This is a Q&A document containing 19 questions and answers for DOE FOA DE-0002967 regarding High-Assay Low-Enriched Uranium (HALEU) Transportation Package development. The document clarifies key aspects of the funding opportunity, including that applicants may submit up to one application per topic area (maximum two total applications), foreign companies must obtain waivers for participation, and the application deadline has been extended to January 31, 2025.

Notable clarifications include: protected data periods can be extended up to 30 years for commercialization purposes; awardees will retain all NRC certifications and licenses; DOE aims to support industry efforts to develop more efficient HALEU transportation packages rather than compete with private industry; various uranium forms (including TRISO fuels, U-AL, U-Si, U-Mo) can be included in proposals; initial batch production can be included within prototyping activities; and both SF-424 and Research and Related Budget forms are required from prime applicants and subrecipients. The Project Management Plan (PMP) should be used as the reference document for various application components including WBS, task descriptions, and milestone summaries.

questions and answers for NOFO # DE-FOA-0002967 (Revised January 6, 2025)

View the file

Other files

File Type Posted
Attachments- HALEU Transportation Package NOFO.pdf PDF
Questions and Answers for FOA # DE-NE0002967 (revised as of 3 February 2025).pdf PDF
NOFO Part 1 -HALEU Transportation NOFO DE-FOA-0002967_005.pdf PDF
NOFO Part 2 DE-FOA-0002967 HALEU Transportation _005 - 3 February 2025.pdf PDF
SF-424 Application for Federal Assistance.pdf PDF
NOFO Part 1 -HALEU Transportation NOFO DE-FOA-0002967_004.pdf PDF
Questions and Answers for FOA # DE-NE0002967 (revised as of 27 January 2025).pdf PDF
Attachments- HALEU Transportation Package NOFO.pdf PDF
NOFO Part 2 DE-FOA-0002967 HALEU Transportation _004 - 27 January 2025.pdf PDF
Questions and Answers for FOA # DE-NE0002967 (revised as of 21 January 2025).pdf PDF
Questions and Answers for FOA # DE-NE0002967 (revised as of 15 January 2025).pdf PDF
NOFO Part 1 -HALEU Transportation NOFO DE-FOA-0002967_003.pdf PDF
NOFO Part 1 -HALEU Transportation NOFO DE-FOA-0002967_003.pdf PDF
Questions and Answers for FOA # DE-NE0002967 (revised as of 14 January 2025).pdf PDF
NOFO Part 2 DE-FOA-0002967 HALEU Transportation _002 - 14 January 2025.pdf PDF
Questions and Answers for FOA # DE-NE0002967 (revised 30 December 2024).pdf PDF
Questions and Answers for FOA # DE-NE0002967 (19 December 2024).pdf PDF
NOFO Part 1 -HALEU Transportation NOFO DE-FOA-0002967_002.pdf PDF
Questions and Answers for FOA # DE-NE0002967 (11 December 2024).pdf PDF
NOFO Part 1 -HALEU Transportation NOFO DE-FOA-0002967_001.pdf PDF
Questions and Answers for FOA # DE-NE0002967.pdf PDF
NOFO Part 2 -HALEU Transportation NOFO.pdf PDF
Attachments- HALEU Transportation Package NOFO.pdf PDF
FundOpp_DE-FOA-0002967.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for DE-FOA 0002967 Date

Question received

Date Answer Posted

Question Answer

11/25/2024 12/02/2024

Question #1

Are proposals limited to four under Topic 1 (up to one each for oxide, metal, UF6, and combination) and four under Topic 2 (up to one each for oxide, metal, UF6, and combination), for a total of up to eight proposals per organization

Applicants may submit up to one application for each topic area.

Applicants may submit one application for Topic Area 1 and one application in Topic Area 2 for a combined maximum of two applications. See NOFO Part 1 Section II.B. (Pages 10-11) for more information.

12/02/2024 12/11/2024 (Answer Revised)

Question #2

Are foreign companies eligible to apply as either prime applicants or sub-recipients?

With regards to foreign companies applying, Prime and Sub-Recipients refer to NOFO part 1 pages 9-10, and NOFO part 2 page 18 for instructions regarding foreign companies applying and how to request a waiver for a foreign company’s participation, if needed.

Applicants can submit to DOE waivers for foreign entity participation at any time before the application due date, or wait and submit the waiver with the application.

12/06/2024 12/11/2024

Question # 3

Under the special statutory authority can the “Protected Data” generated under this NOFO be protected for longer than five years, i.e. 50 years?

Under Topic Area 2, the Offeror is extending previously owned and licensed technical information for modification to meet the DOE requirements for HALEU transportation packages. However, the market for the final product is not expected to be realized for 10-15 years making the 5-year protection moot. Publication of the modifications to existing package technical data will provide access to protected data and

Selectees and recipients may request an extended period of protection (more than 5 years and not to exceed 30 years) if reasonably required for commercialization for specific categories of data first produced under the resulting awards. DOE does not have unlimited rights in data that is not generated under the award, such as data owned by the applicant or produced outside of the award.

The period of protection can be addressed during the negotiation process after award selections are made.

Intellectual Property while eliminating protections for years prior to market need for the product. This will violate IP protections inherent in privately funding research and development and for-profit investment.

12/06/2024 12/11/2024

Question # 4

Will the awardee retain all licenses and NRC certifications in perpetuity for all products resulting from the NOFO award or is the intent for DOE to be the NRC certificate license holder of the newly developed or modified packages?

Awardee will retain all NRC certifications and/or licenses as a result of this NOFO.

12/06/2024 12/11/2024

Question # 5

Many commercial organizations focused on serving the nuclear material transport market have invested time and funding to create special purpose packages that can be licensed to transport HALEU and other sensitive materials to meet the emerging market demand. Is the intent of the DOE NOFO to supersede those efforts through the development of competing technologies and compete with private industry?

No. DOE is working to support industry efforts to develop additional new or updated transportation packages to support the transportation of large quantities of HALEU. DOE seeks more efficient and cost-effective transportation packages for shipping large quantities of HALEU, while maintaining high safety standards.

12/06/2024 12/11/2024

Question # 6

Many Uranium forms and finished materials including uranium salts, TRISO fuels, U-AL, U-Si, U-Mo, are omitted from the NOFO. Are these forms to be included in the development of a new package for this grant opportunity or will this be a focus of a future funding opportunity?

Is there an isotopic characterization range that should be the basis for the design of new or modified packages?

Yes, the listed Uranium forms can be included as a new package for this NOFO as long the proposals meet the objectives and requirements set forth in the NOFO. Any isotope characterization range that can meet the objectives/requirements of the NOFO and pass the NRC criticality criteria will be considered.

12/06/2024 12/11/2024

Question # 7

For the oxide and metal packages, can additional information on material forms the transport package must support be provided, (i.e. powder, metal ingots, spherical TRISO pebbles, etc.) with dimensional data and how much in terms of overall uranium weight is needed to be shipped (either on a per transport or per campaign basis)? Should the design include accommodation of multiple configurations at fuel fabrication facilities?

DOE aims to provide flexibility rather than limitations. The proposal, depending on the type of fuel or combination being pursued, can support multiple configuration or size. The ultimate goal is to maximize large HALEU shipping quantities while maintaining high safety standards.

12/06/2024 12/11/2024

Question # 8

What operational criteria will be considered in the evaluation criteria?

Are transport viability and cost included in the evaluation criteria?

Applications will be evaluated against the technical review criteria included in the NOFO.

12/06/2024

12/11/2024

Question # 9

Can the NOFO application due date be extended to 31 January 2025

Yes, the NOFO application due date has been extended to 31 January 2025. The revised NOFO document reflects this new date.

12/18/2024

12/19/2024

Question #10

Will a foreign entity waiver be required for a subrecipient if the prime grant holder is a FOCI mitigated entity?

Yes, a Foreign Entity Waiver is still required for each proposed foreign subrecipient if the prime grant holder is a FOCI mitigated entity.

Also, ensure that the document Transparency of Foreign Connections is also included in the application.

12/18/2024

Question #11

Please confirm that the R&D Community Benefits template is the proper template to use for this grant

Yes, the R&D Community Benefits Plan template is the template to use for the HALEU Transportation

NOFO.

Question #12

NOFO Part 1 Section 3. In the Required Application Documents list, The Application for Federal Assistance, SF-424 is listed as required. This document appears to be the same document as the Research and Related Budget – Section A-B Form, also listed as required. Can you please clarify?

The Application for Federal Assistance (SF-424) is not the same document as the Research and Related Budget – Section A-B Form.

The SF-424 is the application cover sheet and only the prime applicant is responsible for the SF-424. The Research and Related Budget – Section A-B Form is the budget sheet for the length of the project.

The prime applicant and all subrecipients must submit the budget form.

Both forms are required with your application.

12/26/2024

12/30/2024

Question #13

In NOFO Part 1, Section IV.4, Page 23, WBS and Task Description Summary, should the reference in the NOFO Workplan instructions be to the Project Management Plan (PMP) instead of the SOPO? The PMP template specifically includes requirements for a WBS and Task Descriptions and has a larger 20-page limit.

Use the Project Management Plan (PMP) as the reference for providing a response to NOFO Part 1, Section IV.4, Page 23 under WBS and Task Description Summary.

Question #14

In NOFO Part 1, Section IV.4, Page 23, for the required Workplan under Milestone Summary, should the reference in the NOFO Workplan instructions be to the Project Management Plan (PMP) instead of the SOPO? The PMP template specifically includes requirements for a WBS and Task Descriptions and has a larger 20-page limit.

a response to NOFO Part 1, Section IV.4, Page 23 for the required Workplan under Milestone Summary.

Question #15

In NOFO Part 1, Section IV.4, Pages 23-24 the instructions for the required Workplan under "Go/No-Go Decision Points" and "End of Project Goal", Should the reference in the NOFO Workplan for these items be to the Project Management Plan (PMP) instead of the SOPO?

a response to In NOFO Part 1, Section IV.4, Pages 23-24 with the instructions for the required Workplan under Go/No-Go Decision Points and End of Project Goal.

Question #16

In NOFO Part 1, Section IV.4, Page 25, instructions under the Technical Qualifications and Resources, what definition should be used for "multi-organizational"?

In this NOFO, Multi-organizational means Recipient and Sub-recipients.

Question #17

In NOFO Part 1, Section IV.4, Page 25, the 8th bullet under "Technical Qualifications and Resources" reads " Strategy to address known resource, constraints or challenges, including those involving intellectual property and real property." Should the first comma be removed?

The first comma can be removed so that the 8th bullet under “Technical Qualifications and Resources” so that it reads:

Strategy to address known resource constraints or challenges, including those involving intellectual property and real property

Question #18

In NOFO Part 2, Section IV.D Funding Restrictions, Page 35, can prototyping include initial batch production

Yes, Initial batch production can be included within prototyping. If Initial batch production is included with prototyping, ensure the application clearly states how initial batch production is going to be included within prototyping.

01/02/2025

01/06/2025

Question #19

Clarification request for Question #6.

TRISO fuels (i.e., fresh finished fuel) can be included in the new package concept. Can it also be included in the modified package concept as long as it meets the objectives and requirements set forth in the NOFO?

So long as the application meets the objectives and requirements set forth on the NOFO, applications related to a variety of nuclear fuels and metals may be submitted and considered for award, including what is suggested in this question.