabinets |
| 0 |
| Lateral File Cabinets |
| 2 |
Computer Equipment
| PCs w monitor |
| * 1 |
| Monitor w/dock |
| 30 docks |
| Desk printers |
| 1 (Kelly's color) |
| Copy machine |
| 2 (1 Ricoh; 1 Toshiba) |
Other Items
| Moving crates |
| - |
| Small refrigerator |
| 0 |
| Mail/Moving Carts |
| 1 |
| XL Boxes |
| 100? |
| REG Boxes |
| 15? |
| Postage machine (Pitney Bowes) |
| 1 |
| Storage cabinets |
| 0 |
| Plastic Storage Bins |
| - |
| Microwave |
| 2 |
| Chair Carts |
| 0 |
| Projector screen |
| 1 |
| Car seats |
| - |
| 2-wheeeler |
| 1 |
| TV |
| - |
| Changing Table |
| - |
| White board |
| 4 |
| Lounge Chair |
| 3 |
| Sofa/Bench |
| 1 |
| Modular Furniture Pieces |
| 1 |
| Pack N Play-Boxed |
| - |
| Step ladder |
| 3 |
(1 - 1 step; 2 - 3 step)
| Set of Kids Table w/ 4 chairs |
| - |
| Play Kitchen/Dollhouse |
| - |
Addendum B
JUNK items to be properly disposed of after relocation is completed. Removed from One Roundhouse Plaza Northampton MA:
DDS to Junk
Office Furniture
| Desks |
| 25 |
| Chairs-Rolling |
| 20 |
| Chairs-Guest |
| 34 |
| Chairs-Guest/Stack |
| 1 |
| Tables |
| 17 |
| PC Carts |
| 5 |
| Folding Tables |
| 0 |
| Bookcases |
| 17 |
| Vertical File Cabinets |
| 51 |
Large (4/5 drawer): 32 2 drawers: 19
| Lateral File Cabinets |
| 0 |
Other Items
| Large refrigerator |
| 1 |
| Small refrigerator |
| 0 |
| Storage Cabinets |
| 3 |
| Coat Tree |
| 0 |
| Metal Racks |
| 0 |
| Glider Chairs |
| 0 |
| IT Equipment |
| All |
| White boards |
| 3 |
| Chalk Board |
| 0 |
| Cork Board |
| All |
| Easel |
| 3 |
| Mail Machines |
| 0 |
| TV cart/Stand |
| 3 |
| TV |
| 1 |
| Small Safe |
| 1 |
| Mail bins |
| x 4 |
| Standing paper fixtures |
| 3 |
Addendum C
Inventory count of equipment included in the relocation from to
Office Furniture
Other Items
| Note: |
Month: October Year: 2026
| Sun |
| Mon |
| Tue |
| Wed |
| Thu |
| Fri |
| Sat |
SITE VISIT
BIDS DUE @1PM
DELIVER CRATES
NOTE: Site Visit on 10/14/2026 @ 1PM - MOVE DATE 10/30/2026
Key Information
| Department #1 |
| Department of Developmental Services |
| Department #2 |
| Department #3 |
| Agency Acronym #1 |
| DDS |
| Agency Acronym #2 |
| Agency Acronym #3 |
| FAC |
| 127 |
| Current Address |
| One Roundhouse Plaza, Northampton MA |
| New Address |
| 296 Nonotuck Street, Northampton MA |
Additional Address
| Destination #2 |
| Destination #3 |
| Move Start Date |
| October 30, 2026 |
| Move End Date |
| October 30, 2026 |
| Time Start |
| 8:00 AM |
| Time End |
| 4:00 PM |
| COMMBUYS Submission Deadline |
| October 19, 2026 |
| COMMBUYS Submission Time |
| 1:00 pm |
| Site Visit Date |
| October 14, 2026 |
| Site Visit Time |
| 1:00 PM |
| Total Days to Complete Move |
| 1 Days |