Questions and answers.pdf

PDF 334 KB Posted

Attached to
200 RHS Generator and ATS Requirement
Solicitation number
W50S8R-23-R-0024
Issued by

View the file

Other files

File Type Posted
Attachment 02 - Line Item Listing.xlsx XLSX spreadsheet
Attachment 01 - Provisions and Clauses.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Do you need installation?

No

2. When is delivery required by?

52 weeks

3. Will the owner have equipment and any required rigging to off-load the generator and accessories when it arrives to the delivery location provided?

Yes

4. Will the delivery point be a storage/laydown facility, paved/concrete access roads, or other?Storage facility

5. We plan to provide a company representative, on-site, the day of the delivery to confirm everything is received in good condition. Will this be on-base, and are there any special requirements for this person?

No special requirements. They will be escorted by a government employee.

6. What VOIP communications interface will be used with the transfer switch?

Cisco PBX alerting though SIP Pair. We have VG205 converters.

File details come from the government source that posted it. Updated .