Questions-Answers_20-R-000023_(08-04-20).pdf
PDF 140 KB Posted
- Solicitation number
- 693JJ920R000023
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 693JJ9-20-R-000023_(08-04-20).pdf | ||
| Attachment J.2 - Past Performance Questionnaire.docx | DOCX document | |
| Attachment J.8 - NHTSA Order 700-5.pdf | ||
| Attachment J.3 - Subcontrator Checklist.docx | DOCX document | |
| Attachment J.6.rev - Cost Proposal Template (OCD-Travel).xlsx | XLSX spreadsheet | |
| Attachment J.1 - Question Submittal Form.docx | DOCX document | |
| Attachment J.7 - Standard Form LLL, Disclosure of Lobbying Activities.pdf | ||
| Attachment J.4 - Responsibility Questionnaire.docx | DOCX document | |
| Attachment J.5 - Small Business Subcontracting Plan.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposal: 693JJ920R000023 Questions/Answers
Experimental and Mathematical Biomechanics Injury Research 08/04/2020
Question 1 Section/Part #: Section L.6 Section Title: Proposal Format (Volume I: Technical Proposal Instructions) Paragraph #: 3
This section states a page limit for the technical proposal of “10 pages plus the number of pages per Domain sought.” If an Offeror proposes for only Domain 1, they have 20 pages total for that Domain. If Domain 1 and 2 are to be considered, the Offeror will have 30 pages total, or 15 pages per Domain. Proposing for the first three Domains allows for 40 pages total, or approximately 13 pages per Domain. This seems to put Offerors proposing more Domains at a disadvantage. Would NHTSA consider allowing more pages based on the total number of Domains for which an offeror is proposing?
• Answer: No. The number of allowable pages for each Domain was chosen based on the estimated space needed to provide the information requested in Section L.7. Effective proposals will eliminate duplication where possible, as there is likely to be significant overlap in staffing, facilities, and past performance across Domains.
Question 2 Section/Part #: Section F. 2 Section Title: Period of Performance Paragraph #:
Does the Agency have an anticipated start date for the Contract?
• Answer: It is the intent of the Agency to begin the period of performance at the time of award, prior to September 30, 2020.
Question 3 Section/Part #: Section L.8 Section Title: Cost/Price Proposal Instructions Paragraph #: L.8.1
Can there be more than one Project Manager? As in can there be a Project Manager and Co- Project Manager?
• Answer: As the Project Manager serves as the liaison with NHTSA, a single Project Manager is preferable.
Request for Proposal: 693JJ920R000023 Questions/Answers
Experimental and Mathematical Biomechanics Injury Research 08/04/2020
Question 4 Section/Part #: General Section Title:
Paragraph #:
Are NHTSA contacts able to submit the past-performance questionnaires?
• Answer: Yes.