Radome Requirements Document.pdf

PDF 117 KB Posted

Attached to
Radomes 3 (ea. ) Manufacture and Delivery to Ft. Carson, CO 80913 (1SP BDE)
Solicitation number
W9126024R0002
Issued by

About this file

This document is a Radome Requirements Document that outlines the specifications for three (3) radomes required under the Radomes 3 (ea.) Manufacture and Delivery to Ft. Carson, CO 80913 (1SP BDE) solicitation (Solicitation Number: W9126024R0002).

The radomes must be constructed using RF transparent, fire-retardant materials and be sized to adequately house a trailer-mounted antenna with a minimum height of 250 inches. Key requirements include a riser wall, personnel and trailer access vestibule, fall arrest points, and an APEX maintenance point. The completed radomes must be delivered crated and prepared for safe transport and overseas shipment to Ft. Carson, Colorado. The solicitation is being issued by the Department of the Army Materiel Command Contracting Command at Redstone Arsenal.

View the file

Other files

File Type Posted
Radomes Q_A.pdf PDF
W9126024R0002_Radomes.pdf PDF
RADOME SKETCH.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item # Description Manufacturer Model/Part # QTY Unit of Issue Ship-to-Address

1 Suitable sized Radome constructed with RF Transparent material (installed with riser wall, personnel and trailer access vestibule, fall arrest points, and APEX maintenance point).

TBD TBD 3 Each

1.a.

Radome size to be contractor designed and defined to adequately house trailer mounted antenna with deployed dimensions shown in the outline drawing attachment. (250 inch height minimum)

TBD TBD 3 Each

1.b. Radome construction shall be of fire retardant materials (per ASTM D6413‐99 and ASTM E84‐18).

TBD TBD 3 Each

1.c. Radome material shall have <2.0 dB transmit loss at UHF through Ka‐bands (0.3 to 40 GHz). TBD TBD 3 Each

1.d. Radome structure must have wind rating of at least 60 mph sustained and gusting to 90 mph.

TBD TBD 3 Each

1.e. Radome material shall have an operational temperature range of ‐30° C through +50° C. TBD TBD 3 Each

1.f. Radome structure shall be capable of Solar load of 300 BTUs per square foot. TBD TBD 3 Each

1.g. Radome structure shall be capable of Ice and snow load of at least 10 pounds per square foot.

TBD TBD 3 Each

1.h Radome structure shall provide a fixed input and exhaust port suitable for contractor provided HVAC unit flexible duct.

TBD TBD 3 Each

Radome structure shall provide a personnel and trailer access vestibule with minimum of 12'h X 12'w X 5'd. The vestibule shall be located on the North side of the Radome and does not need to be RF transparent.

TBD TBD 3 Each

2.a. The vestibule shall provide 1 roll‐up type stowed trailer access door of a minimum 11' X 11' on front face of vestibule.

TBD TBD 3 Each

2.b. The vestibule shall provide 1 personnel access door of a minimum 36" X 80" located on one side of vestibule.

TBD TBD 3 Each

2.c. The vestibule shall provide 1 cable access run/port at ground level of approximately 24" wide and 8" tall.

TBD TBD 3 Each

3 The contractor shall provide a minimum of four (4) Spare Panels ‐ For the RF Transparent Radome structure.

TBD TBD 3 Each

4 The contractor shall provide FAA/ICAO Low Intensity Obstruction Warning Light ‐ LED (NVG/NVIS: Compatible).

TBD TBD 3 Each

5 The contractor shall provide a Lightning Protection System ‐ with a Single air terminal, 36" minimum.

TBD TBD 3 Each

6 The contractor shall provide an LED Interior Lighting System. TBD TBD 3 Each

7 The contractor shall provide an HVAC Unit (skid‐mounted w/flexible ducting from HVAC) operating range 0° to 40°C.

TBD TBD 3 Each

8 The contractor shall provide the Instruction Manual for Installation and Deinstallation of the radome.

TBD TBD 3 Each

9 The contractor shall provide the Operation and Maintenance Manual for the radome. TBD TBD 3 Each

Requirements Document

Organization: 1st Space Brigade

1st Space Brigade S‐4 6410 Magrath Ave Bldg 1959

Fort Carson CO 80913

Radome Requirements Document

10 The contractor shall provide the Operation and Maintenance Manual for the HVAC unit. TBD TBD 3 Each

11 The contractor shall provide a list for a Basic Tool kit for operator repairs. TBD TBD 3 Each

12 The contractor shall provide a mounting point and standard 5 lb, Type C fire extinguisher for use inside the radome.

TBD TBD 3 Each

13 The radome shall include a mounting point for; and standard battery powered smoke detector.

TBD TBD 3 Each

14 Total cost/bid of the radome must include shipping. TBD TBD 3 Each

15 The contractor shall ensure radomes are packed in manner for onward overseas shipment (i.e. skidded, crated, boxed, and be able to be easily handed with MHE).

TBD TBD 3 Each

Radome Requirements Document