RDS_24-35_NVVT_VC_Schedule_for_NVVTC_8.24.26.pdf

PDF 963 KB Posted

Attached to
Napa Valley Vine Trail - Vista Carneros RFP
Solicitation number
CML 5921-099
Issued by
Napa County, California

About this file

This is a project schedule document for the Napa Valley Vine Trail - Vista Carneros Gap Closure Project, a multiuse path initiative involving Napa County Department of Public Works. The project aims to complete a four-mile gap in the 47-mile Napa Valley Vine Trail between John F. Kennedy Park and the intersection of Devlin Road at Airport Boulevard. Napa County is procuring a single prime consultant through an RFP to provide comprehensive services including preliminary engineering, environmental assessment, right-of-way work, plans, specifications, estimate preparation, and construction support services. The consultant selection and negotiation process is scheduled to occur between September 23 and October 13, 2026, with board approval of the consultant agreement anticipated on November 3, 2026. The project timeline indicates construction is targeted to commence in spring 2029, with the notice to proceed scheduled for September 3, 2029, and construction duration estimated at 180 days through mid-July 2030.

The schedule reflects a comprehensive design and permitting phase spanning from late 2026 through early 2029, encompassing multiple technical and administrative milestones. Key permitting activities include CDFW Streambed Alteration Agreement, Regional Water Quality Control Board 401 certification, and U.S. Army Corps of Engineers 404 permit reviews, all scheduled between April and December 2028. The project incorporates environmental studies and NEPA documentation review extending from March 2027 through May 2028. Right-of-way certification is scheduled for completion by April 2029, with bid advertisement planned for June 2029 and board award on August 7, 2029. The consultant is required to manage all turnkey services in accordance with Caltrans Local Assistance Procedures, including administrative documentation, responses to Caltrans requirements, and ongoing design support throughout construction.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish Predecessors

2 MTC awards PCA Grant 0 daysFri 11/15/24Fri 11/15/24 3 MTC approves project in TIP 0 days Fri 7/18/25 Fri 7/18/25

4 Request authorization to proceed with PE Phase 0 daysMon 1/5/26 Mon 1/5/26 3 5 NVVTC and Board approve Funding Agreement 37 daysMon 8/24/26Tue 10/13/26

6 Caltrans Coordination/ Field Review 1 dayThu 1/29/26Thu 1/29/26 7 NEPA PES Documents (not including studies) 20 days Fri 1/30/26Thu 2/26/26 6 8 Caltrans sends the E-76 for PE 0 daysWed 7/29/26Wed 7/29/26 7

9 RFP for Consultant Selection 40 daysWed 7/29/26Tue 9/22/26 8 10 Consultant selection and negotiation 15 daysWed 9/23/26Tue 10/13/26 9

11 Board approved agreement with consultant and BT 0 daysTue 11/3/26Tue 11/3/26 12 Conceptual Alignment updates 14 daysTue 11/3/26Fri 11/20/26 11

13 Utility Mapping/Potholing 35 daysMon 11/23/26 Fri 1/8/27 12 14 Supplemental Surveying 15 daysMon 1/11/27 Fri 1/29/27 13 15 35% Plans Update 30 days Mon 2/1/27 Fri 3/12/27 14

16 Geotechnical Drilling and Report 50 daysMon 3/15/27 Fri 5/21/27 15 17 Environmental Studies 190 daysMon 3/15/27 Fri 12/3/27

18 Biology, plants, and wetlands - NES (seasonal) 120 daysMon 3/15/27 Fri 8/27/27 15 19 APE Map, research, site visit, and ASR 120 daysMon 3/15/27 Fri 8/27/27 15 20 Cultural Resources / Section 106 consult 40 daysMon 8/30/27Fri 10/22/27 19

21 Traffic Memo 30 daysMon 3/15/27 Fri 4/23/27 15 22 Water Quality Memo 30 daysMon 3/15/27 Fri 4/23/27 15

23 Air Quality 30 daysMon 3/15/27 Fri 4/23/27 15 24 Arborist - Tree Survey 15 daysMon 3/15/27 Fri 4/2/27 15

25 Complete studies and memos for NEPA CE 30 daysMon 10/25/27 Fri 12/3/27 20 26 Caltrans NEPA Document Review 60 daysMon 12/6/27 Fri 2/25/28 25 27 Revise and respond to comments 20 daysMon 2/28/28 Fri 3/24/28 26

28 Caltrans approves a Categorical Exclusion 30 daysMon 3/27/28 Fri 5/5/28 27 29 Prepare Admin. Draft MND 30 daysMon 12/6/27 Fri 1/14/28 25

30 Review and revise Admin. Draft MND 30 daysMon 1/17/28 Fri 2/25/28 29 31 Circulate the Mitigated Negative Declaration 30 daysMon 2/28/28 Fri 4/7/28 30 32 Prepare response to comments and Board Letter 30 daysMon 4/10/28 Fri 5/19/28 31

33 Board approves the MND and MMRP 30 daysMon 5/22/28 Fri 6/30/28 32 34 65% Plans, Specs, Estimate 80 daysMon 12/6/27 Fri 3/24/28 25

35 Agency Review 20 daysMon 3/27/28 Fri 4/21/28 34 36 Request authorization to proceed with ROW 20 days Mon 5/8/28 Fri 6/2/28 28

37 Right of Way Work 251 daysMon 4/24/28Mon 4/9/29 38 Plat maps, legal descriptions, deeds, etc. 30 daysMon 4/24/28 Fri 6/2/28 35 39 Caltrans reviews and sends the E-76 for ROW 40 days Mon 6/5/28 Fri 7/28/28 36

40 Appraisal, Easement Agreements and Offer 60 daysMon 7/31/28Fri 10/20/28 39 41 Negotiations and settlement 30 daysMon 10/23/28 Fri 12/1/28 40

42 Prepare and approve Board Letter 15 daysMon 12/4/28Fri 12/22/28 41 43 Board approves Easement Agreements 0 days Tue 1/9/29 Tue 1/9/29

44 Send any payments 20 days Tue 1/9/29 Mon 2/5/29 43 45 Complete Right-of-way Certification 15 days Tue 2/6/29Mon 2/26/29 44 46 Right-of-way Certification approval by Caltrans DLA 30 daysTue 2/27/29 Mon 4/9/29 45

47 Permitting 160 daysMon 4/24/28 Fri 12/1/28 34 48 CDFW Streambed Alteration Agreement 120 daysMon 4/24/28 Fri 10/6/28 35

49 Regional Water Quality Control Board 401 120 daysMon 4/24/28 Fri 10/6/28 35 50 US Army Corps of Engineerings 404 40 daysMon 10/9/28 Fri 12/1/28 49 51 Apply for ATP grant funding for final design 118 daysMon 1/5/26Wed 6/17/26

52 Grant award and execution 67 daysWed 11/18/26Thu 2/18/27 53 95% PS&E 40 daysMon 4/24/28 Fri 6/16/28 52,35

54 Agency Review 20 daysMon 6/19/28 Fri 7/14/28 53 55 Request authorization to proceed with construction 10 daysTue 4/10/29Mon 4/23/29 46

56 Caltrans reviews and sends the E-76 for CON 40 daysTue 4/24/29Mon 6/18/29 55 57 Final PS&E 20 daysMon 12/4/28Fri 12/29/28 50,54 58 Board letter with authorization to advertise 20 days Mon 1/1/29 Fri 1/26/29 57

59 Board authorization to advertise 0 days Tue 2/6/29 Tue 2/6/29 60 Put out to Bid - three week minimum 20 daysTue 6/19/29Mon 7/16/29 59,56

61 Open bids 0 daysMon 7/16/29Mon 7/16/29 60 62 Board Letter to award and NOITA 10 daysTue 7/17/29Mon 7/30/29 61

63 Notice of Intent to Award 0 daysMon 7/30/29Mon 7/30/29 62 64 CEO Analyst due date (without protest) 0 daysMon 7/30/29Mon 7/30/29 63 65 County Counsel due date 0 daysMon 7/30/29Mon 7/30/29 64

66 COTB publish deadline 0 daysMon 7/30/29Mon 7/30/29 65 67 Board Award 0 days Tue 8/7/29 Tue 8/7/29

68 Contract, bonds, insurance, Precon, NTP 20 days Tue 8/7/29 Mon 9/3/29 67 69 Notice to Proceed 0 daysMon 9/3/29 Mon 9/3/29 68 70 Submittals 30 days Tue 9/4/29Mon 10/15/29 69

71 SWRCB Construction Stormwater NOI 15 daysTue 10/16/29Mon 11/5/29 70 72 Construction 180 daysTue 11/6/29Mon 7/15/30 71

74 Bid Protest Process, if required 1330 daysWed 8/14/24Tue 9/18/29

75 Bidder protest due 6 daysTue 7/31/29 Tue 8/7/29 63 76 Response to any protest due date 15 days Wed 8/8/29Tue 8/28/29 75 77 Appeal period 5 daysWed 8/29/29 Tue 9/4/29 76

78 COTB notifies appellant of hearing date 10 days Wed 9/5/29Tue 9/18/29 77 79 Board Hearing of appeal 0 daysWed 8/14/24Wed 8/14/24

1/5

7/29

11/3

1/9

2/6

7/16

7/30

7/30

7/30

7/30

8/7

9/3

D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027 Half 1, 2028 Half 2, 2028 Half 1, 2029 Half 2, 2029

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Napa Valley Vine Trail - Vista Carneros Gap Closure Project Design Schedule

RDS 24-35 NVVT Vista Carneros Schedule 8.24.26.mpp Page 1

Project: RDS 15-22 Dry Creek Bridge Date: Mon 8/24/26