Renovate 2N Laboratory - SOW dtd 07232025 .docx

DOCX document 44 KB Posted

Attached to
C1DA--Project 667-26-100 A/E Renovate 2N Laboratory
Solicitation number
36C25625R0134
Issued by

About this file

This document is a Statement of Work (SOW) for architectural and engineering (A/E) services to renovate the 2N Laboratory at the Overton Brooks VA Medical Center in Shreveport, Louisiana. The project involves a total renovation of approximately 6,200 square feet of existing laboratory space, including space layout modifications, HVAC system redesign, electrical and plumbing upgrades, asbestos abatement, and removal of non-load bearing walls. The design must comply with VA space planning criteria for a Level L laboratory, optimize workflow, and address infrastructure requirements for a fully functioning Pathology and Laboratory Medicine Service.

The contract is a Firm-Fixed Price design services contract with a 365-calendar day performance period from Notice to Proceed. The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 541330 with a $25.5M size standard. The A/E firm will be responsible for multiple design submission phases, including 25%, 35%, 65%, 95%, and 100% design development, with iterative reviews by the VA. Construction period services are also required, including site visits, shop drawing reviews, inspections, and preparation of record drawings. The project has a detailed submission schedule with specific deliverables and review timelines for each design phase.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work

Renovate 2N Laboratory - Design Project No. 667-26-100 Overton Brooks VA Medical Center, Shreveport, LA

PROJECT BACKGROUND AND DESIGN SCOPE OF WORK

Overton Brooks VAMC (OBVAMC) has a requirement to design a project to renovate 2N Laboratory, main hospital (Building #1) North Wing. The existing 2N Laboratory area does not provide efficient workflow, and existing finishes are not appropriate for lab work. The total renovated space will be approximately 6,200 SF of existing laboratory space. This requirement is a total renovation of the 2N Laboratory space including, but not limited to, space layout modifications, full redesign of HVAC system and ducting (in accordance with VA HVAC design manual), electrical upgrades, plumbing upgrades, asbestos abatement, and removal of unused/abandoned utilities and/or conduit, and removal of most non-load bearing corridor walls. This contract will provide for complete design (construction documents) and construction period services (CPS).

The 2N laboratory shall be designed in accordance with PG-18-9 – Space Planning Criteria – Chapter 240: Pathology and Laboratory Medicine Service and provide optimal workflow with existing equipment and potential forthcoming replacement equipment in the 2N area. Design must alleviate existing congested hallways. Currently, upright refrigerators are place in the hallway along with storage shelves due to space limitations. For planning purposes, the proposed laboratory can be projected into one of four (4) “Levels”. As stated, the assignment of a “Level” to a proposed laboratory must be based on the assessment of multiple factors. The laboratory level category used in the 2N Laboratory shall be Level L (large): Annual LMIP workload of 500,000 to 1.5 million tests, facility MCG of 1c or 1b, greater than 40 Laboratory FTEs, advanced and complex chemistry, hematology, microbiology, and other clinical laboratory services performed. May provide specialized and reference laboratory services to other VA Medical Centers and the community.

The design team shall provide a comprehensive site investigation and attain a complete understanding of the functional requirements for the 2N Laboratory area along with a complete understanding of the existing utility infrastructure. The design team shall meet with each of the Services located on 2N and develop a space program to meet their needs that are compliant with VA space guidelines/criteria. The design team shall propose floor plan options for VA review, consideration and selection. This is an iterative process. The floor plan options shall consider various alternatives to include the placement and location of workflow space. The equipment must be replaced and sized according to new demand and existing ancillary reheat demand.

The design will address all infrastructure requirements for a fully functioning Pathology and Laboratory Medicine Service. The renovated space shall be fully sprinklered. The renovation shall include a fire alarm and suppression system per VA standards and NFPA requirements and shall be tied into the stations existing monitoring system. The design shall provide a cost-effective high energy efficient HVAC system and all necessary controls to properly support the function of the space and shall be tied into the existing campus Building Automation System (BAS). The design shall include, but will not be limited to, phasing, handicap accessibility, pneumatic tube system modifications, signage, wayfinding, plumbing, electrical, communications, physical security, HVAC, structural, and all required support utilities and features to adequately support the new space. Design shall be in accordance with all applicable VA design guides, design manuals, and standards.

The design shall lay out a construction phasing plan to keep the 2nd Floor North Wing fully occupied and operational throughout the construction duration. 2nd Floor North Wing continuously operates 24 hours a day and seven days a week. Designer must account for phasing needed to facilitate the replacement of mechanical equipment and removal of non-load bearing corridor walls and room separating walls including utilities within. Special considerations must always be made to ensure disruptions to hospital operations are kept to a minimum.

The C&A requirements do not apply, and a Security Accreditation Package is not required.

PERIOD OF PERFORMANCE

The delivery date for this contract shall be 365 calendar days from Notice to Proceed. Performance time to include VA review of each submission as identified.

LOCATION

Overton Brooks Veterans Affairs Medical Center 510 E. Stoner Ave.

Shreveport, LA 71101

DESIGN SUBMISSIONS/DELIVERABLES:

Design submission and deliverables will be in accordance with the A/E Submission Instructions for Minor and NRM Construction Programs; PG-18-15, Volume C

QUALITY ASSURANCE/QUALITY CONTROL (QA/QC)

The Design Offeror or A/E shall develop, execute and demonstrate that the project plans and specifications have gone through a rigorous review and coordination effort. The A/E shall provide an outline of the actions the firm will take during the design process to ensure a quality finished design is achieved.

COST ESTIMATE

A detailed estimate of construction cost (using RS Means, Cost Works) and Market Study/Survey shall be provided with each design submission. Emphasis shall be placed on cost and scope management. The design shall be within the project construction budget and be consistent with the identified project scope. The development of construction documents by the Design Team shall include deductive alternates, up to 10% of the approved project cost estimate.

DRAWINGS

This project will utilize AutoCAD, version 2020. All VA design guides and requirements can be found online at: http://www.cfm.gov/TIL/. Where conflicts occur between VA standards and model codes, the most stringent shall govern.

SITE AND TOPOGRAPHY SURVEY

A topographic survey is not required. As for the site survey, the A/E shall investigate the site, the existing floors above (3rd floor) and below (basement through 1st floor) where tying into the main hospital, to get a good understanding of the existing conditions, structure and utilities. A/E shall make as many site visits as necessary for this investigation. It is the A/E’s responsibility to verify the actual existing conditions. Reference the following attachments:

Attachment B: 667-16-103 Renovate Pathology Redline Drawings Revised

GEOTECHNICAL SURVEY

A geotechnical survey is not required.

UTILITY SURVEY

During the design phase, the A/E will coordinate with VA Staff to obtain information to facilitate the design. All information provided by the VA will be verified by the A/E. Where information is not available, the A/E Team shall perform their own investigation at their own expense. The A/E shall provide the necessary professional services or testing to conduct a complete site utility survey as needed to facilitate the design. The survey must identify all above and below ground utilities associated with the project. An analysis of the capacity of the existing utilities to serve the new addition shall be performed. The result of the survey/study shall be reflected in the design documents and shall indicate the current system capacities and the necessary work required for the utilities to adequately support the new addition.

FIRE PROTECTION ENGINEER REVIEW & CERTIFICATION

The A/E shall have the design plans and specifications reviewed by a 3rd party registered Fire Protection Engineer (FPE) to ensure the design proceeds in accordance with Life Safety Codes (LSC) and applicable National Fire Protection Association (NFPA) codes. The FPE’s review comments shall be provided along with each design submittals beyond the schematic design. With the Final 100% Construction Documents submittal, the A/E shall provide a FINAL certification letter from a registered FPE stating the FINAL plans and specifications are in compliance with the current LSC and NFPA codes.

SEISMIC DESIGN

Design shall be in accordance with the VA’s manual for Seismic Design Requirements (H-18-8), as it applies to Shreveport, LA.

PHYSICAL SECURITY & BLAST DESIGN

The design shall be in accordance with the Physical Security and Resiliency Design Manual (PSRDM) for VA Facilities, Mission Critical Facilities.

HANDICAP ACCESSIBILITY

The design will be required to comply with the Uniform Federal Accessibility Standards (UFAS), the Americans with Disabilities Act (ADA) and PG-18-13 (Barrier Free Design Guide) in all areas.

COMMISSIONING

The A/E shall incorporate the VA’s commissioning specifications into the design and construction documents as applicable. The VA will, by separate contract at time of construction, procure the 3rd party Commissioning Agent to oversee and execute the contract required commissioning activities during the construction phase.

GOVERNMENT FURNISHED INFORMATION

Government furnished information includes, but not limited to, the following information found on the VA’s Technical Information Library website (http://www.cfm.va.gov/TIL) - to be used for this project, as applicable (use most recent version):

PG-18-1Master Construction Specifications for VHA Projects
PG-18-3Design and Construction Procedures
PG-18-4Standard Details and CAD Standards
PG-18-5Equipment Guide List
H-18-8Seismic Design Handbook
PG-18-9Space Planning Criteria
PG-18-10Design Manuals (by discipline)
PG-18-12Design Guides (graphical, by function)
PG-18-13Architectural Accessibility, Barrier Free Design Standards
PG-18-14Room Finishes, Door and Hardware Schedules
PG-18-15Minimum Requirements for A/E Submissions (included as Attachment A)
PG-18-17Environmental Compliance Manual
H-7545VA Cultural Resource Management

Physical Security and Resiliency Design Manual for VA Facilities, Mission Critical Facilities VA Signage & Wayfinding Design Manual VA HVAC Design Manual VA Fire Protection Design Manual VA Asbestos Abatement Design Manual VA Sustainable Design Manual and Guiding Principles Checklist VA-Space & Equipment Planning System (VA-SEPS) VA Architectural Design Manual VA Design Manuals for Estimating, Electrical, Elevator, Lighting, Plumbing & Telecommunications

Chapter 240: Pathology and Laboratory Medicine Service – Space Criteria

LIST OF ATTACHMENTS

Attachment A: AE Submission Requirements Attachment B: 667-16-103 Renovate Pathology Redline Drawings Revised

AE SUBMISSION REQUIREMENTS (SUPPLEMENTAL INSTRUCTIONS)

Reference Attachment A (AE Submission Requirements) for a detailed outline and listing of specific requirements. As indicated under Section C, paragraph 1, below are supplemental instructions relative to AE submission requirements.

NOTE: The VA will have 21 days to review design submission; however, some design submissions may require longer as they require a higher-level review. The AE shall not proceed to the next design submission until comments have been received back from the VA. The AE will be allowed a “time-only” extension equal to the number of days that the VA takes longer than 21 days to return review comments.

The following design milestones are required from Notice of Award:

25% Design Development
60 calendar days after Notice of Award
25% Design Review Meeting
21 calendar days after VA receipt of 25% Design Development
35% Design Development
50 calendar days after VA acceptance of 25% Design Development
35% Design Review Meeting
21 calendar days after VA receipt of 35% Design Development
65% Design Development
60 calendar days after VA acceptance of 35% Design Development
65% Design Review Meeting
21 calendar days after VA receipt of 65% Design Development
95% Design Development
60 calendar days after VA acceptance of 65% Design Development
95% Design Review Meeting
21 calendar days after VA receipt of 95% Design Development
100% Design Development
30 calendar days after VA acceptance of 95% Design Development
100% Design Review Meeting
21 calendar days after VA receipt of Design Development
Total Part One Services/Design Phase Schedule
365 calendar days

a. 25% Schematic Design: Investigate and survey project site. Verify any VA provided data. AE is responsible for collecting any and all data required for the design. The A/E is responsible for measuring and collecting actual field data that may be required. The A/E shall collaborate with VA COR and end user(s) to develop conceptual and viable design options to meet the intended scope of work. The A/E shall develop schematic drawings and design options, along with Pro’s and Con’s with associated cost for review. This schematic design phase is an iterative process and requires close coordination back and forth with the VA COR/Project manager. The preliminary schematic design/layout will most likely require tweaking until a final plan/layout is officially approved by the hospital and COR. Dimensions, areas, spaces, etc. will need to be indicated clearly on the drawings. The AE shall work with the VA COR until an acceptable plan is developed and approved in writing by the VA COR. The A/E final deliverables for this phase are (hard and electronic copies):

1) OBVAMC Approved Plan (Floor Plan)

2) Preliminary Cost Estimate (RS Means, Cost Works)

3) List of probable Specification Sections for this project (redlined Table of Contents)

4) Initial Design Analysis and Approach

b. 35% Design Development: These drawings shall be at the largest scale possible and shall show the utilities, infrastructure, architectural layout of each floor, room dimensioning/square footage, room identification, fire exists (Life Safety), chases, columns and other pertinent information necessary to provide information that will carry the design to the next review.

1) Drawings & Specifications: Provide one 22”x34” size D set and four 17”x22” size C sets. Provide one set of preliminary specifications indicating all of the AE proposed edits (indicate edits in redline format) in a 3-hole punch binder. Drawings and specifications to indicate phasing requirements. Also, provide electronic copies of drawings in PDF format (1 combined PDF, and individual PDF files). Specifications in Word format (individual Word documents per specification section).

2) Cost Estimate: Provide a detailed cost estimate indicating labor, material and equipment cost in RS Means CostWorks format. Estimate shall include Prime Contractors Overhead, Profit, Bond and Labor Burden (typically 30%). This cost estimate shall be submitted in hard copy with the Design Analysis and an electronic copy in PDF format.

3) Design Analysis: Provide a design analysis for each discipline indicating the design rational, thought process and design calculations (including actual field test and test date). Provide a draft preliminary detailed submittal register. Provide a list, by discipline, on what outstanding data or feedback is required from OBVAMC. Provide one hard copy of the Design Analysis and one electronic copy in PDF format.

4) FPE Review/Certification: Provide review comments made by the 3rd party Fire Protection Engineer for this submission.

NOTE: The AE shall not proceed with the 65% design without written concurrence from the VA COR.

c. 65% Design Development: This submission of drawings, specifications and cost estimate shall be very close to complete. This review by the VA shall be to validate that 35% comments were incorporated into the project. The construction documents should be sufficiently developed to cover all work items to be addressed by the project, including clearing defined phasing requirements. No major items missing from this submission. The VAMC review of these documents should result in very minor comments to allow for the next 95% submission. A/E shall provide a list of questions by discipline on anything that’s needed from the VA to continue and fully develop the next 95% design submission. Additionally, the A/E shall provide minutes from the last design review meeting and shall provide responses to all VA comments noted or identified during the last review submission.

1) Drawings & Specifications: Submit in the same manner as the 35% DD submittal. Specifications shall incorporate AE’s edits.

2) Cost Estimate: Submit in the same manner as the 35% DD submittal.

3) Design Analysis: Submit in the same manner as the 35% DD submittal. Include A/E responses to all 35% design review comments.

4) FPE Certification: Submit in the same manner as the 35% DD submittal. Specifications shall incorporate AE’s edits.

d. 95% Design Development: This submission of drawings, specifications and cost estimate shall be complete. This review by the VA shall be to validate that 65% comments were incorporated into the project. There shall be nothing missing from the construction documents. The VAMC review of these documents should result in very minor comments to allow for the next submission to be final. If the comments of this set of documents results in numerous comments, then a 99% review or a check set of certain elements of the design is required before the AE shall proceed to the 100% Final Construction Documents.

1) Drawings & Specifications: Submit in the same manner as the 65% DD submittal.

2) Cost Estimate: Submit in the same manner as the 65% DD submittal.

3) Design Analysis: Submit in the same manner as the 65% DD submittal. Include A/E responses to all 65% design review comments.

4) FPE Certification: Submit in the same manner as the 65% DD submittal.

e. 100% FINAL Construction Documents: This submission shall incorporate all project requirements and previous comments. These documents shall be ready for bidding/construction.

1) Drawings & Specifications: ALL ENGINEERS AND ARCHITECTS PROFESSIONAL “STAMPS” SHALL BE ON THIS SET OF DOUMENTS. Provide one 22”x34” size D set and four 17”x22” size C sets of FINAL construction drawings. Provide one set of FINAL fully edited specifications (specs in a 3-hole punch notebook, printed on both sides of the paper). Drawings and specifications to indicate any phasing requirements. Provide electronic copies of the entire package (Construction Drawings, Specifications, Design Analysis and Cost Estimate). The drawings shall be as both AutoCAD (2020), and PDF format both in individual files per drawing and a combined drawing PDF file. The specifications shall be in separate WORD documents and separate PDF files for each specification section. Also, provide a combined PDF file for each complete volume of the specifications. Coordinate the naming & numbering of the files with the COR.

2) Cost Estimate: Submit FINAL CostWorks cost estimate in the same manner as previous submittal.

3) Design Analysis: Submit FINAL and complete Design Analysis documents including all calculations for each discipline. Provide a final detailed submittal register. Submit in the same manner as the previous submittals. Include A/E responses to all design review comments.

4) FPE Certification: Provide a FINAL certification letter from a 3rd party registered Fire Protection Engineer stating that the FINAL plans and specifications are in compliance with the current Life Safety Code (LSC) and applicable National Fire Protection Association (NFPA) code.

SOLICITATION SUPPORT SERVICES:

· Answer any technical questions/requests for information (RFIs) received from contractors over the duration of the solicitation, including questions asked during the site visit. Questions from contractors may come at multiple times and cover several or a few questions over the course of the solicitation period. Technical question responses will be provided to the Contracting Officer who will distribute the information via amendment to the solicitation.

· Answers to RFIs will be required from the A/E within five (5) calendar days of the date the questions are sent to the A/E from either the project COR or CO. An alternate response period may be submitted for review, however, unless approved by the CO and COR, the A/E is required to comply with the five-calendar-day requirement.

· Throughout the solicitation period, the A/E shall provide addenda as necessary if required to revise specs and drawings.

· In response to any technical questions and/or addenda issued during the solicitation period, the A/E shall provide any final revisions to the 100% FC CD as part of the construction contract. These documents shall be labeled Final Construction.

CONSTRUCTION PERIOD SERVICES (CPS)

A/E shall provide full post design services construction period service IAW the Special Provisions of this contract. The A/E shall review the Contractor's requests for information and cost proposals for construction change orders when requested by the COR. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.

· PRE-AWARD: CPS’s to include assistance with questions, request for information (RFI’s), meeting conference calls, clarifications and addendums during the construction solicitation phase.

· POST-AWARD: CPS’s also include full support through the construction phase to include but not limited to, assisting with questions, clarifications, inspections, reviewing and responding to RFI’s and review/coordination of contract modifications/change orders. Designing and estimating of design omissions.

· POST-AWARD SITE VISITS: CPS’s shall also include a minimum of 15 Site Visits during the construction phase of the project. Type and discipline of site visit shall be determined at the time of need by the COR.

· AS-BUILTS: AE shall also incorporate contractor’s as-builts/redline drawings on AutoCAD (2020) bound and provide both electronic (two CD’s clearly labeled) and hard copy sets. Hard copy sets of as-built drawings shall consist of one full size set and four 22”x34” size sets.

a. REQUEST FOR PROPOSAL DOCUMENTS – INTERPRETATION: The A/E, when requested, shall assist the Contracting Officer and his Contracting Officer Representative to develop the Request for Proposal documents and shall:

(1) recommend any action(s) he deems suitable for the satisfactory prosecution of the design of the proper construction work.

(2) prepare any supplemental drawings, specifications or other documents that may be required to clarify or supplement the Request for Proposal documents.

(3) assess the preparation of Construction Contract Modifications initiated by or through the VA to be executed in accordance with the Request for Proposal documents.

b. MODIFICATIONS/CHANGE ORDER REQUESTS: Modification requests shall be submitted within seven (7) calendar days of submittal to the A/E. This includes the review of the contractor’s change order/modification proposal for construction change orders, as well as the formulation of an IGCE for the modification, as requested. The A/E's reply regarding his/her review of cost proposals and his/her recommendations shall include an independent breakdown of costs in detail, quantities, and unit prices and shall cover both additions and deductions of labor, materials, and equipment. The A/E shall also supply cost estimates as requested by the COR for Request for Proposals for anticipated changes.” All documents in any of the electronic formats listed above. Note - If major modification, VA will provide additional time and document format guidance.

c. SHOP DRAWINGS AND SUBMITTALS: The A/E will, through the VA, review certain submittals and make recommendation. The A/E may be required to hold joint reviews with the VA technical staff on complicated system submittals. Such responsibility shall be carried out with reasonable promptness as to cause no delay.

The A/E shall check Government furnished and/or the construction shop drawings, detail drawings, schedules, descriptive literature and samples, testing laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the design concept and construction documents. The A/E shall recommend approval, disapproval, or other suitable disposition. He shall evaluate the submittals with reference to any companion submittals that constitute a system.

d. SITE VISITS AND INSPECTIONS: During the Construction Period, the A/E shall make visits to the project site. Site visits shall be made as and when requested by the Contracting Officer or his authorized representative. This includes visits to be made during intermediate, air conditioning systems, inspections, for partial final, and final inspection and for special purposes as requested by the Contracting Officer. A site visit is defined, except for payment purposes, as a visit to the site by one man for any part of a day. Only registered architects and engineers thoroughly familiar with the project may make these site visits. The Contracting Officer has the prerogative to determine the professional discipline(s) required for each visit. The A/E shall observe the construction, advise the VA of any deviations or deficiencies. A site inspection report which includes the purpose of the inspection, items reviewed, deficiencies observed, recommendations and additional actions required, shall be furnished to the Contracting Officer or his authorized representative within three calendar days following the site visit date.

(1) Intermediate Inspections: The A/E shall provide registered architects and engineers who are familiar with the design work of the project to act as observers and advisers to the VA team conducting intermediate inspections.

(2) Partial Final and Final Inspections: The A/E shall provide registered architects and engineers in the number and of the disciplines at the time requested by the Contracting Officer to act as observers and advisers with a VA team conducting partial final and/or final inspection(s) of the project.

e. TIMELY RESPONSE: As time is of the essence, particularly during the construction phase, the A/E shall promptly review and approve, disapprove, or take other appropriate action upon all the VA requests. The A/E shall submit recommendations on all shop drawings and other submittals and other requests within ten (10) calendar days after receipt.

RECORD DRAWINGS: The VA shall furnish to the A/E a marked-up set of prints showing all changes made during the construction period. The A/E shall incorporate into the drawings all significant changes marked-up by the VA and any significant changes made by solicitation amendments and construction contract modifications. The revision portion of title block shall be dated and noted “Record Drawings”. The A/E shall prepare record drawings by making changes on the original contract drawings (with amendments posted). A copy of the updated original will be sent to the VA for verification. Upon the verification of the VA, the A/E will submit the originals to the Contracting Officer in hardcopy and on DVD. The A/E shall deliver the record drawings to the Contracting Officer within thirty (30) calendar days after receiving the marked-up documents from the VA. Submission shall be subject to the approval of the Contracting Officer as to quality and completeness.

GENERAL INFORMATION:

a. The A/E contractor shall submit all requests for information in writing to the COR and allow at least three calendar days for the COR to respond.

b. The Contracting Officer must approve all work that is beyond the scope of this statement of work.

c. All design review meetings must have a CO present and meeting recorded.