PERFORMANCE WORK STATEMENT (PWS)
Army Cyber Command
Modular Trailer Office Work Space
Part 1
General Information
1. GENERAL: This is a non-personnel services contract to provide modular trailer office work space and associated maintenance services. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the
Contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction: The contractor shall ensure all work accomplished in accordance with this Performance Work Statement (PWS) meets all applicable Federal, State, and local laws, regulations, and directives to include, but not limited to, the publications in Section 6 and related documents. Provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to provide lease of modular trailer office work space; provide preventative and emergency maintenance as required, and tear down and removal of the modular trailer work space upon conclusion of the contract.
1.2 Background: The United States Army Corps of Engineers (USACE) allowed for the housing of Military and Department of the Army Civilian (DAC) personnel in a 10,752 square feet (16 Plex) modular building at Fort Gordon, Georgia. This was a result of preventing the displacement of workers for the U.S. Army Cyber Command
(ARCYBER) while the new Headquarters Military Construction (MILCON) project was being constructed. The builder BL Harbert responsible for the project leased office space for the construction project team as a part of their accommodation plan, however this commercial lease expired in June 2019. ARCYBER determined that this space was still needed to accommodate ARCYBER personnel currently occupying the space and could be further used for personnel transitioning to Fort Gordon whose security clearances were not fully adjudicated and could not enter the new headquarters until fully cleared. With no plan in place and upon notification of the preparation to remove the trailers, ARCYBER requested to continue usage at the same cost of the succeeding lease with the incumbent without full and open competition for continued occupancy at this leased location. ARCYBER subsequently followed up with follow-on contract award, with the latest contracts expiring in 2023. Currently this modular trailer office space is being occupied by 11th Cyber Battalion (formerly 915th Cyber Warfare Battalion (CWB)) and
ARCYBER personnel. A new MILCON project is being planned for a new facility to house these personnel but is currently scheduled for 2026 at the very earliest and could possibly be further delayed. Until the new facility is available there is no other space available on the installation to house the above personnel and therefore ARCYBER has a requirement to continue leasing this trailer modular office space.
1.3 Objectives: The Contractor shall provide modular office workspace and associated preventative and emergency maintenance services.
1.4 Scope: Provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to provide lease of modular trailer office workspace; provide preventative and emergency maintenance as required, and tear down and removal of the modular trailer workspace upon conclusion of the contract.
1.5 Period of Performance: The period of performance (PoP) shall be for one (1) Base
Year of 12 months and up to two (2) 12-month option years. The PoP is as follows:
Base Period 15 May 2023 – 14 May 2024
Option Period I 15 May 2024 – 14 May 2025
Option Period II 15 May 2025 – 14 May 2026
1.6 General Information
1.6.1 Quality Control: The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s Quality Control Plan (QCP) is the means by which he assures himself that his work complies with the requirement of the contract. The QCP is to be delivered five (5) business days before contract start. The
Contractor shall provide and maintain a QCP that is acceptable to the Contracting Officer
(KO). Changes to the Contractor’s QCP shall be submitted to the KO for review and approval within five (5) business days prior to implementation. The QCP shall be submitted to the KO and Contracting Officer Representative (COR) within five (5) working days when changes are made thereafter. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to his QC system.
1.6.2 Quality Assurance: The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.6.3 Recognized Holidays: The Contractor’s performance shall not be required on the
Federal public holidays listed below. Holidays occurring on weekends will be observed as directed by the Federal calendar (5 U.S.C. 6103).
New Year’s Day Labor Day
Martin Luther King Jr.’s Birthday Columbus Day
President’s Day Veteran’s Day
Memorial Day Thanksgiving Day
Independence Day Christmas Day
Juneteenth
1.6.4 Hours of Operation: The contractor is responsible for conducting business between the hours of 0700 – 1600 hours Monday thru Friday except Federal holidays or when the
Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the
Government facility is not closed for the above reasons. Providing service after regular hours does not authorize overtime.
1.6.5 Place of Performance: The work to be performed under this contract will be performed at the ARCYBER Trailers located at 1103 105th Ave, Fort Gordon, GA 30905.
1.6.6 Type of Contract: The government will award a Firm Fixed Price (FFP) contract.
1.6.7 Security Requirements: Access and General Protection/Security Policy and
Procedures. The Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency
Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (CFR clause 52.204-9, Personal Identity Verification of
Contract Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force
Protection Condition (FPCON) at any individual facility or installation change, the
Government may require changes in contractor security matters or processes.
1.6.7.1 Motor Vehicle Operators. Contractor’s personnel, whose tasks involve operation of any vehicles, shall possess a valid driver’s license, certificates, and permits applicable for the type and class of vehicle being operated. All vehicles used in the performance of this contract shall be maintained and operated in accordance with all State of Georgia and
Federal Highway Vehicle Safety Standards. Seatbelt use on Federal installations is mandatory. Use of cellular telephones while operating vehicles is prohibited on Fort
Gordon except with the use of a “hands free” device.
1.6.7.2 The contractor shall secure a required permit and tank certification for all liquid waste hauling vehicles in accordance with all current applicable Federal, State, and
Local laws, ordinances and regulations.
1.6.7.3 Contractor Vehicle Registration. The Contractor shall maintain valid vehicle registration and insurance on all Contractor-owned or operated vehicles and trailers operating on the installation. Evidence of vehicle ownership and vehicle liability insurance must be present with the vehicle at all times.
1.6.7.4 Contractor and all associated subcontractor employees shall comply with adjudication standards and procedures using the National Crime Information Center
Interstate Identification Index (NCIC-III) and Terrorist Screening Database (Army
Directive 2014-05/AR 190-13); applicable installation, facility and area commander installation and facility access and local security policies and procedures (provided by
Government representative); or, at OCONUS locations, in accordance with status-of-forces agreements and other theater regulations.
1.6.7.5 Physical Security. The Contractor shall safeguard all Government equipment, information, and property in the performance of the PWS.
1.6.8 iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the
COR. This training shall be completed within thirty (30) calendar days of contract award and within five (5) calendar days of new employees commencing performance with the results reported to the COR no later than thirty (30) calendar days after contract award.
1.6.8.1 AT Level I Awareness Training. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training within thirty (30) calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within five (5) calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil
1.6.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.
The contracting officer, Contracting Officers Representative (COR), and other
Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced.
Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.
1.6.10 Contracting Officer Representative (COR): The (COR) will be identified by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral http://jko.jten.mil/ communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the
Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.
1.6.11 Key Personnel: The Contractor shall provide a Program Manager who is responsible for the performance of the work. The Program Manager shall have full authority to act for the Contractor on all contract matters relating to daily operation of the contract. The name of the Program Manager shall be provided by the Contractor to the
KO. The Program Manager shall be available between 0700 - 1600 hours, Monday through Friday except Federal holidays or when the Government facility is closed for administrative reasons. The Program Manager and any individuals designated as key personnel shall be able to understand, speak, read, and write the English language.
1.6.12 Identification of Contractor Employees: Not applicable
1.6.13 Contractor Travel Not Applicable.
1.6.14 Other Direct Costs Not Applicable
1.6.15 Data Rights Not Applicable
1.6.16 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational
Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the
Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may effect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the
OCI.
1.6.17 PHASE IN /PHASE OUT PERIOD: Not Applicable.
1.6.18 Environmental Requirements.
1.6.18.1 Environmental Compliance. The Contractor shall comply with all Federal, State, local, and installation environmental laws, rules, plans, and policies. The
Contractor shall use and store all materials, chemicals, and equipment used in the performance of services on the installation IAW with industry standards, local, State and
Federal laws, and according to manufactures' recommendations. The Contractor shall be financially responsible for all fines and associated costs for hazardous waste management, transportation, and disposal of waste due to the Contractor's noncompliance.
1.6.18.2 Spill Plan. The Contractor shall notify the COR within one (1) hour, if the
Contractor spills or releases any hazardous substances, i.e., substances listed in
40 CFR 302, Designation, Reportable Quantities, and Notification. The Contractor shall submit a Spill Plan to the KO for approval within thirty (30) days of contract award IAW
Spill Prevention Control and Countermeasure Plan.
1.6.18.3 Damage Caused by Contractor. Damages caused by Contractor employees shall be repaired at no cost to the Government. The Contractor shall notify the COR and return the damaged area to its previous condition. The Contractor shall furnish all labor, materials, and equipment to perform the repair work including cultivating and applying seed, sprigging, or placing sod. The Contractor shall maintain all turf repair work to ensure successful growth.
1.6.18.4 Maintenance. The contractor shall provide maintenance services under this contract that shall include, but are not limited to building envelope (every part of the structure that makes it waterproof), everything inside to include wall structures, roofing, flooring, and ceiling repairs, plumbing, electrical, HVAC maintenance repairs, doors, windows and any repairs caused by water penetration into the building.
Emergency maintenance will also be provided when necessary and/or whenever the trailers becomes inoperable unexpectedly.
PART 2
DEFINITIONS & ACRONYMS
2. DEFINITIONS AND ACRONYMS:
2.1 DEFINITIONS: See below.
2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.
2.1.2 CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the
U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations.
This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5 DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key
Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9 QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor.
The Government does not have privity of contract with the subcontractor.
2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.12 WORK WEEK. Monday through Friday, unless specified otherwise.
2.2. ACRONYMS:
ACOR Alternate Contracting Officer's Representative
AFARS Army Federal Acquisition Regulation Supplement
AR Army Regulation
CCE Contracting Center of Excellence
CFR Code of Federal Regulations
CONUS Continental United States (excludes Alaska and Hawaii)
COR Contracting Officer Representative
COTR Contracting Officer's Technical Representative
COTS Commercial-Off-the-Shelf
DA Department of the Army
DD250 Department of Defense Form 250 (Receiving Report)
DD254 Department of Defense Contract Security Requirement List
DFARS Defense Federal Acquisition Regulation Supplement
DMDC Defense Manpower Data Center
DOD Department of Defense
FAR Federal Acquisition Regulation
HIPAA Health Insurance Portability and Accountability Act of 1996
KO Contracting Officer
OCI Organizational Conflict of Interest
OCONUS Outside Continental United States (includes Alaska and Hawaii)
ODC Other Direct Costs
PIPO Phase In/Phase Out
POC Point of Contact
PRS Performance Requirements Summary
PWS Performance Work Statement
QA Quality Assurance
QAP Quality Assurance Program
QASP Quality Assurance Surveillance Plan
QC Quality Control
QCP Quality Control Program
TE Technical Exhibit
PART 3
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
3. GOVERNMENT FURNISHED ITEMS AND SERVICES:
3.1. Services: Not Applicable.
3.2 Facilities: Not Applicable.
3.3 Utilities: Not Applicable.
3.4 Equipment: Not Applicable.
3.5 Materials: Not Applicable.
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this
PWS.
4.2 Secret Facility Clearance: Not Applicable.
4.3. Materials: The Contractor shall provide all materials and servicing equipment to meet the requirements under this PWS.
4.4. Equipment: The Contractor shall provide the necessary equipment required to perform the tasks associated with the requirements of this PWS.
PART 5
SPECIFIC TASKS
5. Specific Tasks:
5.1 Basic Services. The contractor shall provide services for continued lease of modular trailer office work space and associated maintenance as required.
5.2 Maintenance services shall include, but are not limited to building envelope (every part of the structure that makes it waterproof), everything inside to include wall structures, roofing, flooring, and ceiling repairs, plumbing, electrical, HVAC maintenance repairs, doors, windows and any repairs caused by water penetration into the building.
5.3 Contractor shall provide at least two keys for all trailer door locks.
5.4 Emergency maintenance will also be provided when necessary and/or whenever the trailer(s) become(s) partially inoperable unexpectedly. The Contractor shall dispatch maintenance personnel within two hours of notification for emergency maintenance issues.
5.5 Upon completion of the contract, the Contractor shall tear down and remove the modular trailer work space and any associated equipment/materials from the site.
5.6. Service Contract Reporting:
5.6.1 System for Award Management (SAM) Service Contract Report (SCR): The
Contractor shall report ALL Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The Contractor is required to completely fill in all required data fields through the following web address: www.sam.gov. Reporting inputs will be for the labor executed during the period of performance during each Government FY, which runs from
October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk by clicking “View Assistance for SAM.gov” which is located at the top of the SAM.gov website. From there, you can the select “Contact Our
Service Desk” which will allow you to contact SAM.gov directly. If contract period of performance ends prior to September 30, the Contractor has 30 calendar days from end date of the contract to complete the SAM SCR requirement.
Steps for Submitting a Service Contract Report (SCR)
1. Go to www.sam.gov and log in.
2. Select Entity Registrations and then select Service Contract Reporting.
3. SAM displays your entities which have service contracts and meet the reporting criteria. Select View by entity to see the service contracts for each entity.
http://www.sam.gov/ http://www.sam.gov/
4. Next, select Add for the service contract against which you want to create a
Service Contract Report. Each service contract which meets the FAR Subpart
4.1703 reporting thresholds is displayed.
5. You will be taken to the Complete Service Contract Report page. SAM displays the contract details and allows you to report. You are required to enter the following information:
• Total Amount Invoiced: Total dollar amount invoiced for services performed during the previous Government fiscal year under the contract (this amount should include the prime and any subcontract amount).
• Prime Contractor Hours Expended: Prime contractor direct labor hours expended on the services performed during the previous Government fiscal year. The amount you enter is automatically divided by 2,080 hours to calculate a Full Time Employee (FTE) equivalent, displayed under the Prime
Contractor Hours Expended as Prime Contractor FTEs.
6. Report any required Tier 1 subcontractor information by selecting the Add Tier 1
Subcontract Information button.
7. When you are ready to submit the report, select Submit. This saves your report and returns you to the Select Service Contract page where you can create other
SCRs or edit an existing SCR.
Steps for Editing a Submitted Report
1. Follow steps 1-4 above. Any previously submitted SCR will have a View/Edit button instead of an Add button.
2. Select View/Edit. You will be able to view the current SCR, edit available fields, and resubmit the record. You can also delete previously entered information altogether.
STD: All information provided by the Contractor shall be accurate, complete, and not exceed suspense dates noted in corresponding paragraph above.
AQL: 100% Compliant
PART 6
APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.
ACC PAM 70-1 Interim Army Contracting Command – Contracting Officer’s
Representative Policy Guide
ANSI Z4.3-2016 Sanitation – Non-sewered Waste-Disposal Systems –
Minimum Requirements
ANSI Z87.1-2003 Practice for Occupational and Educational Personal Eye and Face
Protection Devices
ANSI/ASQC-Z1.4 National American Standard
ANSI Z245.1 Mobile Refuse Collection and Compaction Equipment – Safety
Requirements
AR 11-27 Army Energy Program
AR 70-13 Management and Oversight of Service Acquisitions
AR 190-5 Motor Vehicles Traffic Supervision
AR 200-1 Environmental Protection and Enhancement
AR 200-5 Pest Management
AR 385-10 Army Safety Program
AR 385-40 Army Accident Investigation and Reporting
AR 420-90 Fire Emergency Services
AR 530-1 Operations Security
29 CFR Part 1910 Occupational Safety and Health Standards
40 CFR Protection of the Environment
40 CFR Subchapter I Solid Wastes
40 CFR 257 Criteria for Classification of Solid Waste Disposal Facilities and Practices
40 CFR Part 302 Protection of Environment, Designation, Reportable Quantities and
Notification
49 CFR 571 Federal Motor Vehicle Safety Standards
Clean Air Act (CAA)
Clean Water Act (CWA)
Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA)
DA PAM 385-40 Army Accident Investigations and Reporting
DoD 4160.21-M Defense Materiel Disposition Manual
DoD Directive 5500.7-R Joint Ethics Regulation
DoDI 4150.07 DoD Pest Management Program
DoDI 5000.72 DoD Standard for Contracting Officer’s Representative (COR)
Certification
EM-385-1-1 Safety and Health Requirements Manual
EO 13423 Strengthening Federal Environmental, Energy, and Transportation
Management
Federal Standard #313 Material Safety Data and Disposal Data for Hazardous
Materials Furnished to Government Activities
FIPS PUB 201-2 Personal Identity Verification (PIV) of Federal Employees and
Contractors
TM 5-634 Solid Waste Management
UFC 3-240-01 Wastewater Collection, with Change 1 11-01-2012
UFC 3-240-03N Wastewater Treatment System Augmenting Handbook
Operation and Maintenance 01-16-2004
42 U.S.C. 6901 Resource Conservation and Recovery Act (RCRA), Solid
Waste Disposal
PART 7
ATTACHMENT/TECHNICAL EXHIBIT LISTING
7. Attachment/Technical Exhibit List:
7.1. Attachment 1/Technical Exhibit 1 – Performance Requirements Summary
7.2. Attachment 2/Technical Exhibit 2 – Deliverables Schedule
TECHNICAL EXHIBIT 1
Performance Requirements Summary
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective
(The Service required—usually a shall statement)
Standard Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)
Method of Surveillance
PRS # 1.
Contractor shall ensure all work accomplished meets all applicable Federal, State, and local laws, regulations and directives to include, but not limited to applicable publications in Part 6 of this PWS.
The Contractor shall provide services IAW
PWS, part 5
2% Deviation from performance Standard; % calculated by dividing the number of defects by the number of observations.
Random Sampling and Customer
Complaints;
Inspections and complaint validations performed by the
COR.
PRS # 2
The Contractor shall develop and maintain a Quality Control Plan approved by the KO.
The Contractor shall provide a QCP IAW
PWS, para, 1.6.1.
Zero Deviation from performance standard.
Review and acceptance by the by the KO on submission of QCP and each revised
QCP.
PRS # 3
Upon completion of the contract, the contractor shall tear down and remove the modular trailer work space and any associated equipment/materials from the site.
The Contractor shall perform IAW PWS, para, 5.4. Zero Deviation from performance standard.
Physical survey of the site by the COR.
TECHNICAL EXHIBIT 2
DELIVERABLES SCHEDULE
Deliverable Frequency # of Copies Medium/Format Submit To
A001
(PWS, para 1.6.1.)
Contractor Quality
Control Plan
Due 5 days after award of contract
1 Electronic
Copy Adobe PDF KO and COR
A002
(PWS para 1.6.8) iWATCH and AT Level I
Awareness
Training, Due 30 days after award of contract or hiring of new employees
1 Electronic
Copy Adobe PDF COR
A003
(PWS, para. 1.6.11)
Key Personnel List
Due 5 days after award of contract
1 Electronic
Copy Adobe PDF
KO and COR.
Provide email and telephone number
A004
(PWS, para. 5.3)
Contractor to provide at least two keys for all trailer door locks
Due 5 days after award of contract 2 keys per lock
N/A COR