This document is a Statement of Work (SOW) for the National Oceanic and Atmospheric Administration (NOAA) to obtain services to remove and replace the wood decking and railing system on the roof of the Network for the Detection of Atmospheric Composition Change (NDACC) building at the Mauna Loa Atmospheric Baseline Observatory in Hawaii. The SOW includes a base contract to replace the wood decking with pressure treated lumber, as well as optional contract line items to replace the stair and handrail system, replace the decking with non-corrosive metal with fiber reinforced bar grating, and perform electrical upgrades. Contractor shall provide design drawings and submittals prior to performing the work. The period of performance is 160 days after notice to proceed. The SOW outlines specific safety, quality control, environmental protection, and warranty requirements. This work is associated with the pre-solicitation REQUIREMENTS-24-2281 for the Mauna Loa Atmospheric Baseline Observatory (MLO) NDACC Roof Repairs issued by the Department of Commerce National Oceanic and Atmospheric Administration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OFWORK (SOW)
National Oceanic and Atmospheric Administration (NOAA)
Mauna Loa Atmospheric Baseline Observatory (MLO) Network for the Detection of Atmospheric Composition Change
(NDACC) Roof Repairs Mauna Loa Atmospheric Baseline Observatory, Hawaii
A. PURPOSE:
The NOAA Global Monitoring Laboratory (GML) (MLO requires services to remove the wood decking sitting on the roof of the NDACC building and replace it with pressure treated wood with options to replace the wood with non-corrosive metal with fiber reinforced bar grating for walking surfaces. This will be a full replacement of the system to include design, inspection of the structural membranes of the decking system, new pressure treated wood decking, and better railing system, with options to replace the stair system, replace the wood decking to non-corrosive metal with fiber reinforced bar grating, and complete electrical upgrades.
B. BACKGROUND:
The NOAA Global Monitoring Laboratory (GML) Mauna Loa Atmospheric Baseline Observatory (MLO) is located on the Big Island of Hawaii, at 11,141 ft. above sea level on the north flank of the Mauna Loa volcano. The site is often regarded as the “premier atmospheric science site on earth” and is home to numerous high-profile data sets including the “Keeling Curve” that first documented the rise in carbon dioxide in our global atmosphere. The observatory conducts well over 250 daily climatological measurements, some as precise as 1 part in a trillion.
At 11,141 feet in altitude the sun (UV) conditions can be strong and the air temp significantly cooler than elsewhere on the island which can be detrimental to the buildings, decks and materials located at the site. The current solar deck sitting on the roof of the NDACC building requires a replacement that includes the demolition and replacement of the horizontal wood decking, inspections of the structural membranes and repairs and reinforcement as needed, a new stairs system, a new railing system and electrical upgrades.
Scientific measurements obtained at MLO often represent the global background conditions for the atmospheric research community. As such, the measurements taken at the site are highly precise and need to be safeguarded to ensure that indoor room air and/or local site contamination does note negatively impact the long-term records. NOAA has developed a comprehensive banned construction materials (chemicals) list and each product used at the site must be cleared against this banned chemical list prior to use. The banned construction materials list will be provided to vendors and NOAA can assist with reviewing individual products as needed.
Furthermore, it will be required to keep the science at MLO operational as much as possible throughout construction activities.
C. PROJECT SCOPE:
GML requires a vendor to remove and replace the existing horizontal wood decking (approximately 660 SF) at the Mauna Loa Baseline Observatory and provide pricing for the option items in this contract.
The general scope of services required for this project include, but are not limited to: labor, material, equipment, transportation, warranty and other related services for completing the full construction as described within this scope of work. The contractor shall provide drawings and submittals prior to performing the work.
1. Contract Line Item 01: Base Contract: Remove Horizontal Wood Decking and Replace with Pressure Treated Lumber Decking
The dimensions for the deck are shown in the drawing in Attachment 1 - NDACC Solar Deck and Attachment 2 - MLO Blue Prints 1996 and these dimensions are for reference only. Contractor must measure the dimensions of the area prior to the work. The contractor shall provide drawings and submittals prior to performing the work.
Contractor shall:
a. Inspect all columns and structural members prior to the work and shall reinforce and replace the structural members as needed.
b. Remove all horizontal wood decking entirely
c. Provide all new pressure treated lumber decking for the Work.
d. Waterproof and treat lumber decking with a UV Stable powder-coated with non-skid surface.
i. Coordinate color of powder coated material with the Government prior to installation.
e. Install pressure treated lumbar decking there are no gaps between the deck boards.
f. Ensure the new deck will accommodate the four (4) "chimneys" coming out of the
NDACC roof.
i. Chimney locations are shown in Attachment 1 - NDACC Solar Deck and
Attachment 2 - MLO Blue Prints 1996.
g. include the removal and replacement of the handrail system. The system shall be pressure treated lumber and shall use metal brackets attached to the railing frame system with a minimum elevation of 42” above the finish floor elevation of the floor decking system.
h. install a metal grating framed platform bolted to the timber top rail, approximately 18” to 24” wide. The new metal framed grating system shall be installed around the entire deck North, West, and East rails. See Attachment 3 - Sketch of Railing System for details. Grating must be submitted and approved by the Government prior to purchasing and installing. Contractor shall provide a shop drawing that illustrates the mounting hardware and support rails system for review approval prior to installation, Work shall be designed and sealed by a Professional Engineer.
i. Grating should overhang the rail on the outside of the deck to allow for more deck space. See Attachment 3 - Sketch of Railing System for details.
ii. Connect all smooth metal grating together with grounding bars or straps.
Contractor to submit the best grounding system.
2. Contract Line Item 02: Option: Replace Entire Stair and Handrail System with Pressure Treated Lumber
a. Inspect all columns and structural members prior to the work and shall reinforce and replace the structural members as needed.
b. Work includes the demolition and removal of the existing wood stairs and handrail system. See Attachment 4 - Pictures of Existing Stairs
c. The contractor shall replace the stairs with pressure treated lumber in the same configuration as existing.
d. Inspect all columns and structural members prior to the work and shall reinforce and replace the structural members as needed.
e. Provide all new pressure treated lumber decking for the Work.
f. Lumber decking must be waterproof and treated with a UV Stable powder-coated with non-skid surface. Contractor to coordinate color of powder coated material with the Government prior to installation.
g. Pressure treated lumber decking must be installed so there are no gaps between the deck boards.
h. New stair and handrail system must be ADA compliant.
3. Contract Line Item 03: Option: Remove Horizontal Wood Decking and Replace with Non-Corrosive Metal with Fiber Reinforced Bar Grating for Walking Surfaces
The dimensions for the deck are shown in the drawing in Attachment 1 - NDACC Solar Deck and Attachment 2 - MLO Blue Prints 1996 and these dimensions are for reference only. Contractor must measure the dimensions of the area prior to the work. The contractor shall provide drawings and submittals prior to performing the work.
Contractor shall:
a. Inspect all columns and structural members prior to the work and shall reinforce and replace the structural members as needed.
b. Remove all horizontal wood decking entirely
c. Provide all new non-corrosive aluminum metal with fiber reinforced bar grating for walking surfaces
d. Aluminum metal grating (allow snow to drop thru) required
e. Decking to be aluminum metal bar grating sized for anticipated loads.
f. Ensure new deck will accommodate the 4 "chimneys" coming out of the NDACC roof. Chimney locations are shown in Attachment 1 - NDACC Solar Deck and Attachment 2 - MLO Blue Prints 1996.
g. Remove and replace the handrail system to be continuous metal attached to the railing frame with metal brackets at 42” high from the decking.
h. install a metal grating framed platform bolted to the top rail, approximately 18” to 24” wide. The new metal framed grating system shall be installed around the entire deck North, West, and East rails. See Attachment 3 - Sketch of Railing System for details. Grating must be submitted and approved by the Government prior to purchasing and installing. Contractor shall provide a shop drawing that illustrates the mounting hardware and support rails system for review approval prior to installation. Work shall be designed and sealed by a Professional Engineer.
i. Grating should overhang the rail on the outside of the deck to allow for more deck space. See Attachment 3 - Sketch of Railing System for details.
ii. Connect all smooth metal grating together with grounding bars or straps and ensure the metal deck is grounded. Contractor to submit the best grounding system.
4. Contract Line Item 04: Option: Replace Entire Stair and Handrail System with Non-Corrosive Metal with Fiber Reinforced Bar Grating for Walking Surfaces.
a. Inspect all columns and structural members prior to the work and shall reinforce and replace the structural members as needed.
b. Work includes the demolition and removal of the existing wood stair and handrail system. See Attachment 4 - Pictures of Existing Stairs
c. The contractor shall replace the stairs and handrails with non-corrosive aluminum metal with fiber reinforced bar grating for walking surfaces to match the deck.
d. Aluminum metal grating (allow snow to drop thru) required
e. Decking to be aluminum metal bar grating sized for anticipated loads.
f. Contractor to replace the entire system in the same configuration as existing.
g. New stair and handrail system must be ADA compliant.
5. Contract Line Item 05: Option: Upgrade Electrical System
Contractor shall coordinate with the government the new electrical layout prior to the work. Contractor shall submit drawings and submittals prior to the start of the work. All electrical components to be located in conduit and using code-compliant outdoor-rated junction boxes, outlets, etc.
Contractor shall:
a. Remove, dispose and replace all existing conduit and flex conduit on the deck running into the building.
b. Coordinate with the government to move conduit and junction boxes to new locations on the deck to facilitate the scientific needs.
c. Investigate the circuits and install two more 20-amp circuits and run new conduit up to the deck. See Attachment 5 - Electrical Modifications Sketch
d. rewire the outlets to the different circuits in the configuration described on Attachment 5-Electrical Modifications Sketch to support future scientific needs.
e. Provide additional outlet receptacles spaced 8’ apart on the rail system on the North, East and West railings. See Attachment 5 - Electrical Modifications Sketch
f. Replace exterior lighting with LED lighting.
g. Reconfigure the light switches to control both the floodlights and the deck lights at the bottom and top of the stairs.
h. Investigate old outlets and ensure each has power and is in working order.
i. Provide watertight enclosure around outlets.
D. DESIGN AND DELIVERABLES
Contractor shall submit a design for the deck and stair replacement to include the new electrical layout. Contractor shall ensure that all of the design items described in this scope of work are addressed and included in the project drawings and specification sections where appropriate. It shall be the contractor’s responsibility to provide all of the design elements for this project. A review meeting to resolve design issues will be held as needed and will include discussion and technical peer review comments. Participants will include GML staff and contractor members as appropriate.
A. The Design Team shall prepare and submit complete documents for review and approval by GML in accordance with standard professional practice and prevailing codes.
B. All submission packages will be reviewed at 50%, and 100% completion stages. Each subsequent review submission package will incorporate the previous review comments.
The 100% set of drawings will be the final set of drawings that will be used for construction.
C. The project design phase will consist of 60 days.
a. From the Notice to Proceed, the Design contractor shall submit 50% drawings within 20 calendar days. GML will have 5 calendar days to review the drawings and return them to the Design contractor.
b. Design contractor shall submit 100% drawings within 20 calendar days. GML will have 5 calendar days to review the drawings and return them to the Design contractor. The Design contractor then will submit a final set of drawings for construction within 10 calendar days.
c. A review cycle consists of:
i. The GML receipt of the design review submission package
ii. The review meeting
iii. Design contractor receipt of comments from GFDL
E. POST AWARD CONFERENCE
The purpose of this meeting (virtual or in person) is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:
daily reporting, invoicing, safety, site access, outage requests, schedule requirements, quality control, and schedule of prices, shop drawings, submittals, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing. Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager (QCM) and major subcontractors. Superintendent, SSHO and QCM shall be designated in writing.
F. SAFETY AND HEALTH PLAN
Site activities performed in conjunction with this project may pose safety hazards which require specialized expertise to effectively address and eliminate. The contractor shall be responsible for preparing and implementing an effective safety and health program, to include a site-specific safety and health plan. The contractor’s Safety and Health Plan shall conform to the requirements defined in U.S. Army Corps of Engineers (USACE) Safety Manual EM385-1-1. Plan must be submitted within 30 days of award and must be approved before the contractor is given notice to proceed with construction.
Contract Personnel visiting the observatory must have federal identification available. A background check may be required for personnel accessing government facilities. The names of all Contract Personnel visiting the site shall be reported to the Technical Contact(s) at least seven
(7) days in advance of the site visit. NOAA must be informed if any Contract Personnel are foreign nationals – additional security clearance may be required. Contract Personnel must be escorted in government facilities.
G. QUALITY CONTROL PLAN
The contractor shall develop, implement, and document an effective project specific quality control plan in accordance with USACE Engineer Regulation (ER) 1180-1-6, Construction Quality Management. This quality control plan shall be submitted to the Contracting Officer for approval within 30 calendar days after contract award. All projects (over $750K) require a QC manager with a certificate of completion from a USACE Construction Quality Management for Contractors (CQM-C), 16 hour course within the last 5 years. This class is available online.
H. PROJECT SCHEDULE
The contractor shall submit a detailed schedule showing all phases of design and construction, including testing, inspection/acceptance, commissioning, training, and other activities as required. Schedule shall be submitted electronically in Microsoft Project compatible formats and .pdf format. Schedule updates are required to be submitted with monthly pay requests. For detailed scheduling requirements, see Attachment 1 Project Construction Progress Schedule.
I. HOURS OF OPERATIONS
The contractor is responsible for performing between the hours of [7:00 AM to 4:30 PM, Monday through Friday], except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The contractor must at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this statement of work when the Government facility is not closed for the above reasons.
Work outside regular working hours requires Contracting Officer approval. Requests must be submitted 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. See Section 10 Utilities for outage information.
Contractor must at all times have someone on property that speaks fluent English.
J. ENVIRONMENTAL PROTECTION
Provide and maintain, during the life of the contract, environmental protection as required. Plan for and provide environmental protective measures to control pollution that develops during construction. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Protect the environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire duration of this Contract. Comply with federal, state, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.
Tests and procedures assessing whether construction operations comply with Applicable Environmental Laws may be required. Analytical work must be performed by qualified laboratories; where required by law, the laboratories must be certified.
Prior to start of any onsite construction activities, perform a Preconstruction Survey of the project site with the Contracting Officer or the COR and the designated NOAA Environmental Representative. Survey shall include photographs showing existing environmental conditions in and adjacent to the site.
Minimize interference with, disturbance to, and damage to fish, wildlife, and plants, including their habitats. The protection of rare, threatened, and endangered animal and plant species identified, including their habitats, is the contractor's responsibility. Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work. Confine construction activities to within the limits of the work indicated or specified.
If asbestos, lead paint, petroleum-contaminated soil, or suspected hazardous waste is found during construction that was not identified in the Contract documents, immediately notify the
Contracting Officer. Do not disturb this material until authorized by the Contracting Officer. The contractor shall provide the necessary licensed Industrial Hygienist to confirm in writing the presence and scope of the hazardous material. The Contracting Officer will issue direction on how to handle the unexpected hazards described by the contractor.
Do not dispose of hazardous waste on Government property. Do not discharge any waste to a sanitary sewer, storm drain, or to surface waters or conduct waste treatment or disposal on Government property without written approval of the Contracting Officer.
The contractor shall minimize the presence of dust at all times, including during nonworking periods. Sprinkle or treat, with dust suppressants, the soil at the site, haul roads, and other areas disturbed by operations. Dry power brooming will not be permitted. Instead, use vacuuming, wet mopping, wet sweeping, or wet power brooming. Only wet cutting will be permitted for cutting concrete blocks, concrete, and bituminous concrete. Do not unnecessarily shake bags of cement, concrete mortar, or plaster. Since these products contain Crystalline Silica, comply with the applicable OSHA standard, 29 CFR 1910.1053 or 29 CFR 1926.1153 for controlling exposure to Crystalline Silica Dust.
The contractor shall implement best management practices (BMPs) for dust control and reducing equipment emissions during construction, including:
1. Watering exposed surfaces.
2. Covering haul trucks transporting loose material.
3. Removing visible mud or dirt track-out onto adjacent public roads.
4. Limit vehicle speeds on unpaved areas.
5. Minimize idling times.
Burning of trash or rubbish is not permitted on project site.
Monthly Invoices: Contractor is required to submit monthly invoices to COR via the IPP system.
Invoices are due by the 7th of each month. The COR will review the invoices and either return them for corrections or process them for payment.
Site Restrictions: Contractor employees must park privately owned vehicles in an area designated by the Contracting Officer. Employee parking must not interfere with existing and established parking requirements of the Government installation. Smoking is prohibited within and outside of all buildings on site, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
Dumpsters: Contractor must provide their own dumpster for all disposal of all trash.
K. PERIOD OF PERFORMANCE
Period of performance is 160 days after Notice to Proceed.
L. FINAL INSPECTION
The contractor shall provide no less than 10 working day notification to the COR prior to final inspection. The purpose of the final inspection is to ensure all systems are fully operational and ready for acceptance by the Government. If any system fails, the contractor shall be liable to pay any costs for government personnel to travel for re-inspection. The Site QC Manager shall sign off on request for final inspection, verifying all items have been completed and are operational and ready for Government acceptance.
M. WARRANTY
At least 30 days before the final inspection, submit two sets of the warranty plan organized in a 3-ring binder. Include within the warranty plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan narrative must contain sufficient detail to render it suitable for use by future maintenance and repair personnel, who may not be familiar with this contract. The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period. Conduct a joint 6 month and 11 month warranty inspection, measured from time of acceptance; with the contractor, Contracting Officer and the owner representative.
The warranty management plan must include, but is not limited to, the following:
Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the contractors, subcontractors, manufacturers, or suppliers involved.
For each warranty, the name, address, telephone number, and e-mail of each of the equipment representatives nearest to the project location.
A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.
As-Built Record of Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:
(1) Name of item.
(2) Model and serial numbers.
(3) Location where installed.
(4) Name and phone numbers of manufacturers or suppliers.
(5) Names, addresses and telephone numbers of sources of spare parts.
(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have warranties longer than one year must be indicated with separate warranty expiration dates.
(7) Cross-reference to warranty certificates as applicable.
(8) Starting point and duration of warranty period.
(9) Summary of maintenance procedures required to continue the warranty in force.
(10) Cross-reference to specific pertinent Operation and Maintenance manuals.
(11) Organization, names, and phone numbers of persons to call for warranty service.
(12) Typical response time and repair time expected for various warranted equipment.
e) The plans for attendance at the 6- and 11-month post-construction warranty inspections conducted by the Government.
N. FINAL CLEAN UP
Provide final cleaning in accordance with ASTM E1971. Remove debris from roadways and sweep/clean paved surfaces. Remove spoils from the project site. Repair all construction areas to previous condition. Remove waste and surplus materials, rubbish, and construction facilities from the site.
O. SUBMITTALS
The contractor shall provide the following submittals for Government review and approval before any onsite work can begin. Submittals shall be transmitted electronically and must be compatible with Microsoft Office applications, unless otherwise approved by the COR. All construction drawing submittals shall also include a hard copy. Upon approval of submittals, the COR will notify the contractor.
Required Submittals:
1. List of Contract Personnel
2. Design/Construction Project Schedule
3. Site Safety and Health Plan
4. Quality Control Plan
5. Appointment letters for site superintendent, QC manager, and SSHO
6. Execution Plan
7. Material and Equipment Submittals
8. Laydown Area Plan
9. Decking and Handrail Shop Drawings
10. Stair and Handrail Shop Drawings
11. Decking Material Submittals
12. Smooth Metal Grating Material Submittals
13. Decking Profile and Attachment Submittals
14. Warranty plan
P. PROJECT SITE ADDRESS
4-2441 Mauna Loa Access Road;
c/o Mauna Loa Observatory Office, 1437 Kilauea Ave. #102 Hilo, Hawaii, 96720
Q. ATTACHMENTS
Attachment 1 - NDACC Solar Deck Attachment 2 – MLO Blue Prints 1996 Attachment 3 – Sketch of Railing System Attachment 4 – Pictures of Existing Stairs Attachment 5 – Electrical Modifications Sketch Attachment 6 – General Material Requirements Attachment 7 – Banned Construction Materials List