Quote Tabulations.Bond Road.2025.pdf

PDF 84 KB Posted

Attached to
Hillsboro Shelter Operator
Solicitation number
S-C03342-00013410
Issued by
Washington County, Oregon

About this file

This is a Quote Tabulations document for the Bond Road Level & Overlay Work project managed by the Linn County Road Department in Oregon. The project involves pavement rehabilitation work on Bond Road, with a pre-bid meeting scheduled for Wednesday, April 9th at 1:00 P.M. PDT. The scope of work includes four primary pay items: Mobilization (1 lump sum), Temporary Traffic Control (1 lump sum), Driveway Paving (4 units), and HMAC or WMAC asphalt overlay (699 tons). Eight contractors submitted quotes for this project: KNL Industries, Inc., Settje Sons Paving, Wildish, Double Eagle Paving, O.A.M., North Santiam Paving, Knife River, and RiverBend Materials.

Bid pricing ranges significantly across the eight submitted quotations, with total project costs spanning from $78,798.00 to $129,840.00. The mobilization costs vary from $0.00 to $7,228.00, temporary traffic control ranges from $0.00 to $12,000.00, driveway paving unit rates span $500.00 to $1,500.00 per unit, and asphalt material costs range from $97.91 to $160.00 per ton. Three of the eight bidders submitted incomplete quotes with zero values across all line items. The variation in pricing reflects different contractor cost structures, material sourcing, and project execution approaches, with the lowest complete bid totaling $78,798.00 and the highest at $129,840.00.

View the file

Other files

File Type Posted
Hillsboro Shelter Request for Proposal.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M2503

Pay Items Quantity Units Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost

Mobilization 1 LS $3,000.00 $3,000.00 $4,797.80 $4,797.80 $4,000.00 $4,000.00 $5,000.00 $5,000.00

Temporary Traffic Control 1 LS $2,100.00 $2,100.00 $5,259.85 $5,259.85 $4,000.00 $4,000.00 $6,500.00 $6,500.00

Driveway Paving 4 Each $600.00 $2,400.00 $796.94 $3,187.76 $850.00 $3,400.00 $1,500.00 $6,000.00

HMAC or WMAC 699 Tons $102.00 $71,298.00 $97.91 $68,439.09 $107.50 $75,142.50 $100.00 $69,900.00

TOTALS: $78,798.00 $81,684.50 $86,542.50 $87,400.00

Pay Items Quantity Units Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost

Mobilization 1 LS $6,600.00 $6,600.00 $3,200.00 $3,200.00 $7,228.00 $7,228.00 $3,000.00 $3,000.00

Temporary Traffic Control 1 LS $6,100.00 $6,100.00 $5,141.00 $5,141.00 $6,075.00 $6,075.00 $12,000.00 $12,000.00

Driveway Paving 4 Each $500.00 $2,000.00 $746.00 $2,984.00 $1,200.00 $4,800.00 $750.00 $3,000.00

HMAC or WMAC 699 Tons $110.00 $76,890.00 $119.52 $83,544.48 $130.98 $91,555.02 $160.00 $111,840.00

TOTALS: $91,590.00 $94,869.48 $109,658.02 $129,840.00

Pay Items Quantity Units Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost Unit Rate Total Cost

Mobilization 1 LS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $5,500.00 $5,500.00

Temporary Traffic Control 1 LS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $3,250.00 $3,250.00

Driveway Paving 4 Each $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $800.00 $3,200.00

HMAC or WMAC 699 Tons $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $119.00 $83,181.00

TOTALS: $0.00 $0.00 $0.00 $95,131.00

KNL Industries, Inc.

Settje Sons Paving

LCRD Estimate

Pre-Level & Overlay Work

Bond Road

Wednesday, April 9th 1:00 P.M. PDT

Linn County Road Department

Wildish Double Eagle Paving O.A.M.

North Santiam Paving Knife River RiverBend Materials

File details come from the government source that posted it. Updated .