This is a Justification and Approval for Use of Exception to Fair Opportunity (J&A) issued by the Department of the Navy's Mid-Atlantic Regional Maintenance Center (MARMC) in Norfolk, Virginia.
The procurement authorizes the addition of non-competitive work under Firm Fixed Price (FFP) Delivery Order N5005426FL001 to East Coast Repair and Fabrication for critical repairs to the USS GUNSTON HALL (LSD-44). The specific work required is repair of a Balanced Joiner Door, identified as Request for Contract Changes (RCC) RCC 77N Work Item 624-11-001. The repairs include removal of the existing joiner door, repair to the ship's bulkhead where the door is mounted, and installation of a replacement door. The statutory authority cited is FAR 16.505(b)(2)(i)(A), permitting non-competitive procurement when urgency prevents fair opportunity without causing unacceptable delays. The J&A justifies the award to East Coast Repair based on the critical nature of the work, the requirement for immediate execution under the same Continuous Maintenance Availability (CMAV) schedule, and the contractor's unique capability and required equipment. The Contracting Officer determined costs are fair and reasonable based on historical data, an Independent Government Estimate (IGE), and the Project Manager's technical knowledge of estimated labor hours and material costs. The document was certified and approved by Lauren Heard, Contracting Officer (Code 426.2), with digital signature dated March 31, 2026.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J&A Number: N50054-26-056
NCH 53.6-2
5. RATIONALE JUSTIFYING USE OF CITED STATUTORY AUTHORITY
IAW FAR 16.505(b)(2)(i)(A) this procurement must be issued on a non-competitive basis due to the urgency of the required support which is under the same availability currently in execution and includes the same period of performance as the awarded delivery order period of performance. This additional work must be issued under a non-competitive basis because if the Government were to provide for fair opportunity, the entire schedule would be delayed by at least 30 days .
Although not discovered during initial work package development for the CMAV, normal door to properly open and close . Estimated time of repair work is approximately . Based on estimated start date and length of repairs, work item 624-11-001 is urgent and compelling to start earliest convenience. Repairs will consist of removal of the existing joiner door; repa meet operational commitments.
To award this work to a contractor other than East Coast Repair and Fabrication would result in unacceptable and costly delays to the USS GUNSTON HALL (LSD 44). The work must be integrated with the existing work package, the actual start date and production duration will be determined by the LMA during work integration analysis in order to support Key Event Work Complete (WC) and avoid delays and disruption to testing other systems in the base work package. Failure to accomplish this work would
East Coast Repair has required equipment and is the only company able to meet the
Government's immediate requirement to provide repair to the USS GUNSTON HALL (LHD 7) Joiner Door repairs in order for the USS GUNSTON HALL (LHD 7) to meet is commitments. To Award this East Coast Repair provides the Government the appropriate avenue to accomplish this repair within the allotted Period of Performance. These repairs are essential for the
. Without the repairs scheduled for the CMAV the joiner door repairs ,
6. DETERMINATION OF FAIR AND REASONABLE COSTS
The Contracting Officer has determined that the anticipated cost to the Government for the supplies/services covered by the J&A will be fair and reasonable. The estimated cost of this work item is based upon historical data as well as the Independent Government Estimate (IGE) and the
(PM) technical knowledge associated with the estimated man hours and material material burden rate were determined to be fair and reasonable at time of contract and delivery order award. The supported information provided should be sufficient to support the fair and reasonable