Replace 2 Lochinvar Shield SNA501.docx
DOCX document 19 KB Posted
- Attached to
- LCC19-03 Water Heaters, Removal & Replacement
- Solicitation number
- DQ1 GJFA 2019000292 1
- Issued by
- Prowers County, Colorado
About this file
This is a Scope of Work document from Lamar Community College in Lamar, Colorado, for boiler replacement services at Todd-Burch Hall. The project involves removing and replacing two existing Lochinvar Shield SNA501-125 water heaters with identical models, completing a heat exchanger cleaning on a third unit, replacing piping and valves for isolation purposes on all three water heaters, installing new condensate neutralizer kits with individual drain pipes for each unit, and setting combustion parameters on all three heaters. Documented quotes are due November 2, 2018, at 1:00 pm MDT, with submissions directed to Ava Bair at the Trustees Building, Room 132, 2401 S. Main Street, Lamar, CO 81052. Bidders are encouraged to schedule site visits or inspections by contacting Sean Lirley, Director of Facilities, at 719.336.1543.
The document specifies that Lamar Community College retains ownership of all components and parts from the two replaced water heaters (#2 and #3). No pricing information, set-asides, funding sources, or contract term details are provided in the scope of work document. Bidders should reference BID #19-03 on the outside of their proposal envelopes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Water Heater Specs Page 1.pdf | ||
| Water Heater Specs Page 4.pdf | ||
| Water Heater Specs Page 3.pdf | ||
| Water Heater Specs Page 2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOILER REPLACEMENT
Replace 2 Lochinvar Shield SNA501-125 water heaters at Todd-Burch Hall and associated work.
Proposal will include the following Scope of Work:
• Remove and replace the existing #2 & #3 Lochinvar Shield water heaters and replace with same Model
• Complete a clean of heat exchanger in #1 water heater
• Replace piping and valves as needed for isolation of each water heater (3)
• Install new condensate neutralizer kits for each water heater with individual drain pipes to floor drain (3)
• Set combustion for all 3 water heaters
Notes:
· Owner retains possession of #2 & #3 water heater components/parts.
· To schedule a site visit/inspection please contact:
· Sean Lirley Director of Facilities Lamar, CO 81052 719.336.1543
Documented Quotes Due: November 2, 2018 at 1:00 pm MDT
| Note on Outside of Envelope: BID #19-03 11/2/18 | ||
| Mail to: | Lamar Community College |
Ava Bair, Trustees Bldg., Room #132 2401 S. Main St.
Lamar, CO 81052