Location: Courthouse, 350 West First Street, Los Angeles, CA 90012-3100

1. Agency & Contracting Activity:

General Services Administration (GSA), Region 9, Acquisition Management Division (AMD), Building Services Branch (9PQS), Los Angeles Service Center (LASC).

2. Nature, Description of Action, and Purpose:

On September 1, 2017, a contract was awarded to for the maintenance of Vertical Transportation Equipment (VTE) at the 350 West 1st Street Courthouse. However, was unable to self-perform all of the services due to the highly specialized nature of the proprietary equipment that was installed during the building’s construction.

In the best interests of both the customer and the government, a new contract was awarded on a sole source basis to to satisfy the required VTE services, with a one-year performance period between October 1, 2021, through September 30, 2022 with an Option to Extend Services in accordance with FAR 52.217-8, allowing for an extension not-to-exceed six (6) months or March 31, 2023.

Initially, this procurement was planned to be aggregated as an Operations & Maintenance (O&M) and Vertical Transportation Equipment (VTE) service contract at 350 W First Street.

However, based on discussions between the Acquisition Management Division (AMD) Section and Branch Chief, it was determined that the small business would have to subcontract the VTE portion out to which is a large business. Based on our prior experience, contract was often delayed by schedule and response time, and GSA had no contract privity with at that time. Elevators were often left inoperable for extensive periods of time impacting various tenants in the building. Based on this experience, it was determined to keep the O&M and VTE requirements separate.

There is no change to the proprietary equipment and approval is sought for another sole source award under FAR Part 13.501 to the Original Equipment Manufacturer (OEM), for the full maintenance, repair, and replacement services located at 350 West First Street, Los Angeles, CA 90012-3100. The prospective contract will contain a Base Year with 4 Option-Year periods.

3. Description of Services & Background:

The services are for full elevator maintenance, repair, and replacement. A Firm-Fixed Price (FFP) contract to is necessary due to the highly specialized nature of the VTE control systems contained at Courthouse, 350 West First Street, Los Angeles, CA 90012-3100. These VTE, for which is the OEM, were installed in the new Courthouse, 350 West First Street, Los Angeles, CA 90012-3100 and accepted in August of 2016. The elevator control systems, specifically the E2 Skyrise OEO, HVS E2, GCS, Hydrofit and MEI Hydro systems encompass the controller and driver mechanisms which use a patented motion-control algorithm to ensure smoother and safer operation. As such these systems are proprietary and cannot be maintained by a third party. The critical components of the VTE are not within the capabilities of companies other than to service.

Date: August 16, 2022 Subject: Justification for Other than Full and Open Competition Authority: FAR Part 13.501 Special documentation requirements.

Contract: Full Elevator Maintenance, Repair and Replacement Services

Anecdotal correspondence from the vendor of the contract awarded in 2017, describes that its procedures are incompatible with the combination of proprietary elevator equipment in the form of E2 controllers and drives. also highlighted the specific need for firmware and programming expertise in order to pass inspection and the 5-year testing.

Potential complications based on previous experience, if a sole source to is not pursued may include, but are not limited to:

(1) Elevator drive failures and inability for repairs

(2) Elevators in non-operational status for extended and/or indefinite time periods

(3) Increased costs on taxpayer/government funds due to non-OEM vendors subcontracting to to successfully perform the service requirements of the prospective contract.

(4) Other technical complications regarding VTE

If a sole source award to is not pursued, the adverse mission impact attributed with the prospective contract will affect time, customer satisfaction, cost increase, court services, prisoner transportation, public safety, and the overall structural integrity of the Courthouse, 350 West First Street, Los Angeles, CA 90012-3100.

Below is the Independent Government Estimate (IGE) for the prospective sole source award, annually:

Base Year Price:

Option 1:

Option 2:

Option 3:

Option 4:

Above Standard Services:

FAR Part 52.217-8 Option to Extend (6 MO if needed):

Total 5-Year Estimated Price:

4. An Identification of the Statutory Authority Permitting Other Than Full and Open Competition:

This acquisition will utilize FAR Part 13.501(a)(ii) in preparation of sole-source justification using the format as prescribed by FAR 6.303-2 modified to reflect the procedures in Subpart 13.5 in accordance with 41 U.S.C. 1901, Simplified Acquisition Procedures.

5. A Demonstration that the Proposed Contractor’s Unique Qualifications or the Nature of the Acquisition Requires Use of the Authority Cited:

The vendor selected for the prospective service contract will be Only possesses the specialized skill and knowledge to maintain the elevators at the courthouse because of the proprietary equipment that is OEM to the company. Efforts by other vendors to perform the elevator requirement will ultimately result in subcontracting to or for the government to contract with via purchase orders, on an as needed basis. Due to the inevitability of involvement, it is in the government’s best interest to contract directly with for this requirement for administrative efficiency, cost savings, and to ensure that the required services will continue.

When was not the Prime Contractor performing VTE services at this location, the Los Angeles Field Office had to issue Additional Service Orders totaling to repair the proprietary VTE systems of Elevator 1 over a period of two years. When added to the recurring costs charged by the Prime Contractor, over this two-year period, the total cost for Elevator 1 equals In comparison, the cost charges for repairs and maintenance for Elevator 1 is when adjusted for a two-year period. This equates to a difference of about for a two-year period or annually that GSA spent to fund the repairs for one elevator.

Based on this data, if is not the Prime contractor and all 15 elevators eventually need repair on these proprietary systems, an approximate increase to the contract cost of about x 15 Elevators x 5 years) may exist. This cost also does not account for the administrative costs the Field Office experienced in negotiating and awarding contract actions for to perform the required maintenance of these proprietary systems. It should also be noted, GSA cannot account for the administrative and logistical costs, along with the mission impact associated with other agencies not being able to use the VTE due to inoperability.

Additionally, under the current sole source contract with the administrative costs of scheduling work and tracking completion of maintenance have decreased. As GSA maintains privity with their performance has and must continue to meet the requirements and timeframes of the established contract.

6. A description of efforts made to ensure that offers are solicited from as many potential sources as is practicable, including whether a notice was or will be publicized as required by Subpart 5.2 and, if not, which exception under 5.202 applies:

None of the exceptions in FAR 5.202 are applicable. is the only vendor qualified to perform the requirement.

7. A determination by the contracting officer that the anticipated cost to the Government will be fair and reasonable:

clearly demonstrates their capabilities to meet all the needs for Full Elevator Maintenance, Repair and Replacement services, based on the OEM nature of the VTE.

Upon receipt of the official quotation, a determination of fair and reasonable pricing will be made using pricing analysis IAW FAR 13.106-3(a)(2)(vi)].

8. A description of the market research conducted and the results or a statement of the reason market research was not conducted:

GSA R9 Facilities Management Division (FMD) completed market research on July 29, 2022.

During the market research, it was verified that is the only vendor qualified to maintain the elevators at the 350 West First Street Courthouse, due to the reasons stated previously in this document. Engineer Technician and Building Management Specialist, FMD, Region 9 affirms the following:

Main passenger 6-car group is designed with Occupant Evacuation Operation OEO/OEE system that works in conjunction with the Fire Alarm panel to provide a secondary means of degree in the event of a fire or emergency. Due to the technical proprietary limitations is the only contractor that is capable of performing the code required testing and will only provide this service if an existing elevator maintenance service contract is in place.

- E2 Skyrise OEO, HVS E2, GCS, Hydrofit and MEI Hydro are proprietary elevator control systems that technically cannot be maintained by 3rd party elevator maintenance contractors.

GSA previously awarded a comprehensive elevator maintenance contract to service the elevators at the New L.A. Courthouse to however, even with all of their determination and dedication they could not perform specific code required function testing. In addition, did experience extensive delays and difficulty with obtaining spare parts from the respective suppliers and manufacturers.

GSA ultimately parted ways with as they did not have the technical resources and capabilities to reliably maintain the elevators. has been the contractor performing comprehensive elevator maintenance services via a sole source procurement and have managed to PASS the 5-year inspections which took substantial effort to complete.

Further market research is unnecessary and adds no further value to the acquisition process because of the proprietary, technical circumstances regarding the maintenance of elevators at the courthouse.

9. Any other facts supporting the use of other than full and open competition:

Please see Section 8 above.

10. A listing of the sources, if any, that expressed, in writing, an interest in the acquisition:

11. A statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisition for the supplies or services required:

During the construction of the 350 West First Street Courthouse, elevators with proprietary OEM were installed. This has required the acquisition team to directly contract with due to the experience with and confirmation that no other vendor is qualified. After awarding this sole source procurement, a redacted justification and approval will be posted per FAR 13.501 requirement within 14 days.

12. The contracting officer’s certification that the justification is accurate and complete to the best of the contracting officer’s knowledge and belief:

Upon signature of the following page, the Contracting Officer (CO), justifies that the supporting data included in the justification is accurate and complete to the best knowledge and belief.

13. Technical/Requirement Certification.

Upon signature of the following page, the Engineering Technician, justifies that the supporting data included in the justification is accurate and complete to the best knowledge and belief.

CERTIFICATION

Pursuant to FAR 13.501, and based upon the above facts, a sole source award is justified due to the highly specialized nature of the equipment.

SARAH CONNOR, Contracting Officer, AMD, LASC, Recurring Services Date: