Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 4
2. AMENDMENT/MODIFICATION NO.
AMENDMENT 002
3. EFFECTIVE DATE
AUGUST 1, 2014
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (IF APPLICABLE)
6. Issued By Code 7. ADMINISTERED BY (If other than Item 6) Code
GSA/FAS/QMAAA
1800 F STREET NW
WASHINGTON, DC 20405
8. Name and Address of Contractor (No., street, county, State and ZIP Code (x) 9A. AMENDMENT OF SOLICITATION NO.
QMAA-FK-140015-D
X 9B. DATED (SEE ITEM 11)
JULY 22, 2014
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended X is not extended.
Offer's must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning ___ONE_____copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
[ ] A. THIS CHANGE ORDER IS ISSUED PURSUANT TO : (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
[ ] B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF :
[ ] C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF :
[ ] D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, X is required to sign this document and return _ONE_ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The above referenced solicitation QMAA-FK-140015-D is amended to:
1) Provide revised Attachment G1 – Chrysler Schedule of Items;
2) Provide revised Attachment G3 – Ford Schedule of Items;
3) Provide revised Attachment G4 – GM Schedule of Items;
4) Revise RFP Section D.8 to change ARO terms on line items 95, 95B, 95C and 95E from 180 days ARO to 195 days ARO; AND
5) Provide questions and answers as submitted in response to the RFP.
The solicitation citations are amended in accordance with the attached pages.
All other terms and conditions remain unchanged.
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
________________________________________ BY ______________________________________________
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA, FAR (48 CFR) 53.243
Solicitation QMAA-FK-140015-D Amendment 002 – Continuation of Standard Form 30
This modification is issued to:
1) Incorporate revised Attachment G1 – Chrysler Schedule of Items
a. Offerors intending to bid Chrysler items are hereby advised that the ProMaster model has been activated for bidding under item 162.
2) Incorporate revised Attachment G3 – Ford Schedule of Items
a. Offerors intending to bid Ford items are hereby advised that the Transit model has been activated for bidding under items 34N and 34X; the E-Series has been activated under item 75G; the F450 model has been activated under item 124B; and the F550 has been activated under item 89D.
b. Offerors intending to bid Ford items 75G, 92, 92F and 94 are advised to consult this revised
Schedule of Items for minimums relating to these items. The Government’s minimum requirements for these models are accurately identified in this revised Attachment G3. Due to systems constraints, these data updates will NOT be visible in AutoBid. For Ford items 75G, 92, 92F and 94, the data listed in this Schedule of Items attachment shall supersede that visible in
AutoBid in defining the Government’s minimum requirements. Any Technical Exceptions taken by Offerors relating to these items should be in relation to the data listed in this Schedule of
Items.
3) Incorporate revised Attachment G4 – GM Schedule of Items
a. Offerors intending to bid GM items are hereby advised that the C2500HD model has been activated for bidding under items 73C, 82C and 122C; the G4500 model has been activated under item 75B; the K2500HD model has been activated under items 77C and 87C; the K3500 model under items 78C, 88C and 128C; the C3500 model under item 83C; and the C3500 model under item 123C.
4) Revise RFP Section D.8 – Time of Shipment
FROM:
D.8 552.211-81 TIME OF SHIPMENT (FEB 1996) (ALTERNATE I—FEB 1996)
**For purposes of this clause, for North American production shipment is defined as the moment a vehicle leaves the manufacturer’s production facility. For vehicles which require oceanic transport, the ship date is defined as the moment a vehicle leaves the port of debarkation.
(a) Shipment is required within 90-195 calendar days after receipt of order (ARO), as defined below.
(b) Each delivery order will specify that shipment is required no later than the number of days shown above. If such order also states that "Early Shipment is Precluded," the Contractor agrees to make shipment no sooner than 90-195 calendar days after receipt of order, as defined below. Earlier shipments may result in non-acceptance of the supplies at the delivery point at the time of arrival.
**For items 73, 73C, 73D, 73E, 73F, 74,74A, 74B, 74C, 74D, 74E, 74F, 74G, 74H, 74J, 75, 75A 75B, 75C, 75E, 75F, 77, 77C, 78, 78C, 78E, 79A, 79B, 79C, 79D, 79E, 79F, 79G, 79H, and 79J, shipment is required within 90 days ARO. For items 82, 83, 84, 87, 88, 95, 122, 123, 124, 128, 129, 134, 141, 142, 144, 147, 149, 162, 22X, 24X, 122C, 122E, 123C, 123E, 124B, 124C, 124D, 124E, 124F, 124G, 124H, 124J, 128C, 128E, 129A, 129B, 129C, 129D, 129E, 129F, 129H, 129J, 134B, 134F, 144A, 144B, 149A, 149B, 32X, 34N, 34X, 44P, 49P, 82C, 83C, 84B, 84C, 84D, 84H, 84J, 87C, 88C, 89A, 89B, 89C, 89D, 89H, 89J, 95B, 95C, and 95E, shipment is required within 180 days ARO. For items 92, 92F, 94, 94B, 154, 159, 154B, 154H, 159A and 159H, shipment is required within 195 days ARO.
TO:
D.8 552.211-81 TIME OF SHIPMENT (FEB 1996) (ALTERNATE I—FEB 1996)
**For purposes of this clause, for North American production shipment is defined as the moment a vehicle leaves the manufacturer’s production facility. For vehicles which require oceanic transport, the ship date is defined as the moment a vehicle leaves the port of debarkation.
(a) Shipment is required within 90-195 calendar days after receipt of order (ARO), as defined below.
(b) Each delivery order will specify that shipment is required no later than the number of days shown above. If such order also states that "Early Shipment is Precluded," the Contractor agrees to make shipment no sooner than 90-195 calendar days after receipt of order, as defined below. Earlier shipments may result in non-acceptance of the supplies at the delivery point at the time of arrival.
**For items 73, 73C, 73D, 73E, 73F, 74,74A, 74B, 74C, 74D, 74E, 74F, 74G, 74H, 74J, 75, 75A 75B, 75C, 75E, 75F, 77, 77C, 78, 78C, 78E, 79A, 79B, 79C, 79D, 79E, 79F, 79G, 79H, and 79J, shipment is required within 90 days ARO. For items 82, 83, 84, 87, 88, 122, 123, 124, 128, 129, 134, 141, 142, 144, 147, 149, 162, 22X, 24X, 122C, 122E, 123C, 123E, 124B, 124C, 124D, 124E, 124F, 124G, 124H, 124J, 128C, 128E, 129A, 129B, 129C, 129D, 129E, 129F, 129H, 129J, 134B, 134F, 144A, 144B, 149A, 149B, 32X, 34N, 34X, 44P, 49P, 82C, 83C, 84B, 84C, 84D, 84H, 84J, 87C, 88C, 89A, 89B, 89C, 89D, 89H and 89J, shipment is required within
180 days ARO. For items 92, 92F, 94, 94B, 95, 95B, 95C, 95E, 154, 159, 154B, 154H, 159A and 159H, shipment is required within 195 days ARO.
5) Provide questions and answers as submitted in response to the RFP.
Q1: Please look at Line Items 95B, 95C and 95E, which have shipment days of 180 ARO. Should they not be
195 days ARO like the other Cargo Body items – 92, 92F, 94 and 94B?
A1: Per this amendment, Line Items 95, 95B, 95C and 95E have been amended to reflect 195 days ARO.
Q2: Line Item 34N [GM model] is a GM CNG system, so ships directly just like cab chassis Line Items. Should it not be moved to D.16 “source inspection requirement will not apply”?
A2: Contract clauses and conditions related to line items are not manufacturer specific. Exceptions taken to any contract terms and conditions (such as Section D.16 – Source Inspection for the specific make/model identified) should be outlined on Attachment D – Vendor Response Document (see page 1). Any exceptions taken to minimum requirements data or data provided in AutoBid should be provided on Attachment E –
Technical Exceptions Worksheet, in accordance with Section F.1. Offerors are instructed to note the additional guidance provided in Item #2 of this amendment.
Q3: Does the phrase…below, mean that the financial entity to whom the funds are assigned must be registered in SAMS [sic]?
“…the Contractor shall require as a condition of any assignment, that the assignee shall register separately in the SAM database…”
- From Attachment A, Clauses Incorporated by Reference, FAR 52.232-33 (g) Payment by Electronic
Funds Transfer – System for Award Management (Jul 2013)
A3: Any assignees involved in an assignment of claims as defined in FAR Subpart 32.8 must be registered in
SAM to receive EFT payments from any contract awards resulting from this solicitation.
Q4: I noticed the Standards now list maximum body width of 80” on a single rear wheel chassis. The Ford
E350 SRW is 79.4” wide at rear tires. I want to make sure we will not have any issues at time of inspection building a body with this width on this vehicle (we’ve been providing 82” wide bodies on both Ford and GM
SRW cutaways to meet the requirement the body does not extend more than 2” past the rear tires on each side).
A4: Offerors bidding the Ford E350 SRW are advised to consult the Federal Vehicle Standards for minimum requirements data on items 92 and 92F. There is a different requirement listed for body width on these items.
Q5: Also, I see a new option for CBU backup camera but cannot find it listed in the Federal Standards 307AT to confirm what the requirements are. The standard backup camera we provide to our commercial customers is
5” color LCD monitor system. Please confirm if this will meet the requirements.
A5: The backup camera (option CBU) is whatever the vendor furnishes as standard commercial practice.
Q6: In order to do an adequate bid and to be competitive as possible we need more time for this solicitation; we intend to bid on most all items and have to sort out subs and where we are going to use them, plus the pricing on about 111 items and options. We would like to see this extended from August 21 to about September 8, which gives us the weekend if we need it.
A6: The Government does not anticipate granting any extensions as they relate to the proposal submission deadlines for this solicitation. Any changes to proposal submission deadlines will be communicated to all offerors via FBO.