RFP QA2 - M870A4 31 JUL 2024 to 01 AUG 2024.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
M870A4 Semitrailer, Lowbed, Construction Equipment Transporter (SLCET) 40-Ton
Solicitation number
QAs31JUL2024-01AUG2024
Issued by

About this file

This document is a Request for Proposal (RFP) for the manufacture of M870A4 Semitrailer, Lowbed, Construction Equipment Transporter (SLCET) 40-Ton trailers. The RFP is solicitation number QAs31JUL2024-01AUG2024 issued by the Department of the Army Materiel Command TACOM Life Cycle Management Command. The contract is for a 5-year base period with two optional ordering periods. The RFP is for the manufacture of trailers, not the transportation or operation of the finished trailers. Contractors must have the appropriate driver's licenses required by the state to transport the finished trailers from their facility. The document provides questions and answers related to this RFP.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

RFP # W912CH-24-R-0025

M870A4 Semitrailer - Questions and Answers

KTRQuestionGovernment Response
12In regards to Clause:

143 52.219-14 LIMITATIONS ON SUBCONTRACTING (DEVIATION 2021-O0008)

Which category does this opportunity fall under?

Supplies, Services, or General Construction?Subject Request for Proposal is for supplies.
13My question about the 40 Ton Bid is the vehicle to be leased out and operated by military staff, or does the contract include the 40 Ton Driver/Operator to transport said equipment?Subject Request for Proposal is for the manufacture of trailers. Any transportation of a finished trailer at the contractor facility will be done with the use of a Government provided tractor and contractor provided driver. The driver must have appropriate license required by the state to drive on public roadways.
23Also I understand it is a five year contract with options to extend up to two more years. Is this correct?Yes, the intent is to issue a five year contract with two optional ordering periods.

B.2.1-B.2.7 detail the ordering periods of the solicitation.