Questions and Answers 438602.pdf

PDF 150 KB Posted

Attached to
Unit Sub-stations
Solicitation number
2110696
Issued by
Suffolk County, New York

About this file

This document is a set of Questions and Answers (Q&A) related to Request for Quote (RFQ) No. 438602 for Unit Sub-stations, issued by the Procurement and Property Management Office of Brookhaven National Laboratory (BNL) located in Upton, NY. The RFQ specifies detailed shipment schedules for the unit substations, requiring the first 5 units to be tested and delivered within 4 weeks after the Manufacturer's Fabrication Time (MFT), followed by additional units delivered at 8, 12, and 14 weeks after MFT. The RFQ also clarifies that metal enclosed switch over fixed mounted Vacuum Circuit Breakers (VCB) on the primary side of the transformer are not acceptable, and that cast-resin transformers are also not acceptable due to BNL's previous experience with failures.

The document also addresses an inquiry about using arc flash detection and mitigation through an SEL-751 relay as an alternative to the specified arc quenching requirements. BNL has indicated that this method is acceptable and meets the requirements of the 2023 National Electrical Code (NEC) Article 240.87.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Procurement and Property

Management Office P.O. Box 5000

Upton, NY 11973-5000

Date: 07/1/2024

Request for Quote RFQ No. 438602 for

Unit Sub-stations

Questions and Answers:

Question 1. Please provide clarification to the requested shipment schedules shown on your form EIC-

IFD-SOW-016 item “6” Schedules.

Answer 1. At the time of contract award, vendor to indicate the start of fabrication and time to complete

(Manufacturer’s Fabrication Time, a specific date) of the first group of unit substations and ready for testing.

Within 4 weeks after the Manufacturer Fabrication Time (MFT), the first 5 units to be tested and delivered.

Within 8 weeks after MFT, 4 additional units to be tested and delivered.

Within 12 weeks after MFT, 3 additional units to be tested and delivered.

Within 14 weeks after MFT, the last 3 units to be tested and delivered.

Question 2. Can we offer metal enclosed switch over fixed mounted VCB in lieu of draw out breaker on primary side of the transformer?

Answer 2. No. The electrical configuration to be installed includes a pad-mount switch upstream and this will provide voltage isolation, allowing for maintenance of the 15kV with no voltage present.

Question 3. Can we offer alternate dry type Cast Resin Transformer? This transformer requires less maintenance and has lesser lead time in current market than liquid filled transformer.

Moreover, these Cast Resin Transformer do not require snubbers.

Answer 3. No. BNL has experienced several failures of cast-coil transformers without any indication of eminent failure. BNL samples the oil in oil filled transformers, providing information on the health of the transformers.

Question 4. With respect to arc quenching requirements of section 26 23 00 paragraph 2.2.H.4&5, would arc flash detection and mitigation through SEL relay be acceptable in lieu of arc quenching requirements? The SEL‐751 relay would utilize overcurrent and fiber optic arc flash detection sensors to mitigate arc flash events.

Answer 4. Arc Flash Detection and Mitigation, as required by NEC 2023, Article 240.87, via SEL-751 relay utilizing overcurrent and fiber optic detection sensors is an acceptable method.”

File details come from the government source that posted it. Updated .