This document is a Statement of Objectives for fall protection equipment required at RAF Fairford. The key requirements include a 3M jib system, portable counterweight base, castors, self-retracting lifeline, safety harness, and associated delivery, installation, and user instruction and certification. The equipment must be delivered and installed within 90 days of contract award. The contractor is responsible for providing all required materials such as concrete. The equipment must be tested and functionality demonstrated on-site. Operation and maintenance manuals are to be provided. The requirement is for the Department of the Air Force United States Air Forces in Europe - Air Forces Africa, as part of Solicitation FA557024Q0007 for Fall Protection Equipment at RAF Fairford.

View the file

Other files for this federal contract opportunity

Other files attached to Fall Protection Equipment - RAF Fairford, newest first.
File Type Posted
RFQ - RAFF Fall Protection Equipment.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RAF Fairford Fall Protection Equipment - Statement of Objectives

Line Items:

CLIN
Description
Quantity
Unit of Measure
0001
3M Jib System code 8530877
1
Each
0002
3M Flexguard Portable Counterweight Base without concrete code 8530869
1
Each
0003
3M Smooth Surface Castor kit code 8530908
1
Each
0004
DBI Sala Ultra-Lok Self Retracting Lifeline - 15Mtr Galv Cable- RSQ Model
1
Each
0005
3M DBI-SALA ExoFi XE100 Comfort Safety Harness With Quick-connect Buckles
1
Each
0006
Commercial Delivery
1
Each
0007
Installation
1
Lot
0008
System User Instruction and Certification (up to 8 individuals)
1
Each

Project:

1. Commercial Shipping to: RAF Fairford, Fairford, Gloucestershire, GL7 4DL.

1. To deliver modular jib System as supplied from 3M as manufacturer.

1. Assembly on site by trained operatives, to include all required equipment.

1. 3M to be on site during assembly and training.

1. Materials required for installation, including concrete, to be supplied by contractor.

1. Product to be tested for function on site, to include possible site requirements.

1. General usage and equipment to be demonstrated on site. Price must include: ‘System User Instruction and Certification’ for up to 8 people (operators), to include basic height safety within 10 days of installation completion.

1. Operation and maintenance manuals to be supplied in either electronic or hard copy.

1. Commercial Shipping to: RAF Fairford, Fairford, Gloucestershire, GL7 4DL.

Delivery Schedule: 90 days after receipt of order.