This is an Engineer's Estimate document for the Napa Valley Vine Trail - Vista Carneros Segment, prepared by Napa County Department of Public Works. The estimate represents a 35% engineering design phase for a four-mile multiuse path project intended to close a gap in the 47-mile Napa Valley Vine Trail between John F. Kennedy Park and the intersection of Devlin Road at Airport Boulevard. The project encompasses demolition, grading, paving, utility work, drainage improvements, retaining walls, signage, and environmental permitting across both City of Napa and unincorporated County areas. Construction is anticipated to begin in Spring 2029, with the selected consultant providing preliminary engineering, environmental assessment, right-of-way services, plans, specifications, estimates, and construction support services through project completion in a turnkey delivery model.
The total project base bid estimate is $6,432,573, with a 15% contingency of $806,422.50, bringing the overall project total to $6,182,572.50. The estimate is segmented into three cost scenarios: Option A (Cost within City of Napa Limits) at $526,925, Option B (Cost within City of Napa Limits) at $449,071, and Cost within County Limits at $5,905,648. Major cost components include earthwork ($300,000), asphalt concrete ($540,000), class 2 aggregate base ($600,000), retaining walls ($312,000), and storm drain/drainage systems ($250,000). The project requires compliance with Caltrans Local Assistance Procedures, and funding sources are not specified in this engineering estimate document.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAPA VALLEY VINE TRAIL - VISTA CARNEROS SEGMENT
ENGINEER'S ESTIMATE
35% Engineering Estimate - Vine Trail Vista Carneros
Updated 8/22/2024
Item
No. Item Description
Estimated
Quantity
Unit of
Measure Unit Cost Item Total (Option A and County)
Cost within City of Napa Limits
Option A
Cost within City of Napa Limits
Option B Cost within County Limits
1 Mobilization 1 L.S. 400,000.00$ 400,000.00$ 50,000.00$ 40,000.00$ 350,000.00$
2 Control of Work 1 L.S. 200,000.00$ 200,000.00$ 20,000.00$ 15,000.00$ 180,000.00$
3 Construction Staking 1 L.S. 100,000.00$ 100,000.00$ 10,000.00$ 10,000.00$ 90,000.00$
4 Dust Control 1 L.S. 25,000.00$ 25,000.00$ 2,500.00$ 2,500.00$ 22,500.00$
Clearing, Grubbing, Vine Removal and Landscape
Restoration 1 L.S. 200,000.00$ 200,000.00$
12,000.00$ 10,000.00$ 188,000.00$
6 Temporary Traffic Control 1 L.S. 100,000.00$ 100,000.00$ 100,000.00$
7 Water Pollution Control Program 1 L.S. 50,000.00$ 50,000.00$ 2,500.00$ 2,500.00$ 47,500.00$
8 Erosion Control 1 L.S. 100,000.00$ 100,000.00$ 10,000.00$ 8,500.00$ 90,000.00$
9 Tree Protection 1 L.S. 50,000.00$ 50,000.00$ 2,000.00$ 2,000.00$ 48,000.00$
Demolition -$
12 Cold Planing Asphalt Concrete Including Sawcut 1 L.S. 20,000.00$ 20,000.00$ 5,000.00$ 5,000.00$ 15,000.00$
13 Removal of Traffic Stripes and Pavement Markings 1 L.S. 10,000.00$ 10,000.00$ 10,000.00$
14 Remove and Dispose Concrete Curb, Gutter and Sidewalk 1000 S.F. 10.00$ 10,000.00$ 5,000.00$ 5,000.00$ 5,000.00$
14 Removal and Trim Tree Trimming 1 L.S. 200,000.00$ 200,000.00$ 1,000.00$ 1,000.00$ 199,000.00$
17 Remove and Dispose Fencing and Gates 1710 L.F. 15.00$ 25,650.00$ 25,650.00$
19 Miscellaneous Demolition and Relocation 1 L.S. 75,000.00$ 75,000.00$ 5,000.00$ 4,000.00$ 70,000.00$
Grading & Paving -$
20 Earthwork 10000 C.Y. 30.00$ 300,000.00$ 50,000.00$ 40,000.00$ 250,000.00$
21 Export Soil 7500 C.Y. 45.00$ 337,500.00$ 15,000.00$ 12,000.00$ 322,500.00$
22 Import Soil 2500 C.Y. 45.00$ 112,500.00$ 5,000.00$ 1,000.00$ 107,500.00$
23 PCC 6" Vertical Curb including Flush Curb and Curb Taper 150 L.F. 50.00$ 7,500.00$ 7,500.00$
24 PCC Curb and 24" Gutter 600 L.F. 45.00$ 27,000.00$ 27,000.00$
25 PCC 4" Sidewalk excluding Ramps 14750 S.F. 30.00$ 442,500.00$ 442,500.00$
26 PCC Curb Ramp including Retaining Curb 10 EA 10,000.00$ 100,000.00$ 100,000.00$
Class 2 Aggregate Base (for Curb, Gutter, Sidewalk, , Path and Shoulders) 6000 C.Y. 100.00$ 600,000.00$
105,000.00$ 95,000.00$ 495,000.00$
28 Drain Rock 150 C.Y. 150.00$ 22,500.00$ 22,500.00$
29 Asphalt Concrete (HMA) 2700 TONS 200.00$ 540,000.00$ 108,000.00$ 90,000.00$ 432,000.00$
30 8” Type A 1/2“ HMA Plug 10 TONS 200.00$ 2,000.00$ 1,000.00$ 1,000.00$
31 Utility Rims Raise/Lower 1 L.S. 50,000.00$ 50,000.00$ 50,000.00$
32 Utility Relocations (Utility Poles along Soscol Ferry) 1 L.S. 300,000.00$ 300,000.00$ 300,000.00$
33 4" Sidewalk Cross Drain 1 L.S. 5,000.00$ 5,000.00$ 5,000.00$
34 Rock Rip Rap 1 LS 20,000.00$ 20,000.00$ 1,500.00$ 1,500.00$ 18,500.00$
35 Adjust Irrigation Control Valve to Grade (Private) 5 EA 500.00$ 2,500.00$ 2,500.00$
36 PIV and RPBP Relocation (Private) 1 EA 3,000.00$ 3,000.00$ 3,000.00$
37 Hydrant Location 1 EA 5,000.00$ 5,000.00$ 5,000.00$
38 Storm Drain / Drainage 1 LS 250,000.00$ 250,000.00$ 15,000.00$ 13,000.00$ 235,000.00$
Other -$
38 Retaining Wall 3900 S.F. 80.00$ 312,000.00$ 312,000.00$
40 Trailhead Structure Foundation 1 EA 20,000.00$ 20,000.00$ 20,000.00$
41 Environmental Permitting / Mitigations 1 LS 250,000.00$ 250,000.00$ 20,000.00$ 20,000.00$ 230,000.00$
Signs and Markings -$
41 Relocate Street Sign, Utility Marker and Reflectors 1 LS 25,000.00$ 25,000.00$ 500.00$ 500.00$ 24,500.00$
42 Eco Counter (Install Only) 1 LS 5,000.00$ 5,000.00$ 5,000.00$
43 Mile Markers (Install Only) 13 EA 500.00$ 6,500.00$ 1,000.00$ 1,000.00$ 5,500.00$
44 Interpretive Sign (Install Only) 1 LS 5,000.00$ 5,000.00$ 5,000.00$
45 Trail Signs 1 LS 30,000.00$ 30,000.00$ 1,500.00$ 1,300.00$ 28,500.00$
46 Thermoplastic Pavement Stripes and Markings 1 LS 20,000.00$ 20,000.00$ 1,000.00$ 1,000.00$ 19,000.00$
47 Truncated Domes 1 LS 10,000.00$ 10,000.00$ 10,000.00$
5,376,150.00$ 449,500.00$ 381,800.00$ 4,926,650.00$
806,422.50$ 67,425.00$ 57,270.00$ 738,997.50$
6,182,572.50$ 516,925.00$ 439,070.00$ 5,665,647.50$
CON CE 250,000.00$ 10,000.00$ 10,001.00$ 240,000.00$
Total 6,432,573$ 526,925.00$ 449,071.00$ 5,905,648$
Sub-Total
Contingency = 15%