This file contains questions and answers from a Request for Information (RFI) issued by the Joint Project Manager for Chemical, Biological, Radiological and Nuclear Protection (JPM CBRN P) regarding the Chemically Protected Deployable Medical System (CP DEPMEDS) Product Support Integrator (PSI) and Material Integration Support requirement. The RFI, issued as of November 20, 2026, is a market research tool only and does not constitute a solicitation, commitment, or authorization to incur costs. The Government seeks industry capabilities to determine acquisition strategy and maximize competition before issuing a formal Request for Proposal (RFP). The Government has not finalized acquisition strategy, contract type, competition restrictions, estimated contract value, or period of performance, and will provide these details in the forthcoming RFP. Contract award is targeted for Fiscal Year 2028, with annual deliveries anticipated to be dependent on component lead times.

The PSI role encompasses procuring and coordinating delivery of commercially available components; receiving, tracking, and consolidating Government-sourced components; applying Item Unique Identification (IUID) markings; maintaining materiel accountability; conducting Preventative Maintenance Checks and Services (PMCS) and Care of Supply in Storage (COSIS); and delivering verified, complete component packages to Pine Bluff Arsenal (PBA) for final system integration. All work will be completed at the contractor's facility until shipment to PBA. Hazardous materials anticipated include fuels, batteries for power generators, refrigerants for environmental control units, and activated charcoal for chemical-biological filters. The Government will retain authority for requisitions, funding, release, acceptance, and disposition decisions; the contractor will not independently obligate Government funds. Specific details regarding Bill of Materials, component specifications, delivery schedules, facility requirements, workforce qualifications, inspection criteria, and compensation structure will be outlined in the forthcoming RFP. This RFI response document addresses 34 vendor questions on topics ranging from acquisition strategy and contract structure to facilities, security clearances, inspection procedures, and payment arrangements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information (RFI) for Joint Project Manager for Chemical, Biological, Radiological and Nuclear Protection (JPM CBRN P) Chemically Protected Deployable Medical System (CP DEPMEDS) Questions and Answer as of 20 November 2026

1. Is this the first issue of this solicitation (is this a re-compete of an existing Army requirement or a new requirement)?

· This is the first Request for Information.

2. Is this a requirement whereby the solicitation is open solely to pre-awarded vendors on a previous Army Blanket Purchase Agreement (BPA), Indefinite Delivery, Indefinite Quantity (IDIQ), or Multiple Award Schedule (MAS) or related Contract Vehicle?

· This is not a solicitation; this is a Request for Information (RFI). The Government has not finalized any acquisition strategy and is inquiring about vendor capabilities to determine what acquisition path will provide maximum competition and mission success.

3. Can the Army please clarify whether this requirement for CP DEPMEDS Product Support Integrator and Materiel Integration Support is being procured through specific related contract vehicles, acquisition programs, or vendor-restricted platforms (such as OASIS+, OASIS SB, GWAC, BPA, IDIQ, GSA Schedule acquisition, state-specific vehicle, or another pre-qualified contract mechanism) that would limit participation to holders of that vehicle, thus requiring only Contractors/Suppliers/Service Providers holding a particular contract vehicle for eligibility to submit a proposal.

· This is not a solicitation; this is a Request for Information (RFI). Requirements and contract type will be included in the Request for Proposal (RFP). The Government has not finalized any acquisition strategy and is inquiring about vendor capabilities to determine what acquisition path will provide maximum competition and mission success.

4. Can you advise if there were/are incumbent provider(s) for these services? If yes, who is/are the incumbent(s), and can you provide a previous contract number?

· This is not applicable.

5. If there is an incumbent, is there a reason the known incumbent may be precluded from bidding on this new or existing requirement?

· This is not applicable.

6. Would the anticipated Key Personnel Position(s) require relocating to the Natick, MA area, or does the PWS for this Army requirement allow for a mix of working remotely and in the Natick, MA area, combined with travel to Army offices/worksites?

· This is not applicable. Relocation is not required.

7. Does this requirement specify that the Prime Contractor must have an active Form DD254 (Top Secret) Facility Clearance or specific CSCS before being awarded? Can proposed Key Personnel hold an active DOE CSCS, such as Q or DoW Top Secret, at the time of quotation submission?

· This is not a solicitation; this is a Request for Information (RFI). Requirements and contract type will be included in the Request for Proposal (RFP).

8. Would a vendor holding a valid Secret Facility Clearance (Secret FCL) be considered for an INTERIM Top Secret Facility Clearance by the DOD/DSS when bidding on a contract that requires TOP SECRET or INTERIM TOP SECRET clearance through the U.S. Department of Defense/Defense Security Service (DOD/DSS)? Additionally, would the Army approve and accept proposals from such vendors and issue a Letter of Authorization (LOA) to upgrade their clearance to the TOP SECRET Clearance Level to meet the contract requirements?

· This is not applicable.

9. Are bidders lacking a DD-254 (Top Secret) Facility Clearance encouraged to participate??

· This is not applicable.

10. For areas where strict requirements exist for an active Secret/Top-Secret Facility Clearance (or DOE-Q | NACI, etc.) and specific past performance requirements as the prime vendor, would the Government consider accepting a Contractor Teaming Agreement (CTA) under the GSA framework to meet both the clearance and past performance criteria?

· This is not applicable.

11. Can you guide the level of effort expected (Total Labor Hours, Labor Hours by Key Team Members, etc.) to complete the Performance Work Statement (PWS)?

· Not at this time. This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

12. Acquisition Strategy, Contract Structure, and Procurement Authority: What acquisition strategy, anticipated contract type, ordering structure, period of performance, estimated contract value, competition restrictions, and funding arrangements does the Government contemplate for the CP DEPMEDS PSI requirement? Specifically, will commercial component purchases be funded through fixed-price CLINs, cost-reimbursement arrangements, materials under a Time-and-Materials structure, or separately authorized orders, and what contractual authority will Product Support Integrator (PSI) have to place supplier orders and commit contractor funds? | Why This Matters: This establishes the fundamental financial and contractual risk profile. The Engagement Team / Product Support Integrator (PSI) must determine how purchased materiel will be funded, whether advance working capital is necessary, which costs are reimbursable, and how to price management fees, procurement administration, logistics services, facilities, and contractor profit. The answers also determine the appropriate prime-contractor and subcontractor structure.

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response. The Government has not finalized any acquisition strategy and is inquiring about vendor capabilities to determine what acquisition path will provide maximum competition and mission success.

13. CP DEPMEDS Configuration Baseline, Bill of Materials, and Procurement Quantities: Will the Government provide an approved and configuration-controlled Bill of Materials (BOM), complete component specifications, part numbers, National Stock Numbers (NSNs), approved manufacturers, sources of supply, quantity requirements, and planned CP DEPMEDS set configurations? How many complete systems or component packages must be supported, what percentage of components will be commercially procured versus Government-sourced, and what procedures will govern engineering changes, component substitutions, and BOM revisions? | Why This Matters: Component quantity, configuration complexity, and procurement-source mix are primary determinants of material expenditure, purchasing workload, inspection effort, warehouse capacity, and kit-completion costs. Without a validated BOM and volume forecast, the Engagement Team / Product Support Integrator (PSI) cannot credibly calculate procurement expenditures, labor hours per kit, inventory requirements, or unit-level prices. Configuration controls also protect against unpriced scope growth.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

14. Delivery Schedule, Production Throughput, and Performance Requirements: What are the Government's anticipated mobilization date, initial operating capability, required monthly or quarterly kit-production volumes, delivery milestones, total period of performance, and expected surge requirements? Will the Government establish measurable performance standards for procurement lead times, inventory accuracy, IUID marking, kit completeness, delivery timeliness, discrepancy resolution, and corrective-action closure? | Why This Matters: The answer establishes the required logistics throughput and service capacity. The Engagement Team / Product Support Integrator (PSI) needs to translate the Government's delivery profile into personnel utilization, shift requirements, receiving and inspection capacity, warehouse operations, subcontractor commitments, and transportation scheduling. Defined performance thresholds also allow the team to establish realistic service-level commitments and avoid unmanageable delivery guarantees.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

15. Government-Furnished Materiel, Property Accountability, and Supply Dependencies: Which Government organizations, depots, suppliers, and inventory systems will furnish CP DEPMEDS components, and what quantities, conditions, release schedules, shipping arrangements, and property-accountability requirements should Product Support Integrator (PSI) anticipate? When will custody and risk of loss transfer to the contractor, and how will Government-caused shortages, late releases, defective materiel, or delayed transportation be documented and treated under the contract? | Why This Matters: Government-sourced component availability may ultimately determine whether complete kits can be delivered on schedule. The Engagement Team / Product Support Integrator (PSI) must identify dependencies it can control versus those requiring Government action, establish property-receipt and reconciliation procedures, and determine liability for damage or loss. This is essential for compliance with applicable Government-property requirements, including FAR Part 45 and contractually applicable FAR 52.245-1 provisions.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

16. Facilities, Warehousing, Geographic Location, and Physical Security: Will the Government provide or designate warehouse, storage, staging, and IUID-marking facilities, or must the contractor independently furnish an appropriately sized commercial logistics facility? What are the projected inventory volumes, space requirements, environmental controls, preservation conditions, physical-security standards, access restrictions, geographic preferences, and facility inspection or approval requirements? Must facilities be near Pine Bluff Arsenal, or may Product Support Integrator (PSI) operate from another location with coordinated transportation? | Why This Matters: Facilities represent a potentially substantial fixed-cost commitment. Requirements for warehouse square footage, racking, climate control, material-handling equipment, controlled access, utilities, insurance, and transportation proximity will influence the overall delivery model. These answers will help the Engagement Team / Product Support Integrator (PSI) determine whether to lease dedicated space, use an established third-party logistics provider, or establish a hybrid operating arrangement.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· All work will be completed at the contractor’s facility until completion of contract deliverable and shipment to PBA.

17. IUID Marking, Serialized Asset Traceability, and Government Information Systems: Which CP DEPMEDS components require Item Unique Identification (IUID), what marking and verification standards apply, and what records must be delivered or entered into Government systems? Will the Government provide the authoritative item master, UII assignments or construction rules, serialization records, data schemas, required interfaces, and access to applicable Government property or logistics platforms? What are the expected data-transfer frequency, validation standards, cybersecurity requirements, and record-retention obligations? | Why This Matters: IUID implementation can require specialized equipment, trained technicians, verification software, database integration, and quality-assurance controls. The Engagement Team / Product Support Integrator (PSI) must understand whether existing logistics platforms can meet the requirement or whether a dedicated solution is necessary. Requirements associated with MIL-STD-130, applicable DFARS IUID provisions, and data interoperability can materially change implementation costs, staffing qualifications, and technology investments.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· The RFP will outline the items requiring IUID markings and registry. Some of these items will already be marked.

18. Inspection, PMCS, COSIS, Quality Assurance, and Acceptance Boundaries: What specific receiving inspections, Preventive Maintenance Checks and Services (PMCS), Care of Supplies in Storage (COSIS), shelf-life controls, preservation activities, functional checks, and quality verification procedures must Product Support Integrator (PSI) perform? Will the Government supply approved inspection criteria, technical manuals, acceptance checklists, and quality-assurance surveillance requirements, and where does PSI responsibility end relative to Pine Bluff Arsenal's final assembly, system integration, testing, acceptance, and fielding? | Why This Matters: Inspection and preservation obligations can range from administrative receiving verification to technically intensive functional testing and equipment maintenance. The Engagement Team / Product Support Integrator (PSI) needs to distinguish these activities to determine the necessary technicians, inspectors, specialized equipment, quality-management systems, and labor categories. Clear acceptance boundaries reduce exposure to defects arising from manufacturing, Government-furnished materiel, or final PBA integration outside the Product Support Integrator (PSI)'s control.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· The RFP will outline this but the simple answer is that COSIS and PMCS will be required while holding all material until shipment to PBA.

19. Workforce Qualifications, Staffing Levels, and Key Personnel Requirements: What workforce competencies, certifications, prior military logistics experience, facility access credentials, background investigations, security clearances, and specialized technical qualifications will be required? Does the Government anticipate designated key personnel, full-time on-site coverage, minimum staffing levels, surge capacity, or specific labor disciplines for program management, procurement, supply-chain management, IUID operations, warehouse operations, logistics coordination, quality assurance, and property accountability? | Why This Matters: These requirements determine The Engagement Team / Product Support Integrator (PSI) 's recruiting strategy, labor-category mapping, subcontracting needs, and salary assumptions. The team must distinguish positions requiring specialized defense logistics expertise from commercially available supply-chain and warehouse personnel. This distinction is central to controlling direct labor costs while preserving technical competence, contract compliance, and reliable staffing.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· The contractor should bid to the RFP and provide the necessary labor disciplines to meet contract requirements.

20. Transportation, Pine Bluff Arsenal Interfaces, and Delivery Acceptance: What delivery destinations, shipment frequencies, transportation modes, packaging specifications, preservation standards, freight-security requirements, delivery appointment procedures, and receiving documentation will apply to CP DEPMEDS component packages? Will delivery be required to a single Pine Bluff Arsenal receiving point or multiple Government locations, and who bears responsibility for freight procurement, transit insurance, shipment damage, installation access, unloading, discrepancy resolution, and rejected or incomplete shipments? | Why This Matters: Transportation costs depend on shipment size, weight, frequency, handling requirements, carrier selection, and delivery geography. The potential need for specialized freight, secure handling, on-site unloading support, or expedited shipments could materially affect total cost. Defining the precise transfer-of-custody and delivery-acceptance point also helps establish achievable performance commitments and prevents unanticipated contractor exposure.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· Generally, this answer is yes, but will be outlined in the RFP. All components will be stored at the contractor facility until completed and coordinated for shipment to PBA.

21. Proposal Evaluation, Past Performance, Risk Allocation, and Best-Value Pricing: What technical capabilities, relevant past-performance characteristics, demonstrable facilities and infrastructure, quality systems, logistics technology, financial capacity, and risk-management practices will the Government emphasize when evaluating potential PSI providers? For a subsequent solicitation, does the Government anticipate a best-value tradeoff or lowest-price technically acceptable evaluation, and would it consider separately priced mobilization, recurring management labor, warehousing, IUID processing, kit assembly, transportation, and component procurement CLINs, with equitable mechanisms for volume fluctuations, obsolescence, supply-chain disruptions, and Government-directed changes? | Why This Matters: The evaluation methodology and risk allocation will directly inform The Engagement Team / Product Support Integrator (PSI) 's proposal architecture, competitive differentiation, teaming decisions, and pricing methodology. Understanding which capabilities are mandatory, which are discriminators, and how Government-directed changes will be handled allows The Engagement Team / Product Support Integrator (PSI) to present a compelling value proposition without absorbing high or uncontrollable costs.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

22. Contractor-Furnished Secure Warehousing, Receiving, Staging, Preparation, Kitting, and Logistics Infrastructure: Will the Government require The Engagement Team / Product Support Integrator (PSI) Engagement Team, acting as the Product Support Integrator (PSI), to provide and operate its own secure warehousing, receiving, inspection, inventory management, preservation, staging, preparation, component-level kitting, and logistics distribution facilities for commercially procured and Government-furnished CP DEPMEDS materiel, or will the Government provide existing facilities, storage infrastructure, equipment, and operational support? Specifically, what are the anticipated warehouse capacity and square-footage requirements, inventory volumes, storage durations, environmental controls, security classifications, physical protection requirements, material-handling equipment, and operational readiness expectations? Will the Product Support Integrator (PSI) be responsible solely for preparing and distributing components and completed kits to Pine Bluff Arsenal (PBA), or will its responsibilities extend to secure storage, handling, packaging, and distribution of fully assembled CP DEPMEDS systems or finished products after Government integration and acceptance? | Why This Matters: This question establishes whether the Engagement Team / Product Support Integrator (PSI) must develop or subcontract a fully functional, secure logistics and distribution operation rather than simply providing procurement coordination and program-management services. The distinction has substantial implications for facility acquisition or leasing, warehouse staffing, capital investments, insurance, physical security, inventory technology, receiving and inspection processes, environmental preservation, and distribution costs. It also clarifies whether the Engagement Team/Product Support Integrator (PSI) responsibilities terminate upon delivery of component packages to PBA or extend into finished-product warehousing and downstream distribution. The answer will determine the most appropriate delivery architecture, including whether partnering with an established third-party logistics (3PL) provider, defense logistics organization, or secure warehousing subcontractor is feasible.

· This is not a solicitation, this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· Generally, this answer is yes, but will be outlined in the RFP. All components will be stored at the contractor facility until completed and coordinated for shipment to PBA.

23. Geographic Locations, Security Requirements, and Operational Responsibilities for Points of Receipt and Materiel Consolidation: What are the Government-designated or anticipated geographic locations, installation addresses, and security requirements for all Points of Receipt (POR), including commercial suppliers, Government depots, military installations, Defense Logistics Agency (DLA) facilities, contractor warehouses, and other authorized materiel transfer locations? Will the Government establish centralized receiving and consolidation points, or must The Engagement Team / Product Support Integrator (PSI) coordinate deliveries from multiple geographically dispersed origins to a contractor-operated facility? Additionally, what installation-access requirements, personnel clearance or vetting standards, vehicle and carrier authorization procedures, facility security controls, chain-of-custody documentation, and receiving inspection protocols will govern these locations? Will the Government permit Product Support Integrator (PSI) to designate and operate an off-installation commercial receiving and consolidation facility, and are there geographic restrictions or proximity requirements relative to Pine Bluff Arsenal? | Why This Matters: The locations and security characteristics of materiel receipt points will directly determine the complexity and cost of inbound transportation, freight coordination, inventory consolidation, personnel deployment, and logistics operations.The vendor needs to establish whether a centralized distribution model is feasible or whether multiple receiving locations, regional logistics partners, or dedicated transportation arrangements will be required. The vendor also needs to understand installation security requirements, access restrictions, carrier eligibility, personnel vetting, and custody-transfer procedures to develop compliant operating procedures and realistic delivery schedules. This information will enable the vendor to evaluate the optimal geographic location for its logistics hub, identify qualified regional partners, and accurately estimate inbound freight, receiving labor, security, and materiel-handling costs.

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· At this time, all deliveries will be sent to PBA in accordance with contract requirements.

24. Points of Distribution, Secure Transportation, Chain of Custody, and Final Delivery Responsibilities: What are the Government-designated Points of Distribution (POD), final delivery destinations, and required security protocols for CP DEPMEDS finished products, component packages, replacement parts, equipment assemblies, and Government-furnished materiel? Is Pine Bluff Arsenal the exclusive contractor delivery destination, or must the Engagement Team / Product Support Integrator (PSI) support additional military installations, Government depots, operational units, fielding locations, or other designated distribution points throughout the Continental United States (CONUS) or Outside the Continental United States (OCONUS)? Specifically, will Product Support Integrator (PSI) be responsible for arranging secure transportation, carrier selection, shipment tracking, chain-of-custody documentation, controlled-access delivery, shipment insurance, proof of delivery, and discrepancy resolution? Will the Government prescribe transportation security standards, approved carriers, delivery routes, shipment visibility requirements, or escort procedures? When will responsibility, custody, risk of loss, and financial liability transfer among the contractor, the Government, and receiving organizations, particularly when materiel or completed systems are transported between contractor facilities, Pine Bluff Arsenal, and final fielding destinations? | Why This Matters: This question defines the geographic and contractual boundaries of the vendor’s outbound logistics and secure distribution responsibilities. The difference between delivering consolidated component kits to a single PBA receiving location and operating a multi-destination distribution network for finished CP DEPMEDS systems is substantial. Additional distribution responsibilities may require specialized transportation subcontractors, enhanced shipment security, increased insurance coverage, dedicated logistics coordinators, carrier qualification, shipment-tracking technology, and more extensive documentation and quality controls. Establishing precise custody-transfer and acceptance points will enable the vendor to allocate transportation risk appropriately, avoid assuming liability for Government-controlled activities, and develop defensible pricing for secure shipping, handling, and distribution services.

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· At this time, all deliveries will be sent to PBA in accordance with contract requirements.

25. Materials and condition: Is an indicative BOM or component list available, including quantities, dimensions, and weights? Would government-furnished equipment arrive new and serviceable, or require testing, cleaning, repair, or refurbishment?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response. Hazardous materials: Would the inventory include hazardous materials, explosives, radioactive sources, compressed gases, fuels, chemicals, or lithium batteries? If applicable, please identify transportation hazard classifications, available Safety Data Sheets, and special storage or handling requirements.

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· The only hazardous materials involved would be fuels and batteries (power generators), refrigerants (ECUs), and activated charcoal (CB filters). No other hazardous chemicals are known at this point.

26. Program scale: What annual purchased-component spending, government-furnished material volume, number of systems, and delivery frequency are anticipated?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

27. Duration and minimum commitment: What contract duration and ordering structure are contemplated? Would there be a minimum purchase commitment or funded workload to support dedicated facilities and staff?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

28. Startup schedule: What award, startup, and first-delivery dates are anticipated? Would a funded mobilization period be considered?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· Targeting contract award in FY28. Deliveries would be dependent on lead times and anticipated to be completed annually.

29. Facilities and operating requirements: What storage footprint, environmental controls, staffing coverage, maintenance activities, and reporting requirements are anticipated? These details would help us estimate warehouse, staffing, maintenance, and reporting costs.

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

30. Location: May receiving, storage, inspection, IUID marking, and consolidation be performed at a contractor-selected facility in Michigan or Florida, with component packages shipped to Pine Bluff Arsenal? What level of on-site support at PBA is expected?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· Generally, this answer is yes but will be outlined in the RFP. All components will be stored at the contractor facility until completed and coordinated for shipment to PBA.

31. Inspection, acceptance, and accountability: What inspection and acceptance criteria are anticipated for incoming government material and completed component packages? How would responsibility be allocated for pre-existing damage, shortages, supplier defects, and loss or damage while material is in contractor custody?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

32. Mandatory qualifications: Are facility or personnel security clearances, third-party quality certifications, cybersecurity requirements, or specific inventory and IUID systems anticipated?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

33. Payment and working capital: Would the contractor be expected to finance component purchases until delivery and acceptance, or are other payment arrangements under consideration?

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.

· See RFI: “The contractor would not independently obligate Government funds or direct Government supply activities. The Government would retain authority for requisitions, funding, release, acceptance, and disposition decisions.”.

34. Compensation structure: Is the Army considering purchased components priced with a markup, separate procurement and logistics service fees, or a combination? We recognize that the RFI invites industry recommendations on contract structure.

· This is not a solicitation; this is a Request for Information (RFI). Requirements will be included in the Request for Proposal (RFP). The RFP should provide enough details to help a contractor with their response.