AE IDIQ Eastern Region - Architect and Engineer Services Contract

This is a Statement of Work and contract specification document for an Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract providing comprehensive Architect and Engineer (A-E) services to the U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), and other federal agencies. The contract covers the NOAA Eastern Region, encompassing 34 states plus Puerto Rico and the U.S. Virgin Islands. The A-E contractor must provide professional services including project management, facility programming, planning, facility condition surveys, cost estimating, value engineering, design services (both design-bid-build and design-build), commissioning, construction management, and construction inspection services. Services are ordered through individual task orders, each negotiated as a firm fixed-price contract based on a detailed scope of work. The contractor must submit price proposals using a seven-item format (labor hours and rates, direct overhead, indirect overhead, materials and supplies, travel, reproduction, and profit), with design costs clearly separated to ensure compliance with a 6% design fee limitation.

The contract specifies detailed deliverables and performance requirements across multiple service categories. Design submittals must progress through 15%, 35%, 65%, 95%, and 100% completion stages, with specifications edited from Unified Facilities Guide Specifications and drawings submitted in PDF and native AutoCAD/Revit formats. Cost estimates must follow UFC 3-740-05 standards and be prepared by certified cost engineers in UniFormat II. The A-E must establish a project management plan with monthly progress reports, project tracking systems, and cost estimating systems. Construction management and quality assurance services include pre-bid and pre-construction conferences, shop drawing reviews, RFI responses (within 5 days), site visit reports, punch list management, and as-built drawing verification. Commissioning services require a NEBB-certified or Building Commissioning Association member to serve as Commissioning Agent, with responsibilities spanning design, construction, acceptance, and warranty phases. The contract prohibits the A-E, its parent firm, subsidiaries, or affiliates from competing for resulting construction contracts under Federal Acquisition Regulation provisions. All deliverables including digital copies must be provided in unlocked, editable native format, with ownership remaining with the Government.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AE IDIQ EASTERN REGION

SECTION C DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.1 GENERAL REQUIREMENTS

This is an Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract for Architect and Engineer (AE) Services as required by the U.S. Department of Commerce (DOC), National Oceanic and Atmospheric Administration (NOAA) and other federal organizations. The purpose of this contract is to provide the Department of Commerce (DOC) and other Government Agencies with a full range of professional Architectural and Engineering (A-E) services including project management, facility programming, planning, facility condition surveys, project cost estimating, value engineering, engineering studies and analyses, architectural and engineering design services including design-build and traditional design-bid-build, commissioning, construction management, and construction inspection services. Except as otherwise specified herein, the Contractor shall furnish the necessary personnel, materials, equipment, services, and facilities and otherwise do all things necessary for or incidental to the performance of the work set forth in the following Statement of Work (SOW).

Projects may be at various locations within the contiguous United States, Alaska, Hawaii, and in the U.S. Territories including Puerto Rico and the Pacific Islands. This contract is intended to serve the NOAA Facility Engineering Office (FEO) and associated NOAA facilities offices with work in NOAA’s Eastern Region. The primary geographic area includes but is not limited to:

Eastern Region:

Alabama Arkansas Connecticut Delaware Florida Georgia Illinois Indiana Iowa Kansas Kentucky Louisiana Maine Maryland

Massachusetts Michigan Minnesota Mississippi Missouri Nebraska New Hampshire New Jersey New Mexico New York North Carolina Ohio Oklahoma

Pennsylvania Rhode Island South Carolina Tennessee Texas Vermont Virginia West Virginia Wisconsin Puerto Rico and the U.S.

Virgin Islands.

C.1.1 PROPERTY, EQUIPMENT, SUPPLIES, FACILITIES, PERSONNEL AND SERVICES

Except as otherwise specifically provided herein, all property, equipment, supplies, facilities, personnel, and services required to perform the work called for under individual task order(s) shall be furnished by the Contractor. All data, materials, information, etc., provided by the Government, or developed by the Contractor in the performance of the work, shall remain the exclusive property of the Government. Digital copies of deliverables shall be provided in unlocked and editable native format. Upon completion or termination of the contract and / or subsequent task order(s), the Contractor shall turn over to the Government all materials (including copies) that were furnished to the Contractor by the Government and all materials that were developed by the Contractor in performance of work under the contract / task order(s).

C.1.2 SCOPE

This Statement of Work (SOW) describes requirements to accomplish the various tasks and defines the services the Architect and Engineer (A-E) shall perform. The primary emphasis of the effort to be ordered by task order under this contract is anticipated to fall in the technical discipline areas of architecture and engineering. The AE will be required to provide traditional design-bid-build and design-build solicitation packages. Task orders will require professional cost estimating services.

Engineering disciplines may include civil, structural, mechanical/HVAC, plumbing, and electrical engineering. Other technical disciplines (examples: environmental, geotechnical, marine/waterfront, value engineering, interior design, landscape design, commissioning, acoustical engineering, laboratory consulting, etc.) may be needed to fulfill the requirements of a task order.

The A-E Contractor shall provide professional architectural, engineering, and consultation services to provide planning, programming, and design solutions to identify and resolve problems in the implementation of Government facility projects. The work may include the preparation of engineering studies, life-cycle cost or trade-off analysis, commissioning / re-commissioning services, value engineering services, feasibility studies, identification of environmental issues, DBIA owner-advisor services, preparation of alternate design solutions, construction cost estimates, verification of construction contractor's efforts, investigation and justification of construction cost overrun, land surveys, geotechnical surveys and soils investigations, pre-design site investigations and documentation of existing facility conditions, engineering and architectural design and review, construction management, construction observation/Quality Assurance, engineering during construction, building commissioning / re-commissioning, assistance in preparing building maintenance planning services, system component training, construction warranty inspections, and follow-up inspections of facilities after construction is complete.

C.1.3 TYPES OF SERVICES

In accordance with the terms of this contract, the Government will request the A-E Contractor to provide Architectural and Engineering services associated with the evaluation, planning, design and construction of new facilities; the renovation/repair/expansion and demolition of existing facilities; and various studies, at NOAA sites. AE IDIQ services may include, but are not limited to, the following:

1) Planning services

a. Master planning

b. Strategic planning

c. Facility planning

d. Move/Logistics planning (related to relocation/phasing)

2) Professional services

a. Owner-advisor services (as defined by DBIA)

b. Program development

c. Space needs/utilization analysis

d. Code-compliance review and analysis

e. Feasibility studies

f. Business case analysis

g. Budget cost estimating

h. Life-cycle cost analysis

i. Cost and schedule risk analysis (CSRA)

j. Sensitivity analysis

k. Environmental surveys

l. Environmental impacts analysis and report in accordance with NEPA

m. Permitting

n. Evaluation for historic significance in accordance with National Register criteria

o. Archaeological surveys and documentation for NHPA Compliance

p. Third-party design and cost estimate reviews

3) Design Services

a. Conceptual design development

b. Conceptual cost estimating for budgeting purposes

c. Preparation of contract documents (Plans and Specifications)

d. Preparation of Performance Work Statements

e. Preparation of Independent Government Cost Estimates (IGCE)

f. Design Build statement of work and RFP development

g. Design Drawings and specifications for minor repair/renovation

h. Interior Design

i. Furniture Design/Procurement Services

4) Post-construction award services

a. Submittal review

b. RFI evaluation and response

c. Design clarifications

d. Construction administration services

e. Construction support services

f. Change Order evaluation and estimation

g. Quality Assurance support

h. Construction observation and inspection services

5) Other Special Consultant and Investigative Services

a. Existing facility investigations

b. Coastal Engineering investigations/studies/reports

c. Building envelope consulting for new construction

d. Building envelope consulting and investigations for existing facilities

e. Existing facility forensic investigations

f. Facility Condition Assessments (FCA’s)

g. As-built drawing verification and development

h. Building modeling

i. Site selection

j. Survey–topographic/boundary/utility

k. Soil borings and testing services / geotechnical analysis

l. Seismic studies/evaluation

m. Environmental studies

n. Environmental/Industrial hygienist services for assessment and remediation

o. Storm water / drainage

p. Archaeological/Historic preservation studies and design

q. Traffic study

r. Security studies

s. Acoustical design

t. Commissioning / Retro-commissioning

u. Post occupancy evaluation

v. Cost estimating/validation studies

w. Peer reviews

x. Exhibit planning/design

y. Claims consultation, analysis, and estimation

z. Value engineering–A/E design team participation in VE study efforts

C.1.4 TYPICAL FACILITIES

Typical facilities may include, but not limited to, the following:

1) Office buildings

2) Warehouses and storage buildings

3) Laboratories and research facilities

4) Wharf and pier structures/infrastructure

5) Seawalls and other coastal construction

6) Communications installations

7) Weather forecast offices

8) Data centers

9) Communication/data equipment installations/platforms

C.1.5 TASK ORDERS

The Government will request services in accordance with the ordering provisions of this contract.

Task orders (TOs) will be issued for individual projects. Each TO will be a negotiated firm fixed price contract based on an individual SOW which shall state:

1) The scope of work to be performed;

2) Anticipated AE IDIQ Contractor tasks including, if any, field work, testing, analyses, design, meeting attendance, documentation of/for each task, etc.;

3) Required Deliverables and Ownership of Material;

4) Government Provided Materials and/or Services;

5) Computer Compatibility Requirements for deliverables;

6) Specialized Codes, Standards, References, and Publications;

7) Schedule of Deliverables

8) Period of Performance with schedule for intermediate milestones

C.1.5.1 ISSUE OF TASK ORDERS

Services to be performed shall be ordered by the issuance of individual task orders. A detailed scope of work will be provided. The A-E shall prepare a price proposal in a seven-item format including the following:

labor- hours and rates, direct overhead, indirect overhead, materials and supplies, travel, reproduction, and profit. The A-E shall provide sufficient detail for each element to allow a thorough analysis by the Government. The A-E shall separate all work to which the 6% design fee limitation applies. The proposal must clearly identify and separate design cost to assure the 6% fee limitation has not been exceeded. The proposal shall be submitted to the CO.

When an agreement is reached, a bilateral task order shall be issued, specifying all agreed terms and incorporating the provisions of this contract. If agreement cannot be reached, the CO shall terminate negotiations with the A-E. In the event such negotiations are terminated, the Government reserves the right to commence negotiations with other architectural and engineering firms.

C.1.6 PROJECT MANAGEMENT AND PLANNING

The A-E shall establish and maintain a project management plan which can be used to track and manage the contract Task Orders. The A-E shall provide project management and planning support to assure that all assigned tasks are completed and submittals made in accordance with the task order schedule. The project management and planning function shall assure the A-E identifies and coordinates critical milestones in the project design and construction schedule with the Government.

The A-E shall identify in writing to the CO and task order Contracting Officer's Representative (COR) issues and decisions requiring Government action, which will impact the project schedule or cost.

The A-E shall provide project management and planning for all areas of engineering support. The A-E shall be responsible for preparing accurate and timely assessments for the Government on status and progress on all Task Orders by subtasks. The A-E shall utilize a project tracking system (a secured website may be utilized for this purpose), and cost estimating system that will measure, evaluate, and report the effect (in time and dollars) of changes to facilities construction projects, and associated tasks.

C.1.6.1 PROGRESS REPORTS

The A-E shall submit a progress report to the CO and the COR with each invoice or at least monthly if no separate invoice is submitted by task at month's end. (A secured website may be used for this purpose). The progress report shall indicate the status of all Task Orders awarded under this contract. The progress report shall be prepared so it conveys the overall status including billings to date, percent of task complete, actual schedule versus planned schedule, major actions, and persons or organizations responsible for completing the actions. A sample report format shall be submitted to the COR for approval within 30 days of the issuance of Notice to Proceed.

The A-E shall submit progress schedules as part of the monthly progress report using Microsoft Project or an A-E proposed and Government-approved alternate program. Provide a schedule for each Task Order to reflect subtasks, task durations, and task interdependencies. The A-E shall identify contractual milestones and report progress and measure A-E and project performance against the milestones and schedules established for all submittals in the delivery schedule of the Task Orders.

C.1.6.2 The A-E shall conduct an initial management review meeting prior to award of the initial Task Order to this contract. At this meeting, the A-E and the Government shall identify primary and secondary points of contact, establish lines of communication, and review procedures for the conduct of the contract. The A-E shall present the methods and approach for developing the plans and schedules to complete the work. The A-E shall present methods of tracking and reporting each of the tasks to be completed under this contract. The A-E shall identify standard office practices for guide specifications, drawing format and cost estimates.

C.1.7 PROJECT COORDINATION

The A-E's Project Manager and the task order COR’s shall conduct Management and Technical Review Meetings when warranted. At least 5 working days prior to each meeting, the A-E shall provide the agenda for the meeting to the COR. Status of tasks and subtasks to be performed, logical relationships among those tasks, major schedule milestones, and discussions of areas of responsibility and accomplishments of the key people assigned to the contract shall be included. The A-E shall identify problems and propose alternate solutions with recommendation of best option. Management Technical Reviews shall include information on project status, with primary emphasis on schedule status and information on key events, significant accomplishments, near-term milestones, cost, problem identification and analysis, and a personal assessment of status by the A-E's Project Manager. The COR shall review the status of Government action items, identify his approval or non-concurrence with the A-E's status report, and discuss the A-E request for payment. The A- E shall prepare the meeting minutes, including presentation material and support documentation, and shall record action items. A copy of the minutes shall be provided to the COR within 5 days of the meeting.

The A-E’s project manager and key technical personnel shall be available for participation in Government reviews, and planning meetings as identified in Task Orders.

The A-E shall establish method(s) of rapid message transmittal (letters and drawings) between the Government and the A-E. Methods shall include, but not be limited to, email, secured website FTP (permitted by NOAA IT Security), multiparty conference calls, use of same day courier services, and use of overnight package service. The A-E shall utilize computer software compatible with the following resident Government systems;

Microsoft Office, and Computer Aided Drafting and BIM (Autocad LT and Revit LT). BIM 360 is currently no approved for use by U.S. Department of Commerce agencies. NOAA intends to require use of BIM on all new construction and most renovation projects. NOAA will provide a BIM Standards document and a BIM Template Revit file for use on these projects. NOAA currently uses the suite of Google tools and has full access to Google Drive, Google Meet, and Google Mail.

C.1.8 HANDLING OF SENSITIVE MATERIAL

It is anticipated that in performing the contract, the A-E may have access to and use of information, material, and data for which release is unauthorized. All DOC Construction of Facilities Program financial and management information; proprietary or procurement sensitive information of other parties contained in or furnished under DOC contracts or agreements; and data submitted to NOAA marked with restrictive legends are restricted documents.

The A-E shall protect the interests of the Government and other parties with respect to such information and data. The A-E agrees not to disclose the NOAA financial and management, proprietary, or procurement sensitive data, material, and information to others without the written consent of the CO; and to abide by the conditions of restrictive legends contained in any data, material and information. These restrictions do not limit the A-E's right to use and disclose any data, material, and information obtained from another source without restrictions.

C.1.9 COMPLIANCE WITH CODES AND STANDARDS

The design for any project shall comply with the current, applicable edition of nationally recognized model codes including, but not limited to, building, fire and life safety, electrical, plumbing and sustainability codes.

Full consideration shall be given to all requirements (other than procedural requirements) of local zoning laws and laws relating to landscaping, open space, setbacks, maximum height, historic preservation, aesthetic qualities, and other similar laws of the state or political subdivision. The A-E shall obtain copies of all applicable codes and ordinances from the appropriate authorities as necessary for reference. The A-E shall consult with appropriate local officials and, upon request, submit plans to local building officials for review in a timely manner. The A-E shall allow local officials a review period of up to 30 days. The A-E shall give due consideration to any recommendations of such officials.

All designs shall allow full access and utilization by the handicapped in accordance with the ABA or ADA, as applicable.

C.1.10 LIMITATION ON CONTRACTING FOR RESULTANT CONSTRUCTION WORK

Pursuant to the provisions of the Federal Acquisition Regulation (FAR), the A-E, its parent firm, subsidiaries, or affiliates are ineligible to compete for construction contracts resulting from design services furnished under this contract.

C.1.11 A-E RESPONSIBILITY Reference FAR 52.236 – 23.

C.1.11.1 The design architects and engineers of record are fully responsible for the sufficiency of design.

The A-E will be responsible for all work and services provided under this contract and the correction of any design errors or deficiencies and reimbursement of any reconstruction costs or damages incurred by the Government resulting therefrom, pursuant to the provisions of clause Responsibility of the Architect-Engineer Contractor, FAR 52.236 – 23.

C.1.11.2 Should Government initiated design changes, as a result of revised criteria, be required during this period, the A-E may be required to perform the necessary redesign work. In those instances, the contract will be modified accordingly, including an adjustment in the contract amount.

C.1.11.3 In the event ambiguities, discrepancies, omissions, or other errors in the drawings and specifications are discovered, the A-E shall revise the contract drawings and specifications and prepare necessary data, including detailed cost estimate, and information to permit issuance of amendments or modifications by the Government. This work shall be accomplished at no additional cost to the Government.

C.1.11.4 Changes to this scope of work shall be made only at the direction of the Contracting Officer.

Should the A-E receive any direction or design criteria that are not included in this contract that requires additional effort beyond the contract criteria, the Contracting Officer shall be notified in writing describing the change and impact. The A-E shall not commence work until approval is received from the Contracting Officer.

C.1.11.5 A-E approval of Contractor shop drawings which are inconsistent with the A-E's original design, and which prove to be inadequate for design intent, may be considered a design error or deficiency by the Contracting Officer.

C.1.11.6 Cost Limitation: When the construction estimates, bids, proposals, or total cost exceeds the cost limitation, the A-E shall immediately notify the COR in writing. With such notification, the A-E shall value engineer, redesign, and resubmit to permit contract award within the cost limitation.

This shall be done at no additional cost to the Government, and the A-E shall reimburse the government for damages (see Federal Acquisition Regulations FAR 52.236-23), including estimated delay damages, such as the additional construction cost escalation, resulting from inaccurate estimates or a failure to produce a design within the cost limitation. The A-E shall bear the burden of proof in the event that unfavorable bids or proposals are the result of conditions that could not possibly be projected.

C.2 PROFESSIONAL SERVICES

C.2.1 FACILITY SURVEYS, COMMISSIONING / RE-COMMISSIONING, COST ESTIMATING, VALUE

ENGINEERING AND ANALYSIS.

The A-E shall provide a full range of architectural and engineering services for the study, evaluation, and analysis of Facilities and Equipment (life cycle-cost, replacement or repair) for NOAA clients. The following list of activities is indicative of the types of services to be provided: It is not intended to be a definitive listing or indicate any order of priority.

1) Topographic surveys and other related support activities (includes identification of wetlands and environmentally sensitive property)

2) Land surveys (metes and bounds)

3) Facility condition surveys of Government facilities for capital improvements program and maintenance

4) Technical inspection of lease buildings

5) Building safety and code compliance inspections

6) Verification of drawings, plans, and other documentation of as-built conditions

7) Site investigations for facility operational problems

8) Geotechnical investigations

9) Engineering and utility studies

10) Coastal engineering studies, to include estimates and impacts from forecasted sea-level rise

11) Life-cycle cost analysis in accordance with UFC 1-200-02, 10 CFR Part 436, Subpart A, and NIST

Handbook 135 Life Cycle Costing Manual for the Federal Energy Management Program

12) Cost and Schedule Risk Analysis (CSRA) in accordance with UFC 3-740-05 Construction Cost

Estimating and GAO Schedule Assessment Guide, GAO-16-89G

13) Sensitivity Analysis in accordance with UFC 3-740-05 Construction Cost Estimating

14) Computerized facility evaluation and report

15) 3D scanning, measurement, and documentation of existing facilities

16) Chemical hygiene for laboratory plans

17) Environmental studies and evaluation including hazardous material studies, PCB, asbestos studies, lead paint, radon gas studies, contaminated soil/fuel spills, oil storage tanks, NEPA studies, and other studies of interior environment required for design

18) Energy efficiency facility studies

19) Pollution prevention facility plans (oil water separators for paving and containment facilities for hazardous materials)

20) Value engineering studies

21) Electromagnetic interference studies

22) Historic preservation act studies (including, but not limited to, Section 106 compliance)

23) Photo documentation of site and buildings for historic preservation and other facility needs

24) Renewable energy studies

25) Identify use of recovered materials and methodology for waste reduction during construction.

26) Commissioning and re-commissioning

27) Independent cost estimates during construction

28) Structural design analysis for hurricane force winds, permafrost conditions, underwater structures, saltwater environments, marsh conditions, etc.

29) Seismic reviews, analysis, and documentation.

30) Owner-advisor services (as defined by DBIA)

C.2.2 PROFESSIONAL PLANNING SERVICES (PPS)

C.2.2.1 In accordance with the terms of this contract, NOAA will request the AE to provide professional planning services associated with the development of new facilities as well as the renovation/repair/expansion/outfitting and demolition of existing facilities at DOC sites. Additionally, NOAA may require the PPS Contractor to develop guidelines and design standards for future facility development. Typical PPS services include, but are not limited to, the following:

1) Strategic Planning

2) Master Planning (i.e., region and site);

3) Facility/Architectural Programming;

4) Space Needs/Utilization Studies;

5) Facility Condition Assessments;

6) Feasibility Studies;

7) Business Case Analysis;

8) Environmental Planning;

9) Preliminary Design (i.e., Concepts);

10) Development of Design Standards and Guidelines;

11) Cost Estimating/Validation Studies;

12) Exhibit Planning/Design;

13) Value Engineering Studies;

14) Peer Reviews;

15) Code Compliance Reviews.

C.2.2.2 TYPICAL PROJECTS

Typical projects for which NOAA may request PPS effort include, but not limited to, the following:

1) Master Planning for an existing facility or campus;

2) Architectural Programming for a new office/research building;

3) Space Utilization Study to determine more efficient use of existing office space;

4) Preliminary Design and Cost Estimating Study for a proposed new regional campus;

5) Planning and estimating to support budget requests for capital improvement projects; and

6) Business Case Analysis (BCA) for proposed new buildings or expansion of existing facilities.

C.2.3 ARCHITECTURAL AND ENGINEERING DESIGN SERVICES

The A-E shall provide a full range of architect and engineer services required for design and support before, during and after construction contract periods. The design effort shall be carried out within guidelines included herein and such additional information as may be furnished to the A-E with each Task Order. The

A-E shall develop site development surveys, design drawings, construction specifications, cost estimates, necessary permits, and approval documents. Task orders may require preparation of traditional design documents or may require design build requirements for work. The following list of activities is indicative of the types of services to be provided. It is not intended to be a definitive listing or indicate any order of priority.

1) Conduct site surveys and pre-design investigations

2) Verify and update record drawings

3) Ensure adequacy of utilities for current and future requirements

4) Conduct pre-design investigations and surveys

5) Prepare 15 percent design submittal

6) Prepare 35 percent design submittal

7) Prepare 50 or 65 percent design submittal

8) Prepare 95 percent design submittal

9) Prepare 100 percent submittal of construction bid documents

10) Prepare design analyses, cost analyses, and engineering calculations for all submittals

11) Prepare construction cost estimates for various stages of design (15%, 35%, 65%, 95%, and

100%)

12) Prepare technical responses to review comments and participate in design review meetings

13) Review designs, specifications, cost estimates, and other documents prepared by others

14) Investigate, document, and propose design concepts for architectural and engineering problems

15) Interior design, furniture, and furnishings

16) Landscape architecture design

17) Survey of sites and buildings related to historic preservation and NHPA requirements

18) Facility evaluation and layout

19) Develop, maintain, and analyze project schedules

20) Prepare facility maintenance plans and list requirements for operating and maintenance manuals

21) Prepare as-built documents or record drawings

22) Life-cycle cost analysis of design alternatives

23) Cost and schedule risk analysis (CSRA)

24) Sensitivity analysis

25) Building commissioning, retro-commissioning, and mechanical systems training

26) Design for facility security systems

27) Design for computer (local area network) systems and all infrastructures associated with computer labs (i.e., UPS systems, backup generators, dedicated and redundant HVAC systems, etc.).

28) Develop design-build requirements documents including Statement of Work (SOW) and performance requirements/specifications, in alignment with the Design Build Institute of America (DBIA) Design-Build Done Right Best Practices

29) Provide owner-advisor services during design-build process (per DBIA)

C.2.4 PREPARATION OF DESIGN DOCUMENTS

The A-E shall develop construction drawings, specifications, cost estimates, analyses, and reports as described in the individual task orders. All construction documents, design calculations, studies, and reports shall be approved and certified by a registered architect, or registered professional engineer. A certified cost engineer shall approve cost estimates. All topographic surveys and construction site survey control shall be performed and certified by a surveyor licensed in the State where the project is located. They shall comply with all local, regional, State, and Federal regulations, standards, codes, and ordinances.

The design documents as a whole, as well as the components and portions thereof, shall permit fully open competitive bidding among interested contractors, manufacturers, and suppliers. Considering the construction period and site-specific conditions, the construction plans and specifications must provide for "constructability" of the facility. The AE shall provide Quality Control (QC) on deliverables. To attain this end, the A-E shall have experienced construction engineers review the construction drawings and specifications during their preparation and provide technical input to the design on an in-progress basis to ensure "constructability" is incorporated, confirmed, and validated.

The plans and specifications shall incorporate sustainability principles and practices and comply with federally mandated environmental and energy design standards. LEED or Green Globes certification will be required only when specified in a Task Order.

C.2.4.1 DRAWINGS shall be Architectural D size. They shall be legible when printed at half size. Drawings shall be submitted electronically in PDF and native format. DWG files for drawings shall be included with native BIM-model files. Quantities for hard copies shall be provided as listed in each task order. Each cover sheet shall include a vicinity map showing the site location in relation to the surrounding highways. A site map of the specific location shall also be included. Vicinity maps shall be located on the site plan sheet at the upper right corner. A location map shall be provided as well, showing the location of the project building or site.

All maps shall show scales, north arrows, and appropriate legends.

All blocks of the title block shall be filled in by the A-E. All sheets shall be numbered. The drawings prepared by the A-E shall be fully detailed and accurately dimensioned with all work completely noted. Provide legends for all symbols, materials, and abbreviations used on the drawings. Details, sections, elevations, and plans shall be identified and cross-referenced. Schedules shall be provided on the drawings for mechanical and electrical equipment.

Prior to 100% final submittal, the A-E shall affix the Designer of Record’s professional seal and signature to the original drawings. This seal shall be that which would be required within the jurisdiction of the State or district in which the project is located.

C.2.4.2 SPECIFICATIONS shall be edited from Unified Facilities Guide Specifications (UFGS) from the Whole Building Design Guide (WBDG). Specifications shall be edited for project specific requirements. Guide specification templates standard with the office of the A-E may be used only subject to written approval by the CO and COR prior to commencement of work. Specification format shall be clear and comprehensive and shall present no conflict in work control and construction management.

Specifications shall be submitted electronically in PDF and native format. Provide hard copies where required by the task orders. Interim specification submittals up to and including the 35 percent submittal, may consist of a Table of Contents listing all sections to be incorporated. Subsequent submittals shall be edited from the approved Guide Spec template using track changes. Guide specifications shall be supplemented when templates do not fully describe project specific requirements. A Table of Contents and a submittal list shall be provided with all specifications. The cover shall bear the name of the project, this contract number and the task order number, the name of the A-E, and the date of preparation. The cover may include the NOAA or agency logo. To ensure comprehensive specifications, the A-E shall not rely on the identification of one manufacturer's product to establish the required characteristics but shall specify the quality, performance, and salient characteristics of the product specified. Except where a single product of only one manufacturer is required to replace or tie into an existing system, sole-source specifications are not permitted. The A-E may specify a single product to establish quality and performance control but must include an "or equal" provision to ensure competitive bidding. The A-E shall include a justification for all sole-source specification in the design analysis.

The A-E shall exercise continuous review procedures to ensure that specifications prepared are applicable to the required work, are free of ambiguous generalities, and are clearly and concisely written to satisfy the requirements of the intended work.

C.2.4.3 DESIGN BUILD RFP or D/B Design Requirement Documents will be required in some task orders rather than traditional plans and specifications. A design build RFP may consist of drawings and/or a written scope of work, as required by the task order. D/B Design Requirement Documents shall be developed to the 30-35% stage, or a stage agreed upon with the CO.

C.2.4.3.1 Design Build Scope of Work shall be in the six part format provided in the Whole Building Design Guide.

Part 1 – Reserved for Contracts Office use.

Part 2 – General Requirements Part 3 – Project Program Part 4 – Performance Technical Specifications Part 5 – Prescriptive Specifications (if applicable) Part 6 – Reference Drawings and Reference Documents

Part 3 Engineering System Requirements (ESR) and Part 4 Performance Technical Specifications (PTS) shall be prepared in the Uniformat II format, when required.

C.2.4.3.2 Design Build Drawings shall be developed to the 35% stage of completion unless specified otherwise in the task order.

C.2.4.4 COST ESTIMATES shall be prepared in accordance with FC 1-300-09N Navy and Marine Corps Design Procedures Chapter 9 and UFC 3-740-05 Construction Cost Estimating. Though it is acceptable, it is not mandatory to submit cost estimates using the Micro-Computer Aided Cost Estimating System (MII Software). Cost Estimates shall be in UniFormat II and must accompany each submittal required by the task order. Refer to FC 1-300-09N Navy and Marine Corps Design Procedures Table 9-1 and Appendix B for cost estimate classification and required minimum level of detail. Estimates shall be prepared by competent firms experienced in cost engineering with recent relevant project experience and must maintain an active Certified Estimating Professional (CEP), or other equivalent certification. Equivalent certification and/or a combination of relevant experience may be acceptable, as approved by the Contracting Officer. Each cost estimate submission shall be accompanied by a Basis of Estimate (BOE) document. Refer to FC 1-300-09N Chapter 9-3 and UFC 3-740-05 Chapter 4-3 for detail and minimum requirements. All cost estimates shall be itemized for direct cost of each item of work by unit cost of material and labor. Overhead and profit shall be shown as added percentages to the subtotals of the direct cost. Maximum allowable profit shall be 10 percent of direct costs. Overhead shall be current and reasonable to the project work. Refer to UFC 3-740-05 Chapters 5 to 13 for further detail. The A-E shall follow cost trends and city cost indexes of the work so that any possibility of cost overrun is recognized at the early stages of design. Lump sum cost estimates will not be accepted. No lump sum or percentage contingencies shall be included in the 100% estimate. The A-E shall provide internal controls to keep the total design cost within the construction cost limitation and ensure the accuracy of the construction cost estimates. Each estimate shall be reviewed in detail by the designers, with a copy of their comments provided to the COR.

The A-E shall establish and submit for the CO's approval an in-house security policy for safeguarding prepared cost estimates. The A-E shall maintain security of all Government cost estimates for one year after the completion of this contract.

C.2.4.5 DESIGN ANALYSIS AND CALCULATIONS shall be submitted with each submittal of plans and specifications. The degree of completion shall be comparable to that of the plans. All computations shall be indexed and arranged in an orderly manner, with appropriate sketches, so that any element of the design can be easily identified. When Computer Aided Design and Drafting Systems (CADD) are utilized to perform design calculations, the analysis shall include CADD program information. The design analysis shall include a general description of computer programs used on major features of the analysis. The design methods shall be described including assumptions, theories, and formulas employed in the design solutions.

Final 100% design submittal shall include a complete set of check computations clearly marked as final 100% design calculations. The practice of sending additional sheets to be incorporated with previously submitted computations is not acceptable.

Hand-written calculations must be legible in the opinion of the CO. Calculations determined to be illegible will not be accepted and must be re-written and resubmitted.

C.2.4.6 BID SCHEDULE -The A-E shall submit a bid schedule with the 100 percent design submission. The bid schedule shall include a brief description of work and construction skills required; plans and specifications applicable to the project; and all basic bid and alternative bid items with a brief description of the work involved. The A-E shall indicate the estimated number of calendar days required for the construction work completion. A-E shall set up schedule for lump sum bids or unit cost for approval by CO.

C.2.4.7 SUBMITTAL STAGES -The development of the required drawings, specifications, cost estimates, and design analyses/calculations shall be submitted at interim stages of development for Government review and comment. These submittal stages shall be as required in each individual task order. Each required submittal shall conform to the applicable requirements for each submittal stage as follows:

C.2.4.8 CONCEPT DESIGN SUBMITTAL (15 %) may be required on the more complex projects and/or where architectural design elements are required to obtain coordinated interior design development or development of exterior design considerations. The submittal is required to ensure that the scope of the required work is recognized and can be provided within available funding.

When provided, this submittal shall completely represent a design concept that accurately reflects the character and/or intended scope of the work. Drawings provided at this submittal shall be accurately dimensioned and elevations provided as necessary to describe the work. A typed narrative description of the concept shall be provided by the A-E to supplement the drawings, specifications, cost estimates, and design analyses.

Cost estimates shall be provided which accurately reflect the cost of the intended project. Where alternate schemes/solutions are included, the cost of each alternative shall be provided. Appropriate security of cost estimates shall be maintained.

This submittal shall satisfy the Government that the A-E has a complete grasp of the intended work and is able to fully develop the design documents to obtain a successful construction bid within the programmed amount. It shall show that all specific requirements of the project are provided and that architectural design considerations have been resolved in a manner to ensure a quality of design, which is esthetically and functionally satisfying.

C.2.4.9 PRELIMINARY DESIGN SUBMITTAL (35 PERCENT) shall include all sheets of the construction drawings that will be required, developed to at least 35 percent of completion for each intended drawing. Level of completion shall be sufficient to show design intent.

The legend and symbol designations shall be included. The legend shall include a list of all drawings to be submitted at 100 percent and status of each. The drawings shall include appropriate equipment schedules with designated column headings indicating information intended to be included in the final schedule. Blank spaces on drawing sheets shall be noted for intended content development. Drawings shall clearly distinguish between existing and new work. Demolition symbols shall clearly distinguish areas to be demolished. All symbols shall be identified. All schedules required for the work shall be included and developed to 35 percent of completion. Sufficient cross sections, elevations, and details shall be shown to provide comprehensive representation of the total work intended.

All sections of the intended specifications shall be listed in a Table of Contents. Key specification sections describing equipment or building systems shall be provided in a markup format.

Design analyses and calculations required for the work shall be provided and shall be fully developed for this submittal. The A-E shall identify all issues requiring Government decision or input. The A-E shall identify conflicts in Government criteria, code, or instruction prior to proceeding to pre-final submittal. Where tests have been performed for proper design of the work, all test data shall be included with this submittal.

Cost estimates shall be itemized and all intended work identified. Appropriate security of cost estimates shall be maintained.

The A-E shall provide the necessary professional investigations and documentation to allow the Government to obtain easements for power, telephones and communication cables, access roads, gas, water and sewer extensions, and similar matters.

C.2.4.10 INTERIM SUBMITTAL (65 PERCENT). This submission, where required by the task order, shall include as a minimum the following: civil, mechanical, and electrical site plans; floor plans and elevations; building details; preliminary finish schedules and color boards; completed electrical load analysis; heating and cooling loads; structural analysis; mechanical, electrical, civil, structural drawings; detailed construction estimates and design analysis; proposed equipment lists; and updated construction schedules.

C.2.4.11 PRE-FINAL DESIGN SUBMITTAL (95 PERCENT) the drawings, cost estimates, and specifications shall be essentially complete except for incorporation of the Government's final comments and provide all requirements for construction contracts documents. The A-E's pre-final submittal shall be complete in all aspects of design. The Government views the pre-final as an un-reviewed 100% submittal. The Government review should require only minor edits and comments. Incomplete or unedited drawings and specifications are not acceptable. All prior review comments shall have been resolved and incorporated into the documents.

All drawings shall be completed with all symbols and legends identified and all schedules completed.

All details, elevations, sections, and diagrams shall be included as required to fully develop the proposed work.

Specifications shall be typed in final format with all provisions included.

Cost estimates shall be in final totals. The cost estimate shall be sufficiently accurate at this stage that the Government can begin funding procedures to ensure timely progression of the project to procurement for contractual proceedings. Appropriate security of cost estimates shall be maintained.

C.2.4.12 FINAL DESIGN SUBMITTAL (100 PERCENT) shall provide all drawings, specifications, and cost estimates ready for construction bid documents.

The final 100% submittal is the 95% submittal with all previous comments incorporated and the documents ready to be issued for the construction contract. Any comment on these documents shall be resolved by the A-E prior to final acceptance of submitted contract documents. The final submittal shall include pdf files for all plans and specifications.

With this submittal, the A-E shall include its estimate of the construction time necessary to accomplish the project, provide the estimate in total calendar days, and identify recognized lag time for items of construction which are anticipated to create delays.

The A-E shall respond to the CO request for information or clarification during the procurement. The A-E shall respond to the CO's request within 2 working days.

C.3 CONTRACT SUBMITTALS AND DELIVERABLES

C.3.1 Each submission shall be accompanied by a transmittal memorandum identifying the submission and describing the materials being provided. A copy of each transmittal memorandum shall be sent to the CO.

Distribution of design submittals will be made by the A-E directly to the reviewers. The A-E is responsible for the method of delivery to insure the submittal is received prior to or on the due date. The number of copies and addresses of reviewers will be provided by the COR. The A-E shall provide deliverables as specified in Task Orders or the following table:

Table of Deliverables and Schedule Requirements

Deliverable Item First Frequency Quantity (E indicates electronic)

Project Tracking System & Cost Estimating System days from

NTP

One Time E

Progress Report 30 days from

NTP

Monthly E

Initial Management and Review Meeting

Prior to initial Task Order

Management and Technical Review Meeting:

Monthly

Agenda 5 days prior E

Meeting documentation day of meeting E

Minutes of meeting 14 days following E

Various surveys, studies, reports, etc. identified by Task Order E + three hardcopies

Architectural and Engineering Services:

Drawings with each design submittal E + Three ½ size

Specifications with each design submittal E

Construction Cost Estimate with each design submittal E

Design Analysis with each design submittal E

Bid Schedule with 100% submittal E

As-built Record Drawings at end of construction E + 2 full-size sets

15% Design Submittal All design submittals are as

35% Design Submittal specified above unless

Interim Design Submittal modified by task order.

90% Design Submittal

100% Design Submittal

Meetings For each task order include a pre-design meeting, and a review meeting at completion of government review of each required submittal. Include other meetings as specified in the task order.

Construction Administration & Observation/Quality Assurance/Cx:

identified by Task Order

Minutes of Pre-Bid Conference 7 days following E

Minutes of Pre-Const Conf 7 days following E

Shop Drawing Review 20 days following receipt by contract

Site Visit Reports 3 days following visit E

Final Punchlist/Final Inspection Report

10 days following inspection E

Const Progress Mtg Minutes 3 days following E

Construction Progress Report Identified by Task Order E

Minutes of Meetings/calls/correspondence.

3 days following each meeting/call/correspondence

E

Disk / CD copy of plans identified by Task Order 3

Draft Commissioning Plan 30 days following const. NTP E

Final Commissioning Plan 30 days following completion of system commissioning

E

O&M Plan end of construction, when required by task order.

E

Schedule requirements are maximums and are in calendar days.

C.3.2 MINUTES OF MEETINGS

The A-E shall maintain records of all telephone calls, meetings, conferences, conference telephone calls, and correspondence pertaining to this contract. The A-E shall distribute meeting minutes within 3 working days after the meeting to all participants.

C.3.3 CONSTRUCTION DOCUMENTS

The A-E shall deliver the original of all construction bid documents, including construction cost estimates to the CO. The specific number of copies of the construction bid documents shall be established in the individual task orders.

C.4 CONSTRUCTION MANAGEMENT AND QUALITY ASSURANCE

As indicated by Task Order, the A-E may be required to provide the day- to-day construction management and observation/quality assurance duties for various new or remodeled facility construction. The following list of activities is indicative of the types of services to be provided during construction management and observation but is not all-inclusive. Additional services or expanded services may be required under each task order (e.g. Full-time on-site inspection services).

1) Pre-Bid Evaluation: Assist the Government in technical evaluation of construction offers.

2) Pre-Bid Conference: Attend pre-bid conference site inspection meetings between the using agency and the potential contractor. The A-E is to provide minutes of the meeting 7 days following the meeting.

3) Pre-Construction Conference: Attend pre-construction conference. The pre- construction conference will be held before the construction Contractor begins work to discuss the details of the contract and management of construction by the A-E and the Government. The A-E and representatives from each of its subcontractors will participate in the Pre-construction conference.

The A-E shall provide minutes of the meeting within 7 days following the meeting.

4) Construction Management Services: Assist the Government COR in performing various aspects of the construction management process:

5) Site Instructions / Request For Information (RFI): The A-E shall assist the COR in responding to RFI’s from the Contractor. The A-E shall respond to all RFI's within 5 days (or notify the COR as to reasons for not being able to respond within this timeframe). The A-E is to retain a complete and up-to-date log of Site Instructions and RFI's issued to the construction Contractor.

6) Site Instructions / Field Adjustments: The A-E shall assist the COR in issuing Site Instructions and Field Adjustments to the Contractor.