Question and Answers 5-30-23.docx
DOCX document 21 KB Posted
- Solicitation number
- 70Z0G823QBNCR0010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 70Z0G823QBNCR0010.pdf | ||
| DOL Wage Rate-2015-4271 Rev 21.pdf | ||
| Attachment 1 - Statement of Work.doc | DOC document | |
| RFQ Schedule 70Z0G823QBNCR0010.doc | DOC document | |
| Attachment 2-Pricing Spreadsheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
1.) What connections specifically are required for the equipment once it's delivered on site?
For the electrical side we have a disconnect with 240 three phase power, for the chill water side of the connections we have 2” Victaulic connections both for inlet and outlet.
2.) What space requires cooling? (e.g. service equipment room, non-residential facility, or personnel occupied spaces)
Personnel Occupied spaces (Living quarters, Cafeteria and offices)
3.) Any additional details that would help with providing an accurate quote?
It’s a 20 Ton chill water system that we are able to tie in directly with 2” Victaulic connections.