RBM 45753 SOW 25FEB25 FM-200.docx
DOCX document 26 KB Posted
- Attached to
- RBM 45753/45762 FM-200 recertification
- Solicitation number
- 52000PR250011456
About this file
This Statement of Work outlines FM-200 Kiddie System Testing and Certification requirements for Response Boat Medium (RBM) 45753/45762 at USCG Station Apra Harbor Naval Base Guam. The contractor must inspect and test the entire system, time delay device, engine shutdown interlock, and damper shutdown interlock, followed by securing the system, recording findings, and re-certifying. The work must be completed within twenty working days from scheduled haul out after contract award.
The associated solicitation (52000PR250011456) indicates the US Coast Guard Surface Forces Logistics Center intends to award a Firm Fixed Price Purchase Order using FAR 13 Simplified Acquisition Procedures. Quotes are due by March 3, 2025, at 9am Eastern and will be evaluated on technical requirements, deadlines, and lowest cost under a Best Value basis. Work will be performed at USCG Station Apra Harbor, Naval Base Guam, with MKC Paul Blas serving as the QA Evaluator. Payment terms are Net 30, with no down payments or advance payments permitted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 15-5693 WAGE RATES.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
USCG Station Apra Harbor Naval Base Guam Sumay Cove Santa Rita, GU 96915
1. GENERAL REQUIREMENTS:
· Response Boat Medium (RBM) 45753/45762 FM-200 Kiddie System Testing and Certification
2. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
Upon acceptance, the contractor shall commence work as soon as availability allows and work diligently to complete the entire work ready for use by twenty working days from scheduled haul out after contract award.
3. SCOPE OF WORK:
Response Boat Medium FM-200 Kiddie System Testing and Certification Contractor shall inspect and test the following:
· Entire system
· Time Delay device
· Engine shutdown interlock
· Damper shutdown interlock Upon completion of inspection and testing, contractor shall secure system, record, and re-certify and present findings to Coast Guard POC.
4. SITE VISIT:
To be determined upon contract being awarded.
5. DESIGNATED CONTRACTING OFFICER’S QA EVALUATOR (QAE)
REPRESENTATIVE:
MKC Paul Blas Email: paulandre.t.blas@uscg.mil Phone: 671-355-4820
6. CONDITIONS AFFECTING THE WORK:
Additional damage could be caused while performing work. Findings will be reported immediately before work continues via Condition found report (CFR) along with commercial quoting of necessary work to be completed outside the original scope of work.
7. AFTER AWARD OF THE CONTRACT:
The contractor must immediately notify the contracting officer’s QAE representative of his intended start date. The work shall be done in accordance with the specification.
8. ORAL MODIFICATION:
No oral statement of any person other than the contracting officer shall in any manner or degree, modifies or otherwise affect the terms of this contract.
9. WORKMANSHIP:
10. All work shall be accomplished with the best standard practices, and by workmen thoroughly experienced in the required trades. The work shall be supervised by experienced personnel and shall be satisfactory to the Contracting Officer.
11. PERMITS:
The contractor shall without additional expense to the government, obtain all appointments, licenses, and permits required for the prosecution of the work. The contractor shall comply with all applicable federal, state and local laws.
12. CLEAN UP:
All HAZWASTE, trash and debris shall be removed from the site and or recycled as applicable. The job site shall be left in a clean and neat manner.
13. UPON COMPLETION OF WORK:
Contact the Contracting Officer’s QAE Representative to arrange for inspection/acceptance of work.